About this file
This Request for Bids (RFB No. 38-2026) is issued by the City of Boulder, Colorado, through its Utilities Department, for the rehabilitation of approximately 56,194 linear feet of sanitary sewer using fold-and-form PVC liners within the City's wastewater service area. The work scope includes service reinstatements, cleaning and CCTV inspections, quality control testing, bypass pumping, mobilization, and traffic control, with work locations and quantities subject to change per contract documents. The RFB was issued on November 10, 2026, with an optional virtual pre-bid meeting scheduled for November 18, 2026, at 1:00 p.m. Mountain Time. Written questions must be submitted by 5:00 p.m. Mountain Time on November 30, 2026. Bids are due by 4:00 p.m. Mountain Time on December 3, 2026, via electronic submission through the Bidnet Direct portal. The successful bidder is expected to be selected on December 14, 2026, and must sign a contract within 15 days of acceptance of the award. The substantial completion deadline is December 31, 2027, with final completion required no later than 30 days after substantial completion.
Awards will be made to the lowest responsible and qualified bidder based on initial cost and life-cycle cost considerations, including maintenance and energy efficiency factors. A bid bond equal to 5 percent of the total bid amount is required. The contract is structured as a unit price contract with a maximum appropriated amount of $4,000,000. Contractor shall maintain performance bonds, labor and material bonds, and required insurance within ten calendar days of award notification. The project is subject to Colorado labor requirements, stipulating that at least 80 percent of each class of skilled and common labor must be Colorado labor. Liquidated damages are set at 0.1 percent of the contract price per day of delay past the substantial completion deadline. All bid submissions are public records subject to disclosure under the Colorado Open Records Act, and the City reserves the right to reject any or all bids, waive irregularities, negotiate contract terms, or cancel the solicitation. Electronic submissions through Bidnet are mandatory, with late submissions permitted only in extraordinary circumstances demonstrating good cause due to technical issues.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Boulder, CO RFB No. 38-2026
CITY OF BOULDER, COLORADO
Finance Department / Purchasing Division 1136 Alpine P.O. Box 791 Boulder, Colorado 80306 Telephone: 720-564-2039 Email: woodss@bouldercolorado.gov
REQUEST FOR BIDS
RFB NO. 38-2026
2027 Sewer Rehabilitation
ISSUE DATE: Tuesday, November 10, 2026
DUE DATE: 4:00 PM, Thursday, December 3, 2026
Bids to be electronically saved to the Bidnet website PRIOR TO Proposal Due Date and Time above.
CONTACT:
Chris Olson
Wastewater Engineering Supervisor 303-441-3293 olsonc@bouldercolorado.gov mailto:olsonc@bouldercolorado.gov
CITY OF BOULDER
NOTICE OF REQUEST FOR BIDS
RFB NO. 38-2026
2027 SEWER REHABILITATION
The City of Boulder (“City”), by and through its Utilities Department, is seeking a qualified contractor to rehabilitate approximately 56,194 linear feet of sanitary sewer using fold-and-form PVC liners in the City's wastewater service area. The work also includes service reinstatements, cleaning and CCTV inspections, QC testing, bypass pumping, mobilization, and traffic control. Work locations and quantities are subject to change in accordance with the Contract Documents.
Bidnet – Required. Solicitation documents will be issued electronically only. A copy of this Request for Bids (RFB) must be obtained only from the Rocky Mountain E-Purchasing System (Bidnet) at:
www.bidnetdirect.com/colorado. Any modifications to this RFB or addenda pertaining to this RFB will be published to the above-mentioned website, and all bidders are responsible to periodically check the website for relevant updates prior to the submittal of a proposal.
Response to RFB. The City will only accept electronic submissions saved to the Bidnet website in response to this RFB. Electronic submissions are required to be considered for an award. To submit your RFB, please visit www.bidnetdirect.com/colorado. Please authorize receiving notices through Bidnet relating to this procurement.
Insurance. This solicitation includes desired contractual insurance provisions. The City is open to alternative insurance policies and considerations. Proposers should not avoid proposing merely due to insufficient insurance. The City is open to alternative policy limits or language, subject to ultimate approval of the City's Risk Manager.
Deadline. The submission deadline is Thursday, December 3, 2026, at 4:00 p.m. Mountain Time. This deadline is mandatory. You must save your submission to the Bidnet website before the deadline. Failure to do so may result in an inability to submit a response that is automatically implemented in the software. Except as set forth herein, no exceptions will be allowed. The City specifically reserves the right to reject late submissions.
Technical Submission Issues. In extraordinary circumstances, the City may permit late submissions if the City, in its sole discretion, determines the bidder has shown good cause due to technical issues. If you experience problems submitting your electronic response, please contact the Bidnet Direct technical support team (800-835-4603) prior to the submission deadline and document the technical errors and your efforts to resolve the same before the submission deadline. Bidders are encouraged to document that their Bidnet submission was saved in case technical issues arise or are later discovered. Your documentation may include e-mailing your submission to woodss@bouldercolorado.gov provided such submission is emailed by the deadline or immediately upon discovery of the issue. An emailed submission does not substitute the requirement for an electronic submission using Bidnet. By this paragraph, the City does not guarantee it will accept submissions that experience technical issues.
http://www.bidnetdirect.com/colorado mailto:woodss@bouldercolorado.gov
Costs. Proposals shall be prepared at the bidder’s sole expense.
Public Record. Bid submissions are public records and subject disclosure under the Colorado Open Records Act (CORA).
