This Request for Proposals (RFP) document is issued by the University of Colorado Boulder, a State of Colorado institution, for Construction Manager/General Contractor (CM/GC) services for the MBE - Idea Forge Renovation project (Notice Number 26-66, Project Number UCB001642) with an estimated total project cost of $8,000,000 and a construction cost of approximately $5,000,000. The project involves the renovation of 8,000 to 13,000 gross square feet within the Ofelia Miramontes and Leonard Baca Education Building to create spaces for the Mechanical Engineering Department including offices, wood shop, machine shop, computing lab, testing spaces, instructional labs, and project assembly rooms. Construction is anticipated to occur between Summer 2027 and Summer 2028 in a partially occupied building, requiring careful phasing strategies to maintain CEAS operations. A mandatory pre-submission conference and site tour is required on November 5, 2026, at 2:30 PM at Building Address 2445 Kittredge Loop Dr., Boulder, CO, MBE Classroom 33. Prequalification submittals are due November 23, 2026, at 2:00 PM MST; shortlisted firms will be notified by December 3, 2026, and must submit sealed fee proposals by December 11, 2026, at 2:00 PM MST, with oral interviews scheduled for December 14, 2026, and selection announced December 16, 2026. The contract is anticipated to commence December 21, 2026, with design beginning approximately November 6, 2026.

Minimum requirements include demonstrated experience on at least two prior projects exceeding $5,000,000 in construction cost using CM/GC delivery methods, bonding capacity up to $7,000,000, and no prior termination by the State for non-performance. The selection methodology weights qualifications at 70 percent and fee proposals at 30 percent to determine the most advantageous overall value. Respondents must comply with Colorado prevailing wage requirements (C.R.S. 24-92-Part 2) applicable to public construction projects of $500,000 or more, employ Colorado labor for at least 80 percent of the work per C.R.S. 8-17-101, and comply with the Buy Clean Colorado Act (C.R.S. 24-92-117) regarding environmental product declarations for eligible materials. The project requires payment and performance bonds at not less than 50 percent of the contract value per C.R.S. 38-26-106. All respondents must acknowledge the sample CM/GC Agreement (SC-6.5 and SC-6.51) as workable without reservation and submit responses electronically through Bidnet; late submittals will be rejected. Funding is appropriated and available through the specified fund number and Speedtype account as identified in the contract documents, with a Fixed Limit of Construction Cost and a Guaranteed Maximum Price (GMP) to be established at the completion of the Design Development Phase.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AFB-CSBV pg. 1

REV 7/2025

REQUEST FOR PROPOSALS

Integrated Project Delivery utilizing

Construction Manager/General Contracting Services

State of Colorado University of Colorado Boulder

Notice Number: 26-66 Project Number: UCB001642 Project Title: MBE – Idea Forge Renovation Estimated Project Cost: $8,000,000

Table of Contents

I. NOTICES

II. PROJECT OVERVIEW

Scope of Services

III. MINIMUM REQUIREMENTS

IV. MANDATORY PRE-SUBMISSION CONFERENCE AND SITE TOUR

V. SCHEDULE

VI. QUESTIONS, CLARIFICATIONS AND ADDENDA

VII. POINT OF CONTACT/CLARIFICATION

VIII. SUBMITTALS OF QUALIFICATIONS

IX. METHOD OF SELECTION AND AWARD

A. Short List B. Oral Interview

X. EVALUATION OF QUALIFICATIONS

A. PREQUALIFICATION SUBMITTAL CRITERIA

1. QUALIFICATIONS OF THE FIRM(s)

2. QUALIFICATIONS OF THE MANAGEMENT TEAM MEMBERS

3. PROJECT MANAGEMENT APPROACH

4. PRIOR PROJECT EXPERIENCE/SUCCESS

5. PEOPLE AND CULTURE

6. MISCELLANEOUS CONSIDERATIONS

XI. ORAL INTERVIEWS EVALUATION CRITERIA

1. QUALIFICATIONS OF THE FIRM

AFB-CSBV pg. 2

2. QUALIFICATIONS OF THE MANAGEMENT TEAM MEMBERS

3. PROJECT MANAGEMENT APPROACH

4. PRIOR PROJECT EXPERIENCE/SUCCESS

5. MISCELLANEOUS CONSIDERATIONS

XII. FEE PROPOSALS

XIII. ACKNOWLEDGEMENT AND ATTESTATION FORM

Appendix A: Evaluation Forms Appendix B: Construction Manager/General Contractor (CM/GC) Agreement with

General Conditions of the Construction Manager/General Contractor Agreement Appendix C: Direct Labor Burden Calculation

Appendix E: Applicable Prevailing Wage Rates & Apprenticeship Contribution Rates

Appendix F: Apprenticeship Utilization Certifications Appendix G: Owner’s Project Requirements

AFB-CSBV pg. 1

I. NOTICES

1. For all projects with a total dollar value above $150,000 Notice of Final Settlement is required by C.R.S. §38-26-107(1). Final Settlement, if required, will be advertised in the same location as the original solicitation.

2. For State Public Works C.R.S. §8-17-101 - Colorado labor shall be employed to perform at least 80% of the work. Colorado labor means any person who is a resident of the state of Colorado at the time of the Public Works project.

3. All respondents accept the conditions of this RFP, including but not limited to, the following:

a. All submittals shall become the property of the State of Colorado and will not be returned.

b. Late submittals shall not be evaluated.

c. The State reserves the right to reject any or all proposals on the basis of being unresponsive to this RFP or for failure to disclose requested information.

d. The State shall not be liable for any costs incurred by respondents in the preparation of submittals and proposals nor in costs related to any element of the selection and contract negotiation process.

e. Any restriction as to the use of submitted materials must be clearly indicated as proprietary. The requested limitation or prohibition of use or release shall be identified in writing on a cover sheet. Blanket claims of proprietary submittals will not be honored. Fee proposals will be considered proprietary.

f. The respondent has reviewed Appendix B and by responding has agreed that the terms and conditions of the sample Construction Management/General Contracting Agreement are expressly workable without reservation.

