Invitation for Bid Summary
This Invitation for Bid (IFB-26-117) is issued jointly by El Paso County Department of Public Works and the Pikes Peak Rural Transportation Authority (PPRTA) for construction services related to the Mesa Ridge Parkway Improvement Project located approximately 5 miles southeast of the Colorado Springs Airport in south-central El Paso County, Colorado. The project involves converting approximately 1.3 miles of existing 2-lane roadway to a 4-lane configuration, including asphalt paving, realignment, regrading, curb and gutter installation, new storm sewer systems, two water quality detention ponds, earthwork, tree removal, bridge and culvert extensions, and surface improvements. A pre-solicitation meeting is scheduled for November 17, 2026, at 12:00 p.m., with a mandatory site visit recommended to evaluate terrain and landscape. The response submission deadline is 2:00 p.m. MST on Tuesday, December 8, 2026, through the Rocky Mountain E-Purchasing System. The anticipated contract award date is January 14, 2027, with a contract term extending through February 29, 2028. The construction is defined as a working day contract with completion required within 270 working days. All work will be performed within El Paso County right-of-way and dedicated easements, except work adjacent to State Highway 21, which must be completed by June 28, 2027, under a CDOT Access Permit.
The project is funded entirely through PPRTA and El Paso County resources with no federal or state oversight; Davis-Bacon requirements do not apply, and no Disadvantaged Business Enterprise (DBE) goal is associated with this project. Responsive and responsible contractors must submit a 5 percent bid guaranty with their response, and the successful contractor must provide a performance and payment bond equal to 100 percent of the offered price within ten calendar days of the Notice of Intent to Award. Prices must remain fixed and firm with no modifications permitted after the submission deadline. Contractors must demonstrate a minimum of one year of satisfactory performance record and provide evidence of five relevant projects completed in the last seven years with similar services, timelines, and magnitudes. The contractor assumes all responsibility for project management, scheduling, utility coordination, surveying, materials testing quality control, and as-built documentation. Construction Management services, inspections, and materials testing for quality assurance will be provided by El Paso County. The County retains 5 percent of estimated payments to a maximum of 5 percent of the original contract amount until final completion and acceptance, with payment processed no more frequently than monthly on a Net 45 basis following invoice and required documentation submission.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Invitation for Bid #26-117 Page of 351
Release Date November 10, 2026
Solicitation Number IFB-26-117
Solicitation Title CONSTRUCTION OF THE MESA RIDGE
PARKWAY IMPROVEMENT PROJECT
Services to be performed for El Paso County – Department of Public Works –
Engineering Division
Responses will be received until 2:00 P.M., MST, Tuesday, December 8, 2026 Electronically through the Rocky Mountain E- Purchasing System
For additional information please contact Matthew Marter Acting Lead Procurement Specialist Email: matthewmarter@elpasoco.com Phone: 719-520-663
Documents included in this package Invitation for Bid Cover Sheet Executive Summary Specifications Special Terms and Conditions General Terms and Conditions Response Submittal Requirements Attachments
The undersigned hereby affirms that (1) he/she is a duly authorized agent of the Contractor , (2) he/she has read all terms and conditions and technical specifications which were made available in conjunction with this solicitation and fully understands and accepts them unless specific variations have been expressly listed in his/her offer, (3) that the offer is being submitted on behalf of the Contractor in accordance with any terms and conditions set forth in this document, and (4) that the Contractor will accept any awards made to it as a result of the offer submitted herein for a minimum of ninety calendar days following the date of submission. Offers must contain, in blue ink, a manual signature of an authorized agent of the Contractor or a verifiable electronic time and date stamped signature in the space provided on all appropriate signature lines in this solicitation. Typed names as signatures are not allowed.
PRINT OR TYPE YOUR INFORMATION
Company Name:
Address: City/State/Zip:
Contact Person: Title:
Email: Phone:
Authorized Representative’s Signature: Date:
Printed Name: Title:
Email: Phone:
El Paso County Contracts and Procurement Division
15 East Vermijo Ave Colorado Springs, CO 80903
INVITATION FOR BID #26-117
COVER SHEET
mailto:XXXXXX@elpasoco.com
Invitation for Bid #26-117 Page of 352
OFFICIAL SOLICITATION DOCUMENTS: El Paso County officially distributes solicitation documents through the Rocky Mountain E-Purchasing System and the County’s website.
Copies of solicitations obtained from any other source are not considered official copies. Only those Contractors who obtain solicitation documents from the Rocky Mountain E-Purchasing System or El Paso County website will be in receipt of officially posted and relevant information regarding solicitations issued by El Paso County. The County and PPRTA cannot be held responsible for incorrect information, nor can it attest to the accuracy of information found on websites other than the Rocky Mountain E- Purchasing System or the County’s website.
PURPOSE OF SOLICITATION: El Paso County (County) and the Pikes Peak Rural Transportation Authority (PPRTA) are requesting bids from qualified, experienced, professional Consultants to furnish all services, labor, materials, and equipment necessary for the CONSTRUCTION OF THE MESA RIDGE PARKWAY IMPORVEMENT PROJECT (“The Project”).
There is El Paso County and PPRTA oversight of the Project.
The Project is being funded through the following sources: Pikes Peak Rural Transportation Authority (PPRTA) and El Paso County. There will be no Federal or State (CDOT) oversight of the project. There is no DBE goal associated with the design of this project. This project is not subject to Davis-Bacon requirements.