Confidential Data. All submitted materials are presumed to be public records. However, confidential data, if unambiguously identified as such, will be held confidential upon request if: (1) it is clearly and unambiguously identified, (2) the request is made as part of the bid, and (3) if the City Attorney’s Office determines the data meets the requirements of the CORA. The City’s Access to Public Records Policy, which includes policies about release of solicitation records, can be found on the City’s Central Records web page under the heading Additional Resources.
Preference. Preference is given to labor, materials, supplies, or provisions produced, manufactured, or grown in the state of Colorado, quality and price being equal to articles or services offered by competitors outside of Colorado.
Digital Accessibility. If the work or services described herein include information technology or digital content that must be made “accessible,” the successful bidder must agree, if requested by the City, to undertake such reasonable efforts that may be needed of the successful bidder to adapt and convert work product to ensure it is accessible within the meaning of §§ 24-85-101, et seq., C.R.S., and its implementing regulations. For contracts which the provision of information technology comprises a primary or material component of the service (such as software and web services) the City anticipates requiring that the successful bidder agrees to ensure legal compliance, subject to limited exceptions.
Socially Responsible Procurement. The City is committed to socially responsible procurement and promoting social equity through its contracts. The City works to ensure open and fair procurements, competitive and fair pricing, environmentally sustainable solutions, and encourage members of the underserved business community to participate in our competitive solicitations.
Attention is called to the fact that not less than the minimum salaries and wages as set forth in the Contract Documents must be paid on this project, and that the Contractor must ensure that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, or national origin (Davis Bacon Wages). If the bidder anticipates hiring employees to work on this job, the bidder should contact the local manpower office for qualified candidates.
Equal Opportunity. The City does not discriminate on the grounds of race, creed, ancestry, religion, religious expression, color, sexual orientation, gender identity, gender expression, genetic characteristics, marital status, age, sex, mental or physical disability, or national origin in consideration of an award.
Disadvantaged business enterprises are afforded a full opportunity to submit proposals.
City’s Reserved Rights. For avoidance of doubt, the City reserves the following rights:
• Right to Supplement or Modify. At any time prior to award, the City reserves the right to supplement or modify its solicitation with additional or different information, questions, contract language, or any other materials the City deems prudent to include in the supplementation or modification. Such supplementation or modification includes the right to modify the bid schedule at any time.
Supplementation or modification will likely occur through Bidnet but may occur by email contact to bidders if the deadline has passed.
https://bouldercolorado.gov/services/central-records
• Right to Reject. The City reserves the right to reject any bid that fails to meet the requirements described herein, the requirements or criteria in the City’s Purchasing Ordinance, or in the City’s Purchasing Policy Manual, as such ordinance or policy manual may be amended from time to time, or any other pertinent standard or criteria established by City. The City reserves the right to require new bids or reject any bid if the City believes it would not be in the best interest of the project or services set forth in this RFB to make an award to a given bidder. This right to reject includes the right to reject any bidder who appears on one or more lists designating the bidder as a debarred or suspended entity or individual for other public procurements.
• Right to Waive Irregularities. The City may waive, or decline to waive, any informality or irregularity contained in any bid.
• Right to Revoke or Cancel Award. At any time prior to the successful bidder and the City entering into a written and signed contract, the City reserves the right to revoke or cancel the award. If, for any reason, the City and a successful bidder are unable to come to terms of agreement, the City may, in its sole discretion, either award to the next highest scoring bidder or cancel this solicitation.
• Right to Negotiate Changes in Scope or Services. The City may negotiate changes to the services or work offered by the successful bidder as part of the final contracting process.
• Right to Make Partial Award. The City may award the contract by sections or in portions and reserves the right to adopt all or part of a bid.
Verbal Communications. Any verbal communications bidders may receive about this solicitation are non-binding upon the City. Vendors should rely only upon written statements issued by the authorized City representatives listed in the Instructions to Bidders and Bid Schedule section of this RFB or a member of the City’s Purchasing Division.
Unauthorized Contacts. A bidder’s unauthorized contacts with City staff about this solicitation may result in disqualification of the bidder.
Contract Terms. All awards are subject to the awarded bidder and the City successfully negotiating and entering into a written and signed contract in a form approved by the City Attorney’s Office. The City’s award to a successful bidder does not constitute consent by the City to (1) any revised terms or conditions contained in exceptions, or (2) any terms or conditions contained in the bid of the successful bidder.
In some instances, contract terms are resolved by appending this solicitation and the successful bid to the contract template attached hereto. This is common for the City’s construction and public works contracts.
However, most contracts necessitate development of a scope of work that further refines and clarifies the services. Bid language may merit modification to contract terms, even where a bidder has not made exceptions. While the City’s position is that, generally, failure to make exceptions results in a waiver of the ability to later claim those exceptions, the City reserves the right to modify the contract as the City and the successful bidder deem appropriate.
In the event of any conflict between this RFB and the contract entered into by and between the City and the successful bidder, the terms and conditions of the contract shall control.
Bidder’s Right to Withdraw. In the event the selected bidder and the City are unable to come to an https://library.municode.com/co/boulder/codes/municipal_code?nodeId=TIT2GOOR_CH8PUPR agreement on final terms for the contract, and provided such inability is due to either (1) the bidder’s exceptions or the City’s required changes in response thereto, or (2) the City’s required revisions to the version of the contract posted with this solicitation (as modified by an addendum), the selected bidder shall have the right to withdraw its bid without penalty or loss of any bid bond required by this solicitation.
Waiver. All bidders agree that damage or claim shall not be brought by any bidder because of rejections, and the bidders shall not seek any recourse of any kind against the City because of such rejections. The filing of any bid in response to this RFB shall constitute a binding agreement of the bidder to these conditions.
Federal, State, or Other Third-Party Approval. Bidders should be aware that some awards may require approval (or non-objection) by one or more third parties. Common examples of this include projects that use state or federal funding and for which, accordingly, state or federal agencies must approve the award (e.g., CDOT approval required for certain transportation projects). The City specifically reserves the right to revoke awards if a state, federal, or other entity providing financing or with oversight rights/responsibilities will not approve of or object to the award, or if the selected bidder is not otherwise fully authorized to perform the services under such state, federal, or third-party entity.
Dated this Tuesday, November 10, 2026
City of Boulder, Colorado A Municipal Corporation
CONSENT TO PROTEST & APPEAL PROCESS AND REMEDIES
Protests, appeals and remedies under this solicitation are governed by Colorado Revised Statutes (C.R.S.)
Sections 24-109-101.1 through 108, C.R.S. (protests and other pre-litigation resolution of controversies) and Sections 24-109-201 through 206, C.R.S., (appeals), Section 24-109-301, C.R.S. (interest accruing on costs), Sections 24-109-501 through 505, C.R.S. (remedies), as amended. Such sections apply in their entirety, except for the City’s purposes, (1) all references to the “state” shall be to the “city”, (2) the City’s assigned purchasing agent renders the City’s initial written decision, and (3) the City’s Purchasing Manager renders the final agency determination upon any appeal therefrom, as well as any other functions and decisions of the “executive director” referenced in those sections.
As described in the statutes referenced, protests and appeals must be made in writing within ten (10) business days. Protests must be timely submitted as e-mail attachments to the purchasing agent for this solicitation at the following e-mail address:
Shay Woods
Woodss@bouldercolorado.gov
Any subsequent appeals from the purchasing agents’ initial determination must be timely submitted within ten (10) business days of the initial decision as e-mail attachments to the Purchasing Manager at the following e-mail address:
Michael Van Ausdal
Vanausdalm@bouldercolorado.gov
In addition, this solicitation is subject to limitations of remedies set forth in Sections 24-109-501 through 505, C.R.S., including, specifically, Section 24-109-505, C.R.S. Those remedies are limited to, in summary, the authority of the City to ratify, terminate, or cancel the solicitation, award, or contract, and, if ratification occurs, a successful aggrieved party’s limitation of remedies to its reasonable costs incurred in connection with the solicitation, including bid preparation costs, plus interest on those costs.
By responding to this solicitation, bidders agree to the protest and appeal processes, requirements, and time limitations, as well as the limited remedies, set forth in the statutes above and as described herein.
mailto:Woodss@bouldercolorado.gov mailto:Vanausdalm@bouldercolorado.gov
INSTRUCTIONS FOR BIDDERS AND BID SCHEDULE
1. Bidders responding to this RFB must submit their bids as specified in this solicitation.
2. One electronic copy of the bid must be submitted online through the Rocky Mountain E-Purchasing System (www.bidnetdirect.com/colorado) and must be addressed to the Project Manager listed below. Bidders are strongly encouraged to familiarize themselves with the Bidnet website in advance of the proposal deadline.
3. Bids must be dated and signed by a duly authorized partner or corporate officer, with that person’s name and title clearly identified. All bid terms, conditions, contents, fees, and charges shall be guaranteed by the bidder for a minimum of forty-five (45) days from the submission deadline. The City may, in its sole discretion, release any bid and return the bid bond prior to the end of such guarantee period.
4. Bidders who have questions concerning the scope of work or services or other requirements set forth in this RFB shall contact the following City representative:
Project Manager Chris Olson, PE, CWP Wastewater Engineering Supervisor City of Boulder Utilities Department Phone: 303-441-3293 Email: olsonc@bouldercolorado.gov
5. The above referenced individual is the only representative of the City with authority to provide any information, clarification, or interpretation regarding the plans, specifications, and any other contract documents or requirements. Contact with any other employee of the City of Boulder regarding this project is not authorized. Any information obtained from those other than an authorized City representative shall be considered invalid in the preparation of a proposal for this project.
6. Bidders who request clarification of the solicitation’s requirements may submit written questions to the project manager at the email address listed above by 5:00 PM (Mountain Time) on Monday, November 30, 2026. All questions and answers will be posted as an addendum on Bidnet. Bidders should rely only on written statements issued by the project manager.
7. Before submitting a bid, each bidder shall:
• Examine the contract documents thoroughly.
• Become familiar with federal, state, and local laws, ordinances, rules, and regulations that may in any manner affect cost, progress, or performance of the work.
• Study and carefully correlate the bidder’s observations with the contract documents.
• Notify the project manager of all conflicts, errors, omissions, ambiguities, or discrepancies in or among the contract documents.
8. All bids timely submitted shall become the property of the City and shall be retained in accordance with the City’s records retention schedule. The City is a Colorado governmental entity and therefore, all information included in proposals and other written information submitted by the bidder to the City is subject to the http://www.bidnetdirect.com/colorado provisions of the CORA. Bidders should expect that their proposal may be viewed by the general public and competitors once submitted to the City, subject to the City’s Access to Public Records Policy. Merely marking information as “confidential,” “proprietary,” or otherwise stating a written intent to protect the information from disclosure is not necessarily sufficient to prevent disclosure under CORA.
9. Bid Schedule (all times Mountain Time) RFB Issued Tuesday, November 10, 2026 Optional Virtual Prebid Meeting Wednesday, November 18, 2026, at 1:00 pm Written Questions due Monday, November 30, 2026, at 5:00 pm Final Addenda Posted Tuesday, December 1, 2026 Bids Due Thursday, December 3, 2026, at 4:00 pm Review of Bids Friday, December 4, 2026 through Friday December 11, 2026 Successful Bidder Selected* Monday, December 14, 2026
*Pursuant to Section 2-8-4(a)(3) of the Boulder Revised Code 1981, the successful bidder is required to sign a contract with the City within 15 days of the successful bidder’s acceptance of the award by the City.
Failure to do so will result in the bidder’s forfeiture of its bid bond.
Interview – Optional. The City may elect to conduct interviews with one or more bidders. The City may do so to better understand the bidders, their teams, their approaches, products, and solutions, and any other information relevant to the work or project described in this solicitation. In some instances, the City may request that the interviews include a presentation by the interviewed bidders. In these instances, bidders may prepare PowerPoint or other written material that may assist the City in understanding and evaluating their bid. Bidders cannot plan on having an interview and, accordingly, are strongly encouraged to include all information necessary for the City’s evaluation in their bid documents. For the avoidance of doubt, the City reserves the right to include information provided by bidders during interviews in the contract documents.
10. Prebid Meeting – Optional Virtual Meeting.
The optional prebid meeting will be held virtually via Microsoft Teams on Wednesday, November 18, 2026, at 1:00 p.m. Mountain Time.
Microsoft Teams meeting link:
https://teams.microsoft.com/meet/2482432200236912?p=SN3VVTV4b5Ti7N8DlR
Meeting ID: 248 243 220 023 691 2 Passcode: me2hd7iJ
Dial in by phone
Phone Number: 720-593-3714 Conference ID: 626 966 922#
Bidders are responsible for ensuring their attendance is documented, including by signing any provided sign-in sheet or otherwise checking in for online meetings so that City representatives understand bidder’s representative is in attendance. This may require provision of company name, attendee name, and contact information.
https://documents.bouldercolorado.gov/WebLink/DocView.aspx?id=185061&dbid=0&repo=LF8PROD2&_ga=2.103231561.839680403.1721847125-955511549.1682975816&cr=1 https://teams.microsoft.com/meet/2482432200236912?p=SN3VVTV4b5Ti7N8DlR tel:+17205933714,,626966922
11. Required Documents for Bid Submission.
To be considered, all bids shall include the following completed forms:
• City of Boulder Bid Proposal. Please include the separate excel spreadsheet with your submission.
• City of Boulder Bid Bond in the amount of 5% of the total bid (form attached).
• City of Boulder Bid Form (attached).
• City of Boulder Acceptance of Terms and Conditions (attached).
In addition, the City requests submittal of the following documents at the time of bid submission, and the City will require such documents be completed and submitted in acceptable form to the City prior to contracting:
• City of Boulder Non-Collusion Certificate (attached).
• City of Boulder Contractor Qualification Form (attached).
• City of Boulder Schedule of Manufacturers and Suppliers (attached).
• City of Boulder Schedule of Proposed Subcontractors (attached).
• Certificate of Good Standing from the Colorado Secretary of State. If your company is not registered with the Colorado Secretary of State, include a statement addressing why it is not required to register or affirming that, prior to entering into a contract with the City, your company will register with the Colorado Secretary of State if the City awards your company the contract.
In addition to the forms attached to this RFB, all above-listed documents, except the Bid Proposal and Certificate of Good Standing, have been included as a separate PDF file in the Bidnet documents section labeled Required Bid Documents. You will also find the Microsoft Excel spreadsheet for pricing in the same documents section in Bidnet. The spreadsheet is labeled 38-2026 2027 Sewer Rehabilitation.
For avoidance of doubt, the City reserves the right to request that bidders correct minor irregularities or issues in the forms submitted, though bidders should not expect to have the opportunity to correct such irregularities or issues. With respect to the City’s contracting terms and conditions, the City reserves the right to negotiate additional or different changes to contract language that the City deems necessary or prudent to account for bidder exceptions.
EVALUATION CRITERIA
The award will be provided to the lowest bid, submitted by a responsible and qualified bidder. Bids the City determines fail to respond to a material component of this Solicitation may be rejected. The lowest bid will include consideration of initial cost and, if applicable, life-cycle cost, including, without limitation, maintenance cost, over the normal lifetime of the product and energy-efficiency in consumption of non-renewal fuels (if applicable). Bidders are only responsible and qualified if the City is satisfied it meets the below responsibility criteria:
• The bidder’s integrity and financial responsibility.
• The bidder’s skill, relevant technical expertise, and ability to complete the contract promptly and satisfactorily.
• Whether the bidder maintains a permanent place of business.
• Whether the bidder has adequate plant, equipment, and support services to perform the contract.
• Whether the bidder has previously performed similar work satisfactorily.
• Whether the bidder is likely to be engaged in work that may impair the ability to finance the work covered by the bid or provide equipment for its proper execution.
• Whether the bidder proposes a reasonable approach to achieve the objectives sought.
• Whether there have been or are any claims that raise a substantial question about the bidder’s ability to perform the contract.
The City applies the above criteria liberally, and may eliminate bidders based upon one or more of these criteria. Bidders must propose high-quality approaches, competitive and reasonable pricing, and provide adequate certainty surrounding the project or risk elimination from consideration. The City may conduct such investigations as the City deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications, and financial ability of any bidder or their proposed subcontractors and other persons and organizations to do the work in accordance with the contract to City’s satisfaction.
Further, the City may consider the qualifications and experience of subcontractors, suppliers, and other persons and organizations proposed for those portions of the work as to which the identity of subcontractors, suppliers, and other persons and organizations must be submitted. The City also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the work when such data is required to be submitted prior to the contract award.
ALL AWARDS ARE SUBJECT TO CONTRACT EXECUTION. If for any reason, the negotiations with the apparent lowest bidder who satisfies all applicable requirements are unsuccessful, the City may terminate those negotiations and begin negotiations with a different bidder, or cancel and repost the solicitation in order to contract with the bidder that best meets the needs of the City.
BID BOND
Note: Complete and return this form with your bid.
RFB Title: 2027 Sewer Rehabilitation
RFB Number: 38-2026
Witness:
, as principal, hereinafter called the “bidding contractor,” and , as “surety,” a corporation properly organized under the laws of Colorado or authorized to do business in Colorado, hereby obligate themselves to the City of Boulder, as obligee, hereinafter called the “City,” in the penal sum of dollars ($ ), which penal sum shall secure the obligation of the bidding contractor to enter into contract with the City for the work associated with
Project Number , if the bidding contractor is so selected by the City.
If the City accepts the bid of the bidding contractor, and if the bidding contractor properly executes a contract with the City to perform the work covered by the award, then this obligation shall be null and void.
In the alternative, if the bidding contractor refuses to enter into contract with the City for work described in the bid, but rather pays to the city the difference between the bidding contractor’s stated bid amount and the actual amount bid by an alternate bidding contractor, who is accepted by the City, then this obligation shall be null and void.
EXECUTED on this day of , 20 .
(Contractor)
By:
(President)
(Surety Company)
By:
(Attorney-in-Fact)
BID FORM
The undersigned bidder does hereby declare and stipulate that the Bid Proposal is made in good faith, without collusion or connection with any other person or persons bidding for the same work, and that it is made in pursuance or and subject to all the terms and conditions of the bid documents all of which have been examined by the undersigned.
Bidders shall submit prices as provided in the Bid Proposal. Should an error occur in the extension of price, the unit price shall govern.
The City of Boulder (“City”) reserves the right to make the award on the basis of the bid deemed most favorable to the City, to waive any informalities or to reject any or all bids.
The bidder shall complete the attached Contractor Qualification Form, with the bid proposal.
Failure to provide this information may be sufficient cause for rejection of the bid.
The bidder shall complete the attached Proposed Subcontractors Form, with the bid proposal.
Failure to provide this information may be sufficient cause for rejection of the bid.
The bidder shall complete the attached Schedule of Manufacturers and Suppliers Form, with the bid proposal. Failure to provide this information may be sufficient cause for rejection of the bid.
Addendum No.(s) have been received.
Attached is an unconditional letter of credit, money order, certified check, or bid bond payable to the City of Boulder in an amount not less than five percent (5%) of the total amount of the bid.
If this bid is accepted, the bidder agrees to sign the contract agreement without qualifications and to furnish the performance bond, labor and material bond and the required evidence of insurance within ten (10) calendar days after notification of award.
All proposals shall be submitted on the bid proposal. The lowest responsible bid will be accepted;
provided, however, that the City shall have the right to reject any or all bids and to waive any informalities or irregularities contained in said bid. The quantities are an estimate only and may be altered to meet actual City requirements.
Submit firm unit prices for the type of construction listed. Overhead shall not be priced and bid separately but shall be included in each bid item as required. All prices are for furnishing and installing the described item.
The bidder proposes to perform all work and provide all labor, materials, and equipment in full accordance with the bidding documents.
Confidential data, if identified as such, will be held confidential upon request, if the request is made as part of the bid and the City Attorney’s Office determines the data meets the minimum requirements of the Colorado Public Records Act.
ATTEST:
Corporation
President Date Address City State Zip Code Phone number
ATTEST: Company Name
Company Partner
Address City State Zip Code
ATTEST:
Individual
Company Name
Address City State Zip Code
Tax Identification Number
It is imperative that the Business and/or vendor name (surname for an individual) and TIN number combination (Employer Identification Number for a Business or Social Security Number for an individual) match exactly.
ACCEPTANCE OF TERMS AND CONDITIONS
The undersigned, as an authorized agent of the bidder, hereby certifies that the bidder:
1. Has received addendums;
2. Is familiar with all instructions, terms and conditions, and specifications stated in this RFB;
3. Is qualified to perform the work and services outlined in this RFB; and
4. Has reviewed the form of agreement attached to this RFB.
Each bidder must indicate exceptions that it takes to any terms and conditions listed in the form of agreement attached to this RFB, as well as the RFB itself. The City reserves the right to not consider exceptions that are not identified on this form. Proposals which take exception to the specifications, terms, or conditions of this RFB or offer substitutions shall explicitly state the exception(s), reasons(s) therefore, and language substitute(s) (if any) in this section of the proposal response. Failure to take exception(s) shall mean that the bidder accepts the conditions, terms, and specifications of the RFB, including the attached form of agreement.
Check the appropriate box below and complete this section as applicable:
☐ Bidder takes no exception to the specifications, terms, and conditions of this RFB.
☐ Bidder takes exception to the following terms and conditions in this RFB:
Signed:
By: ______________________________________
Title: _____________________________________
Date: _____________________________________
For: ________________________________________________________
NON-COLLUSION CERTIFICATE
Note: Return this page with your bid.
The undersigned, being duly sworn, deposes and says that the person, firm, association, partnership or corporation herein named, has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in the preparation and submission of a proposal to the City of Boulder for consideration in the award of the project described in this solicitation.
(Firm Name)
By: ______________________________________ (Authorized Signature)
Printed Name: ___________________________
Title: ________________________________
Email: _______________________________
CONTRACTOR QUALIFICATION FORM
I. General Information
Your Company:
Name:
Address:
How long have you been in business?
How long have you been in business under the present business name? __________________ What former name(s), if any, has your company operated under in the past five (5) years?
What is the largest contract you have been awarded in the past twelve (12) months?
II. Information: Previous Construction Contract
Provide the following information for three (3) contracts you have performed, or are currently performing, within the past five (5) years. At least two (2) contracts must be completed. If you have performed any contract with the City of Boulder, or County of Boulder, or state of Colorado, include information about at least one (1) such contract.
Contract 1
Owner Name
Address Phone
Date Begun Date Completed Dollar Amount
Description of Work
Architect Name
Surety for Performance Bond: ___________
Surety for Labor and Material Bond:
Insurance Company: Name
Major Subcontractor: Name
Major Supplier: Name
Are there any lawsuits, claims, or disputes resulting from this project? If so, please describe:
Contract 2
Description of Work
Architect Name
Surety for Performance Bond:
Contract 3
Description of Work
Architect Name
Surety for Performance Bond:
III. Describe the work you normally perform with your own forces:
IV. Have you, or any officer or partner of your organization, when working for another organization, failed to complete any work awarded to you or such officer or partner? If so, attach a separate sheet of explanation.
V. Are there any claims or law suits against your organization, against predecessor organizations of your organization, or against any officer or partner who currently works for your organization which have been brought during the previous five years? If so, attach a separate sheet of explanation.
VI. Resumes
Provide resumes for at least two (2) persons with your company. One resume should be for an officer of the company: president, vice-president, etc. The second resume should be for an operations manager of the company who has had experience directing a job as a contractor or superintendent. An operations manager may also be an officer of the company.
Officer: Name
Operations Manager: Name
VII. Trade References:
1.
2.
3.
4.
5.
VIII. Bank References:
1.
2.
3.
4.
5.
IX. Name of Bonding Company and name and address of agent:
X. Attach a financial statement, audited if available, (consolidated if the contractor is part of an affiliated group), including contractor's latest balance sheet and income statement showing the following items:
A. Current Assets (e.g., cash, joint venture accounts, accounts receivable, notes receivable, accrued income, deposits, materials inventory, and prepaid expenses):
B. Net Fixed Assets:
C. Other Assets:
D. Current Liabilities (e.g., accounts payable, notes payable, accrued expenses, provision for income taxes, advances, accrued salaries, and accrued payroll taxes):
E. Other Liabilities (e.g., capital, capital stock, authorized and outstanding shares par values, earned surplus, and retained earnings):
Name of firm preparing financial statement and date thereof:
Is this financial statement for the identical organization named in Part I on page one?
If not, explain the relationship and financial responsibility of the organization whose financial statement is provided (e.g., parent-subsidiary).
Will this organization act as guarantor of the contract for construction?
SCHEDULE OF MANUFACTURERS AND SUPPLIERS
Note: The City reserves the right to reject the use of any particular manufacturer.
Name Phone No.
City State Zip Code
Name Phone No.
PROPOSED SUBCONTRACTORS
Note: The City reserves the right to reject the use of any particular subcontractor.
Name Phone No.
PROJECT INFORMATION, SPECIFICATIONS, DRAWINGS
OCTOBER 2026 TABLE OF CONTENTS
CITY OF BOULDER
SEWER REHABILITATION PROGRAM SPECIFICATIONS
DIVISION 0 – CONTRACT REQUIREMENTS
DIVISION 1 – REQUIREMENTS
01 11 00 Summary of the Work Attachment 1: 2027 Sanitary Sewer Rehabilitation Map Sets 01 14 19 Contractor’s Use of Premises 01 14 34 Construction and Schedule Constraints 01 20 00 Measurement and Payment 01 31 19 Project Meetings 01 33 00 Submittal Procedures 01 35 29 Health and Safety 01 42 13 Acronyms and Abbreviations 01 50 00 Construction Facilities and Temporary Controls 01 55 26 Traffic Control 01 57 13 Erosion Control 01 57 19 Environmental Controls 01 65 00 Material Delivery, Storage & Handling
DIVISION 33 – REQUIREMENTS
33 01 30.11 CCTV Inspection of Existing and Rehabilitated Sewers 33 01 30.41 Cleaning of Sewer Pipelines 33 01 30.79 Fold-and-Form Pipe Lining 33 31 10 Sanitary Sewer Bypassing
Design Bid Build Contract
CONSTRUCTION CONTRACT
(Design-Bid-Build)
Department: Utilities
Project Name: 2027 Sanitary Sewer Rehabilitation Program Project Summary: Citywide Sanitary Sewer Rehabilitation
Contractor: Contractor's Legal Name Contract Amount: $Amount
EXHIBITS
Exhibit A Solicitation Exhibit B Response to Solicitation Exhibit C General Conditions Exhibit D Special Conditions
EFFECTIVE DATE:
This Construction Contract (this “Contract”) is made and entered into as of the date appearing on the title page (above) (the “Effective Date”) between the City of Boulder, a Colorado home rule municipality (the “City”), and Contractor's legal name, a Contractor's state of incorporation Contractor's form of entity (“Contractor”). The City and Contractor may hereinafter be referred to individually as a “Party” or collectively as the “Parties.”
Defined terms for this Contract, including these pages comprising the main body of this Contract, are contained at Appendix 1 of Exhibit C.
RECITALS
A. In accordance with the City’s purchasing ordinance, the City issued a solicitation known as RFB 38-2026 (2027 Sanitary Sewer Rehabilitation Program) (the “Solicitation”), for the lining of sewer mains throughout the city, as further described herein (the “Project”). The Solicitation, including any Addendum, is attached as Exhibit A and incorporated by this reference.
B. Contractor responded to the Solicitation, and Contractor’s response is attached as Exhibit B.
C. The City has evaluated proposers and has selected Contractor to perform the Work.
AGREEMENT
NOW, THEREFORE, in consideration of the foregoing and the terms, conditions and covenants included in this Contract, the receipt and sufficiency of which are hereby acknowledged, the Parties, intending to be legally bound, agree as follows:
1. The “Work.” The construction work and services described in the Solicitation and herein constitute the “Work.” Contractor shall perform the Work pursuant to the terms and conditions of the Contract Documents. Contractor agrees to render all services and activities that are necessary to complete the Project except the Parties agree that the “Work” does not include: (a) any architectural, engineering, or other design services that have been, or are to be rendered by, the City or a separate City consultant; or (b) any other services or activities which are expressly identified in these Contract Documents as excluded from Contractor’s services.
2. Payment. Subject to the terms and conditions of this Contract, including any additions or deductions to the Contract Price that occur by Change Order, the City shall pay Contractor, for the performance of the Work, the Contract Price of TYPE WRITTEN DOLLAR AMOUNT DOLLARS ($NUMBER DOLLAR AMOUNT) (the “Contract Price”), as set forth in Exhibit B.
This is a unit price contract, subject to change and payment only as provided in these Contract Documents.
A. Overhead and Profit Markup. Contractor will serve as general contractor for the Work. Unless modified by Exhibit D, Special Conditions, all Work shall be performed at the rates and mark-up set forth in Contractor’s bid. For any Work in which additional payment is warranted or required, such as Extra Work, the Parties agree such Work shall be subject to the following terms and conditions:
A. NOT USED.
B. NOT USED.
C. Additional Markup Terms. The Parties further agree as follows:
The Contract Price in Section 2 above, already includes all markup, overhead, profit, and administrative expenses for the Work and the Project.
The markup percentages above constitute the total allowable markup for all markups, overhead, profits, and administrative expenses, and shall apply for all of the Work. See General Conditions (Exhibit C), Article VII, Changes, for additional terms and conditions governing changes to the Work or Project.
There shall be no different fees or charges to the City for markups, overhead, profits, or administrative expenses unless both (i) the Parties agree to such via a Change Order signed by each Parties’ project manager, and (ii) the resulting markup percentage is lower than those set forth above.
3. Substantial Completion Deadline. Contractor agrees to achieve Substantial Completion on or by the Substantial Completion Deadline. With respect to the Substantial Completion Deadline:
☒ Set Now. The Substantial Completion Deadline is hereby set as December 31, 2027.
☐ Set by Future Change Order. The Substantial Completion Deadline shall be set by a Change Order within sixty (60) days of the Effective Date. If no such Change Order is issued, then the date of Substantial Completion Deadline shall be one hundred and eighty (180) days from the Effective Date.
☐ Set by Notice to Proceed. The Substantial Completion Deadline shall be set by a set number of days following the City’s issuance of a written Notice to Proceed. The deadline date shall be [ # ] days after the date of issuance of the Notice to Proceed. Contractor and the City agree that the City shall not issue the Notice to Proceed unless and until the following occurs:
Reserved.
The date or deadline above shall constitute the “Substantial Completion Deadline” for all purposes under this Contract unless and except as such deadline may be extended by a Change Order or amendment.
The terms and conditions governing Substantial Completion of the Work and Project and the Substantial Completion Deadline are further detailed in the General Conditions (Exhibit C), including, without limitation, Section 608 of that exhibit.
4. Final Completion Date. Unless revised by a Change Order or Amendment, Contractor agrees to achieve Final Completion no later than 30 after the Substantial Completion Date.
5. Liquidated Damages. Contractor shall be liable for liquidated damages for each day that the Substantial Completion of the Work is delayed past the established time limit or limits, accounting for any extension of time agreed to by the City. Liquidated damages per day of delay are hereby set at:
☒ Standard. The City’s default rate of ONE TENTH OF A PERCENT (0.1%) of the Contract Price, which each Party deems reasonable to compensate the City for such delay.
☐ Negotiated. The negotiated rate of $Reserved per day of delay.
☐ Set by Law or Funding Source. A rate set by law or funding source of $Reserved per day of delay.
The terms and conditions governing liquidated damages are further detailed in the General Conditions (Exhibit C), including, without limitation, Section 606 of that exhibit.
6. The Contract Documents. The Contract Documents consist of (a) this Contract (main-body), including its exhibits comprised of the Solicitation (Exhibit A), Contractor’s Response to the Solicitation (Exhibit B), the General Conditions (Exhibit C), the Special Conditions (Exhibit D), (b) the Drawings and Specifications, and City-approved (c) Change Orders, and (d) Amendments.
7. Order of Precedence.
A. To resolve conflicts resulting from errors or discrepancies in these documents, the order of precedence shall be as follows:
1. Amendments
2. Change Orders
3. This Contract
4. Special Conditions (Exhibit D)
5. General Conditions (Exhibit C)
6. Permitting or Licensing Conditions as interpreted by the Permitting or Licensing
Authority
7. Drawings (See General Conditions, Section 301)
8. Technical Specifications
9. Referenced Standard Specifications
10. The Solicitation, including any Addenda thereto (Exhibit A)
11. Contractor’s Response to the Solicitation (Exhibit B)
B. With reference to the Drawings, the order of precedence, as between them, shall be as follows:
1. Figures govern over scaled dimensions.
2. Detail Drawings govern over general Drawings.
3. Addenda/Change Order drawings govern over Contract Drawings.
4. Contract Drawings govern over standard drawings.
8. Notice.
A. Formal Notice – Requirements. Any “Formal Notice” (as described below) shall be in writing to the other Party shall be deemed given (1) if by hand delivery, upon receipt thereof; (2) three (3) days after deposit in the United States mails, postage prepaid, certified mail, return receipt requested; or (3) one (1) day after deposit with a nationally-recognized overnight courier, specifying overnight priority delivery. Either Party may change its address for purposes of this Contract at any time by giving Notice of such change to the other Party.
If to Contractor:
Individual Name Individual Title Street Address City/Town, State ZIP
If to the City:
Individual Name Individual Title Department Street Address Boulder, Colorado 80306
With a copy to:
City Attorney’s Office 1777 Broadway, Second Floor P.O. Box 791 Boulder, Colorado 80306
B. Distinguishing “Formal Notice” from Other Notice. This Section 9 applies only to instances in this Contract where a Party is required to give “Formal Notice.” References in this Contract, inclusive of its exhibits, to other forms of notice, even if required to be in writing, need not comply with this Section 9. The purpose of distinguishing “Formal Notice” from any other form of written notice – such as “notice,” “written notice,” “notice in writing,” or similar phrasing – is to ensure: (1) the Contract Documents clearly identify those matters of significance that require elevation according to this Formal Notice process; and, (2) to permit other notices, even if “in writing,” to be given without compliance with this Section 9.
9. Appropriations. The City uses a purchase order process to complete requisitions for payment.
Work shall only proceed if a purchase order so authorizes the Work. With respect to the full Contract Price, the amount of funds appropriated to pay Contractor for its Work under this Contract is $4,000,000. Before Contractor commences any Work for which the City has agreed to pay a sum in excess of the appropriated amount stated above, Contractor shall request written assurance that the funds in excess of the amount in the preceding sentence have been lawfully appropriated, and the City will provide such written assurance if appropriation occurred.
10. No Multi-Fiscal Year Obligation. The Parties understand and acknowledge that the City is subject to TABOR requirements. The Parties do not intend to violate the terms and requirements of TABOR by the execution of this Contract. It is understood and agreed that this Contract does not create a multiple fiscal year direct or indirect debt or obligation within the meaning of TABOR and notwithstanding anything in this Contract to the contrary, all payment obligations of the City are expressly dependent and conditioned upon the continuing availability of funds beyond the term of the City’s current fiscal period ending upon the next succeeding December
31. Financial obligations of the City payable after the current fiscal year are contingent upon funds for that purpose being appropriated, budgeted, and otherwise made available in accordance with the rules, regulations, and resolutions of the City and applicable law. Any failure of a city council annually to appropriate adequate monies to finance the City’s obligations under this Contract shall terminate this Contract at such time as such then-existing appropriations are to be depleted. Notice shall be given promptly to Contractor of any failure to appropriate such adequate monies.
11. Compliance with Laws. At all times during the performance of this Contract, Contractor shall strictly adhere to all Laws in effect during its time of performance under this Contract. This shall include, by way of example and not by way of limitation, the United States Department of Health, Occupational Safety and Health Administration (OSHA) standards.
12. City Manager and City Attorney. The city manager of the City of Boulder, Colorado, alone has the authority to solicit bids for a contract and must sign the Contract for it to be effective. This Contract must be approved as to form by the City Attorney’s Office.
13. Effective Date. The “Effective Date” is the date appearing on the cover page of the main body of this Contract following signature of all Parties. The city manager is authorized, at the time of their signing, to affix such date to the cover page.
14. Authorization. Contractor warrants that the individual executing this Contract is properly authorized to bind Contractor to this Contract.
15. Binding Effect. This Contract shall be binding upon and inure to the benefit of the heirs, successors and assigns of the Parties.
16. Counterparts and Signatures. This Contract may be signed in multiple counterparts. Each signed counterpart will be treated as an original, and all counterparts together will form one single agreement. Signed copies may be sent by email or other electronic means. Electronic signatures
– including images of handwritten signatures or other electronic representations showing a Party’s intent to be bound – will have the same legal effect as an original handwritten (“wet”) signature. This Contract becomes effective on the date the last Party signs it. The city manager, as the last Party to sign, is authorized to enter the Effective Date on the cover page.
The Parties to this Contract have caused it to be executed by their authorized officers, effective as of the day and year first above written.
CONTRACTOR
(add Contractor’s Legal Name here)
By:…