4. The respondent has reviewed Appendix B and by responding has agreed that the terms and conditions of the sample Construction Manager/General Contractor (CM/GC) Agreement (SC-6.5) and General Conditions of the Construction Manager/General Contractor Agreement (SC- 6.51) are expressly workable without reservation. Any exceptions to the contract must be communicated formally in writing before the bid closes.

5. Per C.R.S. §24-92-115 unless prohibited by applicable federal law, contract for any public project in the amount of one million dollars or more, that does not receive federal money, in the amount of one million dollars or more shall require the general contractor to which the contract is awarded to submit, at the time the mechanical, electrical, or plumbing subcontractor is put under contract, documentation that Identifies the contractors or subcontractors that

AFB-CSBV pg. 2 will be used for all mechanical, sheet metal, fire suppression, sprinkler fitting, electrical, and plumbing work required on the project and certifies that all firms identified participate in apprenticeship programs registered with the United States department of labor’s employment and training administration or state apprenticeship councils recognized by the United States department of labor and have a proven record of graduating a minimum of 15% of its apprentices for at least three of the past five years.

6. Per C.R.S. §24-92-117, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the Buy Clean Colorado (BCCO) Act program requirements. The BCCO Act requires the Office of the State Architect to establish a maximum acceptable global warming potential (GWP) limit for each category of eligible materials, which include asphalt and asphalt mixtures, cement and concrete mixtures, glass, post-tension steel, reinforcing steel, structural steel, and wood structural elements. For any solicitation for a contract for the design of an eligible project, a State Agency or institution shall require the designer who is awarded the contract to include in project specifications when final construction documents are released, a current Environmental Product Declaration (EPD) that meets the maximum acceptable GWP limits for each eligible material specified for the project. A contractor that is awarded a contract for an eligible project shall not install any eligible materials on the project until the contractor submits an EPD for each eligible material procured for the project.

7. Per C.R.S. §24-92-Part 2, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract. Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors. Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize the LCPTracker cloud-based labor compliance and certified payroll application.

8. Preference shall be given to Colorado resident bidders and for Colorado labor, as provided by law.

II. PROJECT OVERVIEW

Introduction

The University of Colorado Boulder (UCB) seeks qualified CMGC contractors for the renovation of the Idea Forge, located within the OFELIA MIRAMONTES AND LEONARD BACA EDUCATION BUILDING (MBE) on the university’s main campus. The Idea Forge describes a variety of spaces (offices, wood shop, machine shop, computing lab, testing spaces, instructional labs, and project assembly rooms) assigned to the Mechanical Engineering Department of the College of Engineering and Applied Science (CEAS). See OPR for Project Goals and additional design criteria.

AFB-CSBV pg. 3

Construction is anticipated to take place between Summer 2027-Summer 2028 in a partially occupied building.

Feasibility: The CMGC will provide feedback on schedule and constructability and will provide a cost estimate at the end of feasibility.

The Design Team will perform an initial feasibility study to determine the subsequent design and construction scope of this project. The feasibility study will also identify other scopes of work that the customer may choose to perform at a later date.

The renovation square footage of this project that is anticipated to continue into design and construction is between 8,000 - 13,000 GSF for a construction cost of $5 million (total project cost $8 million). The final scope will be confirmed after the feasibility study.

Throughout design, the CMGC will attend regular design meetings and provide input on constructability, long-lead items, schedule and phasing strategies, and cost. Since this work will take place in a partially occupied building and the CEAS is interested in phasing the work to maximize operations, studying phasing strategies and their impact on the total project cost and schedule will be important.

The University of Colorado Boulder anticipates using a Construction Manager/General Contractor (CM/GC) approach to project delivery. A Guaranteed Maximum Price (GMP) and an updated project duration schedule will be established by the Architect/Engineer and the Construction Manager/General Contractor in conjunction with the University of Colorado Boulder. The CM/GC will evaluate, among other things, availability of materials and labor, project schedule, project costs as they relate to the established budget, constructability, and will work closely with the Architect/Engineer and the University of Colorado Boulder throughout the planning, design and construction phases of the project. Construction is estimated to commence Summer 2027.

The process to be used in the selection of the CM/GC is comprised of two steps. STEP I is the Submittal of Prequalification as described in Section X. STEP II is the Oral Interview/Fee Proposal as described in detail in Section XI. A Jury Panel of individuals who will be involved in the project and/or understand the required services associated with Construction Management/General Contracting will evaluate responses to this RFP for both STEPS. Upon completion of the evaluation of the Submittals of Prequalification, a limited number of firms will be invited to the oral interviews. Sealed fee proposals will be required only from those firms who are interviewed and are to be submitted as indicated in this RFP. Both qualifications and cost will be considered in the final ranking of firms with qualifications given 70% of the value of the weighted criteria and fees for the Fee Proposal given 30%.

Selection and award of this project will be based on a combination of qualifications and costs that represent the best overall value to the State.

AFB-CSBV pg. 4

Scope of Services The scope of services assistance to the State during the process of assessment, design, construction, and warranty period. Specific tasks to be performed by the Construction Manager/General Contractor (CM/GC) include those generally performed by the CM/GC construction community where the Construction Manager is also the Contractor. A sample copy of the State’s CM/GC contract is contained within the RFP. A Guaranteed Maximum Price (GMP) will be required at the completion of Design Development phase.

Per C.R.S. §38-26-106, if a contract amounts to $150,000 or more, the awarded contractor shall provide payment and performance bonds not less than 50% of the value of the contract. The costs associated with this bond are to be included in the contractor’s proposal.

III. MINIMUM REQUIREMENTS

Notice is hereby given to all interested parties that all firms will be required to meet all minimum requirements to be considered for this project. Interested parties should be prepared to show evidence of the following to be considered as qualified, as a minimum:

1. Not previously terminated by the State for non-performance on a State Buildings contract or procurement.

2. The contractor must have been in the same business under the same name for the last two (2) years.

3. Demonstrated specific contracting experience in projects of similar scope and complexity for at least two (2) projects each in excess of $5,000,000 construction cost utilizing the expertise present in their Colorado Office; and

4. Demonstrated bonding capability up to $7,000,000 for an individual project coincidentally with current and anticipated workloads; provide letter from surety that affirms this capacity.

5. Respondents must acknowledge all issued addenda in their submittal and proposal.

6. Attended and signed in at the Mandatory Pre-Submission Conference

Firms meeting the minimum requirements may obtain additional proposal documents on the website accompanying this advertisement.

All submittals are to be submitted electronically via Bidnet at:

https://www.bidnetdirect.com/colorado/universityofcoloradodesignandconstruction

IV. MANDATORY PRE-SUBMISSION CONFERENCE AND SITE TOUR

To ensure sufficient information is available to firms preparing submittals, a mandatory pre-submittal conference has been scheduled. The intent of this conference is to tour the site and to have University of Colorado Boulder staff able to discuss the project. Firms preparing submittals must attend and sign-in to have their submittals accepted.

AFB-CSBV pg. 5

A mandatory Pre-Submission Meeting will be held at:

Building Address: 2445 Kittredge Loop Dr., Boulder, CO Room: MBE Classroom 33 (East Wing, 1B Level) Date/Time: November 5, 2026 2:30pm-4:00pm

V. SCHEDULE

The following is a tentative schedule of events for the Proposal Submittal process and an outline of the schedule for the balance of the project. All dates are subject to change and changes in the schedule will be issued via addendum.

Request for Proposal Issued 10/23/2026 Mandatory Pre-Submittal Conference and Tour 11/5/2026; 2:30pm-4:00pm Request for Clarifications Due 11/10/2026; 2:00pm Clarification Responses Issued 11/13/2026 Submittals Due (Prequalification: Step I) 11/23/2026; 2:00PM MST Interview Short List Announced 12/3/2026 Sealed Proposal Due

(Evaluation and Award: Step II) 12/11/2026; 2:00PM MST Oral Interviews 12/14/2026 Selection Announced 12/16/2026 Negotiation of Contract (Anticipated) Through 12/21/2026 Anticipated Design Start (Anticipated) 11/6/2026 Anticipated CM/GC Start (Anticipated) 12/21/2026 Anticipated Construction Start/Finish June/July 2027-July 2028

The above schedule is tentative. Responding firms shall be notified of revisions in a timely manner by email or posted on Bidnet/Rocky Mountain E-Purchasing System (RMEPS) website. Respondents may elect to verify times and dates by email, but no earlier than 36 hours before the scheduled date and time.

VI. QUESTIONS, CLARIFICATIONS AND ADDENDA

Owner initiated changes to this RFP will be issued under numerically sequenced addenda.

Owner initiated changes to this RFP will be posted in the form of addenda on [ColoradoVSS / Bidnet/Rocky Mountain E-Purchasing System (RMEPS)].

Questions and requests for clarifications regarding this project shall be submitted before the deadline listed in the above Schedule.

Communication regarding the project during the procurement, outside of this submission process or scheduled procurement milestones is not permitted.

VII. POINT OF CONTACT/CLARIFICATION

Name: Blake Guyer, Project Manager Agency: University of Colorado Boulder Email Address: blake.guyer@colorado.edu

Name: Kristi Maulding, Planner Agency: University of Colorado Boulder Email Address: kristi.maulding@colorado.edu

AFB-CSBV pg. 6

VIII. SUBMITTALS OF QUALIFICATIONS

1. This RFP document, it’s appendices, and any written addenda issued prior to the closing of the solicitation, and written clarifications shall serve as the only basis for the proposal.

2. All submittals must comply with the following items, a through f. The State retains the right to waive any minor irregularity, or requirement should it be judged to be in the best interest of the State.

a. Qualifications shall be formatted and tabbed in the exact form and numeric sequence of the Evaluation Form (1 through 7) in Appendix A. A two-sided single-page cover letter addressed to Blake Guyer outlining the firm(s) qualifications is required at the front of the submittal. Not counting the cover page, tabs, and required Acknowledgement and Attestation form, the entire submittal is to be no more than (20) 8 ½’ x 11” sized pages in portrait format, minimum 10 font. Cover letters, and resumes do count toward the maximum page count.

b. Qualifications shall be evaluated in accordance with criteria as indicated in PREQUALIFICATION SUBMITTAL CRITERIA and ranked on the corresponding Evaluation Form in Appendix A.

c. Response to all items shall be complete.

d. All references shall be current and relevant.

e. Complete and execute the appropriate Acknowledgment and Attestation Form as provided in Section VI and submit at the back of the Prequalification Submittal.

f. An electronic copy of the qualification package is due 11/23/2026 and shall be received no later than 2:00 PM MST.

Late submittals will be rejected without consideration. The State of Colorado assumes no responsibility for costs related to the preparation of submittals.

IX. METHOD OF SELECTION AND AWARD

A. Short List

1. From the submittals received, a short list of qualified respondents shall be identified using the scoring indicated on the enclosed Evaluation Form, Appendix A.

2. Firms failing to meet the minimum required qualifications will not receive further consideration.

B. Oral Interview

1. Mandatory oral interviews shall be conducted for the short-listed firm(s) only. Interview times and location will be arranged by the

AFB-CSBV pg. 7

University of Colorado Boulder and all short-listed firms will be notified in advance through Bidnet. At the option of the State, a visit to the short-listed firm(s) managing home office and/or representative field office may be required.

C. Fee Proposals

1. Only those firms shortlisted for interview are required to submit their sealed proposals. (Only one copy is required on the scheduled submission date.) Fee Proposals will remain sealed until after the qualitative scoring and will then be opened. The Fee Proposal will then be considered (equivalent to 30 percent of the weighted criteria) in conjunction with the qualitative score from the response and interview (equivalent to 70 percent of the weighted criteria).

2. Fee Proposals shall be submitted on the form provided in Section XII, without modification. A Fee Proposal shall be accompanied with sufficient detail to clearly identify the fee for service and include a detailed schedule of estimated (not-to-exceed) reimbursable and non-reimbursable costs. The percentage of the cost of work is not acceptable value. The Fee Proposal should be prepared independently in accordance with the following:

a. Fees are outlined in Exhibit A of the Sample Agreement attached to this solicitation as Appendix B.

b. Any specific services requested in the RFP and its appendices that are not included should be clearly identified. Exclusion of any required service may result in the proposal being found non-responsive.

c. Provide a CM/GC staff schedule with staff by name, position and man-hours (assume 8-hour days) per month estimated on the project.

d. Provide a detailed estimate of reimbursable costs including breakdown of direct salaries and payroll fringes (DPE) for on-site CM/GC personnel associated with the services. Not-to-exceed reimbursable expenses shall be provided at direct cost.

e. Provide a detailed estimate of non-reimbursable expenses (included in fee).

AFB-CSBV pg. 8

f. The State reserves the right to reject any Fee Proposal not prepared in the above manner. Proposals that exceed the available funds may be rejected outright but the State reserves the right to negotiate a reasonable fee for service within the available funds. The CM/GC contract will be a bonded lump sum contract including not-to-exceed reimbursables with a Guaranteed Maximum Price to encompass all construction work; some not-to-exceed allowances may be included as directed by the State.

3. This Fee Proposal is a binding offer to perform the services associated with the Scope of Services described in this RFP and the Designated Services and Method of Payment Matrix in Appendix B.

The State reserves the right to negotiate a cost adjustment based on scope clarification after selection and prior to contract execution.

D. Method of Selection and Award

1. The Jury Panel shall complete a combined evaluation of qualifications and fee in accordance with the criteria as indicated in Section X, EVALUATION OF QUALIFICATIONS and Section XI ORAL INTERVIEWS EVALUATION CRITERIA. Numerical ranking and selection of the most qualified firm (including fee) will then occur on the corresponding evaluation forms in Appendix A.

2. The final fee amount and scope of services may be negotiated at the State’s discretion. The award and contract will be contingent on the availability of key proposed Project Management Team staff.

E. After selection and award all proposals, qualifications and ranking documents will be made available to the public on the agency or institutions solicitation platform.

X. EVALUATION OF QUALIFICATIONS

A. PREQUALIFICATION SUBMITTAL CRITERIA

1. QUALIFICATIONS OF THE FIRM(s)

• Provide a description of the composition and management structure of your firm. Identify the firm’s roles and responsibilities and relevant experience with projects of similar scope and complexity and similar fast track project delivery methods. Describe how the firm’s experience will relate to the success of this project.

• Provide a description and separate graphic organizational chart complete with working titles identifying the lines of authority, responsibility and coordination.

• Provide a detailed description of the process of how your firm selects qualified sub-contractors and manages them effectively on complex multi-phased projects. How does your organization attempt to utilize disadvantaged and small businesses

AFB-CSBV pg. 9

• Provide a detailed description of how your firm will maximize the Colorado construction workforce on this project.

• Provide your firm’s safety record over the last ten years and describe your firm’s efforts to retain and support employees.

2. QUALIFICATIONS OF THE MANAGEMENT TEAM MEMBERS

• List all members of the proposed full-time project team including but not limited to: superintendent, project engineer, project manager, cost estimator, etc. Include relevant qualifications and experience as it pertains to these members working on projects as a team.

• Describe the qualifications and relevant experience of the superintendent including demonstrated experience working on projects of similar scope and complexity and time commitment for this project.

• Describe the qualifications and relevant experience of other key in-house staff and time commitments for this project.

• Identify all current office locations of the assigned staff and any other resident expertise intended to be provided under this RFP.

3. PROJECT MANAGEMENT APPROACH

• Provide a strategic project approach summary: Include discussion of your firm’s approach in providing successful Construction Management/General Contracting services based on prior experience in cost, schedule and quality effectiveness. Include specific examples (1–2-page excerpts) of actual products (estimates, progress reports, schedules, constructability reviews, value engineering studies, forms, general conditions budgets, organizational structures, etc.).

• Providing a description of construction work Project Management Team has capability to competitively bid and self-perform, including qualifications to do such. It is the perception of the University of Colorado subcontracting CM/GC construction work is in the State’s best interest in terms of price competition. The University of Colorado may, at its discretion, limit the types and amount of work Project Management Team bids and self-performs.

4. PRIOR PROJECT EXPERIENCE/SUCCESS

a. Select your three (3) most relevant projects and provide, at a minimum, the following:

• The project/contract name

• Description of services provided

• Overall construction cost of project, as applicable, including initial contract value and change orders including reasons for change orders

• Organizational structure of service delivery under the contract (include the owner’s organization as it interfaced with the respondent’s contract)

• Key assigned in-house staff (name and title)

AFB-CSBV pg. 10

Note which (if any) of the in-house staff are included in your proposed team.

• Subcontracts (service) used in the performance of the contract

• Schedule history, including original proposed schedule and actual schedule

• Reference(s) for Owner and Architect as described in Section

VIII, SUBMITTALS OF QUALIFICATIONS

• Continuing services, if any

Relevant projects should include examples of complex renovations of similar scope and cost.

b. Timeliness

In general, Construction Management/General Contracting work is seen as successful if it is on time, on budget, and of high quality of workmanship. Timeliness is generally based on completion by the originally scheduled date and is indicated by a Certificate of Occupancy. Please demonstrate for each of the above projects how timely delivery occurred.

c. Budget Considerations

Similar to timeliness, being on budget historically means the work was completed within the originally identified available budget.

Demonstrate for the above projects examples of how you accomplished the following cost control services. For the purposes of this RFP, the State is interested not only in being within budget but also in the respondents’ ability to address these issues:

• Conceptual estimating

• Value analysis

• Alternate solutions

• Scope reduction that maintains project function

• Cost/benefit analysis

Demonstrate for the above projects examples of how you accomplished the above cost control services.

d. Quality

Construction quality has the obvious traditional connotations (workmanlike, in compliance with the specifications, normal standard of care, etc.). Demonstrate for the above project examples how a high quality of workmanship was achieved.

e. Services Disruption

Demonstrate how your services on the above project examples dealt with issues of disruption at existing facilities, etc. if applicable.

AFB-CSBV pg. 11

f. Project Acceptability

Please discuss how your Construction Management/General Contracting services helped achieve owner satisfaction regarding project quality and acceptability with your project examples.

g. Compliance

Provide information on how compliance with industry standards of care, building codes, etc. was achieved.

5. PEOPLE AND CULTURE

a. Describe how your team is incentivized to hire and promote diverse individuals

b. Describe how your team attempts to contract with Service- Disabled Veteran Owned Small Businesses or historically disadvantaged businesses

6. MISCELLANEOUS CONSIDERATIONS

a. Claims/Litigation History of Firm

Provide information on any past, current or anticipated claims (i.e., knowledge of pending claims) on respondent contracts;

explain the litigation, the issue, and its outcome or anticipated outcome.

b. Apprenticeship Training Program (Optional for Step I)

Where an Apprentice Training Program certified by the Office of Apprenticeship located in the Employment and Training Administration in the United States Department of Labor exists in the State, or a comparable program for the training of apprentices is available in the State:

1. Each submitter shall demonstrate access to the certified program or a comparable alternative (Note that it is the responsibility of the submitter to demonstrate the comparability of a non-certified program) and,

c. Each submitter’s subcontractor at any tier with a contract value of two hundred fifty thousand dollars or more shall demonstrate access to the certified program or a comparable alternative.

d. Apprenticeship Training Program (Optional for Step I)

e. Other

This category is included in other items provided by the submitter. Inclusions may include standard firm promotional literature, testimonials, awards, corporate memberships in professional organizations or sponsorships, additional

AFB-CSBV pg. 12 project/contract histories, etc., intended to demonstrate why your firm is uniquely qualified for this project.

XI. ORAL INTERVIEWS EVALUATION CRITERIA

(Note that the primary focus of the Oral Interview evaluation in addition to the Fee Proposal will be the proposed project management team members’ capabilities).

1. QUALIFICATIONS OF THE FIRM

• Explain the composition and structure of your project management team and how the firm will support their efforts in the field throughout this project.

• Are the lines of authority, responsibility and coordination clearly identified?

2. QUALIFICATIONS OF THE MANAGEMENT TEAM MEMBERS

• Explain the prior experience with projects of similar scope and complexity and similar project delivery methods of the superintendent and all other project management team members. Explain their roles and responsibilities and authority and why they are the right team members for this project.

• Explain anticipated project management team staff current and projected workload.

• Identify all current office locations and the resident expertise intended to be provided under this RFP. Identify the location of the staff for the performance of this contract, their expertise, and generic equipment that will be located in Colorado and act in support of the anticipated contract.

3. PROJECT MANAGEMENT APPROACH

• Explain the strategic project approach for this project in summary:

Include discussion of your team’s approach in providing successful CM/GC services based on the needs of this specific project utilizing the team’s prior past experience including cost, schedule, and quality control.

Explain, in particular, how the team will identify conflicts, long-lead items, and unknown conditions during the design phase and what they will do to reduce impacts on cost, schedule and quality based on these items.

• Explain the construction work, the project management team has the capability to competitively bid and self-perform including qualifications to do such work.

• Provide a detailed description of how your project management team will select qualified sub-contractors and manage them effectively on this project.

AFB-CSBV pg. 13

4. PRIOR PROJECT EXPERIENCE/SUCCESS

• Explain the most relevant projects the superintendent and the team members have completed together and/or separately and what their role was. (University of Colorado at its discretion contact references and/or conduct independent performance analysis on projects on which the team member has worked).

• Provide descriptions of other related experiences of superintendent and other project management team members.

• Provide an example of how the superintendent successfully dealt with a challenging unknown existing condition on a previous renovation project.

5. MISCELLANEOUS CONSIDERATIONS

• Craft Labor Capabilities: Describe the availability of resources that will be utilized to successfully complete the project.

• Apprenticeship Training Program (Mandatory for Step II): Describe access to federal or state-approved apprenticeship programs, as available.

• Other: This category is included for other items provided by the presenter. Inclusions may include testimonials, awards, corporate memberships in professional organizations or sponsorships, additional project/contract histories, etc., intended to demonstrate why this management team is uniquely qualified for this project.

XII. FEE PROPOSALS

1. Only those teams short listed for interview are required to submit their sealed proposals. Shortlisted teams will receive correspondence noting their scheduled time for their interview as well as where to send their Fee Proposal. Fee Proposals are due on the scheduled submission date prior to the start of oral interviews. Only one sealed copy is required. Fee Proposals will remain sealed until after the qualitative scoring and will then be opened. The fee amount will then be considered (30 %) in conjunction with the qualitative score from the response and interview (70 %).

2. Carefully review the CM/GC Contract sample (Appendix B) before initiating your response submittal. Any exceptions to the contract must be communicated formally in accordance with Section VI. QUESTION, CLARIFICATIONS AND ADDENDA.

3. Appendix E and F of this RFP includes mandatory State apprenticeship and prevailing wage requirements based on the construction value of the project.

4. The State reserves the right to make non-material changes to the appended model agreement, including additions and /or modifications that may be necessary to more completely describe the services defined or implied herein.

5. Any approved reimbursable expenses made under the terms of the final agreement shall be a direct pass-on cost with no adjustment to the fee described therein.