The County of El Paso, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 US.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all proposer that it will affirmatively ensure that any contract entered into pursuant to this solicitation, disadvantaged business enterprises (DBE) will be afforded full and fair opportunity to submit proposals in response to this solicitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
TERM OF CONTRACT: The awarded contract(s) is anticipated to commence on January 14, 2027, and shall remain in effect through February 29, 2028.
TERM OF CONTRACT – MULTI-YEAR: The contract awarded is a Working Day Contract. The services called for shall commence on the date of contract execution by all Parties and shall be completed within two hundred and seventy (270) Working Days. This is a multi-year (2-year) agreement by where the services of the Consultant shall be in effect January 14, 2027, through February 29, 2028. Continuation of the Agreement beyond the initial period is a PPRTA and County prerogative and not a right of the Consultant and will be exercised only when such continuation is clearly in the best interest of PPRTA and the County.
NON-APPROPRIATION: Pursuant to C.R.S.§ 29-1-110, as amended, the financial obligations of the County and PPRTA as set forth herein after the current fiscal year are contingent upon funds for the purpose being appropriated, budgeted and otherwise available. The awarded agreement will automatically terminate on January 1st of the first fiscal year for which funds are not appropriated. The County shall give the Contractor written notice of such non- appropriation
SCHEDULE OF ACTIVITIES: The following activities and dates tentatively outline the process to be used to solicit Contractor responses and to review each Contractor Response:
INVITATION FOR BID #26-117
EXECUTIVE SUMMARY
Invitation for Bid #26-117 Page of 353
November 10, 2026 Release Invitation for Bid November 17, 2026 @ 12:00 p.m. RECOMMENDED Pre-Bid Meeting November 20, 2026 @ 2:00 p.m. Deadline for Submitting Questions December 8, 2026 @ 2:00 p.m. Response Submission Deadline December 2026 Issue Notice of Intent to Award January 14, 2026 (estimated) Contract Award
PRE-SOLICITATION MEETING: A pre solicitation meeting will be held as shown above in the Schedule of Activities, at the El Paso County Department of Public Works located at 3275 Akers Drive, Colorado Springs, CO.
A representative of the Contractor is encouraged to attend this meeting in order to become familiar with the Specifications.
EXAMINATION OF SITE AND CONTRACT DOCUMENTS IS RECOMMENDED: The Contractor is advised to carefully examine the requirements outlined in the Specifications. It is not the intent of the specifications to cover each and every detail. Any problems that may arise must be promptly reported to the County and will be subject to the decision of the County and PPRTA. The submitter is expected to carefully examine the size and scope of the proposed work prior to submitting its submittal. The Submitter certifies that it has examined the location of the proposed Work and is familiar with the specifications and all contract documents related thereto, and the local conditions at the place where the Work may be performed. The Submitter should carefully check all the quantities and understand that the County will not be responsible for any errors or omissions on the part of the Submitter in making their submittal.
RESPONSE TO QUESTIONS: Questions which arise during the Response preparation period regarding issues around this Solicitation, purchasing and/or award should be directed electronically, via the Rocky Mountain E- Purchasing system, to Matthew Marter, Acting Lead Procurement Specialist, Contracts & Procurement Division, El Paso County. The Contractor submitting the question(s) shall be responsible for ensuring that the question(s) is received by the date and time listed above in the Schedule of Activities for submitting the question(s).
ACCESSIBILITY COMPLIANCE: Should the Contractor provide a service which provides information and communication technology (ICT), the Contractor shall make commercially and technologically reasonable efforts to comply with all applicable provisions of C.R.S. §24-85-101, et seq., and the Accessibility Standards for Individuals with a Disability as established by the Governor’s Office of Information Technology (OIT) pursuant to Section C.R.S. §24-85-103 (2.5). Contractor shall also make commercially and technologically reasonable efforts to comply with all State of Colorado technology standards related to technology accessibility and with Level AA of the most current version of the Web Content Accessibility Guidelines (WCAG), incorporated in the State of Colorado technology standards. The Contractor who provides ICT will also procure and provide an accessibility and compliance report utilizing the current ITIC Voluntary Product Accessibility Template (VPAT 2.5Rev WCAG) and/or manual testing reports from a qualified testing company to demonstrate reasonable efforts to comply with all State of Colorado technology standards.
The term AI does not include the incidental or routine use of generally available consumer tools that employ AI for limited ancillary functions, such as internet search engines (e.g., Google Gemini), spelling and grammar correction tools (e.g., Grammarly), or similar background or assistive technologies that do not generate substantive content or perform autonomous decisionmaking directly related to service deliverables.
Invitation for Bid #26-117 Page of 354
El Paso County and PPRTA are soliciting bids from qualified, experienced contractors to provide all labor, materials, and equipment necessary to complete phases of the
CONSTRUCTION OF THE MESA RIDGE PARKWAY
IMPROVEMENT PROJECT. The material and labor services to be purchased pursuant to this solicitation are funded by Pikes Peak Rural Transportation Authority (PPRTA) and El Paso County.
It is expected that the business and their team members have significant experience with this type of work. The successful Contractor shall be considered and shall remain an independent Contractor throughout the term of any contract awarded pursuant to this Solicitation.
The County of El Paso, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (79 Stat. 252, 42 US.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all submitters that it will affirmatively ensure that any contract entered into pursuant to this solicitation, disadvantaged business enterprises (DBE) will be afforded full and fair opportunity to submit bids in response to this solicitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for any award.
The Project is being funded through the following sources: Pikes Peak Rural Transportation Authority (PPRTA) and El Paso County. There will be no Federal or State (CDOT) oversight. El Paso County and PPRTA will have oversight of the project. There is no DBE goal associated with the design of this project. This project is NOT subject to Davis-Bacon requirement.
The successful Contractor shall be solely responsible for scheduling and coordinating work of the sub-contractors, suppliers, and other individuals or entities performing or furnishing any of the work under direct or indirect contract with the successful Contractor.
The successful Contractor shall provide and assume full responsibility for all services, materials, equipment, and labor necessary for completion of the services outlined in this Solicitation as awarded.
The construction contract is a working day contract, and construction shall be completed in two hundred and seventy (270) working days.
I. BACKGROUND / GENERAL INFORMATION
The Mesa Ridge Parkway Improvements Project is located in the south-central part of El Paso County, Colorado approximately 5 miles southeast of the Colorado Springs Airport. Mesa Ridge Parkway is currently an approximately 1.3 mile, 2-lane road with Powers Boulevard (SH21) acting as its western terminus and Marksheffel Road as its eastern terminus. The road is currently classified as an urban principal arterial but operates as a minor collector in existing condition, which the Project seeks to improve.
The proposed improvements seek to bring the roadway to a 4-lane configuration and include asphalt paving, realigning, regrading, new curb and gutter, new storm sewer system, and two water quality detention ponds. A new section of road will be cut through involving an extensive amount of earthwork and tree removal. Extensions shall also be constructed for the existing drainage culverts and bridge related to Jimmy Camp Creek’s tributaries.
A site visit is highly recommended to evaluate the terrain and landscape.
Underground and surface utilities are in conflict throughout the project site, with coordination and relocation work being required during construction. All utilities will be performing the relocation work during construction. Known utilities in the area are Colorado Springs Utilities (Gas & Electric), Comcast, CenturyLink/Lumen, SECOM/UPN Fiber, and Security Water and Sanitation Districts.
All work will be performed in El Paso County right-of-way or in an easement acquired by the County, except for work adjacent to SH21 which shall be performed under CDOT Access Permit 222100 and completed by June 28, 2027. Access to local businesses and private property shall always be maintained during
SUMMARY OF WORK / SPECIFICATIONS
Invitation for Bid #26-117 Page of 355 construction.
II. SCOPE OF WORK
The proposed Project consists of paving, realigning, regrading, removal and replacement of structures, new curb and gutter, new storm sewer system, and installation of two water quality detention ponds along the corridor. It shall also include surface improvements including installation of new sidewalk connections and rework of existing intersection controls. A new section of road will be cut through involving an extensive amount of earthwork and tree removal. Existing bridges (Structure No. EPC 2938-01.09) and culverts along the corridor shall also be widened to accommodate the expanded roadway. A site visit is highly recommended to evaluate the terrain and landscape.
All work shall be performed within El Paso County right-of-way and dedicated easements (“EPC ROW”) acquired for the Project, except for work adjacent to SH21 which shall be performed under CDOT Access Permit 222100 and completed by June 28, 2027. Access to drainage easements shall be from temporary easements and right of entry acquired by the County. Staging and stockpiles shall be within EPC ROW unless written permission is obtained from property owner(s).
The Project requires close collaboration and/or coordination with affected utility provides during construction, which include but are not limited to: Colorado Springs Utilities (Gas & Electric)), Security Water and Sanitation Districts (Water & Sanitary), Comcast (Telecom/Fiber), CenturyLink (Telecom/Fiber), and SECOM / UPN (Fiber).
Construction Management (CM) services, inspections and materials testing for quality assurance will be provided by El Paso County.
A. TECHNICAL REQUIREMENTS
These bid specifications incorporate the documents entitled “STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION”, Colorado Department of Transportation, State of Colorado (2023), the “Pikes Peak Region Asphalt Paving Specifications” (version 7, March 31, 2026) and the “El Paso County Engineering Criteria Manual” (July 2023) as if physically attached and bound herein. The bid specification documents also incorporate the document entitled “COLORADO STANDARD PLANS, COLORADO DEPARTMENT OF TRANSPORTATION, M&S STANDARDS PLANS LIST” (July 31, 2019), as if physically attached and bound herein.
Each Bidder / Contractor shall be responsible for procuring sufficient copies of the “Colorado Department of Transportation STANDARD SPECIFICATIONS”, the “COLORADO STANDARD PLANS - M&S STANDARDS”, and the “EL PASO COUNTY ENGINEERING CRITERIA MANUAL”, for use in proposing and construction of the Project.
The Colorado Department of Transportation Standard Specifications for Road and Bridge Construction, 2025, controls construction of this Project. The special provisions supplement the Standard Specifications and take precedence over the Standard Specifications and Construction Plans. When specifications or special provisions contain both English units and SI units, the {English} units apply and are the specification requirement. All methods of procedures, materials, control or work, materials, and basis of measurements not herein covered will comply with the Standard Specifications for Road and Bridge Construction, Department of Transportation, State of Colorado, 2025.
Asphalt materials and activities shall be in accordance with the “Pikes Peak Region Asphalt Paving Specifications”, Version 7, unless otherwise noted in the Project Special Provisions.
Construction signage shall follow the federal “MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES”, latest edition (MUTCD).
The El Paso County Engineering Criteria Manual and the Pikes Peak Region Asphalt Paving Specifications can be downloaded from: https://publicworks.elpasoco.com/policies-manuals/.
https://publicworks.elpasoco.com/policies-manuals/
Invitation for Bid #26-117 Page of 356
B. PROJECT SPECIAL PROVISIONS
NOTE: This section is attached as a separate document.
C. CDOT STANDARD SPECIAL PROVISIONS
NOTE: This section is attached as a separate document.
D. CONTRACTOR RESPONSIBILITIES
The successful Contractor shall:
• be considered and shall remain an independent Contractor throughout the term of any contract awarded pursuant to this Solicitation.
• be solely responsible for scheduling and coordinating work of the subcontractor, suppliers, and other individuals or entities performing or furnishing any of the work under direct or indirect contract with the successful Contractor.
• provide and assume full responsibility for all services, materials, equipment, labor, transportation, and incidentals necessary for performance, start up, and completion of the services outlined in this Solicitation.
1. Project Management: The Contractor shall identify a Project Manager who will work directly for and support the County Project Manager in the management and administration of the Project. The Contractor’s Project Manager shall be responsive on a daily basis Monday through Friday for the duration of the Project. The Contractor shall also identify an Assistant Project Manager capable of filling in for the Project Manager in the event that the Project Manager is not available due to travel, illness, or other event that will be longer than one week in length. The County Project Manager will be the primary point of contact for the County, however daily coordination and communications shall occur between the Contractor and the Project Inspector.
Schedules: Provide a baseline schedule broken out by tasks for work, availability of materials, equipment & labor, etc. to maximize construction efficiency. Schedules shall include start date, key tasks, project milestones, phasing, completion date etc. and shall be as comprehensive as practicable. The Contractor shall also provide a 3-week lookahead at least three days before the weekly progress meetings.
Trimble Unity Construct: The Contractor shall utilize the Trimble Unity Construct software platform for project management and administration throughout the term of the Contract. The Contractor shall conduct Project operations, outlined by the County’s Project Manager or as defined in the Project Special Provisions, utilizing the Trimble Unity Construct platform.
2. Invoicing: The Contractor shall be responsible for invoicing the County. Invoices shall not reference more than one contract or purchase order. Invoices may not be submitted more frequently than once a month, and payment is Net 45 after receipt of invoice and ALL required backup documentation. The Contractor shall submit all listed information/documents/forms with their invoice. The Contractor shall submit invoices which shall contain, at a minimum, the following detailed information:
a. Contract #
b. Issued Purchase Order #
c. Invoice #
d. Invoice date
e. Timeframe covered by Invoice.
f. Type and amount of labor and materials used for Invoice time period.
g. Dollar amount in unit price, extended price, and total value of Invoice
h. Invoice shall be signed by Contractor.
i. CDOT Form 1418
j. Updated and accurate baseline schedule
The County reserves the right to withhold / delay payment until all required information and paperwork are submitted.
Invitation for Bid #26-117 Page of 357
3. Superintendent: The successful Contractor shall employ a competent superintendent who shall be the primary representative for the Contractor and all communications given to, and all decisions made by, the superintendent shall be binding to the Contractor. Notwithstanding, the superintendent shall be, at all times, an employee of the Contractor under its sole direction and not an employee or agent of the County.
The County reserves the right to request termination and replacement for any Superintendent who fails to perform or demonstrates a lack of experience in the field of construction oversight.
4. Pre-Construction Conference: Prior to work commencing on the Project, a Pre-Construction Conference will be held at the El Paso County Department of Public Works, 3275 Akers Drive, Colorado Springs, CO, 80922. It is anticipated that a Limited Notice to Proceed shall be issued to the Contractor from the County Project Manager (PM) prior to the date of the Pre-Construction Conference.
5. Legal Relations & Responsibility to The Public: The Contractor shall keep fully informed of all Federal, State, and Local laws, ordinances, and regulations and all orders and decree of Bodies or tribunals having any jurisdiction or authority, which may in any manner affect those engaged or employed on the Work or which in any way affect the conduct of Work, or Contractor’s ability to perform the Work.
Contractor shall always observe and comply with such laws, ordinances, regulations, orders, and decrees, and shall protect and indemnify the County of El Paso, and their representatives, to include employees, agents, consultants, and subcontractors of each, against any claim or liability arising from or based on the violations of any such law, ordinance, regulations, order, or decree, whether by itself or its employees.
6. Construction Requirements: After Work has started under a contract award, the Contractor shall maintain a sufficient work force, machinery, and materials, on site at all times to ensure a smooth progression of Work and a timely completion of the Project within the allotted time. The Contractor shall be required to maintain rigid control of all materials, which must comply with the specifications as stated.
Contractor shall assure that Work is not done, nor equipment parked, in areas outside the construction boundaries.
7. Surveying: All surveys for the project shall be provided by the Contractor. CADD files are included with this IFB for information only and without a warranty against deficiencies of any kind. Use of the CADD files are provided as a courtesy and does not entitle the Contractor to compensation for damages or loss which could be attributed to such use.
8. Character of Workers, Methods, & Equipment: The Contractor shall at all times employ sufficient labor and equipment to properly perform the Work per this solicitation. All workers shall have sufficient skill and experience to properly perform the Work assigned them. All equipment which is proposed to be used on the Work, shall be of sufficient size and in such mechanical conditions as to meet the requirement of the Work. If in the opinion of the El Paso County Engineer, employees and/or a certain type of equipment are not producing the Work required by the contract, the Contractor shall discontinue the use of said employees and/or equipment, when notified in writing.
9. Load Restrictions & Truck Routes: Haul routes shall be planned, prior to bidding, observing load limits on bridges or roadways, existing roadway conditions, and Federal, State, and Local governmental regulations regarding truck traffic and truck routes. The Contractor shall comply with all legal load restrictions in hauling of materials on public roads.
10. Inspections: Quality control (QC), including but not limited to, materials testing is the Contractor’s responsibility. The schedule of minimum required QC testing and associated frequencies has been provided in the bid documents. Type of testing and/or frequencies may change depending on field conditions and Contractor’s means and methods but shall generally conform to CDOT’s “2026 FIELD MATERIALS MANUAL” (issued 07/01/2025) unless otherwise specified. El Paso County (EPC) or its Contractor shall provide Construction Management (CM) services and will conduct materials testing for quality assurance (QA). Any QA testing performed by EPC, or their Contractor does not relieve the Contractor of their QC testing responsibilities.
Invitation for Bid #26-117 Page of 358
11. As-Built Plans: The Contractor, in coordination with EPC shall keep a detailed marked-up plan set which records all changes to the construction plans. The Contractor shall turn over the marked-up plan set to the County at the end of the project or upon request by the County.
12. Utilities: The Contractor shall coordinate all utility removals, resets, adjustments, or other work as necessary to construct the Project and maintain utility service with each affected utility company. The Work shall require full cooperation between the Contractor and the utility companies. Utility relocations during construction may be required. The Contractor shall be responsible for coordinating the utility relocates to ensure that no delays or required rework occurs because of the utility relocations. The Contractor and its subcontractors shall not interfere or hinder the progress or completion of the work being performed by the utility providers and their contractors and consultants at or near the site. Known conflicts with Black Hills Energy and Comcast within the Right-of-Way, have been relocated with utility infrastructure abandoned in place and noted in Construction Plans & Specifications. See attachments for further details and utility specific as-builts.
13. Public Relation Services: The Contractor shall identify a Public Relations Officer (PRO) for this Project, conforming to the Revisions to Section 626 as identified in the Project Special Provisions, who will support the County in outreach and communications for the Project.
14. Material Control: The Contractor shall be required to maintain rigid control of all materials which must comply with the specifications as stated. All materials not conforming to the requirements of the specifications at the time they are used shall be considered unacceptable.
15. Unacceptable Work/Unauthorized Work: Upon failure on the part of the Contractor to comply with any order of the County Engineer made under the provisions of this article, the County Engineer will have authority to cause unacceptable work to be remedied or removed and replaced, and unauthorized work to be removed, and to deduct the costs from any monies due or to become due to the Contractor.
E. RETAINAGE, PAYMENT, AND ACCEPTANCE
1. Partial payment will be made no more frequently than once a month, for Work satisfactorily completed, and accepted by the County Engineer, as the Work progresses. Said payments will be based upon an invoice submitted by the Contractor, and if necessary, a written estimate prepared by the County’s Inspector of the value of Work performed and materials furnished and placed in accordance with the contract. The County shall retain 5% of the amount estimated as payable, exclusive of mobilization and payments for materials on hand, to a maximum of 5% of the original contract amount, until successful completion and acceptance by the County of the entire contracted Work. The County Project Manager will approve and process payment requests. Then the balance less all previous payments shall be paid after an appropriate Notice of Final Payment has been published by the County Contracts & Procurement Division.
2. The County reserves the right to not approve payment wherein the service claimed on the invoice is not, in the County’s sole opinion, satisfactory or cannot be adequately verified by the County. If the County must supply services and/or contract with another Contractor for the services contracted hereunder, due to Contractor’s inability to perform as required, the cost will be charged back to the Contractor.
3. Upon notice from the Contractor of presumptive completion of the entire contracted Work, the County Project Manager will make an inspection. If all the Work provided per the contract is found to have been satisfactorily completed, the County Engineer will make final acceptance and shall notify the Contractor in writing of this acceptance. The Department of Public Works will submit a Notice of Substantial Completion to the Contracts & Procurement Division, from which a Notice of Final Payment will be published by Contracts & Procurement. Retainage cannot be released nor is final payment made prior to the release date listed in the Notice of Final Payment.
4. Final payment will be made after the Contractor has indicated in writing its acceptance of such final payment as full and complete, has released El Paso County from all claims arising from the prosecution of
Invitation for Bid #26-117 Page of 359 all Work under the contract, and after Notice of Final Payment has been published by the County Contracts & Procurement Division.
III. RESPONSE FORMAT AND REQUIRED DOCUMENTATION
Failure to respond in the required format or failure to provide required information may deem your submittal non-responsive.
To facilitate an effective review process, responses must be submitted on 8.5” x 11” paper, with a minimum font of 10, and all pages should be numbered in the following manner: page or pages, with a maximum of 50 (fifty) pages. All acronyms in the response must be defined.
Attachments/Exhibits included in this solicitation, that require signature and/or are a required document to be returned with your Responses shall be included as an exhibit to your Responses and will not be included in the page limit. Requested items in the appendices will not be included in the page limit. Schedules may be submitted on 11" x 17" sheets and are counted as one page.
Submittals should be prepared simply and economically providing a straightforward, concise description of the Contractor’s ability to perform the requirements of this Solicitation.
ELECTRONIC SUBMISSION OF OFFERS: El Paso County will only accept electronic bid Responses submitted through the Rocky Mountain E-Purchasing system. A Submittal Log will be posted after the County has had an opportunity to review and verify the submittals offered to the County and PPRTA.
The original Offer must be received before the due date and time through an electronic package transmitted through the Rocky Mountain E-Purchasing system. The Contractor is responsible for ensuring its Response is posted by the due date and time outlined in the solicitation document.
If the submittal arrives late, it will not be included in the electronic lockbox.
The Solicitation Opening for IFB-26-117 will take place VIA TELECONFERENCE utilizing the call-in information below:
Participant-guest login:
A. Dial access number: 1-719-520-7660 B. Enter the participant-guest pass code: 51488# C. Attendee access code: 1234#
Proposers are NOT required to participate. No in-person entry to our building will be permitted.
To enable the County to conduct a uniform review of the information submitted in response to this Solicitation, Contractors must address the following information, numbered to directly correspond with the number of the Table of Contents section of the submitted Response. The County reserves the right to reject submittals that do not follow the required format. Include concise, complete information which will demonstrate that your firm is uniquely qualified to provide the products and services specified in this Solicitation.
ALL signatures on required documents must be in blue ink or a verifiable electronic time and date stamped signature in ONE PDF document. Typed names as signatures are not allowed.
1. Provide response without reference to El Paso County logo or company logo in one PDF document.
2. Submit response in a tab format that follows a clearly outlined Table of Contents that identifies all material and attachments that comprise your response by section and by page number. I.e. – Required Documentation section, Evaluation Criteria section, etc. as outlined on the Response Submittal Requirements page.
3. Cover Letter, one-page limit. Submit a Cover Letter on official business letterhead that:
a. Positively states your willingness to comply with all work requirements and other terms and conditions as specified in this Solicitation.
b. Provides, in brief concise terms, a summation of your submittal and identifies the points
Invitation for Bid #26-117 Page of 3510 that make your firm uniquely qualified for this project.
c. Is signed by an Authorized Representative of your firm who has the authority to commit to the proposed work.
4. Provide documentation that satisfies the Required Document Requirements
a. Contractor Information Form
b. Proprietary / Confidential Statement
c. Artificial Intelligence Use Attestation
d. Subcontractor list (if applicable)
e. Exhibit 1 – Exceptions Form
f. Exhibit 2 – Lobbying Certification
g. Exhibit 3 – Non-Collusion Affidavit
h. Exhibit 4 – Minimum Insurance Requirements
i. Completed and signed Cover Sheet
j. Addendum(s) Acknowledgement, if applicable
k. Universal Entity Identifier (UEI) Number
l. Bid Form - Contractor shall use the Bid Form attached to this IFB or as amended via addendum(s). Other forms/formats will not be accepted.
m. Documentation of Meeting Minimum Requirements
n. Work Plan and Schedule - Schedules submitted for this bid shall assume a contract award per the IFB Schedule of Activities.
5. Provide documentation that satisfies the criteria to be reviewed.
6. Provide the completed and signed Cover Sheet
7. Addendum(s) Acknowledgement, if applicable
8. Submission Form
9. Documentation of Meeting Minimum Requirements 10.Universal Entity Identifier (UEI) Number
11. Additional Attachments, if applicable
IV. ATTACHMENTS
1. Mesa Ridge Parkway Bid Form
2. Mesa Ridge Parkway AD Construction Plans
3. Mesa Ridge Parkway Grading and Erosion Control Plans
4. Mesa Ridge Parkway Project Special Provisions
5. Mesa Ridge Parkway Project Standard Special Provisions
6. Mesa Ridge Parkway QC Materials Testing Frequency Schedule
7. Mesa Ridge Parkway Drainage Report
8. Mesa Ridge Parkway Hydrology Memo
9. Subcontractor Monthly Payment Summary
10. Subcontractor Periodic Payment Confirmation
11. ESQCP Application Form
12. PPRTA Special Funding Provisions
13. PPRTA General Conditions to Construction Contract
REMAINDER OF PAGE LEFT INTENTIONALLY BLANK
Invitation for Bid #26-117 Page of 3511
Bidders are required to use attachment 1. Mesa Ridge Parkway B i d Form to provide a bid for this solicitation. Failure to use attachment 1. Mesa Ridge Parkway Bid Form may result in y o u r bid being found non-responsive.
Bidders may not change or alter the amounts, quantities, or information in the bid form. Editing or changing details of the Bid Form may result in your bid being non-responsive.
BID FORM
Invitation for Bid #26-117 Page of 3512
1. METHOD OF AWARD – LOWEST OFFERED
AGGREGATE PROJECT PRICE: It is the intent of the County to award this Solicitation to the responsive, responsible Contractor who offers all items, whose pricing offers the lowest cost when all items are added in the aggregate and whose offer will be most advantageous to the County.
• A recommendation for an award based on the lowest bid shall be made if that bid meets all the specifications as outlined in the IFB, with no unacceptable exceptions. If the lowest bidder takes exception(s) to the specifications it is considered the low bid and should be recommended for award.
• However, the lowest-dollar bidder is not required to be recommended for award if it:
• Does not meet all the specifications as outlined in the IFB.
SPECIAL TERMS AND CONDITIONS
Invitation for Bid #26-117 Page of 3513
• Takes exception to any of the specifications that is not acceptable.
• Cannot meet acceptable delivery requirements.
• Has additional costs that make the overall total cost higher than the next low bid.
• Has an unacceptable warranty limitation(s).
• Has past documented history by the requesting department/office, by reference(s) or in the Contracts and Procurement Division file of poor quality, delivery or other information that would affect the operation of the requesting department/office.
2. BID GUARANTY IS REQUIRED FOR A PERCENTAGE OF THE TOTAL PRICE: All Responses shall be accompanied by a Bid Guaranty in the form of a Certified Check, Cashier’s Check or Bid Bond, made payable to EL PASO COUNTY, in the amount that represents 5% of the total base price. The Bid Guaranty shall be made payable to County and shall be conditioned upon the successful Vendor submitting a specified performance bond within ten (10) calendar days following written notice of award. Any Response which is not accompanied by a Bid Guaranty shall be considered nonresponsive and ineligible for award. In the event the selected Vendor fails or refuses to submit the performance bond within the time stated, the Bid Guaranty/Security submitted with the Response will be forfeited as liquidated damages because of such failure or default. The bid guarantees will be returned after the opening of Responses to all except the three lowest responsible, responsive Vendors and the remaining guarantees shall be returned to these Vendors after the contract with the selected Vendor(s) is executed.
3. PERFORMANCE BOND BASED ON A PERCENTAGE OF THE OFFERED PRICE: The Vendor to whom a contingent award is made shall duly execute and deliver a Performance and Payment Bond to the County in an amount that represents 100% of the price offered by the Vendor. The Vendor may deliver multiple bonds in lieu of a single bond, provided the total amount of these bonds equals the amount specified above.
The bond shall be delivered to the County’s Contracts and Procurement Division within ten (10) calendar days after a Notice of Intent to Award is given to the Vendor, either verbally or in writing. If the Vendor fails to deliver the bond within this specified time frame, including any extensions which may be granted by the County, the County shall declare the Vendor in default of the contractual terms and conditions, and the Vendor shall surrender its Bid Bond. In lieu of a Performance and Payment Bond, the County will accept a cash bond in the form of a certified cashier’s check made payable to El Paso County.
Should an Extension(s) or Amendment(s) be completed on the contract that increases the amount of the contract, it shall be a requirement that the Vendor request additional bonding capabilities from their Bonding Agent to match the amended contract amount and the Vendor shall be responsible for paying any fees associated with the increase in the bonding amount. The County shall not be responsible for nor pay for any bonding fee increases.
4. PRICE OFFERS SHALL BE FIXED AND FIRM: The prices offered by the Contractor shall remain fixed and firm. No changes in the Bid shall be allowed after the date and time of the Solicitation opening due to an error by the Contractor. Bids may not be withdrawn after the time and date set for the Solicitation opening for a period of ninety calendar days.
5. POST INTENT TO AWARD MEETING: The Contractor may be required to attend a post intent to award meeting with the County to discuss the terms and conditions of the contract. This meeting will be coordinated by the Contracts and Procurement Division once a Notice of Intent to Award has been issued.
6. COMPETENCY OF CONTRACTORS – MINIMUM ONE (1) YEAR OF EXPERIENCE AND OPERATIONAL REQUIREMENTS: Bids will only be considered from Contractors which have been engaged in the business of performing the Work as described in this Solicitation. Contractors must be able to produce evidence that they have an established satisfactory record of performance for a minimum of one (1) year and have sufficient financial support, equipment, and organization to ensure that they can satisfactorily execute the services if awarded a contract. The term ‘equipment and organization’ as used herein shall be construed to mean a fully equipped and well-established company in line with the best business practices in the industry and as determined by the proper authorities of the County and PPRTA.
The Contractor shall submit, with its bid, such evidence of its qualifications including a maximum of five (5) relevant projects with similar services, timelines and/or magnitudes performed by the Contractor in the last seven (7) years and relevant projects with similar services, timelines and/or magnitudes performed by the Contractor’s Project Manager, Superintendent and/or Foreman(s). Similar services shall be specific to the
Invitation for Bid #26-117 Page of 3514 following:
The County and PPRTA may consider any evidence available to it (including, but not limited to, the financial, technical, and other qualifications and abilities of the Contractor) in making the award in the best interests of the County.
7. QUALIFICATIONS OF CONTRACTOR: The County and PPRTA may make such investigations as deemed necessary to determine the ability of the Contractor to perform the work, and the Contractor shall furnish all information and data for this purpose as the County and PPRTA requests. Such information includes but not limited to: current/maximum bonding capabilities, current licensing information, audited financial statements, history of the firm on assessments of liquidated damages, contracts cancelled prior to completion and/or lawsuits and/or pending lawsuits against the firm and/or its principals. The County reserves the right to reject any Response if the evidence submitted by, or investigation of, such Contractor fails to satisfy the County that such Contractor is properly qualified to carry out the obligations of the Solicitation and to complete the work contemplated therein. Conditional Responses will not be accepted.
8. PAST PERFORMANCE: The County may review Past Performance with El Paso County, PPRTA, or another entity and/or make such investigations as deemed necessary to determine the ability of the Contractor to perform work outlined in this solicitation. If the County has terminated a contract with the Contractor within the past three (3) years, the Contractor may be asked to furnish information for this investigation as the County requests. Such information includes but not limited to: current/past company references, current licensing information, history of the firm on assessments of liquidated damages, contracts cancelled prior to completion and/or lawsuits and/or pending lawsuits against the firm and/or its principals. The County reserves the right to reject any Response if the evidence submitted by, or investigation of, such Contractor fails to satisfy the County and PPRTA that such Contractor is properly qualified to carry out the obligations of the Solicitation and to complete the work contemplated herein.
Conditional Responses will not be accepted.
9. LIQUIDATED DAMAGES FOR INCOMPLETE PROJECTS: If required, Liquidated Damages shall be invoked as specified in the “STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION”, Colorado Department of Transportation, State of Colorado (2023).
10. CONFLICTS WITHIN THE CONTRACT DOCUMENTS: In the event that conflicts exist within the Contract Documents, the policies stated in the following paragraphs shall govern: A. Project Special Provisions (PSP) shall supersede Construction Plans (Plans), and Plans shall supersede SOQ Specifications (Specifications).
B. Addenda shall supersede all other Contract Documents to the extent specified. Subsequent addenda shall supersede prior addenda only to the extent specified.
The Plans, PSP and Specifications are intended to agree and be mutually explanatory and shall be accepted and used as a whole and not separately. Should any item be omitted from the Plans, PSP or Specifications as specified, it shall be implied that such omissions are contained in all three as necessary for the proper construction of the work herein specified. Should any error or disagreement between the three exist or appear to exist, the Contractor shall not avail itself of such manifestly unintentional error or omission but must have same explained or adjusted by the County’s project manager before proceeding with the work in question.
11. CONSIGNMENT OF CONTRACT NOT ALLOWED: No part of this contract can be consigned to another Contractor.
12. SUBCONTRACTORS OF WORK SHALL BE IDENTIFIED: As part of its Response, the Contractor shall be required to identify any and all subcontractors that will be used in the performance of the contract resulting from this Solicitation. The Contractor shall also identify the capabilities, experience, and portion of the work to be performed by the subcontractor(s). The competency of the subcontractor(s) with respect to skill, responsibility and business standing shall be considered by the County when making the award in the best interest of the County.
Invitation for Bid #26-117 Page of 3515
13. CURRENT PERMITS REQUIRED: Contractor must obtain and pay for all required permits, licenses, inspection fees, etc., and will comply with all laws, ordinances, and regulations associated with construction of the Project. Damages, penalties and/or fines imposed by the County on the Contractor for failure to obtain required permits, licenses, certificates or pay fees shall be borne by the Contractor. The Contractor shall enclose a current copy of their applicable permits, licenses, and inspection certificates with their Response.
14. LICENSES REQUIRED FOR TRADES: Professional contractors performing services in/for the County and PPRTA must show that they have been duly licensed by the municipality where the work is being performed, if required by that municipality, prior to being awarded a contract by the County.
15. LABOR, MATERIALS AND EQUIPMENT TO BE SUPPLIED BY THE CONTRACTOR: Unless otherwise provided in this Solicitation, the Contractor shall furnish all labor, materials, and equipment necessary for satisfactory contract performance. When not specifically identified in this Solicitation, such materials and equipment shall be of a suitable type and grade for the intended purpose.
16. VARIATIONS ALLOWED IF INDICATED: For purposes of Response review, Contractors must indicate any variances to the Specifications, terms, and conditions, and attached Sample Agreement no matter how slight. If variations are not stated in the Contractor’s Response, it shall be construed that the Response fully complies with the Specifications, terms, and conditions, and attached Sample Agreement. Notwithstanding the above, it is hereby agreed and understood that the County reserves the right to reject these variations if they individually, or as a whole, do not meet the standards established in the Specifications.
17. ADDITIONAL SERVICES MAY BE PURCHASED DURING CONTRACT PERIOD: Although this Solicitation specifies an exact location where services are to be performed for the County, it is understood and agreed that the County and PPRTA may, during the term of the awarded contract, request additional services for the same or other locations within the proximity of the Project limits from the successful Contractor. This option, if exercised, is the prerogative of the County and PPRTA and shall be honored by the Contractor as a condition of contract award.
18. ACCIDENT PREVENTION: The Contractor shall be required to take safety precautions in an effort to protect persons and property. All Contractors, Contractors and sub-Contractors shall conform to all OSHA, State and County regulations while performing under the terms and conditions of the awarded contract. Any fines levied by the above-mentioned authorities because of inadequate compliance with these requirements shall be borne solely by the Contractor which is responsible for same.
DEFICIENCIES IN WORK TO BE CORRECTED BY CONTRACTOR: The successful Contractor shall promptly correct all deficiencies in service and/or any work that fails to conform to the Contract Documents. All corrections shall be made immediately after such deficiencies and/or non-conformances are verbally reported to the Contractor by the County’s Project Manager. The Contractor shall bear all costs of correcting such rejected work. If the Contractor fails to correct the work within the period specified in this Solicitation, the County reserves the right to place the Contractor in default of its contractual obligations, obtain the services of another Contractor and charge the Contractor for these costs, either through a deduction from the final payment over to the Contractor or through invoicing.
19. COMPLETION OF WORK: The Contractor shall adhere to the timeline and milestones provided in its Response in which it will commit to perform the work and/or service. All work shall be performed in accordance with good commercial practice and the timeline and milestones shall be adhered to by the successful Contractor, except in such cases where the timeline will be delayed due to acts of God, strikes, or other causes beyond the control of the Contractor. In these cases, the Contractor shall notify the County of the delays in advance of the original timeline so that a revised timeline can be negotiated.