This is Addendum #1 to solicitation BL062-26 issued by Gwinnett County on March 20, 2026, addressing the removal and replacement of epoxy floors at various parks locations. The project encompasses multiple facilities that are open to the public for inspection. No pre-bid conference is scheduled for this solicitation. The addendum clarifies that a moisture barrier is required to be installed as part of the epoxy flooring work at all specified locations. Contractors must acknowledge receipt of this addendum by signing and returning it with their bid submission, as failure to do so may result in bid rejection.
Gwinnett County has secured approved funding for the project and expects competitive pricing from all bidders. The county will award the contract to the lowest responsive and responsible bidder. No bid bond is required for submission. Pricing should reflect comprehensive costs for the removal and replacement of epoxy floors including the mandatory moisture barrier installation at all designated park locations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BL062_26 Inv.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
March 20, 2026
Addendum #1
BL062-26
Removal and Replacement of Epoxy Floors at Various Parks Locations
Please see a summation of the questions and answers below for the referenced solicitation.
Questions:
Q1. Will there be a pre-bid conference for this project?
A1. There are no plans for one at this time. The facilities listed in the bid are open to the public.
Q2. Is there a budget the County is working within?
A2. There is approved funding for this project. Gwinnett County expects each contractor to bid a competitive price. Award will be made to the lowest responsive and responsible bidder.
Q3. Will a bid bond be required?
A3. No.
Q4. Who will determine if an epoxy moisture barrier is required?
A4. A moisture barrier is required to be installed.
Thank you, Casey Beauston, CPPB Purchasing Associate III
This addendum should be signed in the space provided below and returned with your bid. Failure to do so may result in your bid being deemed non-responsive.