This is a Request for Proposals (RFP 2027-006) issued by the Municipal Subdistrict of the Northern Colorado Water Conservancy District for the Chimney Hollow Spillway Fall Protection project located in Colorado. The scope of work consists of designing, furnishing, installing, testing, and certifying a continuous fall protection system for an 8-foot by 10-foot box culvert spillway at Chimney Hollow Reservoir spanning 2,963 linear feet with capacity for three simultaneous users. The system must provide 100 percent tie-off along the full inspection route with pass-through intermediate brackets and curve components on a sloped alignment with grades up to 25 percent. The solicitation was issued on November 3, 2026, with a mandatory pre-proposal meeting scheduled for November 13, 2026, at 10:00 AM (MT) at Northern Water's Main Campus in Berthoud, Colorado. The proposal question deadline is November 24, 2026, at 12:00 PM (MT), and proposals are due December 15, 2026, at 2:00 PM (MT) through the Rocky Mountain E-Purchasing System (RMEPS). Respondents may be invited to interviews on January 18, 2027. The contract term begins upon execution and Notice to Proceed and continues until final completion and acceptance of all work, including delivery of closeout documents and completion of warranty obligations.
The cost proposal must include lump-sum pricing for nine itemized scope components covering mobilization, site assessment, engineering, materials, installation labor, testing and certification, training, documentation, and all permits and overhead, with total base proposal pricing serving as the evaluation basis. Additional separately stated pricing is required for allowances covering unforeseen conditions and unit prices for additional linear footage, shuttles, and field labor, as well as optional post-installation services including annual inspections and recertification. Respondents must warrant workmanship for at least one year and assign all manufacturer warranties to the Subdistrict. The evaluation criteria allocate 100 total points across qualifications and experience (20 points), project team (15 points), project approach (25 points), schedule capability (15 points), project references (10 points), cost proposal (10 points), and contract terms acceptance (5 points). No set-asides are identified for this solicitation. The Subdistrict reserves the right to reject all proposals, negotiate terms with the selected respondent, and proceed to the next highest-rated respondent if the selected respondent fails to execute the contract within 30 days of the Notice of Intent to Award. Proposals are valid for 90 calendar days after the proposal due date.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
RFP 2027-006
FOR
CHIMNEY HOLLOW SPILLWAY FALL PROTECTION
Solicitation Date: November 3, 2026 Proposal Due Date: December 15, 2026, at 2:00 PM (MT)
TABLE OF CONTENTS
I. INTRODUCTION
II. NORTHERN WATER BACKGROUND
II.1 Northern Colorado Water Conservancy District
II.2 Municipal Subdistrict
III. PROCUREMENT OVERVIEW
III.1 Request for Proposals
III.2 Pre-Proposal Meeting
III.3 Proposal Questions
III.4 Proposal Documents
IV. INSTRUCTIONS TO RESPONDENTS
IV.1 Schedule
IV.2 Confidentiality and Public Disclosure
IV.3 Modification or Withdrawal of Proposals
IV.4 Conflicts of Interest
V. SCOPE OF SERVICES
V.1 Contract Term
VI. CONTENTS OF PROPOSALS
VI.1 Qualifications and Experience
VI.2 Project Team
VI.3 Project Approach
VI.4 Anticipated Schedule
VI.5 Project References
VI.6 Cost Proposal
VI.7 Contractual Terms
VII. SELECTION PROCEDURE
VII.1 Interviews
VIII. AWARD OF CONTRACT
IX. RIGHTS OF THE SUBDISTRICT
X. ATTACHMENT A – TIMETABLE
XI. ATTACHMENT B – SCOPE OF SERVICES
1. Project Location and Site Conditions
2. System Performance Requirements
3. Design and Engineering Services
4. Materials and Components
5. Installation
6. Testing, Certification, and Commissioning
7. Training
8. Documentation and Deliverables
9. Warranty and Post-Installation Support
10. Respondent Responsibilities and Site Requirements
XII. ATTACHMENT C – COST PROPOSAL
XIII. ATTACHMENT D – CHIMNEY HOLLOW FACILITIES MAP
XIV. ATTACHMENT E – PROPOSAL CONTACT INFORMATION AND
ACKNOWLEDGMENT
XV. ATTACHMENT F – DRAFT CONTRACT
XVI. ATTACHMENT G – ACKNOWLEDGMENT OF SUBDISTRICT CONTRACT
XVII. ATTACHMENT H – SAMPLE CERTIFICATE OF INSURANCE
I. INTRODUCTION
The Municipal Subdistrict of the Northern Colorado Water Conservancy District (Subdistrict) is issuing this Request for Proposals (RFP) from qualified Respondents for the Chimney Hollow Spillway Fall Protection project. The Work consists of designing, furnishing, installing, testing, and certifying a fall protection system along the box culvert spillway at Chimney Hollow Reservoir, including associated engineering, training, documentation, and commissioning services.
II. NORTHERN WATER BACKGROUND
Northern Water is headquartered in Berthoud, Colorado (approximately 40 miles north of Denver) and has more than 195 full-time staff members engaged in the operations, engineering, environmental, financial, and administrative functions of the Northern Colorado Water Conservancy District and the Municipal Subdistrict. Most staff work out of Northern Water’s headquarters in Berthoud with some out of Northern Water’s Willow Creek Campus in Granby, Colorado.
II.1 NORTHERN COLORADO WATER CONSERVANCY DISTRICT
The Northern Colorado Water Conservancy District (Northern Water) is a political subdivision and a quasi-municipal corporation of the state of Colorado created by decree of the District Court of Weld County, Colorado, on September 20, 1937, pursuant to the Water Conservancy Act. The Water Conservancy Act empowers Northern Water or any duly created subdistrict to acquire water; to obtain rights-of-way for certain water works; to contract with the United States or otherwise; to provide for construction of water facilities; to assume contractual or bonded indebtedness; to administer, operate, and maintain physical works; to conserve, control, allocate, and distribute water supplies for supplemental use; and to derive the revenues needed to accomplish its purposes.
As authorized under the Water Conservancy Act, Northern Water has created four water activity enterprises:
• Southern Water Supply Project (SWSP) Water Activity Enterprise
• Pleasant Valley Pipeline (PVP) Water Activity Enterprise
• Northern Integrated Supply Project (NISP) Water Activity Enterprise
• Hydropower Water Activity Enterprise
Northern Water was created to contract with the U.S. Bureau of Reclamation (Reclamation) to build the Colorado-Big Thompson Project (C-BT Project). The C-BT Project provides supplemental water for irrigation of more than 550,000 acres of farm and ranch land and for use by more than 1.1 million people in eight Northeastern Colorado counties. Northern Water also engages in water management and https://www.northernwater.org/deliver-water/canals-pipelines-and-outlets/southern-water-supply-project https://www.northernwater.org/deliver-water/canals-pipelines-and-outlets/pleasant-valley-pipeline https://www.northernwater.org/deliver-water/plan-for-the-future/northern-integrated-supply-project https://www.northernwater.org/deliver-water/plan-for-the-future/northern-integrated-supply-project https://www.northernwater.org/deliver-water/hydropower planning activities for the purpose of meeting present and future water supply needs of water users within its boundaries.
The majority of C-BT Project water comes from mountain snowmelt in the upper Colorado River basin west of the Continental Divide. Northern Water delivers on average 200,000 acre-feet of untreated water each year to the South Platte River Basin. The C-BT Project was constructed and is mostly owned by the United States through Reclamation. Northern Water owns the portions of the C-BT Project downstream of Horsetooth Reservoir and Carter Lake. Northern Water and Reclamation jointly operate and maintain the C-BT Project.
II.2 MUNICIPAL SUBDISTRICT
The Municipal Subdistrict, Northern Colorado Water Conservancy District (Subdistrict), is a separate political subdivision and quasi-municipal corporation of the State and was created by decree of the District Court of Weld County, Colorado, on July 6, 1970. It was organized in 1970 for the principal purpose of developing a water supply for use by six (6) Front Range communities. Today, the Subdistrict provides a water supply to 17 public entities.
As authorized under the Water Conservancy Act, the Subdistrict has created two water activity enterprises:
• Windy Gap Project Water Activity Enterprise
• Windy Gap Firming Project Water Activity Enterprise
Today, the organization continues its early mission of collecting water west of the Continental Divide and delivering it to Northeastern Colorado for agricultural, municipal, domestic, industrial, and environmental uses. In addition to the current and future projects driving day-to-day operations, Northern Water also provides regional leadership through water efficiency programs, data collection and delivery, source water protection, and interagency cooperation.
For additional information about Northern Water and the Municipal Subdistrict, visit www.northernwater.org/.
III. PROCUREMENT OVERVIEW
III.1 REQUEST FOR PROPOSALS
This RFP process will be conducted solely via the Rocky Mountain E-Purchasing (RMEPS) website.
Respondents interested in submitting a Proposal may obtain the RFP documents by visiting the RMEPS website www.bidnetdirect.com/colorado and selecting Vendor Login or Vendor Registration, as https://www.northernwater.org/deliver-water/windy-gap-project https://www.northernwater.org/deliver-water/plan-for-the-future/chimney-hollow-reservoir-project http://www.northernwater.org/ applicable. Any information about this RFP received from any other source cannot be validated as accurate or complete. Respondents are encouraged to register with RMEPS to be able to download all pertinent documents and submit the Proposal. All related documents and any subsequent addenda will be posted to RMEPS.
Electronic Proposals for the Chimney Hollow Spillway Fall Protection RFP will be received from interested Respondents through the RMEPS system on Tuesday, December 15, 2026, by 2:00 PM (MT). Submit the complete, unredacted Proposal as a single PDF file. If submitting a redacted version, upload it as a separate PDF file through RMEPS. If you have any problems uploading your file on the RMEPS site, contact the RMEPS Support Team at 800-835-4603, option #2, or email e-procurementsupport@bidnet.com. Please note that this is an electronic lockbox; late Proposals will not be accepted. Please allow sufficient time to upload your Proposal before the deadline.
The complete, unredacted electronic Proposal submitted through RMEPS will be considered the record copy. Clearly label the filenames to distinguish the unredacted Proposal and any redacted version submitted in accordance with Section IV.2.
The electronic copy must be received by the Proposal due date and time. If a Respondent submits its electronic Proposal after the deadline, the electronic copy will not be accepted into RMEPS and will not be opened.
All communications regarding this RFP shall be directed exclusively to the Procurement Officer through RMEPS. Respondents shall not contact any other Subdistrict or Northern Water Board member, officer, employee, or agent regarding this solicitation. Failure to comply with this requirement may result in disqualification.
III.2 PRE-PROPOSAL MEETING
Attendance at the Pre-Proposal Meeting is highly recommended. The meeting will be held in person.
Attendees will meet at Northern Water’s Main Campus and travel together to the project site.
Date: Friday, November 13, 2026, at 10:00 AM (MT) Location: Northern Water – Building F, 220 Water Ave, Berthoud, CO 80513
III.3 PROPOSAL QUESTIONS
Before submitting a Chimney Hollow Spillway Fall Protection Proposal, each Respondent shall become fully informed about the extent and character of the required Work. All Proposal questions must be submitted in writing through RMEPS. Questions received after the deadline will not be considered.
All questions and associated answers, together with any other document changes, will be issued via RMEPS in the form of an addendum. All addenda will become part of the Contract documents. The Subdistrict will not provide and will not be responsible for oral clarification.
The deadline for Proposal questions is Tuesday, November 24, 2026, at 12:00 PM (MT).
If needed, an addendum will be issued by Thursday, December 3, 2026.
III.4 PROPOSAL DOCUMENTS
To assist Respondents in responding to this RFP, the following documents are incorporated into this RFP by reference (collectively, the “Proposal Documents”):
• Attachment A – Timetable
• Attachment B – Scope of Services
• Attachment C – Cost Proposal – Required submittal.
• Attachment D – Northern Water Facilities Map
• Attachment E – Proposal Contact Information and Acknowledgment – Required submittal.
• Attachment F – Draft Contract
• Attachment G – Acknowledgment of Subdistrict Contract – Required submittal.
• Attachment H – Sample Certificate of Insurance
Respondents must include completed Attachments C, E, and G with their Proposal. These required documents will not be counted toward the Proposal page limit.
IV. INSTRUCTIONS TO RESPONDENTS
IV.1 SCHEDULE
The Work is anticipated to begin after Contract execution and issuance of a Notice to Proceed. The Respondent shall propose a project schedule showing the duration and completion date for each task, the relationships among tasks, and key milestones. The final completion date will be established in the Contract based on the accepted project schedule. Respondents will be notified in advance of any changes to the procurement schedule through an addendum to this RFP. All dates identified herein are subject to revision by addendum. In the event of any conflict between schedules contained in this RFP, Attachment A – Timetable shall prevail.
IV.2 CONFIDENTIALITY AND PUBLIC DISCLOSURE
Once submitted, the Proposals, any comments regarding this RFP, and any other information, materials, or data provided by Respondents: (1) will become the property of Northern Water; (2) may not be returned to Respondents; and (3) will be subject to the Colorado Open Records Act (Colorado Revised Statutes § 24-72-201 et seq., hereinafter referred to as “CORA”). Northern Water will disclose all such materials in response to a CORA request unless the Respondent requests confidential treatment and submits the materials required below at the time of the initial Proposal. In the event of threatened or actual litigation regarding the redactions, the Respondent shall be responsible for the defense of the redactions and any costs or other financial impact to Northern Water relating to the threatened or actual litigation. Northern Water reserves the right to require the Respondent to make a deposit with Northern Water to cover its anticipated costs relating to any dispute regarding the disclosure of the materials, and to disclose the materials if the deposit is not provided.
A Respondent requesting confidential treatment of any portion of its Proposal or other submitted materials shall complete all of the following at the time of the initial Proposal:
• Clearly mark all information for which confidential treatment is requested in the complete, unredacted Proposal or other submitted materials, and identify each marked page and section on a confidentiality summary page placed at the end of the complete, unredacted Proposal;
• Upload a redacted version of the Proposal or other materials for disclosure as a separate PDF file through RMEPS, in addition to the complete, unredacted Proposal required by Sections III.1 and VI, and clearly label the filenames to distinguish the redacted and unredacted versions; and
• Include a page-by-page justification statement immediately following the confidentiality summary page in the complete, unredacted Proposal, identifying each redaction, the basis under CORA for the Respondent’s determination that the information is protected, and why the information should not be disclosed upon request.
In the event of a request to Northern Water for the disclosure of documents prepared or provided by the Respondent, Northern Water will promptly advise Respondent of such request in order to give Respondent the opportunity to object to the disclosure of any material it may consider exempt from disclosure. However, Northern Water retains full discretion to disclose any materials it deems necessary in response to a CORA request, including materials marked as confidential by Respondent. Respondent waives any claim against Northern Water based on such disclosure. In the event of the filing of a lawsuit to compel disclosure, Northern Water will tender all such material to the court for judicial determination of the issue, and Respondent agrees it will either:
• Intervene in such lawsuit and oppose disclosure of the materials; or
• Waive any claim of privilege or confidentiality.
If Respondent chooses to intervene in such lawsuit and opposes disclosure of any materials, Respondent agrees to defend, indemnify, save, and hold harmless Northern Water, its officers, agents, and employees, from any claims, damages, expenses, loss, or costs arising out of Respondent’s intervention and/or opposition to disclosure.
IV.3 MODIFICATION OR WITHDRAWAL OF PROPOSALS
Respondents may modify or withdraw a previously submitted Proposal through RMEPS at any time before the Proposal due date and time. To modify a Proposal, the Respondent must withdraw the prior submission and upload a complete revised Proposal through RMEPS before the deadline. The most recent complete Proposal received through RMEPS by the due date and time will be considered the Respondent’s official submission. A withdrawn Proposal will not be considered unless it is resubmitted through RMEPS before the deadline. No Proposal may be withdrawn for ninety (90) calendar days after the Proposal due date. Proposals may not be modified after the deadline unless requested by the Subdistrict.
Late submission of Proposals will not be accepted.
IV.4 CONFLICTS OF INTEREST
Respondents shall fully disclose to the Subdistrict all known or potential conflicts of interest that could influence or appear to influence the Respondent’s judgment or performance of the Work. This includes, without limitation, all relationships that could create such conflicts and any financial interest the Respondent may have that relates to the Work, including compensation the Respondent has received or expects to receive from entities other than the Subdistrict related to the Work.
V. SCOPE OF SERVICES
The Subdistrict is seeking a qualified Respondent to design, furnish, install, test, and certify a fall protection system for the 8-foot by 10-foot box culvert spillway at Chimney Hollow Reservoir. The system must provide continuous, 100 percent tie-off for the full 2,963-foot inspection route and support up to three simultaneous users.
The selected Respondent shall provide all labor, materials, equipment, supervision, and coordination necessary to complete the Work in accordance with the requirements set forth in this RFP. A more detailed description is attached hereto as Attachment B.
V.1 CONTRACT TERM
The Contract term shall begin on the execution date and continue until final completion and acceptance of the Work, including delivery of all required closeout documents and completion of warranty obligations, unless earlier terminated in accordance with the Contract.
VI. CONTENTS OF PROPOSALS
Submit the complete, unredacted Proposal as a single PDF file. If submitting a redacted version, upload it as a separate PDF file through RMEPS. The Proposal shall not exceed twenty-five (25) pages, excluding individual resumes and the section addressing contractual terms. Individual resumes shall be limited to two (2) pages each. Attachments C, E, and G and any requested redlined Contract exceptions are also excluded from the page limit.
The confidentiality summary page and page-by-page justification statement required by Section IV.2 are excluded from the page limit and shall be placed at the end of the complete, unredacted Proposal. A redacted version shall retain the corresponding Proposal page numbering and may not contain additional substantive Proposal content. Failure to comply with these requirements may render the Proposal non-responsive. This section is the sole authoritative reference for Proposal length and page-limit exclusions.
No other section modifies these requirements.
Respondents are encouraged, but not required, to provide one (1) redacted PDF Proposal excluding information that is not subject to disclosure under the Colorado Open Records Act (CORA). Please refer to Section IV.2 of this RFP for additional information. A Respondent submitting a redacted version must upload both the redacted and unredacted files through RMEPS. If a redacted copy is not received, the Respondent’s original copy will be used to respond to public records requests.
Proposals shall follow the format below and address each of the following:
VI.1 QUALIFICATIONS AND EXPERIENCE
This section of the Proposal shall summarize the Respondent’s recent experience performing work of similar size, scope, and complexity. The Proposal will be evaluated on the Respondent’s demonstrated experience designing, furnishing, installing, testing, and certifying engineered fall protection systems in spillways, water facilities, or similarly challenging outdoor environments. Consideration will be given to the Respondent’s experience with fall protection systems, curved alignments, concrete anchorage design and installation, fall-clearance analysis, multi-user systems, corrosion-resistant components, proof-load testing, commissioning, training, and compliance with applicable OSHA requirements and the ANSI/ASSP Z359 Fall Protection Code. Respondents may include no more than five (5) projects completed within the past five (5) years or currently in progress.
For each related project, provide the following information:
a. Name of client.
b. Name and current contact information of the primary client contact.
c. Date the relevant work was completed or indication that the project is ongoing.
d. Specific role of the Respondent on the project.
e. Location of the office having primary responsibility for the project.
f. Name of the project manager or service lead.
g. Initial contract amount and initial completion date, if applicable.
h. Final contract amount and final completion date, if applicable.
i. Description of the involvement of staff proposed for the Subdistrict’s project.
Information regarding projects that did not actively involve members of the proposed project team should be minimized.
VI.2 PROJECT TEAM
Respondents shall propose a project team and include a diagram depicting the team organization. The Proposal will be evaluated on the qualifications, expertise, availability, and relevant experience of the personnel assigned to the Chimney Hollow Spillway Fall Protection project, including experience in engineered fall protection system design, structural and concrete anchorage engineering, fall-clearance analysis, installation on curved spillway alignments, corrosion-resistant systems, proof-load testing, commissioning, training, and compliance with applicable OSHA requirements and the ANSI/ASSP Z359 Fall Protection Code. Consideration will be given to the clarity of proposed roles and responsibilities, the relevance of key personnel to the project requirements, and the availability of assigned staff to complete the Work within the proposed schedule. Resumes shall emphasize relevant experience and include each individual’s geographic office location, proposed role, and qualifications.
a. Identify the proposed project manager, qualified person, Colorado-licensed Professional Engineer, system designer, installation superintendent, competent person responsible for inspection and testing, trainer, and any other key personnel assigned to the project.
b. Identify the geographic office location to which each proposed team member is normally assigned.
c. Describe the proposed responsibility and function of each identified team member, including responsibility for design, engineering approval, installation, testing, certification, training, and project coordination.
d. Summarize the background, relevant fall protection experience, education, licenses, certifications, and qualifications of each proposed team member.
e. Provide primary project contact information for coordination with the Subdistrict
VI.3 PROJECT APPROACH
Respondents shall demonstrate an understanding of the Chimney Hollow Spillway Fall Protection project objectives and provide a proposed approach for designing, furnishing, installing, testing, certifying, and commissioning the permanent fall protection system. The Proposal will be evaluated on the clarity and soundness of the Respondent’s methodology for conducting the site assessment and field survey; verifying spillway alignment, concrete conditions, embedded reinforcement, access constraints, and fall-clearance requirements; completing engineered design and stamped submittals; procuring compatible corrosion-resistant components; installing the 2,963-linear-foot pass-through system for three simultaneous users; performing proof-load testing and commissioning; and providing training, as-built documentation, certification, and closeout deliverables. Consideration will also be given to how well the proposed approach maintains continuous tie-off, addresses curved alignment and expansion joints, protects the spillway and waterway, accommodates operational restrictions, and complies with applicable OSHA requirements and the ANSI/ASSP Z359 Fall Protection Code.
Respondents shall describe how they will deliver the requested services, including their proposed work plan, design and installation sequencing, assumptions, site access and coordination with the Subdistrict, quality-control and safety processes, environmental protection measures, schedule management, testing and certification procedures, training approach, and anticipated deliverables for each phase of the Work.
VI.4 ANTICIPATED SCHEDULE
The Work is anticipated to begin after Contract execution and issuance of a Notice to Proceed.
Respondents shall submit a proposed project schedule identifying the anticipated timing and duration of each major task, including site assessment and field survey, design development and stamped submittals, Subdistrict review, material procurement and fabrication, mobilization and installation, testing and certification, commissioning and training, and final documentation and closeout. To the extent practicable, the schedule shall depict task sequencing, dependencies, deliverable submission dates, site-access requirements, operational constraints, and key project milestones. The Proposal will be evaluated on the reasonableness and completeness of the proposed schedule, consistency with the project requirements, the Respondent’s communication and progress-reporting approach, and its ability to coordinate effectively with Subdistrict staff and complete the Work within the proposed schedule. The final completion date will be established in the Contract based on the accepted project schedule.
VI.5 PROJECT REFERENCES
This section of the Proposal shall include current or recently completed project references for work of similar size, scope, and complexity, preferably involving the design, furnishing, installation, testing, and certification of engineered fall protection systems in spillways, water facilities, or similarly challenging outdoor environments. References should demonstrate the Respondent’s ability to deliver work comparable to the Chimney Hollow Spillway Fall Protection project, including pass-through systems, curved alignments, concrete anchorage, multi-user capacity, corrosion-resistant components, proof-load testing, commissioning, and training.
Respondents shall provide references for no more than five (5) projects completed within the past five
(5) years or currently in progress. Respondents may use the same projects to satisfy Sections VI.1 and VI.5; separate sets of projects are not required. Information provided in Section VI.1 may be incorporated by cross-reference rather than repeated, provided that each cross-reference identifies the applicable project and the specific Proposal page or pages containing the required information. For each project offered as a reference, Section VI.5 shall include the client’s name and the primary client contact’s name and current contact information. All remaining reference details required below shall be provided either directly in Section VI.5 or through specific cross-references to Section VI.1. Respondents remain responsible for ensuring that the information provided collectively addresses every requirement of both sections. For each reference, provide the following information:
a. Name of client.
b. Name and current contact information of the primary client contact.
c. Date the project was completed or indication that the project is ongoing.
d. Specific role of the Respondent in designing, furnishing, installing, testing, certifying, commissioning, or training users on the referenced fall protection system.
e. Location of the office having primary responsibility for the project.
f. Name of the project manager or service lead assigned to the client.
g. Initial contract amount.
h. Involvement of staff proposed for the Subdistrict in the referenced project.
i. Brief description of the reference project’s relevance to the Chimney Hollow Spillway Fall
Protection scope and performance requirements.
VI.6 COST PROPOSAL
Respondents shall complete and submit the Cost Proposal in Attachment C. The Cost Proposal must include a total base proposal with separate lump-sum pricing for each listed scope component; all requested allowances and unit prices; pricing for optional post-installation services; a proposed project delivery schedule; pricing assumptions and exclusions; and a proposed payment schedule. The Total Base Proposal shall equal the sum of Items 1 through 9 in Attachment C and shall exclude the separately stated unforeseen-conditions allowance, additional-work unit prices, and optional post-installation services. The Total Base Proposal will be the pricing basis for the Cost Proposal evaluation; separately stated allowance amounts, unit prices, and optional service prices will be reviewed for completeness and reasonableness but will not be added to that evaluation amount. Any additional work or optional services require the Subdistrict’s written authorization in accordance with the Contract, and an allowance amount does not itself authorize work or payment. Prices must include all labor, engineering, supervision, materials, equipment, mobilization, testing, certification, commissioning, training, documentation, permits, freight, travel, taxes, bonds, insurance, overhead, profit, and all other costs necessary to complete the Work. Respondents shall complete the certification and signature fields in Attachment C.
Failure to provide complete pricing may render the Proposal non-responsive.
VI.7 CONTRACTUAL TERMS
Included with this RFP is a sample Draft Contract (Attachment F) and a sample Certificate of Insurance showing the required types of insurance and limits (Attachment H) that the Subdistrict intends to use for obtaining the services of the prospective Respondent. Respondents are required to review the Draft Contract and indicate whether the Contract terms, including insurance requirements, are acceptable. If revisions to the Contract terms are requested, the Respondent must provide suggested revisions as part of the Proposal. Any exceptions not noted as part of the Proposal will not be negotiable during Contract finalization. Exceptions to terms will be considered as part of the evaluation process.
VII. SELECTION PROCEDURE
Proposals will be reviewed, evaluated, and scored by a Subdistrict Evaluation Committee of three or more personnel using the criteria and point values listed below. The selection process is intended to identify the highest-rated responsive Respondent whose Proposal represents the best overall fit and value for the Subdistrict’s project needs. Fit and value will be assessed through the stated evaluation criteria, including qualifications, project team, approach, schedule, references, cost, and acceptance of Contract terms and insurance requirements. This process is designed to identify the Respondents whose Proposals are most advantageous to Northern Water based on the following criteria:
1. Qualifications and Experience (20 points)
2. Project Team (15 points)
3. Project Approach and Relation to Subdistrict’s Needs (25 points)
4. Ability to Meet Project Schedule (15 points)
5. Past Project References (references may be contacted during the review process) (10 points)
6. Cost Proposal (10 points)
7. Ability to Meet Contract Terms and Insurance Requirements (5 points)
Proposal submittals will be independently evaluated and scored by each Evaluation Committee member based on the criteria outlined above. Each criterion listed above has a designated point value and will serve as the basis for reviewing the written Proposals.
Proposals will be evaluated based on the extent to which each response addresses the applicable evaluation criteria, demonstrates cost transparency, and is responsive to the requirements of this RFP.
The rating scale corresponds to the total points available for each criterion, with the maximum points awarded for an outstanding response. Scores from all evaluators will be tabulated, and Respondents receiving the highest overall scores may be invited to participate in interviews, if deemed necessary by the Subdistrict. Proposal scores will be compiled by the Procurement Officer.
VII.1 INTERVIEWS
Interviews may be held at the discretion of the Subdistrict to assist in the selection process. Interviews will be separately scored. The format for the interview will be as follows:
1. Respondent Presentation
2. Question-and-Answer Session: Respondents should be prepared to answer questions regarding their respective Proposals. The Subdistrict may provide Respondents with questions before the interview date.
3. Approach to Pricing: Respondents should be prepared to present, discuss, and answer questions regarding their approach to pricing.
Respondent interviews will be scheduled for January 18, 2027 at Northern Water’s headquarters in Berthoud, Colorado, or via a virtual meeting. It is strongly recommended that the Respondent keep this day available for a possible interview.
Final selection will be based on the final overall evaluation results, including interviews if conducted.
The highest-rated responsive Respondent will be the Respondent whose Proposal represents the best overall fit and value for the Chimney Hollow Spillway Fall Protection project under the stated evaluation criteria, subject to successful Contract negotiation and the Subdistrict’s reserved rights.
VIII. AWARD OF CONTRACT
Once the Evaluation Committee has completed evaluations and interviews, if conducted, the Subdistrict shall notify all Respondents of its selection and the identity of the successful Respondent.
The successful Respondent shall execute a Contract with the Subdistrict within 30 days after the Notice of Intent to Award and shall submit a Certificate of Insurance in compliance with the insurance requirements. If the selected Respondent fails to enter into the Contract with the Subdistrict, the Subdistrict reserves the right to proceed to the next highest-rated responsive Respondent based on the final overall evaluation results described in Section VII. This process shall continue until the Contract is executed with a responsive Respondent, the Subdistrict announces that it is rejecting all Proposals, or the Proposal Validity Period expires, whichever occurs first. For purposes of this RFP, the “Proposal Validity Period” is the ninety (90) calendar days after the Proposal due date, consistent with Section IV.3 and Attachments C and E.
The Subdistrict reserves the right to reject any and all Proposals, to waive informalities or irregularities, to request clarification or additional information, to negotiate final terms with the selected Respondent, and to make an award in the best interest of the Subdistrict.
IX. RIGHTS OF THE SUBDISTRICT
The Subdistrict reserves, holds, and may exercise, at its sole discretion, the following rights and options regarding this RFP and selection process in accordance with applicable law:
1. To determine that any Proposal received complies, or fails to comply, with the terms of this RFP.
2. To waive any technical non-conformance with the terms of this RFP.
3. To conduct investigations of any or all Respondents, as the Subdistrict deems necessary or convenient, to clarify the information provided as part of the RFP and to request additional information to support the information included in any Proposal.
4. To suspend or terminate any portion of or all the selection process described in this RFP at any time, in its sole discretion. If terminated, the Subdistrict may commence a new selection process or exercise any other rights provided under applicable law without obligation to the Respondents.
5. To eliminate from further consideration any Respondent who communicates regarding this RFP with Subdistrict or Northern Water Board members, officers, employees, or agents other than the Procurement Officer through RMEPS, as required by Section III.1.
[Remainder of Page Intentionally Left Blank]
X. ATTACHMENT A – TIMETABLE
SCHEDULE
RESPONSIBLE
PARTY
DEADLINE
Issue Request for Proposals Subdistrict November 3, 2026
Recommended Pre-Proposal Meeting
Subdistrict November 13, 2026, at 10:00 AM (MT)
Questions Due Respondents November 24, 2026, at 12:00 PM (MT)
Issue Addendum, if needed Subdistrict December 3, 2026
Proposals Due Respondents December 15, 2026, at 2:00 PM (MT) Notification of Interview Invitation (Only if Necessary)
Subdistrict December 29, 2026
Conduct Interviews (Only if Necessary)
Subdistrict January 18, 2027
XI. ATTACHMENT B – SCOPE OF SERVICES
Subdistrict personnel will inspect the spillway monthly. The work exposes them to slip, trip, and fall hazards on sloped, wet, and uneven concrete surfaces.
The new fall protection system must provide continuous, 100 percent tie-off for the full length of the spillway. Staff must be able to travel the entire inspection route without disconnecting and reconnecting at intermediate supports. The system must allow up to three employees to be attached and working at the same time.
1. Project Location and Site Conditions
The Respondent’s design and installation must account for the following site conditions:
a. A curved alignment along the inside radius of the 8-foot by 10-foot box culvert spillway, with grades up to 25 percent, requiring curve-capable intermediate and corner components.
b. An exposed outdoor environment with water flow, standing water, freeze-thaw cycling, ultraviolet exposure, and debris.
c. Existing concrete wall conditions, including surface condition, embedded reinforcement, construction joints, and expansion joints.
d. Limited access points and staging areas for equipment and materials.
e. Periodic spillway operations that may affect Work scheduling and site access.
2. System Performance Requirements
The fall protection system must meet the following minimum requirements:
a. Total spillway length of 2,963 linear feet, including curved components and grades up to 25 percent.
b. Designed for three simultaneous users.
c. Anchorages rated to support at least 5,000 pounds per attached worker.
d. Overall system rated to 15,000 pounds of force to accommodate three attached users.
e. Pass-through intermediate brackets and curve components that allow shuttles or travelers to move freely along the full length without the user detaching.
f. End anchors are equipped with energy absorbers, tensioning devices, and tension indicators as required by the engineered design.
g. Intermediate support spacing and deflection limits that keep required fall clearance within available site conditions.
h. Provisions to accommodate concrete expansion joints and thermal movement without compromising system integrity.
i. Compliance with OSHA 29 CFR 1910.140, applicable provisions of 29 CFR 1926 Subpart M, and the ANSI/ASSP Z359 Fall Protection Code. This includes Z359.6 requirements for engineered active fall protection systems.
3. Design and Engineering Services
The fall protection system must be designed and certified by a qualified person. Design documents must be stamped by a Professional Engineer licensed in the State of Colorado. Design services include:
a. A site assessment and field survey of the spillway wall, including verification of alignment, radius, wall thickness, and concrete condition.
b. Structural calculations for anchorage loads, cable tension, maximum arrest forces, and system deflection under single-user and three-user fall scenarios.
c. Fall clearance calculations based on the specified connecting devices, such as self-retracting lifelines or energy-absorbing lanyards, and on-site obstructions.
d. Anchor and fastener design, including embedment depth, edge distance, and spacing based on actual concrete conditions.
e. Shop drawings showing component layout, bracket locations, mounting details, end terminations, and access and entry points.
f. Rescue considerations, including recommended rescue methods and equipment for a suspended worker within the spillway.
The Subdistrict will review design submittals before material procurement or installation begins.
4. Materials and Components
All components must be suitable for long-term exposure to water and outdoor conditions. Minimum material requirements include:
a. Stainless-steel or equivalent corrosion-resistant components, end anchors, intermediate brackets, curve brackets, tensioners, and energy absorbers.
b. Stainless-steel mechanical or adhesive concrete anchors compatible with the existing wall conditions.
c. A minimum of three compatible shuttles or travelers that pass through intermediate and curve brackets without manual operation.
d. Permanent system identification labels or tags at each access point stating capacity, number of allowable users, installation date, and inspection requirements.
All components must be supplied as part of the same manufacturer’s system or verified as compatible by the engineer of record. Substitutions require the Subdistrict’s written approval.
5. Installation
The Respondent must furnish all labor, equipment, materials, and supervision needed to complete the installation. Installation activities include:
a. Mobilize equipment and materials and establish staging areas approved by the Subdistrict.
b. Locate embedded reinforcement before drilling. Adjust anchor locations as needed and obtain approval from the engineer of record.
c. Install all components according to the approved design and the manufacturer's instructions.
d. Patch or seal any abandoned drill holes and restore disturbed surfaces.
e. Clean the Work area and remove all debris, packaging, and excess materials from the site.
The Respondent must protect the spillway structure, water quality, and surrounding areas throughout the Work. No debris, concrete dust, slurry, or chemicals may enter the waterway.
6. Testing, Certification, and Commissioning
Before the system is placed into service, the Respondent must:
a. Proof-load test concrete anchors according to the engineered design and the anchor manufacturer’s requirements.
b. Verify that the installed system conforms to the approved design and confirm free shuttle travel across all intermediate and curve brackets for the full 2,963-foot length.
c. Complete a documented inspection of the installed system by a competent person.
d. Provide written certification from the engineer of record that the system was installed as designed and meets the specified ratings.
e. Conduct a commissioning walk-through with Subdistrict staff.
7. Training
The Respondent must provide on-site training for Subdistrict personnel who will use or inspect the system. Training must cover:
a. Proper connection, travel, and use of the shuttles or travelers along the system.
b. Compatible personal fall arrest equipment and fall clearance considerations.
c. Pre-use inspection procedures and periodic competent person inspection requirements.
d. Recognition of damage, wear, corrosion, or deployed energy absorbers.
e. Rescue planning and procedures specific to the spillway.
The Respondent must provide the Subdistrict with training materials and attendance records.
8. Documentation and Deliverables
The Respondent must deliver the following:
a. Stamped design drawings and engineering calculations.
b. Product data sheets and manufacturer's installation instructions for all components.
c. Anchor proof-load test results.
d. As-built drawings showing final component locations and any field adjustments.
e. Certification letter from the engineer of record.
f. An inspection, maintenance, and recertification manual, including recommended inspection intervals and replacement criteria.
g. A system-specific rescue plan recommendation.
h. Warranty documentation.
Deliverables must be provided in both electronic and hard-copy formats.
9. Warranty and Post-Installation Support
The Respondent must warrant its workmanship for at least one year after final acceptance. All manufacturer warranties for system components must be assigned to the Subdistrict. The Respondent must also:
a. Identify recommended recertification intervals.
b. Describe available annual inspection and recertification services.
c. Describe the availability of replacement parts for the life of the system.
10. Respondent Responsibilities and Site Requirements
The Respondent must:
a. Submit a site-specific safety plan before mobilization, including fall protection for installation crews working before the permanent system is commissioned.
b. Coordinate all Work schedules and spillway access with the Subdistrict and accommodate operational restrictions related to water flow.
c. Follow all site security, access, and environmental protection requirements established by the Subdistrict.
d. Obtain any required permits and comply with all applicable federal, State of Colorado, and local regulations.
e. Ensure installation personnel are trained and qualified in the installation of engineered fall protection systems.
f. Promptly report any unforeseen site conditions, such as deteriorated concrete, that may affect the design or installation.
XII. ATTACHMENT C – COST PROPOSAL
Respondents shall complete and submit this Cost Proposal with their Proposal. Complete all applicable fields. Enter “Included” where a cost is incorporated into another line item and “N/A” where a line item does not apply. Attach additional details only if needed to explain assumptions, exclusions, or alternate pricing. All prices shall remain firm for at least ninety (90) calendar days after the Proposal due date.
The Total Base Proposal is the sum of Items 1 through 9 below. State the unforeseen-conditions allowance, additional-work unit prices, and optional post-installation service prices separately; do not include them in the Total Base Proposal. The Total Base Proposal is the pricing basis for the Cost Proposal evaluation under Section VI.6. Additional work and optional services require the Subdistrict’s written authorization in accordance with the Contract. The proposed allowance is not guaranteed compensation and does not authorize work or payment.
Cost Proposal
Item Scope Component Pricing Basis Amount Notes
Mobilization, site access coordination, staging, and site-specific safety planning
Lump Sum $
Site assessment, field survey, concrete evaluation, and reinforcement locating
Professional engineering, calculations, stamped design drawings, fall-clearance analysis, and shop drawings
Fall protection system materials for 2,963 linear feet, including wire rope, anchors, brackets, curve components, tensioners, energy absorbers, a minimum of three compatible shuttles or travelers, labels, and all other required components
Installation labor, equipment, access systems, drilling, anchorage installation, cable installation, tensioning, sealing, restoration, cleanup, and environmental protection
Anchor proof-load testing, system inspection, commissioning, and engineer-of-record certification
On-site user and inspector training, training materials, and attendance records
8 As-built drawings, product data, test records, inspection and maintenance manual, rescue plan recommendation, warranty documents, and electronic and hard-copy deliverables
Permits, freight, travel, taxes, bonds, insurance, overhead, profit, and all other costs not separately listed
TOTAL BASE PROPOSAL $
Allowances and Unit Prices
Description Unit Estimated Quantity
Unit Price / Allowance
Additional fall protection beyond 2,963 linear feet, furnished and installed Linear Foot As directed $
Additional shuttle or traveler Each As directed $
Concrete repair or specialized anchorage due to unforeseen conditions Allowance 1 $
Additional field labor Crew-Hour As directed $
Additional engineering services Hour As directed $
Optional Post-Installation Services
Optional Service Pricing Basis Price Annual competent-person inspection and written report Per Visit $
Engineer recertification of the complete system Per Event $
Additional on-site user or inspector training session Per Session $
Emergency inspection following a fall-arrest event or reported damage Per Visit $
Proposed Delivery Schedule
Milestone Duration Start Completion Notice to Proceed and kickoff meeting
Site assessment and field survey
Design development and stamped submittal
Subdistrict review and Respondent revisions
Material procurement and fabrication
Mobilization and installation
Testing, certification, commissioning, and training
Final documentation and closeout
Total calendar days from Notice to Proceed to final completion __________ days
Pricing Assumptions and Exclusions: __________________________________________________
Proposed Payment Schedule:________________________________________________________
Respondent Certification: The undersigned certifies that the prices stated above are complete and include all costs necessary to perform the Work described in the RFP, except for expressly identified exclusions.
Respondent’s Name:_________________________________________________________________
Authorized Signature:__________________________Date:_________________________________
Printed Name and Title:_______________________________________________________________
XIII. ATTACHMENT D – CHIMNEY HOLLOW FACILITIES MAP
XIV. ATTACHMENT E – PROPOSAL CONTACT INFORMATION AND
ACKNOWLEDGMENT
Respondent acknowledges receipt of the Subdistrict’s Request for Proposals, confirms that it has read the RFP, and agrees to be bound by its terms, conditions, and provisions. Respondent also makes the following representations to the Subdistrict:
a. All statements and representations made in this Proposal are true to the best of the Respondent’s knowledge and belief.
b. Respondent confirms that it can meet the terms provided in this Proposal.
c. This Proposal is a firm and binding offer for ninety (90) calendar days after the Proposal due date.
d. Respondent further agrees that the method of award is acceptable.
e. Respondent agrees to execute a Contract with the Subdistrict within 30 days after Notice of
Intent to Award. If the Contract is not executed within 30 days, the Subdistrict reserves the right to cancel the award and proceed to the next highest-rated responsive Respondent.
Respondent’s Name:_________________________________________________________________
Physical Address: ___________________________________________________________________
Respondent’s FEIN:__________________________________________________________________
Name of Respondent’s Authorized Agent:________________________________________________
Signature of Authorized Agent: ________________________________________________________
Authorized Agent Title:______________________________________________________________
Authorized Agent Email Address:______________________________________________________
Primary Contact for Project: __________________________________________________________
Title: _____________________________________________________________________________
Email Address: _____________________________________________________________________
Phone Number: ____________________________________________________________________ NOTE: The Respondent must sign and return…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .