About this file

Request for Proposals Summary

This Request for Proposals (RFP) document is issued by the City of Louisville Department of Public Works Engineering Division for professional design-build services to rehabilitate an existing culvert crossing beneath South Boulder Road in Louisville, Colorado. The project involves slip lining rehabilitation of a CMP arch pipe approximately 60" x 40" located approximately 250 linear feet east of Main Street. The scope of work encompasses field investigation, hydraulic and structural analysis, engineering design, permitting coordination, construction, testing, and project closeout. A pre-proposal meeting is scheduled for November 18, 2026, at 2:00 PM MST via Microsoft Teams, with attendance highly recommended but not mandatory. Proposals must be submitted via email in PDF format to the Public Works Department and Kayla Corcelli by 2:00 PM MST on December 4, 2026, with late submissions not accepted. Contract approval and execution is anticipated by January 5, 2027, with substantial completion expected no later than December 31, 2027.

The project requires a firm, fixed lump-sum price for complete design and construction services, with separate identification of engineering design and construction costs. All slip lining and in-channel construction activities must be scheduled during the off-season from October 31 to March 31 annually, with work completion by March 31, 2027, or reinitiation after October 31, 2027 if necessary. The selected Design-Build Firm shall provide Performance and Labor and Material Payment Bonds equal to one hundred percent of the total contract amount. Liquidated damages are assessed at $1,000 per calendar day for failure to substantially complete within 150 calendar days from the commencement date. The Design-Build Firm must comply with City of Louisville standards, CDOT drainage and roadway standards, Mile High Flood District criteria, FHWA culvert rehabilitation guidance, Colorado state requirements, and OSHA safety regulations. Proposals must include team qualifications, technical approach, preliminary schedule, warranty information for the slip lining system, and at least three references for similar projects completed within the preceding five years.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposals (RFP)

To Provide

Professional Design-Build Services For

South Boulder Road Slip Lining Project (SBR Slip Lining)

RFP

November 2026

For Submittal and Presentation

To The Selection Committee

City of Louisville Department of Public Works

Engineering Division

NOTICE TO CONTRACTORS

Project Name: 2026 South Boulder Road Slip Lining Project City of Louisville Project Number: 503499-660314

Thank you for your interest in the Request for Proposals (RFP) for the South Boulder Road Slip Lining Project for Professional Design and Build Services for the City of Louisville.

Proposals (pdf format only) shall be submitted via email to the Public Works Department at pworks@louisvilleco.gov and Kayla Corcelli at kcorcelli@louisvilleco.gov by 2:00 pm M S T (City clock), F r i d a y , D e c e m b e r 4 , 2 0 2 6 , at which time proposals will be date and time stamped upon receipt. Please put the following in the email subject line: “South Boulder Road Slipline Proposal.” Only proposals received prior to the deadline noted above will be considered. No late proposals will be accepted.

A pre-proposal meeting is scheduled for Wednesday, November 18, 2026, at 2:00pm MST. This meeting will be held virtually via Microsoft Teams (link provided below).

Please contact Kayla Corcelli at kcorcelli@louisvilleco.gov if you need additional options to join the meeting. The purpose of the pre-proposal meeting is to provide assistance to interested consultants in interpretation of the Request for Proposals, Scope of Services, Sample Contract, and other technical matters. Attendance is not mandatory, but highly recommended.

Pre-proposal Meeting via Microsoft Teams Join: https://teams.microsoft.com/meet/2373757594712767?p=QJDHpc39jVpTdZZN4j Meeting ID: 237 375 759 471 276 7 Passcode: s9kr6Dy9 mailto:pworks@louisvilleco.gov mailto:kcorcelli@louisvilleco.gov mailto:kcorcelli@louisvilleco.gov https://teams.microsoft.com/meet/2373757594712767?p=QJDHpc39jVpTdZZN4j

REQUEST FOR PROPOSALS

The City of Louisville (“City”) is soliciting proposals from qualified Design-Build Firms (“Contractor” or “Design-Build Firm”) to provide professional engineering design, hydraulic analysis, permitting support, construction services, and all associated labor, materials, and equipment necessary to complete the slip lining rehabilitation of the existing culvert crossing South Boulder Road approximately 250 linear feet east of Main Street in Louisville, Colorado. The existing culvert has been determined to be in poor condition.

This project shall be delivered using a Design-Build delivery method. The selected Design-Build Firm shall be responsible for all engineering, hydraulic calculations, final design, permitting coordination, construction, testing, and project closeout services necessary to complete the Work.

The Contractor shall demonstrate through signed and sealed engineering calculations that the rehabilitated culvert maintains adequate hydraulic performance. The slip lining system shall be designed to match the hydraulic capacity of the existing pipe, assuming good condition. The Contractor will be required to verify the allowable flow rate(s) with Goodhue ditch representatives and City staff. The existing culvert is a CMP arch pipe approximately 60” x 40”.

An exhibit showing the culvert location is provided below along with images of the culvert inlet end section and outlet manhole.

Culvert Location Exhibit

South End Section Image

North Manhole Image (looking North)

North Manhole Image (looking South)

PROJECT DESCRIPTION:

The City intends to rehabilitate an existing culvert crossing beneath South Boulder Road east of Main Street. The culvert inlet is open on the south side of South Boulder Road and outlets to a manhole on the north side of South Boulder Road along the property line of the Steel Ranch South and Christopher Village developments. The culvert is in poor condition and requires installation of a slip liner system within the existing culvert structure. Hydraulic considerations must be taken into account to ensure that the rehabilitated culvert does not alter hydraulic performance enough to exceed maximum allowable flow rates as established by the Goodhue Ditch company and the City of Louisville.

The project generally includes:

• Field investigation and verification of existing culvert conditions;

• Hydraulic and structural analysis of the existing and proposed sliplined culvert;

• Preparation of engineering drawings and technical specifications;

• Acquiring any necessary permits from City of Louisville or the Goodhue Ditch

Company.

• Coordinate access by means of a temporary construction easement (NOTE: The

City will acquire the temporary construction easement with the property owner on the south side of South Boulder Road. On the north side of South Boulder Road, easements exist for access to the outlet manhole. Any additional temporary easements required on the north side will be the responsibility of the Contractor).

• Culvert cleaning and preparation;

• Installation of slip liner materials;

• Grouting and annular space filling;

• Inlet and outlet improvements as necessary;

• Erosion protection and site restoration;

• Testing and inspection services;

• Record drawings and final documentation.

The Contractor shall furnish all labor, materials, equipment, engineering, supervision, permitting, and incidentals necessary for a complete and operational project.

PROJECT OBJECTIVES:

The primary objectives of this project are:

1. Extend the useful service life of the existing culvert;

2. Minimize roadway disruption and excavation;

3. Maintain or improve structural integrity of the culvert system;

4. Ensure hydraulic performance is acceptable for the design storm event;

5. Provide a durable, long-term rehabilitation solution.

HYDRAULIC DESIGN REQUIREMENTS

The Design-Build Firm shall prepare and submit signed and sealed hydraulic calculations prepared by a Professional Engineer licensed in the State of Colorado.

The hydraulic analysis shall:

• Evaluate existing culvert capacity;

• Evaluate post-slip-line hydraulic performance;

• Demonstrate that the rehabilitated culvert does not exceed the flow rate of the existing culvert (assuming good condition) in the 100-yr storm event;

• Include headwater and tailwater analyses;

• Address energy losses associated with the proposed liner;

• Evaluate inlet and outlet control conditions;

• Include assumptions, methodologies, and modeling software utilized;

• Include all supporting calculations and exhibits.

The City reserves the right to require revisions to the design if the proposed slip lining solution adversely impacts hydraulic performance or upstream flooding conditions.

SCOPE OF SERVICES

Phase 1 – SITE ANALYSIS AND DESIGN APPROACH The Design-Build Firm shall:

• Conduct site visits and field verification;

• Verify existing culvert dimensions and condition;

• Perform CCTV inspection if necessary;

• Identify utility conflicts;

• Review available drainage and as-built information;

• Identify environmental or permitting constraints.

Phase 2 – CONCEPTUAL DESIGN:

The Design-Build Firm shall:

• Develop conceptual rehabilitation alternatives;

• Recommend appropriate slip liner material and installation method

PHASE 3 – SCHEMATIC DESIGN:

• Prepare preliminary plans

PHASE 4 – DESIGN DEVELOPMENT: Upon approval of Schematic Designs and authorization from the City to proceed, the Design-Build Firm shall prepare Design Development documents. These Development Documents shall be the basis for the design and construction of the Project and shall include:

• Prepare hydraulic calculations;

• Prepare structural calculations;

• Prepare traffic control plans;

• Prepare construction drawings and technical specifications;

• Coordinate with regulatory agencies as required.

Deliverables shall include:

• 30% Design Submittal;

• 60% Design Submittal;

• Final Design Package.

All design documents shall be stamped by a Professional Engineer licensed in Colorado.

PHASE 5 – CONSTRUCTION SPECIFICATIONS AND CONSTRUCTION: From approved Final Design Development Documents, the Design-Build Firm will prepare construction drawings and Specifications setting forth in detail the requirements for the construction of the Project, and based upon codes, laws, or regulations.

Construction:

The Design-Build Firm shall:

• Acquire all necessary permits including but not limited to Goodhue Ditch permit, City of Louisville Right-of-Way permit

• Furnish all labor, materials, and equipment;

• Implement traffic control;

• Clean and prepare existing culvert;

• Install slip liner system;

• Perform annular grouting operations;

• Restore disturbed areas;

• Conduct testing and inspections;

• Coordinate all construction activities with the City.

The Contractor shall maintain access and minimize impacts to South Boulder Road traffic throughout construction. The existing ditch and culvert crossing must remain active during the irrigation season. Unless otherwise approved in writing by the City, all slip lining and associated in-channel construction activities shall be scheduled during the off-season, which extends from October 31st to March 31st annually. If the in-channel work cannot be completed by March 31st, 2027, it must be initiated after October 31st, 2027.

There may be some flexibility with the ditch company on these dates pending anticipated flowrates. Work outside of the channel, such as site restoration, may continue during the irrigation season from March 31st to October 31st. Substantial completion is expected no later than December 31st, 2027.

1. The Design-Build Firm and the City will work closely together to monitor the design in accordance with prior approvals so as to ensure that the Project can be constructed within the amount of time as defined above.

As Construction Drawings and Specifications are being completed, the Design-Build Firm will keep the City advised of the effects of any City requested changes on the Contract Time Schedule and/or the Total Contract Amount. Construction of the Project shall be in accordance with these Drawings and Specifications as approved by the City and incorporated in exhibits. These Drawings and Specifications shall remain the property of the City and may be used by the City on this or other projects without the written consent of the Design-Build Firm.

DESIGN CRITERIA

The proposed design shall comply with:

• City of Louisville standards;

• CDOT drainage and roadway standards;

• Mile High Flood District criteria;

• Applicable FHWA culvert rehabilitation guidance;

• State of Colorado requirements;

• OSHA safety regulations.

WARRANTY REQUIREMENTS

The proposal shall clearly identify all warranties associated with the proposed slip lining system and installation.

At a minimum, the proposal shall include:

• Manufacturer’s warranty for liner materials;

• Contractor workmanship warranty;

• Warranty duration periods;

• Description of covered defects or failures;

The City prefers long-term material performance warranties and reserves the right to consider warranty provisions during proposal evaluation.

TENTATIVE RFP & PROJECT SCHEDULE:

1st Advertisement .............................................................................. November 11, 2026 2nd Advertisement…………………………………………………………November 16, 2026 Pre-Proposal Meeting ....................................................................... November 18, 2026 Questions Deadline .......................................................................... November 20, 2026 Proposal Submission Deadline ......................................................... ..December 4, 2026 Contract Approval / Execution……………………………………………....January 5, 2027 Substantial Completion…………………………………………….…….December 31, 2027

PROPOSAL REQUIREMENTS

Proposals shall include the following:

1. Cover Letter

Address the cover or introductory letter to:

Emma Boff, P.E.

Civil Engineer II Department of Public Works City of Louisville 749 Main Street Louisville, CO 80026

Include the following elements of information in the letter at a minimum:

• Project location.

• Certification that the information and data submitted in true and complete to the best knowledge of the individual signing the letter.

• Name, email address, and telephone number of the individual to contact regarding their submittal.

• City of Louisville requires an original signature signed in ink, by a representative of the firm fully authorized to submit proposals and sign contracts on the firm’s behalf.

The letter shall include a statement to that effect.

• Acknowledgement of all addenda issued.

2. Team Qualifications Include:

• Company background;

• Relevant culvert rehabilitation experience;

• Design-Build experience;

• Key personnel resumes;

• Colorado licensure information.

3. Technical Approach Describe:

• Proposed slip lining methodology;

• Hydraulic evaluation approach;

• Structural design approach;

• Construction sequencing;

• Traffic control strategy;

• Risk mitigation measures.

4. Preliminary Schedule Provide a detailed project schedule including design and construction phases.

5. Cost Proposal Proposers shall submit a firm, fixed lump-sum price for the complete design and construction of the project. The price shall include all engineering, permitting, materials, labor, equipment, construction, testing, restoration, and incidental work necessary to provide a complete and operational pipe rehabilitation system meeting the performance requirements outlined in this RFP. Proposers shall separately identify the lump-sum cost for engineering design and construction. The combined amount shall constitute the total proposed design-build contract price. The proposed price shall include all costs associated with completing and refining the design to satisfy the performance requirements. Contract price adjustments shall be permitted only for authorized changes in scope or as otherwise expressly provided in the contract.

6. Warranty Information Provide:

• Proposed material warranty terms;

• Workmanship warranty terms;

• Expected service life of the proposed liner system;

• Manufacturer support information.

7. References Provide at least three references for similar projects completed within the last five years.

STANDARD TERMS AND CONDITIONS

When preparing a proposal for submission in response to this RFP, proposers should be aware of the following terms and conditions which have been established by the City of Louisville:

• This request for proposals is not an offer to contract. The provisions in this RFP and any purchasing policies or procedures of the City are solely for the fiscal responsibility of the City, and confer no rights, duties or entitlements to any party submitting proposals. The City of Louisville reserves the right to reject any and all proposals, to consider alternatives, to waive any informalities and irregularities, and to re-solicit proposals.

• The City of Louisville reserves the right to conduct such investigations of and discussions with those who have submitted proposals or other entities as they deem necessary or appropriate to assist in the evaluation of any proposal or to secure maximum clarification and completeness of any proposal.

• The successful proposer shall be required to sign a contract with the City in a form provided by and acceptable to the City. The contractor shall be an independent contractor of the City.

• The City of Louisville assumes no responsibility for payment of any expenses incurred by any proponent as part of the RFP process.

• The following criteria will be used to evaluate all proposals:

o The proposer’s interest in the services which are the subject of this RFP, as well as their understanding of the scope of such services and the specific requirements of the City of Louisville.

o The reputation, experience, and efficiency of the proposer.

o The ability of the proposer to provide quality services within time and funding constraints.

o The general organization of the proposal: Special consideration will be given to submittals which are appropriate, address the goals; and provide in a clear and concise format the requested information.

o Other selection factors within this RFP or the City’s purchasing policies, or that City determines are relevant to consideration of the best interests of the City.

• All responses to this RFP become the property of the City upon receipt and regardless of selection or rejection, and will not be returned, except that the City may return late responses submitted after the response deadline. Any trade secrets or confidential commercial or financial information submitted with any response is subject to potential disclosure, and submitting it constitutes proposer’s waiver of any recourse against the City in respect to disclosure and proposer’s agreement to indemnify the City for any costs, legal fees or expenses incurred in relation to any proceeding concerning disclosure of such information.

Any trade secrets for confidential commercial or financial information submitted with a response shall be clearly segregated and marked; provided; however, that neither cost information nor the total RFP will be considered proprietary. The City will notify the proposer of any request for disclosure of information so segregated and marked that may be subject to nondisclosure, and it will be the responsibility of the proposer to object and to pursue any legal actions pursuant to Colorado law. A proposer hall notify the City within 24 hours of notification by City of request for disclosure of the proposer’s objections to disclosure and the proposer’s intent to pursue lawful protection under Colorado law.

SAMPLE AGREEMENT

AGREEMENT

THIS AGREEMENT is made and entered into this _____ ___ day of __________ in the year 2026 by and between:

CITY OF LOUISVILLE, COLORADO

(hereinafter called OWNER or CITY) and

(hereinafter called DESIGN-BUILD FIRM or CONTRACTOR)

WHEREAS, CITY desires to acquire the services of DESIGN-BUILD FIRM to complete the South Boulder Road Slip Lining Project, City Project Number: 503499-660314 (the “Project”), at South Boulder Road (the “Project Site”).

NOW, THEREFORE, in consideration of the mutual covenants hereinafter set forth, OWNER and DESIGN-BUILD FIRM agree as follows.

SECTION 1. CONTRACT DOCUMENTS.

A. The Contract Documents consist of this Agreement, the Amendments, and Exhibits described in Section 6 hereof, Change Orders, Work Directive Changes, Field Orders and the solicitation documents, including addenda relating thereto. All of the foregoing Contract Documents are incorporated by reference and made part of this Agreement (all of said documents, including this Agreement, being referred to herein as the “Contract Documents”). A copy of the Contract Documents shall be maintained by Design-Build Firm at the Project Site at all times during the performance of the Work.

B. In case of any inconsistency or conflict among the provisions of the Agreement and any other terms and conditions of any documents comprising the Contract Documents, the provisions of the Agreement shall control. Concerning the Contract Documents, the order of precedence shall be as follows: (1) The Agreement, including Amendments and Exhibits; (2) Change Orders; (3) Work Directive Changes; (4) Field Orders; and (5) the Solicitation Documents, including addenda. The Contract Documents listed above represent the entire agreement between parties hereto, and supersede prior negotiations, representations, or agreements, either written or oral.

C. City shall furnish to the Design-Build Firm up to three (3) sets of the Contract Documents for execution of the Work. Additional copies of the Contract Documents shall be furnished upon request, at the cost of reproduction.

SECTION 2. SCOPE OF WORK.

B. Generally, Design-Build Firm will provide all planning, design, and architectural/engineering services required for the proper design of, and all labor, materials, supplies and other items and services necessary for the construction of the Project (“Work”) as set forth in Exhibit T, Scope of Work, and for all other services necessary for the construction of the Project.

C. Design-Build Firm’s Responsibility with respect to design phase of the Project (also referred to as the Design Phase).

1. The Design-Build Firm shall prepare and the City shall approve a Design Phase schedule, including the following:

Phase 1 – SITE ANALYSIS AND DESIGN APPROACH

• Conduct site visits and field verification;

• Verify existing culvert dimensions and condition;

• Perform CCTV inspection if necessary;

• Identify utility conflicts;

• Review available drainage and as-built information;

• Identify environmental or permitting constraints.

Phase 2 – CONCEPTUAL DESIGN:

• Develop conceptual rehabilitation alternatives;

• Recommend appropriate slip liner material and installation method

PHASE 3 – SCHEMATIC DESIGN:

• Prepare preliminary plans, develop project budget.

PHASE 4 – DESIGN DEVELOPMENT: Upon approval of Schematic Designs and authorization from the City to proceed, the Design-Build Firm shall prepare Design Development documents to fix the size and character of the project as to structural, mechanical, materials, and other appropriate essential items in the Project. These Development Documents shall be the basis for the design and construction of the Project and shall include:

• Prepare hydraulic calculations;

• Prepare structural calculations;

• Prepare traffic control plans;

• Prepare construction drawings and technical specifications;

• Coordinate with regulatory agencies as required.

Deliverables shall include:

• 30% Design Submittal;

• 60% Design Submittal;

• Final Design Package.

All design documents shall be stamped by a Professional Engineer licensed in Colorado.

PHASE 5 – CONSTRUCTION SPECIFICATIONS AND CONSTRUCTION: From approved Design Development Documents, the Design-Build Firm will prepare construction drawings and Specifications setting forth in detail the requirements for the construction of the Project, and based upon codes, laws, or regulations.

Construction:

The Design-Build Firm shall:

• Furnish all labor, materials, and equipment;

• Implement traffic control;

• Clean and prepare existing culvert;

• Install slip liner system;

• Perform annular grouting operations;

• Restore disturbed areas;

• Conduct testing and inspections;

• Coordinate all construction activities with the City.

The Contractor shall maintain access and minimize impacts to South Boulder Road traffic throughout construction. The existing ditch and culvert crossing may remain active during the irrigation season.

All slip lining and associated in-channel construction activities shall therefore be scheduled during the off-season beginning October 31 unless otherwise approved in writing by the City.

2. The Design-Build Firm and the City will work closely together to monitor the design in accordance with prior approvals so as to ensure that the Project can be constructed within the amount of time as defined in Section 5. As Construction Drawings and Specifications are being completed, the Design-Build Firm will keep the City advised of the effects of any City requested changes on the Contract Time Schedule and/or the Total Contract Amount. Construction of the Project shall be in accordance with these Drawings and Specifications as approved by the City and incorporated in exhibits. These Drawings and Specifications shall remain the property of the City and may be used by the City on this or other projects without the written consent of the Design-Build Firm.

SECTION 3. CONTRACT AMOUNT.

In consideration of the faithful performance by Design-Build Firm of the Work to the full satisfaction and acceptance of City, City shall pay the Design-Build Firm, in accordance with Exhibit V, Fee Schedule, for Work requested and rendered under this Agreement, a total not to exceed ________________ DOLLARS, $_________ ( “Total Contract Amount”).

A. Design Phase fees. For the performance of the design services set forth herein and for profit and overhead related to these services, a total not to exceed fee of $___________ shall be paid to the Design-Build Firm. The Pre-Construction Phase Fee for the Project shall be paid in monthly payments. The first monthly payment shall become due thirty (30) days following the issuance by the City of the Notice To Proceed with design services for the Project and monthly thereafter based on the project schedule and approval by City of design deliverables.

B. Construction Phase Fee. Prior to commencement of the Construction Phase of the Project, the City will direct the Design-Build firm in writing to proceed with the Construction Phase. The Design-Build Firm’s compensation for services performed during the Construction Phase shall be a total not to exceed fee of $________, which amount includes a maximum $________ for general conditions expense and a contingency of $_______. No portion of the contingency shall be paid or applied to the Project except upon execution of a Change Order signed by both parties. The Construction Phase Fee shall be paid in monthly payments. The first monthly payment shall become due thirty (30) days following the issuance of the Construction Phase Notice to Proceed by the City. The final monthly payment shall be paid only when construction of the Project is finally completed and occupancy of is accepted by the City, and only after final settlement and all other conditions to final payment have been satisfied. If construction is authorized only for a part of the Project, the fee paid shall be proportionate to the amount of work authorized by the City.

SECTION 4. BONDS.

A. Design-Build Firm shall provide Performance and Labor and Material Payment Bonds, in the form prescribed in Exhibit B, in the amount of one hundred (100%) of the Total Contract Amount, the cost of which shall be paid by Design-Build Firm.

B. If the surety for any bond furnished by Design-Build Firm is declared bankrupt, becomes insolvent, its right to do business is terminated in the State of Colorado, or it ceases to meet the requirements imposed by the Contract Document, the Design-Build Firm shall, within five (5) calendar days thereafter, substitute another bond and surety, both of which shall be subject to the City’s approval. Failure by the Design-Build Firm to maintain its bonds in full force and effect at all times, including the warranty period, shall be grounds for termination of the Agreement.

SECTION 5. CONTRACT TIME AND LIQUIDATED DAMAGES.

A. Time is of the essence in the performance of the Work under this Agreement. Design-Build Firm shall commence the Work within ten (10) calendar days from the commencement date established in each Phase’s Notice to Proceed (“Commencement Date”). No Work shall be performed at the Project Site prior to such Commencement Dates. Design-Build Firm shall provide forty-eight (48) hours’ notice prior to beginning the Work. The Work shall be substantially completed within one hundred and fifty (150) calendar days from the Commencement Date. The work shall be fully completed and deemed ready by the City for final completion within thirty (30) calendar days from Substantial Completion Date. The Contract Time shall be the time period from the Commencement Date to the date of final completion totaling one hundred and eighty (180) calendars days (“Contract Time”).

B. City and Design-Build Firm recognize that, since time is of the essence for this Agreement, the City will suffer financial loss if the Work is not substantially completed within the time specified in the Scope of Work. Should Design-Build Firm fail to substantially complete the Work within the time period noted above, City shall be entitled to assess, as liquidated damages, but not as a penalty, One Thousand DOLLARS, $1,000 for each calendar day thereafter until Substantial Completion is achieved. The Project shall be deemed to be substantially completed by the City on the date the City’s Representative certifies in writing that the Project, or specified part thereof, is sufficiently completed in accordance with the Contract Documents, so that the Project or specified part can be utilized for the purposes for which it is intended. Along with such certification, the Owner shall compile a “punch list” of any remaining exceptions that do not adversely affect the use of the Project. Completion of these items will be required prior to final payment as provided in the Fee Schedule.

C. Design-Build Firm hereby expressly waives and relinquishes any right which it may have to seek to characterize the above noted liquidated damages as a penalty, which the parties agree represents a fair and reasonable estimate of the City’s actual damages at the time of contracting if Design-Build Firm fails to substantially complete the Work in accordance with the progress schedule.

D. When any period of time is referenced to by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday or legal holiday.

E. Design-Build Firm’s Exclusive Remedy: In the event the construction Substantial or Final Completion date is extended, regardless of whether delay is caused by an act or neglect of the City, or is attributable to the City, the Design-Build Firm’s sole and exclusive remedy is an extension of the of the construction completion date.

SECTION 6. EXHIBITS INCORPORATED

The following documents are expressly agreed to be incorporated by reference and made a part of this Agreement.

Exhibit A: General Terms and Conditions Exhibit B: Forms of Performance Bond and Labor and Material Payment Bond Exhibit C: Notice of Award Exhibit D: Notice to Proceed Exhibit E: Form Change Order Exhibit F: Form of Field Order Exhibit G: Work Change Directive Instructions Exhibit H: Form of Work Change Directive

Exhibit I: Sample Form of Application for Payment Exhibit J: Form of Contractor’s Proposal Request Exhibit K: Form of Contractor’s Overtime Request Exhibit L: Form of Claim Release Exhibit M: Insurance and Safety Exhibit N: Form of Certificate of Substantial Completion Exhibit O: Form of Final Inspection Report Exhibit P: Form of Certificate of Final Completion Exhibit Q: Form of Guarantee Inspection Report Exhibit R: Contract Definitions Exhibit S: Scope of Work Exhibit T: Project Schedule Exhibit U: Fee Schedule

SECTION 7. NOTICES

A. All notices required or made pursuant to this Agreement by the Design-Build Firm to the City shall be in writing and delivered by hand or by United States Postal Service Department, first class mail, postage pre-paid, return receipt requested, addressed to the following:

City of Louisville 749 Main Street Louisville, Colorado 80027 Attention: Cameron Fowlkes, PE

B. All notices required or made pursuant to this Agreement by City to Design-Build

Firm shall be made in writing and shall be delivered by hand or by United States Postal Service Department, first class mail, postage pre-paid, return receipt requested, addressed to the following:

Contractor

Street Address City, State

Attention: _______________

C. Either party may change its above-noted address by giving written notice to the other party in accordance with the requirements of this Section.

SECTION 8. MODIFICATION

No modification or change to this Agreement shall be valid or binding upon the parties unless in writing and executed by the party or parties intended to be bound by it.

SECTION 9. SUCCESSORS AND ASSIGNS

Subject to other provisions hereof, this Agreement shall be binding upon and shall inure to the benefit of the successors and assigns of the parties to the Agreement.

SECTION 10. GOVERNING LAW

This Agreement shall be deemed entered into in Boulder County, Colorado, and shall be governed by and interpreted under the laws of the State of Colorado. Any action arising out of, in connection with, or relating to this Agreement shall be filed in the District Court of Boulder County of the State of Colorado and in no other court or jurisdiction.

SECTION 11. NO WAIVER

The failure of the City to enforce at any time or for any period of time any one or more of the provisions of the Agreement shall not be construed to be and shall not be a waiver of any such provision or provisions or of its right thereafter to enforce each and every such provision.

SECTION 12. ENTIRE AGREEMENT

Each of the parties hereto agrees and represents that the Agreement comprises the full and entire agreement between the parties affecting the Work contemplated, and no other agreement or understanding of any nature concerning the same has been entered into or will be recognized, and that all negotiations, acts, work performed, or payments made prior to the execution hereof shall be deemed merged in, integrated and superseded by the Agreement.

SECTION 13. SEVERABILITY

Should any provision of the Agreement be determined by a court to be unenforceable, such a determination shall not affect the validity or enforceability of any other section or part thereof.

IN WITNESS WHEREOF, OWNER and DESIGN-BUILD FIRM have signed this Agreement in duplicate. One counterpart each has been delivered to OWNER and CONTRACTOR. All portions of the Contract Documents have been signed, initialed or identified by OWNER and CONTRACTOR.

This Agreement will be effective on __________________, 2026.

OWNER: CITY OF LOUISVILLE,

COLORADO

By: _____________________________ Christopher Leh, Mayor

Attest: ___________________________ Genny Kline, City Clerk

DESIGN-BUILD FIRM:

By:_____________________________________ Name: __________________________________

Title: __________________________________

ATTEST:

By:_______________________________ Name, Title

EXHIBIT A

GENERAL TERMS AND CONDITIONS

1. INTENT OF CONTRACT DOCUMENTS

1.1. It is the intent of the Contract Documents to describe a functionally complete project (or portion thereof) to be constructed in accordance with the Contract Documents. Any work, materials or equipment that may reasonably be inferred from the Contract Documents as being required to produce the intended result shall be supplied whether or not specifically called for. When words which have a well known technical or trade meaning are used to describe work, materials or equipment, such words shall be interpreted in accordance with that meaning.

Reference to standard specifications, manuals or codes of any technical society, organization or association or to the laws or regulations of any governmental authority having jurisdiction over the Project, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, law or regulation in affect at the time the Work is performed, except as may be otherwise specifically stated herein.

1.2. If during the performance of the Work Design-Build Firm discovers a conflict, error or discrepancy in the Contract Documents, Design-Build Firm immediately shall report same to the City in writing, and before proceeding with the Work affected thereby shall obtain a written interpretation or clarification from the Design-Build Firm’s Architect/Engineer. Design-Build Firm shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to Design-Build Firm with the Contract Documents before commencing any portion of the Work.

1.3. Drawings are intended to show general arrangements, design and extent of Work and are not intended to serve as shop drawings. Specifications are separated into divisions for convenience of reference only and shall not be interpreted as establishing divisions for the Work, trades, subcontracts, or extent of any part of the Work. In the event of a discrepancy between or among the drawings, specifications of other Contract Document provisions, Design-Build Firm shall be required to comply with the provision which is the more restrictive or stringent requirement upon the Design-Build Firm, as determined by its Architect/Engineer. Unless otherwise specifically mentioned, all anchors, bolts, screws, fittings, fillers, hardware, accessories, trim and other parts required in connection with any portion of the Work to make a complete, serviceable, finished and first quality installation shall be furnished and installed as part of the Work, whether or not called for by the Contract Documents.

2. INVESTIGATION AND UTILITIES

2.1 Design-Build Firm shall have the sole responsibility of satisfying itself concerning the nature and location of the Work and the general and local conditions, and particularly, but without limitation, with respect to the following: those affecting transportation, access, disposal, handling and storage of materials; availability and quality of labor; water and electric power; availability and condition of roads; work area; living facilities; climatic conditions and seasons; physical conditions at the Project Site; topography and ground surface conditions; nature and quality of the surface materials to be encountered; equipment and facilities needed preliminary to and during performance of the Work; and all other costs associated with such performance. The failure of Design-Build Firm to acquaint itself with any applicable conditions shall not relieve Design-Build Firm from any of its responsibilities to perform under the Contract Documents, nor shall it be considered the basis for any claim for additional time or compensation.

2.2. Design-Build Firm shall locate all existing roadways, railways, drainage facilities and utility services above, upon, or under the Project Site, said roadways, railways, drainage facilities and utilities being referred to in this Section 2 as the "Utilities". Design-Build Firm shall contact the owners of all Utilities to determine the necessity for relocating or temporarily interrupting any Utilities during the construction of the Project. Design-Build Firm shall schedule and coordinate its Work around any such relocation or temporary service interruption. Design- Build Firm shall be responsible for properly shoring, supporting and protecting all Utilities at all times during the course of the Work.

3. PROGRESS PAYMENTS FOR CONSTRUCTION PHASE

3.1. Prior to submitting its first Application for Payment, Design-Build Firm shall submit to City, for its review and approval, a schedule of values based upon the Total Contract Price, listing the major elements of the Work and the dollar value for each element. After its approval by the City, this schedule of values shall be used as the basis for the Design-Build Firm's Applications for Payment. This schedule shall be updated and submitted along with a completed and notarized copy of the Application for Payment form attached to the Agreement as Exhibit I.

3.2. Prior to submitting its first Monthly Application for Payment, Design-Build Firm shall submit to City a complete list of all its proposed subcontractors and materialmen, showing the work and materials involved and the dollar amount of each proposed subcontract and purchase order. The first Application for Payment shall be submitted no earlier than thirty (30) days after Commencement Date of construction.

3.3. If payment is requested on the basis of materials and equipment not incorporated into the Project, but delivered and suitably stored at the Project Site or at another location agreed to by the City in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that upon payment by City, the City shall receive the materials and equipment free and clear of all liens, charges, security interests and encumbrances, together with evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect City’s interest therein, all of which shall be subject to the City's prior written approval.

3.4. Design-Build Firm shall submit three (3) copies of each of its Applications for Payment to the City on or before the 25th day of each month for work performed during the previous month. Invoices received after the 25th day of each month shall be considered for payment as part of the next month's application. Within ten (10) calendar days after receipt of each Application for Payment, the City shall either: (1) indicate approval of the requested payment; (2) indicate approval of only a portion of the requested payment, stating in writing the reasons therefore; or (3) return the Application for Payment to the Design-Build Firm indicating, in writing, the reason for refusing to approve payment. In the event of a total or partial denial of the Application for Payment, the Design-Build Firm may make the necessary corrections and resubmit the Application for Payment for reconsideration within ten (10) calendar days of receiving notice of refusal.

If re-submittal of the Application for Payment is refused, in whole or in part, the Design-

Build Firm may submit a written request to the City’s Representative for an administrative decision within two (2) business days of receiving notice of refusal. Upon receiving a timely request, an administrative decision shall be rendered within ten (10) calendar days with written notification provided to the Design-Build Firm.

3.5. Except for applications for payment for Work performed relating to the Design Phase as specified in the Scope of Work, City shall retain five percent (5%) of the gross amount of each monthly payment request or five percent (5%) of the portion thereof approved by the City for payment, whichever is less, up to one hundred percent (100%) completion. Such sum shall be accumulated and not released to Design-Build Firm until final payment is due. Any interim interest on such sums shall accrue to City.

Due to circumstances beyond the Design-Build Firm’s control and at the City’s sole discretion, a percentage of the amount retained from the gross amount of each monthly payment may be reduced prior to final completion of the Project and said percentage released to Design- Build Firm upon receiving a certificate of substantial completion and approval from the Architect/Engineer. Release of any portion or percentage of sums retained prior to final completion of the Project shall in no way imply approval or acceptance of Contractor’s work.

3.6. Monthly payments to Design-Build Firm shall in no way imply approval or acceptance of Design-Build Firm's work.

3.7. Each Application for Payment shall include or be accompanied by release and certification provisions acceptable to the City certifying that all materials, labor, equipment and other bills associated with that portion of the Work payment is being requested or have been paid in full. The City shall not be required to make payment until and unless such certification furnished by Design-Build Firm.

4. PAYMENTS WITHHELD

4.1. The City may decline to approve any Application for Payment, or portions thereof, because of subsequently discovered evidence or subsequent inspections. The City may nullify the whole or any part of any approval for payment previously issued and City may withhold any payments otherwise due Design-Build Firm under this Agreement, to such extent as may be necessary in the City’s opinion to protect it from loss because of: (a) defective Work not remedied;

(b) third party claims filed or reasonable evidence indicating probable filing of such claims; (c) failure of Design-Build Firm to make payment properly to subcontractors or for labor, materials or equipment; (d) reasonable doubt that the Work can be completed for the unpaid balance of the Total Contract Amount; (e) reasonable indication that the Work will not be completed within the Contract Time; (f) unsatisfactory prosecution of the Work by the Design-Build Firm; or (g) any other material breach of the Contract Documents. If these conditions are not remedied or removed, City may, after three (3) days written notice, rectify the same at Design-Build Firm's expense. City also may offset against any sums due Design-Build Firm the amount of any liquidated or un-liquidated obligations of Design-Build Firm to City relating to or arising out of this Agreement.

5. FINAL PAYMENT

5.1. City shall make final payment to Design-Build Firm within thirty (30) calendar days after the Work is finally inspected and accepted by City in accordance with Section 19.1 herein provided.

5.2. Design-Build Firm's acceptance of final payment shall constitute a full waiver of any and all claims by Design-Build Firm against City arising out of this Agreement or otherwise relating to the Project, except those previously made in writing and identified by Design-Build Firm as unsettled at the time of the final Application for Payment. Neither the acceptance of the Work nor payment by City shall be deemed to be a waiver of City’s right to enforce any obligations of Design-Build Firm hereunder or to the recovery of damages for defective Work not discovered by the City at the time of final inspection.

6. SUBMITTALS AND SUBSTITUTIONS

6.1. Design-Build Firm shall carefully examine the Contract Documents for all requirements for approval of materials to be submitted such as shop drawings, data, test results, schedules and samples. Design-Build Firm shall submit all such materials at its own expense and in such form as required by the Contract Documents in sufficient time to prevent any delay in the delivery of such materials and the installation thereof.

6.2. Whenever materials or equipment are specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular supplier, the naming of the item is intended to establish the type, function and quality required. Unless the name is followed by words indicating that no substitution is permitted, materials or equipment of other suppliers may be accepted by City if sufficient information is submitted by Design-Build Firm to allow the City to determine that the material or equipment proposed is equivalent or equal to that named. Requests for review of substitute items of material and equipment will not be accepted by City from anyone other than Design-Build Firm and all such requests must be submitted by Design-Build Firm to City within thirty (30) calendar days after Notice of Award is received by Design-Build Firm.

6.3. If Design-Build Firm wishes to furnish or use a substitute item of material or equipment, Design-Build Firm shall make application to the City for acceptance thereof, certifying that the proposed substitute shall perform adequately the functions and achieve the results called for by the general design, be similar and of equal substance to that specified and be suited to the same use as that specified. The application shall state that the evaluation and acceptance of the proposed substitute will not prejudice Design-Build Firm's achievement of substantial completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for the Project) to adapt the design to the proposed substitute and whether or not incorporation or use by the substitute in connection with the Work is subject to payment of any license fee or royalty.

All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service shall be indicated. The application also shall contain an itemized estimate of all costs that will result directly or indirectly from acceptance of such substitute, including costs for redesign and claims of other contractors affected by the resulting change, all of which shall be considered by the City in evaluating the proposed substitute.

The City may require Design-Build Firm to furnish at Design-Build Firm's expense additional data about the proposed substitute.

6.4. If a specific means, method, technique, sequence or procedure of construction is indicated in or required by the Contract Documents, Design-Build Firm may furnish or utilize a substitute means, method, sequence, technique or procedure of construction acceptable to the City, if Design-Build Firm submits sufficient information to allow the City to determine that the substitute proposed is equivalent to that indicated or required by the Contract Documents. The procedures for submission to and review by the City shall be the same as those provided herein for substitute materials and equipment.

6.5. The City shall be allowed a reasonable time within which to evaluate each proposed substitute. The City shall be the sole judge of acceptability, and no substitute will be ordered, installed or utilized without the City’s prior written acceptance which shall be evidenced by either a Change Order or an approved Shop Drawing. The City may require Design-Build Firm to furnish at Design-Build Firm's expense a special performance guarantee or other surety with respect to any substitute.

7. DAILY REPORTS, AS-BUILTS AND MEETINGS

7.1. Unless waived in writing by City, during the Construction Phase, Design-Build Firm shall complete and submit to the City on a weekly basis a daily log of the Design-Build Firm's work for the preceding week in a format approved by the City. The daily log shall document all activities of Design-Build Firm at the Project Site including, but not limited to, the following:

7.1.1. Weather conditions showing the high and low temperatures during work hours, the amount of precipitation received on the Project Site, and any other weather conditions which adversely affect the Work;

7.1.2. Soil conditions which adversely affect the Work;

7.1.3. The hours of operation by Design-Build Firm and subcontractor personnel;

7.1.4. The number of Design-Build Firm and subcontractor personnel present and working at the Project Site, by subcontract and trade;

7.1.5. All equipment present at the Project Site, description of…