AFB-CSBV pg. 14

6. Any and all products, systems, methods, and procedures developed, as a result of this agreement shall remain the exclusive property of the State.

7. Immediately following the Acknowledgement and Attestation Form is a Fee Proposal Form to be utilized to summarize the fee proposal for the services.

Only those firms short-listed will be required to submit fee proposals as directed by University of Colorado Boulder.

8. This RFP document, it’s appendices, and any written addenda issued prior to the submitting proposals, and written clarifications prior to the interview shall serve as the only basis for proposals.

9. The respondent, by submitting this proposal, does hereby accept that minor changes by the State to the exhibited contract and its exhibits, which do not adversely affect the respondent, shall not be cause for withdrawal or modification of the amounts submitted herein. Exceptions to the RFP documents and/or modification of the proposal may render the proposal non-responsive.

10. Upon due consideration and review of this document along with its appendices, written addenda, and written clarifications prior to the interview, the respondent does hereby submit the following proposal for Construction Management/General Contracting fees, consistent with the schedules provided in the Scope of Services. Respondents are hereby advised that it is the State’s desire to accelerate design and construction schedules where reasonably possible, without adverse cost impact.

11. Respondent should complete the Fee Proposal Form by filling in all blanks on the form that follows.

12. Respondents should include a separate detailed not-to-exceed reimbursable estimate.

AFB-CSBV pg. 15

XII. FEE PROPOSAL FORM

CONSTRUCTION MANAGER/GENERAL CONTRACTING (CM/GC) SERVICES

Project Number: UCB001642 Project Title: MBE - Idea Forge Renovation Project Date:

1. CM/GC Preconstruction Fee $ ________________

2. CM/GC Construction Fee $ ________________

3. General Conditions On-Site CM/GC Staff $ ________________

4. Other Reimbursable General Conditions (NTE) $_________________

Total CM/GC Fee $ _________________

Fees are to be calculated per Exhibit A (SC-6.5), CM/GC Designated Services and Method of Payment.

Please provide a detailed breakdown to adequately describe the CM/GC staff provided, term of their services, and associated anticipated reimbursable costs so as to demonstrate as complete an understanding as possible of the services provided.

Reimbursable general condition expenses are generally confined to the on-site CM/GC construction phase staff reimbursed at direct personnel expense, plus those on-site materials, equipment and facilities to support the work of the CM/GC staff and construction subcontractors.

Acknowledge receipt of Addendum Nos. _______________

Anticipates Services outside the United States or Colorado1* Yes No

If the respondent anticipates services under the contract or any subcontracts will be performed outside the United States or Colorado, the respondent shall provide in a written statement which must include, but need not be limited to the type of services that will be performed at a location outside the United States or Colorado and the reason why it is necessary or advantageous to go outside the United States or Colorado to perform such services. (Does not apply to any project that receives federal moneys)

Will comply with 80% Colorado Labor Yes No

For State Public Works Project per C.R.S 8-17-10, Colorado labor shall be employed to perform at least 80% of the work. “Colorado Labor” means any person who is a resident of the state of Colorado at the time of the Public Works project. Respondents indicating that their proposal will not comply with the 80% Colorado Labor requirement are required to submit written justification along with the proposal submission. A governmental body that

1 Does not apply to projects for Institutions of Higher Education that have opted out of the State Procurement Code.

AFB-CSBV pg. 16 allows a waiver shall post notice and justification for the waiver on its web site. (Does not apply to any project that receives federal moneys)

Design/Build entity is a Service-Disabled Veteran Owned Small Business2* Yes No A Service-Disabled Veteran Owned Small Business (SDVOSB) per C.R.S. 24-103-905, means a business that is incorporated or organized in Colorado or maintains a place of business or has an office in Colorado and is officially registered and verified by the Center for Veteran Enterprise within the U.S. Department of Veteran Affairs. Attach proof of certification along with the proposal submission.

Applicant or Corporate Officer Signature

Title

2 Does not apply to projects for Institutions of Higher Education that have opted out of the State Procurement Code.

IPD CM/GC RFP

Rev 07/2025

XIII. ACKNOWLEDGEMENT AND ATTESTATION FORM

1. Several versions of the Acknowledgment and Attestation Form follow this section.

Proper completion of the appropriate form is a mandatory requirement for a respondent to be considered responsive to this RFP Prequalification Submittal.

2. Qualifications made by a respondent in executing this form may render a submittal non-responsive as determined by the State.

XIII. ACKNOWLEDGEMENT AND ATTESTATION FORM

(Partnership Format)

Date: ______________________________

By responding to this RFP, the respondent(s) certify that he/she has reviewed the Construction Management/General Contracting sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and finds them expressly workable without change or modification.

We certify and declare that the foregoing is true and correct.

Subscribed on _______________________________ at ____________________________ Date City

___________________________, State of _______________________________________ County State

1)___________________________________________ Partner Signature3

Typed Name:_________________________

2)___________________________________________ Partner Signature

Typed Name:_________________________

Notary:________________________________________________ ________________ Date

Commission Expires:_____________________________________

Offeror Acknowledges Receipt of Addendum No. ____, ____, ____, ____ (Addenda MUST be acknowledged)

3 Add additional signatures if there are more than two partners.

(Joint Venture Format)

Date: ______________________

By responding to this RFP, the respondent(s) certify that he/she has reviewed the Construction Manager/General Contractor sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and finds them expressly workable without change or modification.

Subscribed on _______________________________ at _________________________, ___________________________, State of _____________________________________.

County State

1)_______________________ ______________________ _________________ Venture Partner Binding Signature Date

________________________ Typed Name: _____________________________ Type of Business Title: ____________________________________

Witness Date

Typed Name: _____________________________

2)_______________________ ______________________ _________________ Venture Partner Binding Signature Date

________________________ Typed Name: _____________________________ Type of Business Title: ____________________________________

Witness Date

Typed Name: _____________________________

Note:

1. Add additional venture partners as necessary.

2. Witnesses of venture partners shall be corporate secretary for corporations, partners for partnerships, and notaries for sole proprietorships.

3. Attach venture agreement

4. Type of business shall identify the venture partner as a corporation, venture, partnership, sole proprietorship, or other legal entity.

(Corporate Format)

By responding to this RFP, the respondent(s) certify that he/she has reviewed the Construction Management/General Contracting sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and finds them expressly workable without change or modification.

___________________________, State of _____________________________________.

Corporate Officer Signature Date

Secretary Date

Note: Use full corporate name and attach corporate seal here.

(SEAL)

(Sole Proprietorship Format)

By responding to this RFP, the respondent(s) certify that he/she has reviewed the Construction Management/General Contracting sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and finds them expressly workable without change or modification.

___________________________, State of _____________________________________.

Respondent Date

Typed Name: ________________________

Notary: ______________________________ ____________________________ Date

Commission Expires: ___________________

Offeror Acknowledges Receipt of Addendum No. ____, ____, ____, ____ (Addenda MUST be acknowledged)

Appendix A: Evaluation Forms

Appendix A1: Prequalification Submittal/Evaluation Form Appendix A2: Oral Interview /Evaluation Form Appendix A3: Submittal and Interview Ranking Matrix

Cynthia Mcclure-Begley Cross-Out

IPD-GMP-App-A

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

APPENDIX A: EVALUATION OF QUALIFICATIONS FORM:

INTEGRATED PROJECT DELIVERY

Name of Firm:____________________________________________________________________ Name of Project: UCB001642-MBE-Idea Forge Renovation Evaluator No:_______________________________________ Date:______________________________________________

RFP REFERENCE MINIMUM REQUIREMENTS Y ____ N ____

ACKNOWLEDGEMENT AND ATTESTATION INCLUDED: Y ____ N ____

If the minimum requirements have not been met, specify the reason(s):

INSTRUCTIONS:

1. Weights are to be assigned prior to evaluation and are to be consistent on all evaluation forms.

2. Use only whole numbers.

3. Rating: 0 = not provided, 1 = Unacceptable, 2 = Poor, 3 = Fair, 4 = Good, 5 = Excellent

4. Total score includes the sum total of all criteria.

5. A passing score (as a percentage of the total points available) is to be established by the state prior to evaluation.

1. QUALIFICATIONS OF THE FIRM(S) Weight Rating Score ◻ Overall qualifications 5 X = ◻ Organizational structure/lines of authority 3 X = ◻ Subcontractor selection and management 4 X = ◻ Colorado workforce 2 X = ◻ Safety/employee support 4 X

2. QUALIFICATIONS OF MANAGEMENT TEAM MEMBERS Weight Rating Score

◻ Qualifications of the full project team 5 X = ◻ Qualifications and relevant experience of superintendent 5 X = ◻ Qualifications and relevant experience of in-house staff 4 X = ◻ Location/Access 2 X =

3. PROJECT MANAGEMENT APPROACH Weight Rating Score ◻ Approach to successful CM/GC Services

Cost Effectiveness 4 X = Schedule effectiveness 5 X = Quality effectiveness 4 X =

◻ Competitively Bid/Self Performed Work 3 x =

4. PRIOR PROJECT EXPERIENCE/SUCCESS Weight Rating Score ◻ Project #1 4 X =

Timeliness Disruption Budget Considerations Quality Acceptability/Punchlist Compliance

◻ Project #2 4 X = Timeliness Disruption Budget Considerations Quality Acceptability/Punchlist Compliance

◻ Project #3 4 X = Timeliness Disruption Budget Considerations Quality Acceptability/Punchlist Compliance

5. PEOPLE AND CULTURE Weight Rating Score

◻ Hiring and Promotion Practices 3 X = ◻ Subcontracting Practices 3 X =

6. MISCELLANEOUS Weight X Rating = Score

◻ Claims/litigation history 3 X = ◻ Apprenticeship Training Program 3 X =

◻ BCCO 3 X =

Total Score: _________

STATE BUILDINGS PROGRAM

APPENDIX A1: EVALUATION OF QUALIFICATIONS FORM:

INTEGRATED PROJECT DELIVERY

Name of Firm:____________________________________________________________________ Name of Project: UCB001642-MBE-Idea Forge Renovation Evaluator No:_______________________________________ Date:______________________________________________

INSTRUCTIONS:

1. Weights are to be assigned prior to evaluation and are to be consistent on all evaluation forms.

2. Use only whole numbers.

3. Rating: 0 = not provided, 1 = Unacceptable, 2 = Poor, 3 = Fair, 4 = Good, 5 = Excellent

4. Total score includes the sum total of all criteria.

5. A passing score (as a percentage of the total points available) is to be established by the state prior to evaluation.

1. QUALIFICATIONS OF THE FIRM(S) Weight

Rating

Score

5 x =

2. QUALIFICATIONS OF MANAGEMENT TEAM

MEMBERS

4 X =

3. PROJECT MANAGEMENT APPROACH

4 X =

4. PRIOR PROJECT EXPERIENCE/SUCCESS

5 X =

5. MISCELLANEOUS

3 X =

Total Score: _________

STATE BUILDINGS PROGRAM

APPENDIX A2: QUALIFICATIONS AND PROPOSAL RANKING

MATRIX: INTEGRATED PROJECT DELIVERY

INSTRUCTIONS/EXAMPLE:

1. QUALIFICATIONS 70% / FEE 30%

2. Insert total score from each evaluator's SUBMITTAL review.

3. Add all evaluators’ total scores and divide by the number of evaluators to determine the average score for each firm’s qualifications.

4. The maximum score for qualifications on the evaluation form is equivalent to 70 points and is equivalent to the maximum points available for qualifications. Therefore, each firm’s score is determined as a percentage of the maximum points available. To score each average qualification score, use the example formula.

5. Assume the highest score is 600.

SCORING OF QUALIFICATIONS

FIRM B: 600 X 70 points = 70 points

FIRM C: 500 X 70 points = 58.33 points

FIRM A: 400 X70 points = 46.66 points

6. Determine score for each firm’s sealed proposal with the lowest fee being equivalent to a maximum score of 30 points. To score each proposal, use the example formula.

7. Assume the lowest Proposal was $100,000.

SCORING OF PROPOSALS

FIRM A: $100,000 X 30 points = 30 points $100,000

FIRM B: $100,000 X 30 points = 24 points $125,000

FIRM C: $100,000 X 30 points = 20 points $150,000

8. Add the average qualification score to the Proposal score to determine cumulative qualifications and fee score.

9. Numerically rank all firms with the highest scoring firm being the most qualified and advantageous to the state.

FIRM

QUALIFICATIONS

AVE.

QUALS

SCORE

PROPOS

AL

PROPO

SAL

RANK

EVAL

#1

EVA

L #2

EVA

L #3

EVA

L #4

EVA

L #5

EVA

L #6

Appendix B: Construction Manager/General Contractor (CM/GC) Agreement with General Conditions of the Construction Manager/General Contractor Agreement (Forms SC- 6.5 and SC-6.51) (Sample)

SC-6.5

Rev. 09/2026

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONSTRUCTION MANAGER /

GENERAL CONTRACTOR (CM/GC)

AGREEMENT

(STATE FORM SC-6.5)

State Agency University of Colorado Boulder

Department I.D.

GFB

Contract I.D. Number N/A

Project Number

Project Name

Contractor Name

Principal Representatives: For the Contractor:

For the State:

Name Name University of Colorado Boulder Company Name 1540 30th Street Address Line 1 Boulder, CO 80301 Address Line 2 Email City, State ZIP

Email Designated Representative:

Micheal C. Turman Assistant Vice Chancellor, Design & Construction University of Colorado Boulder 1540 30th Street Boulder, CO 80301 mike.turman@colorado.edu

ATTACHMENT 1: The General Conditions of the Contractor’s Design/Bid/Build (D/B/B) Agreement (SC-6.23)

SAMPLE

Appendix B mailto:mike.turman@colorado.edu

Rev. 09/2026 TOC

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) AGREEMENT

(STATE FORM SC-6.5)

TABLE OF CONTENTS ........................................................................ Page Table of Contents for the entire Agreement is located in THE GENERAL CONDITIONS

OF THE CONSTRUCTION MANAGER.GENERAL CONTRACTOR (CMGC) AGREEMENT (SC-

6.51)

RECITALS:

1 ARTICLE 1 PERFORMANCE OF THE WORK

THE WORK

CONTRACT DOCUMENTS

2 ARTICLE 2 EXHIBITS TO THE AGREEMENT

EXHIBITS

3 ARTICLE 3 CONSTRUCTION MANAGER’S SERVICES

AVAILABLE FUNDS

BUDGETING AND FIXED LIMIT OF CONSTRUCTION COST

CONSULTATION AND VALUE ENGINEERING

CONSTRUCTION COSTS

OTHER PRECONSTRUCTION SERVICES

CONTROL OF THE WORK

SCHEDULE AND COORDINATION

AMENDMENTS AND CHANGE ORDERS

PRINCIPAL REPRESENTATIVE CONSULTANTS

START UP

4 ARTICLE 4 TIME OF COMMENCEMENT AND COMPLETION

COMMENCEMENT

COMPLETION

5 ARTICLE 5 COMPENSATION

CONSTRUCTION MANAGER’S FEE

ADJUSTMENTS IN FEE

PAYMENT OF FEE

GUARANTEED MAXIMUM PRICE

CONTRACT SUM

6 ARTICLE 6 CONDITION PRECEDENT

SAMPLE

Appendix B

Rev. 09/2026 TOC

FUTURE APPROPRIATIONS

OBLIGATIONS

7 ARTICLE 7 OPTIONAL PROVISIONS AND ELECTIONS

MODIFICATION OF ARTICLE 2. EXECUTION, CORRELATION, INTENT OF

DOCUMENTS, COMMUNICATION AND COOPERATION

MODIFICATION 1 OF ARTICLE 27. LABOR AND WAGES

MODIFICATION 2 OF ARTICLE 27. LABOR AND WAGES

MODIFICATION OF ARTICLE 39. NON-BINDING DISPUTE RESOLUTION –

FACILITATED NEGOTIATIONS

MODIFICATION OF ARTICLE 45. GUARANTEE INSPECTIONS AFTER COMPLETION

MODIFICATION OF ARTICLE 46. TIME OF COMPLETION AND LIQUIDATED

DAMAGES

8 ARTICLE 8 NOTICE IDENTIFICATION

EXHIBIT A DESIGNATED SERVICES AND METHOD OF PAYMENT

EXHIBIT B CONSTRUCTION MANAGER’S CERTIFICATION

EXHIBIT C REQUEST FOR PROPOSAL

EXHIBIT D CONSTRUCTION MANAGER’S FEE PROPOSAL

EXHIBIT E SALES AND USE TAX FORM

EXHIBIT K BUILDING CODE COMPLIANCE POLICY

SUPPLEMENTARY GENERAL CONDITIONS: FEDERAL PROVISIONS

SUPPLEMENTARY GENERAL CONDITIONS: UNIVERSITY OF COLORADO BOULDER

(Supersedes State Contract Requirements)

SIGNATURE PAGE

THE PARTIES HERETO HAVE EXECUTED THIS AGREEMENT

Each person signing this Agreement represents and warrants that the signer is duly authorized to execute this Agreement and to bind the Party authorizing such signature.

In accordance with §24-30-202, C.R.S., this Contract is not valid until signed by the State Controller (or an authorized delegate) per the Fiscal Rules of the individual Institution of Higher Education

Project Number/Name:

Contract ID No.: N/A

CONTRACTOR

By:

Date: __________________

STATE OF COLORADO

The Regents of the University of Colorado, a Body Corporate

OFFIC…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .