biddoc.pdf
PDF 405 KB Posted
- Attached to
- OIM Statewide Geohazards Mitigation
- Solicitation number
- RFP 27-202832 NM
- Issued by
- Larimer County, Colorado
About this file
Summary of RFP 27-202832 NM: OIM Statewide Geohazards Mitigation
This Request for Proposals (RFP) is issued by the Colorado Department of Transportation (CDOT) Office of Innovative Mobility (OIM) to procure an on-call contractor for mitigation and management of geologic hazards affecting Colorado's state transportation system during emergency and urgent need situations. The solicitation seeks services for rockfall and rock slope stabilization and/or soil slope stabilization work throughout Colorado, with the contractor responsible for ensuring traffic and personnel safety during all operations. The proposal submission deadline is December 15, 2026, at 2:00 p.m. Mountain Time via BidNet Direct. A virtual public proposal opening will occur on Tuesday or Thursday, December 15 or 17, 2026, at 3:30 p.m. The estimated Notice of Intent to Award will be published January 20, 2027, with a desired contract start date of March 1, 2027. The initial contract term is one year, with the option for CDOT to unilaterally renew for up to four additional one-year periods at its sole discretion, for a total potential duration not to exceed five years.
Contractors must submit pricing using the specified format for labor rates, materials, equipment, and other costs for both standard and federal emergency response (ER) hourly rates. Pricing shall be firm through the initial contract term, with any subsequent price increases limited to the annual Consumer Price Index for Denver-Aurora-Lakewood and requiring 90-day advance notice. The contractor will be reimbursed on a time-and-materials basis for invoiced work, with mileage reimbursed at Colorado state rates (not to exceed GSA rates), lodging at actual commercial rates up to GSA per diem limits, and subcontractor costs reimbursed at cost plus 5%. The solicitation encourages responses from Service Disabled Veteran Owned Small Businesses (SDVOSBs), which receive a 5% evaluation preference if certified by the U.S. Department of Veterans Affairs. No specific set-asides are established. Proposals will be evaluated on understanding and project approach (25%), overall experience and qualifications (30%), project team and service delivery capability (20%), cost proposal (20%), and feasibility and completeness (5%), with SDVOSB certification receiving an additional 5% preference consideration if applicable.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 27-202832 NM Page 1 of 37
Request for Proposals
RFP 27-202832 NM:
OIM Statewide Geohazards Mitigation
Published November 10, 2026
RFP 27-202832 NM Page 2 of 37
SOLICITATION AND RESPONSE COVER SHEET
Request for Proposal (RFP)
RFP 27-202832 NM - OIM Statewide Geohazards Mitigation Per the attached specifications, terms and conditions.
INSTRUCTIONS: Offeror (Offeror) must complete this cover sheet and attach it with their proposal.
Offerors are urged to read the solicitation document thoroughly before submitting a proposal.
Submit Proposal to:
BidNet Direct Help Desk 800-835-4603 / support@bidnet.com
Purchasing Agent:
Name: Natalie A. Martinez Email: natalie.a.martinez@state.co.us
Due Date: December 15, 2026, Tuesday Time Due: 2:00 PM Mountain Time
Offerors Information Offeror F.E.I.N.: __________________
Payment Terms:
(Minimum of Net 45) _____________
Offeror DUNS#: __________________ Delivery Date: __________________
Authorized Signature:
Signature acknowledges acceptance of all terms and conditions of the solicitation. ________________________________________________________
Typed/Printed Name and Title: ________________________________________________________ Authorized Signatory Email: ________________________________________________________
Legal Company Name: ________________________________________________________ Doing Business As: ________________________________________________________
Address: ________________________________________________________ City: _________________ State: ______ Zip: ___________
Phone Number: _________________ Fax Number: ___________________ Contact for Clarifications: ________________________________________________________
Contact Title: ________________________________________________________ Contact Phone Number: _________________ Fax Number: ___________________ Contact Email Address: ________________________________________________________
Offeror to answer and acknowledges by its signature above:
- Confirm that you are aware that the award notice will be published on CDOT website: ____ Yes
- My company is registered on BidNet, Direct: _____Yes / _____No
- Registered with the Colorado Secretary of State ____No / ____Yes, and #________________________
- Offeror proposes using Subcontractors for this project: _____Yes / ____No
- Offeror has reviewed Modifications made to this RFP – list the Modification # last reviewed: _____
- If claiming SDVOSB (Service Disabled Veteran Owned Small Business) attach proof of certification: __Yes / __NA https://www.bidnetdirect.com/register mailto:support@bidnet.com mailto:natalie.a.martinez@state.co.us https://www.codot.gov/business/procurement-and-contract-services/cdot-supplier-information
RFP 27-202832 NM Page 3 of 37
Please read this solicitation thoroughly before responding. Illegible responses may be rejected as non-responsive.
The Colorado Department of Transportation (CDOT) reserves the right to reject any and all proposals or parts thereof, and to waive informalities or irregularities. By submission of a proposal, Offeror agrees to the State of Colorado terms and conditions.
By submission of a proposal, Offeror agrees as follows:
· Except as replaced, modified, or supplemented by CDOT for this solicitation, all items in the State of Colorado Solicitation Instructions/Terms and Conditions are considered part of, and are incorporated by reference into this document.
· Offeror testifies that bid prices were arrived at independently and there was no collusion involved.
· The Offeror/Vendor guarantees to the State that they understand and agree to the terms and conditions of this solicitation and that they will not default from performance by virtue of a mistake or misunderstanding. Offerors shall seek clarification from CDOT of any specifications, terms and/or conditions that they determine to be unclear. The failure of an Offeror to seek clarification may be deemed a waiver of any such clarification.
· Pursuant to CRS 24-30-202.4 (as amended), the state controller may withhold debts owed to state agencies under the vendor offset intercept system for: (a) unpaid child support debt or child support arrearages; (b) unpaid balance of tax, accrued interest, or other charges specified in Article 22, Title 39, CRS; (c) unpaid loans due to the student loan division of the Colorado Division of Higher Education; (d) owed amounts required to be paid to the unemployment compensation fund; and (e) other unpaid debts owing to the state or any agency thereof, the amount of which is found to be owing as a result of final agency determination or reduced to judgment as certified by the controller.
· OFFERORS: See the solicitation document below for the response deadline and other response submission information and requirements.
· Offerors responding to this solicitation must fill out the Solicitation and Response Cover Sheet in its entirety, sign and return with the Offeror's response. This page must bear a physical or electronic signature, as electronic signature is defined in the "Uniform Electronic Transactions Act", section 24-71.3-102 (8), evincing an intent by the vendor to be bound by its response. Failure to do so may disqualify the Offeror’s response.
· The authorized signatory understands and agrees that misrepresentation made in this response and/or subsequent discussions or information presented to the State may be deemed sufficient cause for the refusal by the State to execute a contract as a result, and that that later discovery of any omission or misrepresentation made in the solicitation response and/or subsequent discussions or information presented to the State may be grounds for the cancellation of an existing contract.
RFP 27-202832 NM Page 4 of 37
1. INTRODUCTION
A. General Information
On behalf of the Colorado Department of Transportation (CDOT), the Office of
Innovative Mobility (OIM) is issuing this Request for Proposals to procure a Contractor for on-call mitigation and management of geologic hazards that affect the state transportation system in emergency and urgent need situations.
B. Background and Overview
This Contract is for mitigation and management of geologic hazards that affect the state transportation system in emergency and urgent need situations. The Work will be as needed, located throughout the State and shall not be performed without CDOT approval.
CDOT recognizes the effect geologic hazards have on the transportation system. These hazards include rockfall, debris flow, landslides, sinkholes, embankment distress and other geotechnical related highway deterioration. The task of managing these hazards is the goal of the Geohazards and Geotechnical Services Programs.
The Contractor is responsible for conducting all work in a manner that ensures the safety of traffic and on-site personnel. Contractor shall provide the Work at the prices and rates established in a Master Contract. The Master Contract shall list all
Goods/Services that are required to be delivered to CDOT as part of the Work (each a
“Deliverable”). The Work under the Master Contract shall be done in accordance with any Plans, Special Provisions or other Contract Documents issued with the site specific
SOW and shall be coordinated with the CDOT Project Manager. For the purpose of this
Contract the terms CDOT Supervisor and CDOT Project Manager shall refer to the CDOT representative responsible for coordinating the Work with the Contractor.
C. Sole Point of Contact
i. The State’s sole point of contact for this solicitation is Purchasing Agent, Natalie Martinez, who may be reached via email at natalie.a.martinez@state.co.us.
RFP 27-202832 NM Page 5 of 37
ii. Because phone lines may not be consistently monitored, email is the preferred method of communication. The individual listed above is the sole point of contact for this solicitation. Initiating contact with anyone other than this individual may result in Offeror disqualification.
D. Schedule of Activities
i. This Schedule of Activities is for information and planning purposes only.
Schedules for Activities listed as “Estimated” may be subject to change depending on the needs of the State. All times are considered in Mountain
Time (MT), as adjusted for daylight savings.
a. The date of publication for this solicitation via Rocky Mountain E-
Purchasing, BidNet Direct is November 10, 2026.
b. Respondents may submit written inquiries via BidNet concerning this solicitation to obtain clarifications. The State, in its sole discretion, may not accept inquiries received after the date and time indicated. Where appropriate, inquiries should include references to any relevant
Section/paragraph of the solicitation. All questions must be submitted in writing via BidNet, no later than Tuesday, November 24, 2026 at 2:00 p.m. MT.
c. The estimated date for the State’s responses to vendors’ written inquires to be published on BidNet Direct is December 3, 2026 at 5:00 p.m. MT.
Responses to Respondent’s inquiries will be published on BidNet collectively, as a modification to the solicitation. Respondents shall not rely on any verbal statements that alter any specification or other term or condition of the solicitation. Such changes are valid only if provided in writing by the Procurement Contact.
d. All proposals must be submitted in the method described below no later than Tuesday, December 15, 2026 at 2:00 p.m. MT.
e. A public opening of the proposals will be held virtually via conference call on Tuesday or Thursday, at 3:30 PM Immediately following the
RFP 27-202832 NM Page 6 of 37 closing of this solicitation. Attendees to the conference may call in at 1-
405-437-2030 using PIN 314 560 377#. Note: while proposals will be logged during this meeting, the purpose of this proposal opening is simply to log the proposals received.
f. The estimated date for top proposers to be selected and notified of an interview, if appropriate is January 6, 2027.
g. The estimated date for interviews/demonstrations from selected proposers is January 13, 2027.
h. The estimated date for the publication of an Intent to Award on BidNet
Direct is January 20, 2027.
E. Start Date
The desired Contract start date is March 1, 2027.
F. Anticipated Award and Award Term
i. CDOT expects to issue a Standard Personal Services Contract to the successful
Offeror. CDOT has provided Attachment B – Standard Personal Services
Contract Template for reference. The anticipated initial term of the Contract shall be 1 year. Initial term of the Contract shall be from date of execution through the initial term of the award. This Contract may unilaterally be renewed for up to four (4) additional one-year periods at the sole discretion of the State upon written notice to the Contractor, including, but not limited to prices, rates and service delivery requirements. The total duration of the Award, including all options, is not anticipated to exceed five (5) years. The Contractor agrees to deliver under this solicitation for the full initial term and any renewals. CDOT may elect to renew services annually contingent upon: (1) the results and recommendations generated through this Award; (2) the State’s satisfaction and acceptance of the selected Contractor’s services and deliverables upon completion of each anticipated contract year; and (3) availability of funding to continue services.
ii. The State may extend the Contract beyond the anticipated term in accordance
RFP 27-202832 NM Page 7 of 37 with the Colorado Procurement Code, and in the event that the State determines an extension is necessary.
iii. The State may, within its sole discretion, choose not to exercise any option or extension term in the Award for any reason. If the State chooses not to exercise any option or extension term, it may re-procure the goods and/or services in its sole discretion.
G. CONTRACTOR RESPONSIBILITIES:
The selected consulting team will work closely with CDOT staff to implement all tasks outlined in the statement of work, using the methodology identified in the proposal.
Additionally:
● Coordinate regularly with project manager
● Proactively address issues as they arise during the duration of the project
● Submit invoices no less than once a month
2. REQUIREMENTS
A. Accessibility Requirements
All work performed as a result of this solicitation must comply with all applicable provisions of §§24-85-101, et seq., C.R.S., and the Accessibility Standards for
Individuals with a Disability, as established by the Office Of Information Technology pursuant to Section §24-85-103 (2.5), C.R.S. and 3) all State of Colorado technology standards related to technology accessibility and with Level AA of the most current version of the Web Content Accessibility Guidelines (WCAG), incorporated in the State of Colorado technology standards.
B. Insurance Requirements
The awarded Offeror will be required to submit a certificate(s) of insurance evidencing insurance coverage for, at minimum, the types and amounts of insurance as required by the Insurance provision listed in Attachment B – Standard Personal Services
Contract Template of this solicitation, prior to execution of the Contract.
C. Compliance with Federal Requirements
When a procurement involves the expenditure of federal assistance or federal
RFP 27-202832 NM Page 8 of 37 contract funds, the Procurement Official shall comply with the appropriate federal law and the rules and regulations promulgated pursuant to such laws which are mandatorily applicable.
D. FEDERAL CLAUSES AND CERTIFICATIONS
Offerors are required to complete Attachment D - Federal Clauses and
Certifications with their response to this RFP.
E. PERFORMANCE OUTSIDE OF COLORADO
Awarded Offeror, per Section 24-102-206, C.R.S., prior to contracting shall disclose in a written statement whether it anticipates performing or subcontracting any services under the contract, where such subcontracted services will be performed under the contract, including any subcontracts, and whether any subcontracted services under the contract or any subcontracts are anticipated to be performed outside the United States or the state. If the prospective vendor anticipates services under the contract or any subcontracts will be performed outside the United States or the state, the vendor shall provide in its written statement a provision setting forth why it is necessary or advantageous to go outside the United States or the state to perform the contract or any subcontracts. See Attachment C - Service Disclosure
Form.
F. COLORADO SECRETARY OF STATE REGISTRATION & CERTIFICATE OF GOOD STANDING:
Prior to Contract execution, the awarded Offeror must provide the State with a
Certificate of Good Standing with the Colorado Secretary of State. Offerors do not need to submit this Certificate unless they are awarded this solicitation. Award of a contract will be contingent upon the successful Offeror submitting this certificate.
3. SCOPE OF WORK
A. Scope of Work and Deliverables
This Scope of Work describes the deliverables sought through this RFP and the scope of what the awarded Offeror will be expected to offer through the contract resulting from this RFP. The Scope of Work is intended to provide interested
Offeror’s with sufficient basic information to submit a proposal. It is not intended to limit a proposal’s content or exclude any relevant or essential data. For full
RFP 27-202832 NM Page 9 of 37
Scope of Work see Attachment A – Scope of Work.
4. REQUESTED PROPOSAL FORMAT
Submissions must be electronic and submitted through BidNet Direct in one file. If file size does not permit one file, then clearly mark the sections of your submittal.
Firms responding to this RFP should address the following items in no more than 20 pages, single-sided (excluding appendices), minimum 11 pt. font, 8.5 x 11 letter size paper, 1 inch margins per submission. Do not leave pages blank. All pages must be clearly numbered and sections labeled. 11x17 formatting can be used if it’s necessary to properly display charts, maps, or similar information in your appendices. Text should not be presented in 11x17 format.
Proposals should be submitted providing the information required in an organized manner following the topic headings listed below and must provide details of how your organization anticipates providing the services required. This format will allow for more efficient evaluation by the committee and provide Offerors with a means of ensuring all requested information is included as part of the submitted documentation.
Proposals must detail the Offeror’s understanding of, and approach to, the project, including how each element of the Scope of Work will be accomplished, identification of any work to be performed, or anticipated to be performed, by subcontractors. This section of the proposal should contain information amounting to more than a mere duplication or rephrasing of the RFP; instead, the Offeror should demonstrate an understanding of the State’s needs and objectives. In other words, answer the question: What is the reason for this solicitation and work described herein?
To be considered responsive, Offerors must adhere to and include the following when preparing their proposal:
● Reference by RFP subsections the information responding to.
● Describe in full the subject item. The description may be in narrative or outline format, while remaining as brief and concise as possible.
● Reference to, and attachment of, any supporting documentation assisting in the description of, or contribution to, any identified and addressed item.
RFP 27-202832 NM Page 10 of 37
The proposal should include details of the following:
A. UNDERSTANDING & PROJECT APPROACH:
Please describe in detail how your proposal will meet or exceed the mandatory project requirements detailed in Attachment A – Scope of Work and Exhibit 4 –
Mock Scenarios, and why your company should be selected for this contract. Based on the scope of work, please describe your overall understanding of what is required to meet CDOT’s purpose and goals for this RFP and with developing an approach that demonstrates a working knowledge of how to efficiently and effectively manage multiple and diverse tasks as follows:
1. Offeror must demonstrate an understanding of the project needs and the reasons and objectives for the required work.
2. Offeror must demonstrate a clear approach to executing the tasks identified in the Scope of Work effectively and wisely.
3. Proposal must address all elements of the project in a comprehensive, creative, simple and clearly communicated manner.
4. Accessibility Requirements: Offeror shall describe how their proposed solution will meet or exceed the accessibility requirements detailed in this solicitation.
5. Mandatory Requirements: Offeror shall describe how their proposed solution will meet or exceed the mandatory requirements detailed in this solicitation.
B. OVERALL EXPERIENCE AND QUALIFICATIONS:
Offeror shall describe how the Offeror’s experience and capabilities make it the ideal candidate to perform the work. Describe experience with similar projects. Proposal must list and describe all relevant work experience and qualifications on activities described in Attachment A – Scope of Work, including but not limited to:
1. Offeror must have staff with at least five years of experience with and demonstrate proven ability to provide Rockfall and Rock Slope Stabilization services including subtasks listed and/or Soil Slope Stabilization services including subtasks listed.
2. Offeror must have staff with at least five years of experience with slope stabilization near highway infrastructure.
RFP 27-202832 NM Page 11 of 37
3. Offeror must have staff with at least five years of experience with demonstrate expertise and familiarity with urgent need response to geohazard events.
4. Offeror must have staff with at least five years of experience with demonstrate ability to respond to geohazard events within 8 hours of notification.
5. Offeror must list references with contact information for three (3) clients where similar services have been performed by your company within the last 5 years.
Include the names of the organization, contact person, phone number, e-mail address, and a brief description of the services provided. Reference checks may be performed to verify information and to ascertain the quality of the services provided. CDOT reserves the right to pursue and contact references related to projects named in the proposal; however, reference checks are not limited to contacts explicitly named in the proposal. While checking references, CDOT reserves the right to contact any individual or entity that may be relevant.
C. ORGANIZATIONAL PERSONNEL & ABILITY TO PROVIDE SERVICES:
Offeror shall indicate key personnel who will be assigned to the project and describe their experience to address all elements in the Scope of Work and their time availability as follows:
1. Describe the key staff and other project support members who will be directly assigned to this project and the project’s team size. The role and experience of key staff should be fully explained, while support staff and general experience may also be identified. The Project Team should identify and include individuals experienced in all elements of this Statement of Work. The description should include the key staff members’ roles on the project, their disciplines, experience with similar projects, and their availability to work on this project and perform project tasks in a timely manner. Offeror must provide a statement of project personnel qualifications and experience to be approved by the CDOT Project
Manager. No change in personnel assigned to the project will be permitted without the written approval of the CDOT Project Manager. Any substitution of project key personnel will require approval by the CDOT Project Manager.
RFP 27-202832 NM Page 12 of 37
Substitutes shall have at least equivalent qualifications to the initial key personnel. Direct experience working together as a team on similar projects will be considered of significant value. A project organization chart may be included to identify key proposed team members and respective roles.
2. The proposal must include resumes for all key personnel limited to two (2) pages each. The proposed team must collectively demonstrate all required experience areas. Resumes are not counted towards page count listed in Section 5 above.
3. Proposed Schedule of Tasks and Deliverables:
Provide a task-by-task plan to accomplish the work detailed in the Scope of Work, including the project timeline, in months required, to accomplish each task and the sequence for tasks that cannot be accomplished simultaneously.
4. Identify when the project personnel identified above will be available to start the work from the Notice-to-Proceed date.
5. Describe the Offeror’s company, the location of their main office and associated yards, and the types of work the Offeror generally performs.
6. Describe the Project Team’s current and estimated contractual project workloads, not just with CDOT. Offeror shall demonstrate adequate capacity to perform this project within the context of existing workload commitments.
7. Describe backup staffing approaches and response times to ensure planned deliverables are met, regardless of individual staff availability (e.g., annual leave, commitments to other clients, etc.).
8. Offeror must demonstrate a long-standing history of delivering customer excellence and accountability to deliverable timelines and outcomes.
9. Offeror must demonstrate the proven capacity to effectively deliver projects on budget and with the right level of expertise on staff.
10. Offeror’s Organization
Offeror is encouraged to provide information regarding its organization which has not been specifically requested, but which the Offeror believes relevant and of benefit to the project.
RFP 27-202832 NM Page 13 of 37
D. COST PROPOSAL & NARRATIVE:
1. Contractors and any sub-contractor’s prices and rates, shall be firm through the initial term of the Contract. Requests for proposed price/rate increases must be submitted a minimum of 90 days prior to the proposed effective date, with detailed supporting documentation/justification, to the Department of
Transportation, Center for Procurement Office. Only one price increase will be considered during any Contract Year following the initial Contract Year/Term.
Any price increase to be considered by CDOT shall not exceed on a percentage basis the then-current annual Consumer Price Index (CPI) for Denver-Aurora-
Lakewood over the Contract’s prior pricing. CDOT reserves the right to purchase additional products/services per the specification as detailed in the Statement of Work and the agreed upon final pricing.
2. Costs not presented using the format will be considered non-responsive and may lead to the rejection of the submitted proposal from further consideration.
3. All employee rates of pay will be compared to CDOT figures of the same employee classifications. Employee rates and indirect costs should be consistent with audited MPA rates and indirect costs if the Contractor has a Master Price
Agreement (MPA) already established with CDOT.
4. Costs for subcontractors shall be reimbursed at cost plus 5% in accordance with state rules and any federal requirements.
5. Proposal must also include the maximum rate of escalation for successive years in the event of contract renewal.
6. Offeror shall provide the Services at the prices and rates provided by the Offeror in this section using the format shown below. CDOT will pay Offeror on a reimbursement basis, provided the Offeror submits invoices to CDOT containing itemized detail specific to the Work and obligations outlined in Attachment A –
Scope of Work and Exhibit 4 – Mock Scenarios.
7. Offeror shall itemize mileage, per diem, lodging, printing/binding, and any other expenses the Offeror deems necessary at cost, not to exceed the current State of Colorado allowable rates.
Mileage
RFP 27-202832 NM Page 14 of 37
● Mileage shall be reimbursed at the current mileage rate for 2WD vehicles approved in accordance with State Fiscal Rules.
● The use of 4WD vehicles shall only be permitted with the prior, written approval of the CDOT Project Manager and shall be reimbursed at the current mileage rate for 4WD vehicles approved in accordance with State
Fiscal Rules.
● Mileage shall not include normal commuting miles.
● The Colorado mileage reimbursement rate is less than the GSA rate and
CDOT cannot pay a vendor at a higher rate than the Colorado mileage rate.
Lodging
● Lodging shall be reimbursed at the actual cost of commercial lodging (or an approved alternative in accordance with State Controller Policy) for the
Contractor's employees for work under this Contract up to an amount no greater than the current GSA CONUS per diem allowable rate.
8. It is understood that equipment owned or materials held in stock by the
Contractor that can be mobilized immediately are often more efficient for implementing emergency response work than equipment or materials that are rented or purchased as needed and cannot be delivered immediately to a job site. As such, Contractors are encouraged to submit additional bid items for commonly used materials and equipment owned by the company and expected to be used as part of the Contract that are not listed on the included bid item lists.
9. Invoices shall only include hours spent to complete the Work and hours outside of these to meet union or other company requirements shall be the responsibility of the Contractor.
10. All items for which a Contractor provides a rate are expected to be available at the work site in the response timeframe outlined under the “Contractor
Responsibilities” section of this Statement of Work.
11. Traffic control will be paid for as a subcontracted service.
RFP 27-202832 NM Page 15 of 37
12. Fuel shall not be charged separately but shall be included in the bid items for equipment or included in the invoice for rental equipment.
13. Site visits to observe slope conditions and site considerations shall be coordinated with the CDOT Project Manager prior to the Work when possible.
Personnel hours for site visits shall be subject to prior approval and compensated only for travel and on-site time approved by the CDOT Project
Manager. Coordination costs to plan for the Work and arrange for equipment, subcontracting or other items will not be paid for separately but shall be incorporated into the line-item costs of the Master Contract.
14. Mobilization will be paid for on a site-by-site basis as preapproved by CDOT
Project Manager. Out-of-state travel will not be paid for separately and should be included into the line item costs of the Master Contract. For Rockfall and
Rock Slope Stabilization Work, mobilization shall not exceed the time and material costs associated with transporting personnel and equipment to the site to begin the Work and from the site when the Work is complete. For Soil
Stabilization Work, mobilization shall be included as a line item in the project proposal with a written description supporting the proposed costs associated with mobilization to the specific site.
15. It is understood that personnel located within the state of Colorado that can be mobilized immediately are often more efficient for implementing emergency response work than out of state personnel. As such, the Contractor is encouraged to prioritize the use of in-state personnel whenever possible. Use of out-of-state employees requiring extended overnight stays will be subject to approval by the CDOT Project Manager and such charges shall be communicated to the CDOT Project Manager prior to travel arrangements.
16. Payment for Work resulting from changed conditions encountered shall be negotiated by the designated CDOT Supervisor. Any changes to the initial scope of work shall be documented by formal written Amendment.
COST PROPOSAL AND BUDGET FOR CONTRACT:
Contractor capabilities and cost will be evaluated through response to the following
RFP 27-202832 NM Page 16 of 37 set of mock scenarios. The mock scenarios are based on actual geohazard events that have occurred on Colorado highways. Please provide responses for all scenarios for which the Contractor is proposing to provide services for listed in each Task #1
– Rockfall and Rock Slope Stabilization and/or Task #2- Soil Slope and Subsurface
Stabilization for which the Contractor is proposing. Work for this Contract will be by
Standard Contract according to State Fiscal Rules. Work will be designated by the
CDOT Geohazards Program or CDOT Region representative in the Master Contract scoping process as one of two categories: 1) Rockfall and Rock Slope Stabilization or
2) Soil Slope Stabilization. Contractors may submit proposals and pricing for (1)
Rockfall and Rock Slope Stabilization Work or (2) Soil Stabilization Work or both (1) and (2) depending on their experience and qualifications.
Offeror must provide a detailed proposed budget for each deliverable/task on an annual basis for all items listed in Attachment A – Scope of Work and Exhibit 4 – Mock
Scenarios. For the purposes of this proposal, provide Labor and Equipment pricing related to each task with the proposed labor and equipment pricing table. In the estimate, please include line-item estimates (price and quantity) for items in the pricing table necessary to complete the tasks listed in Attachment A – Scope of Work that you are submitting your response for. Guidance for Other Applicable costs for the estimate have been provided. For evaluation purposes, please provide proposed pricing for both regular and federal ER rates. Offeror shall complete the work identified in Attachment A – Scope of Work and Exhibit 4 – Mock Scenarios based on the prices and rates submitted in the following format:
E. Rate Schedule
1a. Task #1 Labor Rates – Rockfall and Rock Slope Stabilization
Note: The Contractor shall add any employee classifications and hourly rates they have access to and feel are necessary in addition to those listed below. The Contractor may not remove any of the items/positions listed. If the Contractor does not have the items/position, respond with “N/A”.
Item
Employee Classification Standard Hourly Rate
Federal ER Hourly Rate
Total Hours at
Total Cost
RFP 27-202832 NM Page 17 of 37
Standard Rate
1 Scaler
2 Scaler Foreman
3 Blasting Foreman
4 Project Foreman
5 Laborer
6 Equipment Operator
TOTAL Labor Costs: $_______________
1.b Task #1 Materials, Equipment and Other Costs – Rockfall and Rock Slope Stabilization
Note: The Contractor shall add any equipment or material classifications and rates they feel are necessary in addition to those listed below that are available for urgent need use and owned by the Contractor. The Contractor may not remove any of the items/positions listed. If the Contractor does not have the items/position, respond with “N/A”.
Item
Item Description Unit of Measure
Standard Unit Price
Federal ER Unit Price
Quantity at Standard Price
Total Cost
7 Hand Drill HR
8 Crane Basket and Crane Basket Drill
HR
RFP 27-202832 NM Page 18 of 37
9 Track Drill HR
10 Air Bag (two feet or less)
DAY
11 Air Bag (larger than two feet)
DAY
12 Rock Splitter HR
13 Air Compressor (300 CFM or less)
HR
14 Air Compressor (greater than 300
CFM)
HR
15 Air Canister (for on slope airbag use)
DAY
16 Support Truck HR
17 Grout Plant HR
18 Anchor Testing Equipment
HR
TOTAL Materials/Equipment/Other Costs: $_________________
2. Task #2 - Soil Slope Stabilization – Materials, Equipment and Other Costs
Note: The Contractor shall add any service, equipment, material or installed-item rates they feel are necessary to perform Soil Stabilization Work as described in this Statement of Work that are owned and operated by The Contractor.
RFP 27-202832 NM Page 19 of 37
Item # Item Description
Unit of Measure
Unit Price Federal ER Unit Price
Quantity Total Price
EXAMPLE Soil Nail Linear Foot
$X.XX per foot
$X.XX per foot
TOTAL Soil Slope Stabilization Item Pricing: $_________________
B. GRAND TOTAL for Year 1 of Contract: $________________
GRAND TOTAL for Year 2 of Contract: $________________ GRAND TOTAL for Year 3 of Contract: $________________ GRAND TOTAL for Year 4 of Contract: $________________ GRAND TOTAL for Year 5 of Contract: $________________
C. GRAND TOTAL COST OF PROJECT FOR YEARS 1-5 = $_________________
The above project budget includes all fees, costs, and expenses, including, but not limited to, labor costs, travel expenses, parts, service, repair, removal, replacement, mileage charges, supplies, mailing charges, installation, testing, communications, order and order tracking, reporting, debugging, analysis, delivery charges, and other expenses unless otherwise specified.
C. REQUIRED APPENDICES (NOT COUNTED TOWARDS PAGE COUNT):
1. Solicitation and Response Cover Sheet
2. Attachment C – Services Disclosure Form
3. Attachment D – Federal Certifications (signed and notarized)
4. Resumes
F. OPTIONAL APPENDICES (NOT COUNTED TOWARDS PAGE COUNT):
RFP 27-202832 NM Page 20 of 37
1. Sample Reports
2. Charts
3. Graphs
4. Other Supporting Documentation
G. CONFIDENTIAL/PROPRIETARY INFORMATION:
The State of Colorado is subject to the requirements of §24-72-200.1, C.R.S., et seq., Colorado Open Records Act.
An Offeror may submit, as a part of its proposal, a written request for classification of certain portions of the proposal as a trade secret or other confidential or proprietary information. Material for which the Offeror is requesting confidentiality must be clearly identified and separated from other portions of the proposal to facilitate public inspection of the non-confidential portion of the proposal. Commingling of confidential and non-confidential information is not acceptable. Neither cost nor price information nor any information that will be included in a resulting Contract will be considered confidential. If any of the materials submitted by the Vendor to CDOT are clearly and prominently labeled trade secret, privileged information, or confidential commercial, financial, geological, or geophysical data by the Offeror, CDOT will endeavor to advise the Offeror of any request for the disclosure of such materials prior to making any such disclosure. Under no circumstances, however, will CDOT be responsible or liable to the Offeror or any other Person for the disclosure of any such labeled materials, whether the disclosure is required by law, by court order or occurs through inadvertence, mistake or negligence on the part of CDOT. CDOT will inform Offeror if a request for the information is made by a third party and will give Offeror a chance to defend against any action seeking the materials.
The Offeror must include the rationale for any request to classify portions as a trade secret or confidential or proprietary, including references to the authority that allows for such treatment.
In no event shall an entire proposal be classified as confidential. The Procurement
Official or his or her designee shall determine if the information identified in the
RFP 27-202832 NM Page 21 of 37
Offeror’s request is exempt from disclosure in accordance with §24-72-204, C.R.S., and shall inform the Offeror in writing of his or her determination. If denied, the
Offeror will have the opportunity to withdraw its entire proposal, or to remove the proprietary restrictions. If the Offeror does not agree with the determination, the
Offeror may protest the determination in accordance with article 109 of the
Colorado Procurement Code and the terms of this solicitation. Reference
Procurement Rule R-24-101-401-03.
Any additional Offeror information, which may be part of the evaluation/negotiation process and for which an Offeror claims confidentiality, is subject to the same requirements and processes identified in this Section 1.8.
i. Submission of Confidential/Proprietary Information:
All material submitted in response to this RFP will become subject to the
Colorado Open Records Act, C.R.S Section 24-72-201 et. Seq.
CDOT neither requests nor encourages the submission of confidential/proprietary information in response to this RFP. All written requests for confidentiality shall be submitted with Offeror’s proposal response in strict adherence with the following procedures. Questions regarding the application of this procedure must be directed to the
Purchasing Agent facilitating this RFP.
ii. Procedure for Submission:
1. Written request for confidentiality shall be electronically submitted directly to the purchasing agent no less than 48 hours in advance of proposal submission date and deadline along with written submittal which must state specifically what elements of the proposal should/would be considered confidential/proprietary. In the subject line of the e-mail to the Purchasing Agent the vendor shall place “REQUEST FOR
CONFIDENTIAL/PROPRIETARY INFORMATION – (BID NUMBER)”. This has no bearing on the proposal submission deadline, which will remain unchanged.
2. The confidential/proprietary information submitted must be readily identified, marked and separated/packaged from the rest of the proposal
RFP 27-202832 NM Page 22 of 37 i.e., uploaded in a separate file. The written request must state
SPECIFICALLY, AND IDENTIFY BY PAGE NUMBER, what elements of the proposal are to remain confidential. The request must also IDENTIFY THE
BASIS for the claim of confidentiality. Specific reasoning, rooted in
Colorado law such as the Colorado Open Records Act and applicable case law, as to why each element is to remain confidential, other than recitation of a specific state or federal statute, is required. In other words, Offerors cannot simply cite the CORA statute; they must provide explicit reasoning.
3. If CDOT accepts the vendor request for confidentiality/proprietary information, the CDOT Purchasing Official will make a written determination as to the apparent validity of any request for confidentiality. The written determination of the Purchasing Official will be sent to the Offeror. Proposals that are determined to be at variance with this procedure may be declared non-responsive by the Purchasing
Official, and not given further consideration.
4. The proposal, along with approved confidential/proprietary information must be received by the proposal deadline listed in this document.
5. After award, the proposals shall be open to public inspection subject to any continued prohibition on the disclosure of confidential data, C.R.S.
Title 24, Article 72, Part 2 or as otherwise provided by law.
3. EVALUATION METHODOLOGY
A. EVALUATION PROCESS
A comprehensive, thorough, complete and impartial evaluation of each proposal received will be conducted in accordance with §24-103-203(7), C.R.S, which states, “The award shall be made to the responsible Offeror whose proposal is determined in writing to be the most advantageous to the state, taking into consideration the price and evaluation factors set forth in the request for proposal.”
B. Evaluation Committee
RFP 27-202832 NM Page 23 of 37
i. An Evaluation Committee will be established utilizing measures to ensure the integrity of the evaluation process. These measures include the following:
a. Selecting committee members who do not have a conflict of interest regarding this solicitation.
b. Facilitating the independent review of proposals.
c. Requiring the evaluation of the proposals to be based strictly on the content of the proposals.
d. Ensuring the fair and impartial treatment of all Offerors.
ii. The objective of the Evaluation Committee is to conduct reviews of the proposals that have been submitted, to hold frank and detailed discussions among themselves, and to recommend an Offeror for award.
C. Proposal Evaluation Criteria
i. The State will evaluate proposals to determine if each Offeror meets all mandatory qualification requirements; provided, however, that the State has the authority to waive non-material mandatory requirements in certain circumstances. Reference Procurement Rule R-24-103-301-03. The mandatory qualification requirements are scored on a Met/Not Met basis and only those proposals found to meet all mandatory requirements, other than non-material mandatory requirements waived by the State, can be considered for a Contract resulting from this solicitation.
Failure of the Offeror to provide in his/her proposal any information requested in this RFP may result in disqualification of the proposal. It is the sole responsibility of the proposing individual or firm to ensure all information requested in the RFP is included.
ii. A responsiveness checklist will be utilized by the Purchasing Agent to determine the responsiveness of the proposal. These criteria will be graded as yes, no, or non-applicable (N/A) and include:
a. Proposal received on time via BidNet Direct
b. All items are priced clearly in unit measures specified
RFP 27-202832 NM Page 24 of 37
c. No exceptions to terms or other solicitation language
d. Signature of Company Officer to the proposal/offer
e. Specs/Drawings submitted for products proposed as ‘equal’ to specified brand
f. Financial information submitted per solicitation document
g. Correct number of pages submitted per solicitation document
h. DBE and/or SDVOSB documentation included and complete
iii. The award shall be made to the responsible offeror whose proposal is determined in writing to be the most advantageous to the state, taking into consideration the price and the evaluation factors set forth in the request for proposals. No other factors or criteria shall be used in the evaluation. The contract file shall contain the basis on which the award is made. No property interest of any nature shall accrue until the contract is awarded and signed by both parties. The specifications within this RFP represent the minimum performance necessary for response.
iv. A determination of responsibility or non-responsibility shall be governed by
C.R.S. 24-103-401.
v. Standards of Responsibility:
(a) Factors to be considered in determining whether the standard of responsibility has been met include whether a prospective contractor or vendor:
1) has or can obtain the appropriate financial, material, equipment, facility, personnel resources and expertise to indicate the capability to meet all contractual requirements;
2) has a satisfactory record of performance;
3) has a satisfactory record of integrity;
4) does not appear on any debarred lists;
5) is qualified legally to contract with the state; and
6) has supplied all necessary information in connection with the inquiry concerning responsibility.
(b) The prospective contractor or vendor shall supply information requested by
RFP 27-202832 NM Page 25 of 37 the procurement official concerning the responsibility of such contractor. If such contractor or vendor fails to supply the requested information, the chief procurement officer or procurement official shall base the determination of responsibility upon any available information.
vi. Ability to Meet Standards:
The prospective contractor or vendor may demonstrate the availability of necessary financing, equipment, facilities, expertise, and personnel by submitting upon request:
(a) Evidence that such contractor possesses such necessary items;
(b) Acceptable plans to subcontract for such necessary items; or
(c) A documented commitment from, or explicit arrangement with a satisfactory source to provide the necessary items.
vii. Written Determination of Non-Responsibility Required:
If a prospective contractor or vendor who otherwise would have been awarded a contract is found to be non-responsible, a written determination of non-responsibility setting forth the basis of the finding shall be prepared by the procurement official. A copy of the determination shall be sent promptly to the non-responsible prospective contractor or vendor. The determination shall be made part of the procurement record.
viii. Proposals will be evaluated by the Evaluation Committee using the evaluation criteria listed below. The evaluators will consider whether the Scope of Work requirements in the solicitation have been addressed, and they will review the capabilities of the Offeror, as well as the quality of the approach proposed, the price, and any other aspect determined relevant to the evaluation criteria.
ix. The evaluation criteria to be used in evaluating the proposals are as follows
(and are listed in no particular order):
A. Understanding of Scope of Work & Project Approach: (25%)
Offeror described in detail how their proposal will meet or exceed the mandatory requirements detailed in Attachment A – Scope of Work. Based on the scope of work, Offeror described their overall understanding of what is
RFP 27-202832 NM Page 26 of 37 required to meet CDOT’s purpose and goals for this RFP and developed an approach that demonstrates a working knowledge of how to efficiently and effectively manage multiple and diverse tasks as follows:
1. Offeror demonstrated an understanding of the project needs and the reasons and objectives for the required work.
2. Offeror demonstrated a clear approach to executing the tasks identified in the Scope of Work effectively and wisely.
3. The proposal addressed all elements of the project in a comprehensive, creative, simple, and clearly communicated manner. The proposal may also identify additional areas to cover in the training.
4. The proposal addresses how the training can be tailored to meet the diverse needs of first responders across the state.
5. Accessibility Requirements: Materials should meet accessibility requirements (WCAG2.1 & 508 compliant) and should be easily differentiated for various audiences.
6. Mandatory Requirements: Offeror described how their proposed solution will meet or exceed the mandatory requirements detailed in this solicitation.
B. Overall Experience & Qualifications: (30%)
Offeror described how the Offeror’s experience and capabilities make it the ideal candidate to perform the work. Offeror described experience with similar projects. Proposal listed and described all relevant work experience and qualifications on activities described in Attachment A – Scope of Work, including but not limited to:
1. Offeror demonstrated proven ability to provide Rockfall and Rock Slope
Stabilization services including subtasks listed and/or Soil Slope
Stabilization services including subtasks listed.
2. Offeror provided experience with slope stabilization near highway infrastructure.
3. Offeror demonstrated expertise and familiarity with urgent need response
RFP 27-202832 NM Page 27 of 37 to geohazard events.
4. Offeror demonstrated ability to respond to geohazard events within 8 hours of notification.
14. Offeror listed references with contact information for three (3) clients where similar services have been performed by your company within the last 5 years. Included the names of the organization, contact person, phone number, e-mail address, and a brief description of the services provided. Reference checks may be performed to verify information and to ascertain the quality of the services provided. CDOT reserves the right to pursue and contact references related to projects named in the proposal; however, reference checks are not limited to contacts explicitly named in the proposal. While checking references, CDOT reserves the right to contact any individual or entity that may be relevant.
C. Project Team and Ability to Provide Services: (20%)
Offeror indicated key personnel who will be assigned to the project and described their experience to address all elements in the Scope of Work and their time availability as follows:
1. Described the key staff and other project support members who will be directly assigned to this project and the project’s team size. The role and experience of key staff was fully explained, while support staff and general experience was also identified. The Project Team was identified and included individuals experienced in all elements of this Statement of Work.
The description included the key staff members’ roles on the project, their disciplines, experience with similar projects, and their availability to work on this project and perform project tasks in a timely manner.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .