BL038_24 Ad1.pdf
PDF 202 KB Posted
- Solicitation number
- PE-77023-NONST-2024-000000120
- Issued by
- Gwinnett County, Georgia
About this file
This document is an addendum to the BL038-24 contract for the West Gwinnett Aquatic Center Pool Renovations project in Gwinnett County, Georgia. The scope of work has been revised to require that work on the indoor pools be completed by August 23, 2024, and work on the outdoor pool start on September 3, 2024 after the Labor Day holiday. The pre-bid meeting is optional, but all interested contractors are urged to attend. The county has approved funding for this project, and the contract will be awarded to the lowest responsive and responsible bidder.
The county expects each contractor to submit a competitive bid for this project. There is no engineer's estimate provided, but the county will not consider bids from firms currently on the Gwinnett County ineligible source list. Contractors must acknowledge this addendum when submitting their bids, or their bids may be deemed non-responsive.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BL038_24 INV.pdf | ||
| BL038_24 Award Notice.pdf | ||
| BL038_24 Ad2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
February 27, 2024
ADDENDUM #1
BL038-24, West Gwinnett Aquatic Center Pool Renovations
REVISIONS:
R1. I. SCOPE OF WORK, #1 shall be revised to the following: Work on the indoor pools should be completed no later than August 23, 2024. Work on the outdoor pool should start on September 3, 2024 after the Labor Day holiday. All work shall be coordinated with the County Representative.
R2. I. SCOPE OF WORK, #1a. shall be removed from the scope of work.
QUESTIONS & ANSWERS:
Q1. Can you clarify if the pre-bid meeting is mandatory?
A1. The pre-bid meeting is optional. However, all interested contractors are urged to attend.
Q2. What is the County’s budget for this project? What is the engineer estimate for this project?
A2. There is approved funding for this project. Gwinnett County expects each contractor to bid a competitive price. Award will be made to the lowest responsive and responsible bidder.
This addendum should be acknowledged in the space provided on page 13 of the bid documents and returned with your bid. Failure to do so may result in your bid being deemed non-responsive.