biddoc.pdf

PDF 729 KB Posted

Attached to
Palmer Renovation Abatement Project
Solicitation number
S2027-1001
Issued by
El Paso County, Colorado Springs City, Colorado

About this file

This is a Request for Proposals (RFP) issued by Colorado Springs School District 11 for asbestos abatement services at Palmer High School. The District seeks qualified, Colorado-certified contractors to remove and properly dispose of asbestos-containing materials including plaster, floor tile, mastic, drywall, block filler, foundation sealant, and thermal system insulation in accordance with Colorado state regulations and federal requirements. A mandatory pre-proposal conference and job walk is scheduled for Monday, October 19, 2026, at 10:00 a.m. at Palmer High School, with attendance required for proposal submission eligibility. Contractor questions must be submitted by October 23, 2026, at noon, and proposals are due November 4, 2026, by 2:00 p.m. Mountain Time through the Bidnet platform. The anticipated award date is November 10, 2026. The contract period of performance runs from February 25, 2027, through March 29, 2027, for substantial completion, with full project completion required by April 28, 2027. Work is divided into two phases: the first and second floors (pre-abatement demolition February 18–24, 2027; asbestos abatement February 25–March 17, 2027) and the third floor (pre-abatement demolition February 18–March 10, 2027; asbestos abatement March 11–29, 2027).

The contract does not specify a total project amount in the available documentation. Liquidated damages are assessed at $2,000 per calendar day for failure to achieve substantial completion within specified timeframes for any designated phase area. The contractor must maintain comprehensive insurance coverage including workers' compensation, general liability of no less than $5 million per occurrence and aggregate, and automobile liability of $1,000,000 per person and accident. The contractor is responsible for all labor, equipment, containment, safety materials, transportation, and disposal costs, with no additional compensation for quantity variances discovered during field examination. A comprehensive closeout binder including daily logs, containment pressure documentation, air clearance certification, and waste chain-of-custody records is required as a condition for final payment release. This project is not funded by federal monies; it is financed by the District subject to annual Board of Education appropriations.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

S2027-1001 Colorado Springs School District 11

SOLICITATION AND AWARD COVER PAGE

1. Contract Number: 2. Solicitation Number:

#S2027-1001

3. Type of Solicitation:

√ Negotiated RFP

4. Date Issued:

October 13, 2026

5. Issued by:

Jocelyn Kupferman, Contracting Officer Colorado Springs School District 111115 N. El Paso St.

Colorado Springs, CO 80903Phone: 719-520-2030 Email: jocelyn.kupferman@d11.org

6. Brief Description of Requirements:

District 11 is seeking contractors to propose on an asbestos abatement project at Palmer High School.

Documents are available on Bidnet at:

https://www.bidnetdirect.com/colorado/colorado-springs-school-district-no-11

7. Project Name: Palmer HS Renovation Asbestos Abatement Project

8. TABLE OF CONTENTS FOR SOLICITATION

Section A – Solicitation /Schedule Section F – Pricing and Cost Offer Sheet Section B – Scope of Work Section G – Representations & Certifications Section C –Terms and Conditions, General Section H – Attachments Section D – Terms and Conditions, Project Specific Section I – Proposal Instruction and Submission Requirements Section E – Contract Administration Section J – Evaluation Criteria

9. District Tax Numbers: Federal Employee Identification # : 84-6001179 State of Colorado Tax Exemption #: 98-02922-0000

OFFEROR TO COMPLETE BLOCKS #10 THROUGH #18.

10. Acknowledge receipt of Amendments to RFP by initialing following spaces > #01 #02 #03 #04 #05 #06

11. Name of Contractor: 15. Email of Signature Authority:

12. Street Address of Contractor: 16. Signature of Authority:

13. City/State/Zip: 17. Printed Name of Authority:

14. Phone Number of Signature Authority: 18. Date Signed:

AWARD INFORMATION (to be filled in by District Contracting Officer)

19. Items accepted: 20. Amount (s):

21. Period of Performance: 22. Option Years:

23. Accounting/Appropriations: 24. Printed name of Contracting Officer:

Jocelyn Kupferman

25. Award Date: 26. Contracting Officer Signature:

mailto:jocelyn.kupferman@d11.org https://www.bidnetdirect.com/colorado/colorado-springs-school-district-no-11 https://www.bidnetdirect.com/colorado/colorado-springs-school-district-no-11 https://www.bidnetdirect.com/colorado/colorado-springs-school-district-no-11

Request for Proposals (RFP) #S2027-1001

Palmer HS Renovation Asbestos Abatement Project

Colorado Springs School District 11 Solicitation Available: October 13, 2026

Offers Due: November 4, 2026 by 2pm Mountain Time

The District will post ALL RFP documents on D11’s website and Bidnet’s Strategic Sourcing Platform.

All Proposals must be submitted through Bidnet at:

https://www.bidnetdirect.com/colorado/colorado-springs-school-district-no-11

Register at Bidnet, in order to propose:

https://www.bidnetdirect.com/public/user-registration

Need Help? Please contact Bidnet directly at support@bidnet.com or 1.800.435-4603 Option 2 for technical questions or issues related to your submission. Please note, if you have previously registered in Bidnet, it is not necessary to register again.

POINT OF CONTACT:

Jocelyn Kupferman, Contracting Officer Procurement and Contracting

1115 N. El Paso St.

Colorado Springs, CO 80903

Phone: 719-520-2030 Email: jocelyn.kupferman@d11.org https://www.bidnetdirect.com/colorado/colorado-springs-school-district-no-11 https://www.bidnetdirect.com/public/user-registration mailto:support@bidnet.com mailto:jocelyn.kupferman@d11.org

TABLE OF CONTENTS

SOLICITATION AND AWARD COVER PAGE

SECTION A -- SOLICITATION SCHEDULE

SECTION B -- SCOPE OF WORK

SECTION C -- GENERAL TERMSAND CONDITIONS

SECTION D -- PROJECT SPECIFIC TERMS AND CONDITIONS

SECTION E -- CONTRACT ADMINISTRATION

SECTION F -- OFFEROR’S PRICING SHEET

SECTION G -- REPRESENTATIONS AND CERTIFICATIONS

SECTION H -- ATTACHMENTS & OTHER SUPPORTING DOCUMENTS

SECTION I -- PROPOSAL INSTRUCTIONS TO OFFERORS

SECTION J -- EVALUATION CRITERIA AND AWARD

A. SECTION A -- SOLICITATION SCHEDULE

A.1 PRE-PROPOSAL CONFERENCE

This solicitation will include a MANDATORY Pre-Proposal Conference:

DAY, DATE: Monday, October 19, 2026 TIME: 10:00 am MT PLACE: Palmer High School

301 N. Nevada Ave., Colorado Springs, CO 80903 Meet outside the main entrance on the corner for N Nevada and Platte.

If the pre-proposal conference is mandatory, only contractors in attendance will be permitted to submit proposals. The District will record company and representative names of those in attendance.

A.2 SOLICITATION SCHEDULE

EVENT PROJECTED DATE COMMENTS

Solicitation Available/Notification 10/13/2026 In Bidnet Mandatory Pre-Proposal Conference/Job-Walk

10/19/2026 10:00 a.m. at Palmer High School

Contractors’ Questions Due 10/23/2026 By Noon – submit on Bidnet

District distributes Addendum, if needed

10/28/2026 In Bidnet

Offers Due 11/4/2026 By 2 p.m. MT – submit on Bidnet

Evaluation Schedule 11/6/2026 Anticipated Award Date 11/10/2026 Via email

**All dates are subject to change**

A.3 TERM OF AGREEMENT

A.3.1 The designated period of performance will be February 25, 2027 through March 29, 2027 Substantial Completion.* Contractor must fully complete project by April 28, 2027.

*Substantial Completion for this project is defined in Item B.3.10.

A.3.2 Any financial commitment of the District arising out of this Contract is subject to annual appropriation by the Board of Education.

B. SECTION B -- SCOPE OF WORK

B.1 GENERAL

The following is presented to describe the general expected vendor performance requirements. Offerors must submit how and when they are capable of supplying the required products and services and completing the work within the required time. Offerors are free to suggest other product(s) brands and models, work service procedures, or project approaches, designs, or exceptions to this general scope of work. Those exceptions must be clearly (bold, underlined, etc.) indicated in your offer. If an Offeror cannot perform as described or takes exception to any element, those exceptions must be fully described in their Offer and an alternate plan or approach presented. Award will not be based on price alone.

B.1.1 The apparent silence of any scope of work/specification(s) and any supplemental amendment specifications as to any details or the omission from it of a detailed description concerning any point shall be regarded as meaning that only the best commercial practices are to prevail. Contractors are to submit written questions through Bidnet to the Contracting Office, by Noon on Friday, October 23, 2026. This solicitation document is requesting Offers from responsible/capable contractors who desire to sell to the District their products and/or services at a negotiated price.

B.1.2 Clean-Up Contractor shall keep the premises free from accumulation of debris, surplus material, waste material, dirt piles and rubbish caused by the work. Contractor shall perform clean-up daily and transport rubbish to an on-site location designated by Contractor. Contractor is responsible for containment and removal. The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work and premises any surplus materials that are not the property of the District. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer and shall remove surplus material, waste material, and dirt and rubbish, tools, equipment and scaffolding.

A. Final Clean-Up:

1. Exterior: In addition to items specified below, all surfaces on exterior, concrete, metal, etc., affected by the work shall be carefully and thoroughly cleaned.

2. Glass: Both sides of all glass affected by the work shall be carefully and thoroughly cleaned by professional window cleaners and left absolutely clean and free from paint, labels, grease, dirt, etc.

3. Hardware: Clean and polish all hardware affected by the work and leave clean and free from paint, grease, dirt, etc.

4. Equipment: Carefully and thoroughly clean all items or equipment, mechanical, electrical, cabinets, ductwork, etc., which have been affected by the work.

B. All work areas within the area of responsibility shall be left in clean condition before being accepted by the District. The Contractor shall be required to clean only those areas which are affected by the work. It is anticipated that this will be limited to the work areas indicated on the plans, areas adjacent to the work areas which are affected by the work, the areas on the site where the Contractor’s trailer(s) are located, and any other interior or exterior areas which have been dirtied or damaged by the Contractor’s operations under this contract.

C. Any damage caused by the Contractor shall be accomplished within the period of performance of the Contract. No extension of time will be granted to complete repair

(including repainting) operations. The project shall not be considered substantially complete until it has been cleaned as indicated.

B.1.3 Work Area B.1.3.1 The Contractor shall limit their operations to the area approved by the District. Work area is limited to work areas indicated on the plans, areas adjacent to the work areas, areas around Contractor trailers, and any other interior or exterior areas the Contractor’s operations affect.

B.1.3.2 The awarded Contractor shall be required to attend and provide advice and guidance at subsequent weekly/monthly project construction site meetings conducted by the District. Occasionally a project meeting may be held at an administrative location other than the construction site. Contractor is responsible for providing a summary of the daily construction activities at each meeting; along with any construction issues not addressed in specifications and contract, new discovery items such as changes in codes and regulations, weather problems, labor problems, sub-contractor problems, supply delivery problems, or anything that could affect the project. These concerns shall be in writing. Contractor shall send employees to the meetings with appropriate knowledge of the project and employees that can fully discuss detail aspects of the project. Others that may be attending these meetings are: other District Project Managers or other Executive Directors, District school employees, District Facilities Department resident engineers or craft employees, members of the public, project designers/Architects and Engineers, Commissioning Agents, or other Consultants who may be presenting information. District reserves the right to request Contractor provide other documents related to the project success (such as: partial Schedule of Values, delivery timelines (Gantt charts) or spreadsheet of building deliverables, and/or training schedules) at these meetings to be used as discussion items.

B.1.4 Schedule Details B.1.4.1 Within ten (10) calendar days after the work commences on the contract or another period of time determined by the Contracting Officer, the Contractor shall prepare and submit to the Contracting Officer for approval one (1) copy (preferred to be electronic) of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment).

The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule. The schedule shall include a provision for weather delays.

B.1.4.2 The Contractor shall enter the actual progress on the schedule as directed by the Contracting Officer, and upon doing so shall immediately deliver one (1) electronic copy of the annotated schedule to the Contracting Officer. If in the opinion of the Contracting Officer, the contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress without additional cost to the District.

B.1.4.3 Failure of the Contractor to comply with the requirements of the schedule shall be considered sufficient grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the Default terms of the contract.

B.2 BACKGROUND

Colorado Springs School District 11 serves over 22,000 students and employs approximately 3,600 full and part-time employees, both instructional and operation.

The District has thirty-four elementary schools, ten middle schools (grades 6-8), four traditional high schools, one consolidated alternative/early colleges/vocational campus, one satellite alternative ed campus, and six District-authorized charter schools in their portfolio.

Palmer High School is requesting proposals from qualified, Colorado-certified asbestos abatement contractors to provide asbestos abatement services at Palmer High School. The work includes removal and proper disposal of asbestos-containing plaster, floor tile, mastic, drywall, block filler, foundation sealant and thermal system insulation (TSI) in accordance with applicable Colorado state regulations and federal requirements.

B.3 SCOPE OF WORK

B.3.1 Technical/Functional/Performance Requirements

1. OVERVIEW

This Scope of Work (SOW) outlines the strict non-negotiable requirements for selective pre-abatement demolition and hazardous materials abatement at Palmer High School. The Abatement Contractor (AC) shall seamlessly coordinate all field activities to ensure strict adherence to the performance schedule, regional regulatory compliance, and total site security on an active educational campus.

2. SCHEDULE & MILESTONES

Work must be executed sequentially and within the, tight windows defined below. Substantial Completion is defined as the state where all hazardous material removal is entirely complete, final independent air clearance criteria have passed, containment barriers are safely removed, and the area is officially declared safe for the General Contractor to resume standard renovation activities.

Project Phase Area Pre-Abatement Demo (GC Windows)

Asbestos Abatement (AC Windows)

1st and 2nd Floors 02/18/2027 – 02/24/2027 02/25/2027 – 03/17/2027

3rd Floor 02/18/2027 – 03/10/2027 03/11/2027 – 03/29/2027

3. LIQUIDATED DAMAGES

Time is of the essence for this project due to the constraints of an active high school academic calendar. If the Abatement Contractor fails to achieve Substantial Completion within the specified timeframes for any designated phase area, the Abatement Contractor shall pay to the District the non-negotiable sum of $2,000.00 per calendar day as Liquidated Damages. These damages represent a fair and reasonable forecast of the actual administrative, safety, air-monitoring, and trade disruption costs incurred by the District due to a delay, and are explicitly structured as a compensatory remedy rather than a penalty.

4. PRE-ABATEMENT DEMOLITION & DISCOVERY PROTOCOLS

4.1 General Contractor Baseline Scope

The General Contractor (GC) will execute and complete the following selective architectural strip-out work prior to the Abatement Contractor's (AC) scheduled mobilization within the respective zones:

1st & 2nd Floors: Complete removal of all interior doors, hardware, wood casework/cabinets, selective lockers and demolition of designated non-asbestos-containing wall partitions situated directly within the abatement scope area.

3rd Floor: Complete removal of all ceilings, light fixtures, electrical devices, doors, wood cabinets, lockers and non-asbestos-containing wall partitions across the entire scope area.

4.2 Discovery of Deficiencies & Additional Demolition Needs

If, during mobilization or the setup of negative pressure enclosures, the Abatement Contractor identifies or documents that additional structural components, finishes, or non-asbestos walls must be demolished to successfully access or complete the specified hazardous removals, the AC must formally notify the District Project Manager (PM) in writing within twenty-four (24) hours of initial identification.

The District PM will evaluate, respond, and arrange for the execution of the necessary supplemental work within seventy-two (72) hours from the receipt of the written notice. The AC shall not proceed with disturbing any conflicting elements without explicit written clearance from the PM.

5. ASBESTOS ABATEMENT SCOPE OF WORK

The Abatement Contractor (AC) shall furnish all specialized labor, safety materials, containment equipment, insurance, engineering controls, transportation, and legally compliant landfill disposal services required to completely abate the following materials, as explicitly detailed and designated on the project drawings:

Floor Materials: Complete removal of all asbestos-containing floor tile and associated black mastic adhesives.

Thermal System Insulation (TSI): Complete removal and cleanup of all asbestos-containing pipe insulation, fitting insulation, boiler insulation, or related thermal system compound materials.

Wall Systems: Controlled removal of asbestos-containing plaster finishes and underlying scratch coats on designated structural wall partitions.

Ceiling Systems: Controlled demolition of asbestos-containing plaster ceilings, along with the simultaneous removal of 12x12 ceiling tiles and associated puck mastic adhesive nodes directly adhered to the plaster substrate.

6. STRUCTURAL PROTECTION & PROPERTY PRESERVATION

6.1 Substructure Protection

During the aggressive mechanical or manual removal of hazardous plaster finishes from walls and ceilings, the AC must implement protective techniques to preserve the existing masonry, terracotta, framing, and permanent structural components situated immediately behind the plaster. Any impact damage, gouging, or structural degradation causing damage shall be stopped and alternate methods of removal shall be discussed prior to proceeding.

6.2 High-Value Architectural Asset Preservation

The AC must engineer and implement protective measures to preserve, seal, and completely isolate the following architectural elements from cross-contamination, impacts, or containment anchoring damage:

Trophy Cases: The central built-in display trophy cases on both levels must be fully isolated behind timber hoarding panels and sealed dust-tight.

Structural Columns in front of the Trophy Cases: All exposed support columns within the active abatement footprint must be securely wrapped and padded.

Plaster Detailing: All decorative, non-abated plaster moldings and historic finishes situated directly above the trophy cases on both floors must remain undisturbed and strictly protected throughout the duration of the project.

7. REGULATORY COMPLIANCE, SUBMITTALS & QUANTITIES

7.1 Mandatory Pre-Work Submittal Package

The Abatement Contractor shall submit a comprehensive PDF submittal package to the District PM and Environmental Consultant for formal approval prior to any physical site mobilization or equipment delivery. No work or site staging may begin without written approval of this package, which must contain:

State Notification: A valid copy of the mandatory 10-day notification submitted to the Colorado Department of Public Health and Environment (CDPHE) Asbestos Unit.

Corporate & Worker Licensing: Valid State of Colorado Asbestos Abatement Contractor certifications, along with up-to-date state certifications, current medical clearances, and negative respirator fit-test records for all onsite supervisors and workers.

Site-Specific Safety Plans: A detailed Health and Safety Plan (HASP) including standard Respiratory Protection Programs, specialized engineering layouts of Negative Pressure Enclosures (NPE), and location details for decontamination units.

7.2 Field Quantity Verification & Baseline Scope Expectations The quantities and spatial dimensions indicated on the contract drawings represent baseline estimates developed for procurement. The Abatement Contractor is strictly responsible for field-verifying all dimensions, layout details, and exact material quantities prior to commencing with removal activities. By moving on to the removal work, the AC explicitly affirms that their bid is comprehensive and sufficient to achieve full project completion. No contract sum adjustments or change orders will be authorized for quantity variances that could reasonably be discovered during a standard visual field examination.

8. FIELD REPORTING, CONSULTANT COORDINATION & DISCOVERY

8.1 Daily Progress Reporting & Schedule Recovery Mandate

The AC shall generate and submit an electronic Daily Progress Report to the District PM every working day no later than 8:00 AM, capturing the performance data from the immediately preceding shift. The report must contain: the square/linear footage abated per material type, an statement declaring whether the phase area is trending on schedule. If a phase falls behind the baseline milestone calendar, the AC must attach an actionable Schedule Recovery Plan outlining specific corrective measures—such as increased workforce staffing, extended shift durations, or modified containment sequencing—to guarantee compliance with the Substantial Completion deadline without additional cost to the District.

8.2 Communication Protocol with District PM & Environmental Consultant The AC shall maintain open, professional lines of communication with the District PM and the District’s designated independent Environmental Consultant/Industrial Hygienist, John Harness. John Harness is tasked with executing all regulatory independent visual inspections, baseline validation sampling, and final air clearance sampling. The AC must closely coordinate with Mr. Harness and provide a minimum of twenty-four (24) hours advance notice prior to requiring a final visual containment check or air clearance sample draw. Short-notice testing requests that result in trade delays will be the sole responsibility of the AC.

8.3 Unforeseen Asbestos Containing Materials (ACM) Protocol

If, during the destructive demolition of walls, ceilings, or architectural assemblies, the AC encounters, exposes, or suspects any previously hidden, undocumented Asbestos-Containing Material (ACM) or Thermal System Insulation (TSI) not explicitly delineated on the contract drawings, the AC shall immediately halt all localized removal activities affecting said material. The AC shall leave the area structurally stable, prevent physical disturbance, and immediately provide verbal and textual notification to the District PM and John Harness. Work shall remain suspended in the immediate micro-zone until the District can execute testing, render a formal safety evaluation, and issue written instructions regarding the appropriate path forward.

9. SITE LOGISTICS, WATER, & POWER

The General Contractor will provide reasonable quantities of temporary construction utility connections, specifically water and power, necessary for abatement execution. The AC shall submit a utility requirement plan—explicitly detailing required electrical voltages, single/three-phase configuration, total amperage draw, water volumes, and specific physical connection points—to the GC a minimum of two

(2) weeks prior to onsite mobilization.

The GC will install and maintain temporary security construction fencing around the perimeter of the 'Front 9' entrance plaza. The AC is authorized to utilize this secured, designated exterior plaza area exclusively for waste container/dumpster placement, material staging, and safety load-out operations.

10. CAMPUS SITE SAFETY & SECURITY

Because Palmer High School remains an active educational campus, strict environmental safety and physical security are non-negotiable contractual requirements. The primary school building structure must remain completely secure at all times. Exterior doors, entry points, or safety airlocks shall not be propped open at any time for any reason. The AC must ensure absolute dust and physical isolation of the active work zones from students, administrative staff, and unauthorized personnel, strictly adhering to all OSHA, EPA, and state regulatory safety standards.

11. COMPREHENSIVE PROJECT CLOSEOUT BINDER

As a condition precedent to the authorization of final project retention release and formal contract closeout, the Abatement Contractor must compile and deliver a comprehensive, digitally indexed Closeout Binder to the District PM and John Harness. This closeout documentation package must contain:

Daily Logs: Complete copies of all daily project field logs, containment sign-in/sign-out registries, and shift supervisor notes.

Containment Logs: Continuous, uninterrupted differential pressure manometer charts or digital data logs demonstrating constant negative pressure across all Enclosures.

Clearance Certification: Copies of all final visual inspection signs-offs and formal aggressive air clearance laboratory analysis reports issued and signed by John Harness.

Waste Chain of Custody: Fully executed EPA/CDPHE Waste Shipment Records (WSR) and landfill-stamped tipping manifests proving the safe, legal disposal of all hazardous materials at a licensed facility within thirty (30) days of removal.

B.3.3 Specifications Contractor to review the District’s website and prepare their proposal in accordance with the District’s Design and Construction

Standards:

Design & Construction Standards -

Colorado Springs Schools District 11

B.3.4 Reporting Requirements Contractor will report progress and how their efforts match the project schedule.

Contractor will also prepare progress meeting minutes and distribute to District and other meeting attendees.

B.3.5 Training Requirements Contractor will train District staff on proper use and maintenance of new equipment.

B.3.6 Value Added Items Contractors are welcome to include descriptions and supporting information in their proposal packages, regarding any approach or materials they feel can add value to the project (or decrease costs, project time/schedule and/or difficulty). Alternative proposal pricing may be submitted by copying the Pricing Schedule, Section F and submitting multiple times for multiple unique approaches.

B.3.7 Performance Time and Schedule The designated period of performance will be March 29, 2027 for substantial completion. Contractor must fully complete project (including resolving any punch list items) by April 28, 2027.

B.3.8 Material Submittals Contractor must provide product information for Project Manager Approval, prior to ordering materials.

B.3.9 Warranty of Construction Contractor to warrant all work and materials for a minimum of one (1) year from project completion. Contractors must also propose based on Warranty information in Section C.24.

B.3.10 Substantial Completion The District defines Substantial Completion for this project as the work has been completed and is ready for the next phase of the demolition/renovation project.

https://www.d11.org/aboutd11/operations/builtenvironment/construction-design https://www.d11.org/aboutd11/operations/builtenvironment/construction-design

B.3.11 Schedule Contractor will propose their project approach and schedule as part of their proposal submittal. District and Contractor will finalize schedule as part of pre-construction kick-off discussions. The schedule will start and end within the period of performance identified in section A.3.1 and B.3.7 of this document.

C SECTION C -- GENERAL TERMS AND CONDITIONS

The following administrative Terms and Conditions shall apply to all District solicitations and subsequent Contracts.

C.1 TERM OF THE CONTRACT

C.1.2 Term of Agreement The period of performance is specified in Section A.1.3 and B.3.7. The Notice to Proceed (NTP) will also reflect the start date.

C.1.3 District Obligation This Contract is not intended to create a multiple fiscal year debt or other obligation and the District’s obligations hereunder shall be interpreted and limited in such a manner as to avoid creation of a multiple fiscal year debt or other obligation under the terms of Article X, Section 20, Paragraph 4(b) of the Colorado Constitution.

C.1.4 Multiple Year Commitment Subject to Colorado Revised Statutes (C.R.S.) §24-103-503 entitled Multi-year Contracts, any multiple year commitment beyond the current fiscal year is subject to availability of appropriated funds in future fiscal years. If funds are not available in a fiscal year to continue the contract, the contract will be terminated at no cost to the District, upon a 30-day written notice. Upon termination, any materials, supplies, or items of equipment, which have not been fully paid for by the District will be returned to the vendor at the vendor’s expense. The District will not purchase similar materials, supplies, or items of equipment during the anticipated life of the terminated contract without notification of the terminated contractor and consideration of reinstating the terminated contract.

C.2 ASSIGNMENTS

This Contract may not be assigned to any other party without written approval from the District which may be withheld in the District’s discretion. In the case of insolvency or purchase by a Third Party, Contractor shall do all of the following:

A. Notify the District in writing 90 days prior to assignment.

B. Provide software source code, if applicable, to the District at no additional cost; or C. Ensure the Novation agreement is granted by the new District at no additional cost to the District.

D. Provide new Federal Tax ID information.

This Contract and all of the terms and provisions hereof shall be binding upon and shall inure to the benefit of both Parties to the extent permitted hereunder. Notwithstanding the foregoing any such assignment shall be subject to the District’s approval.

C.3 CONTRACT RELATIONSHIP

The relationship between the Contractor and the District is a contractual relationship. It is not intended in any way to create a legal agency or employment relationship. The Contractor shall at all times maintain its status as an independent contractor and both parties acknowledge that neither is an agent, partner or employee of the other for any purpose. The Contractor shall be responsible for causing all required workers compensation insurance to be provided for all of its employees and subcontractors.

C.4 NO THIRD PARTY BENEFICIARY

It is expressly understood and agreed that enforcement of the terms and conditions of this Contract, and all rights of action relating to such enforcement, shall be strictly reserved to the Parties hereto, and nothing contained in this Contract shall give or allow any such claim of action by any other or third person or entity on such Agreement. It is express intention of the Parties hereto that any person or entity, other than the Parties to this Contract, receiving services or benefits under this Contract shall be deemed to be incidental beneficiaries only.

C.5 APPLICABLE LAW

The Contractor shall comply with all Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this Contract. This Contract shall be construed in accordance with and governed by the laws of the State of Colorado.

Federal Funding: If the District will pay for the Contract related to this RFP with any federal funds, that designation will be clearly stated in this RFP and the following clauses, in accordance with Appendix II to Part 200—Contract Provisions for Non- Federal Entity Contracts Under Federal Awards, apply:

In addition to other provisions required by the Federal agency or non-Federal entity, all Contracts made by the non-Federal entity under the Federal award must contain provisions covering the following, as applicable.

(A) Contracts for more than the simplified acquisition threshold currently set at $150,000, which is the inflation adjusted amount determined by the Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) as authorized by 41 U.S.C. 1908, must address administrative, contractual, or legal remedies in instances where contractors violate or breach contract terms, and provide for such sanctions and penalties as appropriate.

(B) All contracts in excess of $10,000 must address termination for cause and for convenience by the non-Federal entity including the manner by which it will be affected and the basis for settlement.

(C) Equal Employment Opportunity. Except as otherwise provided under 41 CFR Part 60, all contracts that meet the definition of “federally assisted construction contract” in 41 CFR Part 60-1.3 must include the equal opportunity clause provided under 41 CFR 60-1.4(b), in accordance with Executive Order 11246, “Equal Employment Opportunity” (30 FR 12319, 12935, 3 CFR Part, 1964-1965 Comp., p. 339), as amended by Executive Order 11375, “Amending Executive Order 11246 Relating to Equal Employment Opportunity,” and implementing regulations at 41 CFR part 60, “Office of Federal Contract Compliance Programs, Equal Employment Opportunity, Department of Labor.”

(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal program legislation, all prime construction contracts in excess of $2,000 awarded by non-Federal entities must include a provision for compliance with the Davis-Bacon Act (40 U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”). In accordance with the statute, contractors must be required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, contractors must be required to pay wages not less than once a week. The non-Federal entity must place a copy of the current prevailing wage determination issued by the Department of Labor in each solicitation. The decision to award a contract or subcontract must be conditioned upon the acceptance of the wage determination. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency. The contracts must also include a provision for compliance with the Copeland “Anti-Kickback” Act (40 U.S.C. 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”). The Act provides that each contractor or sub-recipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency.

(E) Contract Work Hours and Safety Standards Act (40 U.S.C. 3701-3708). Where applicable, all contracts awarded by the non-Federal entity in excess of $100,000 that involve the employment of mechanics or laborers must include a provision for compliance with 40 U.S.C. 3702 and 3704, as supplemented by Department of Construction - July 2020 6 Labor regulations (29 CFR Part 5). Under 40 U.S.C. 3702 of the Act, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.

(F) Rights to Inventions Made Under a Contract or Agreement. If the Federal award meets the definition of “funding agreement” under 37 CFR §401.2 (a) and the recipient or sub-recipient wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the recipient or sub-recipient must comply with the requirements of 37 CFR Part 401, “Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements,” and any implementing regulations issued by the awarding agency.

(G) Clean Air Act (42 U.S.C. 7401-7671q.) and the Federal Water Pollution Control Act (33 U.S.C. 1251-1387), as amended—Contracts and sub-grants of amounts in excess of $150,000 must contain a provision that requires the non-Federal award to agree to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387). Violations must be reported to the Federal awarding agency and the Regional Office of the Environmental Protection Agency (EPA).

(H) Debarment and Suspension (Executive Orders 12549 and 12689)—A contract award (see 2 CFR 180.220) must not be made to parties listed on the government-wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 CFR part 1986 Comp., p. 189) and 12689 (3 CFR part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.

(I) Byrd Anti-Lobbying Amendment (31 U.S.C. 1352)—Contractors that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352. Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the non-Federal award.

(J) See §200.322 Procurement of recovered materials.

This Project IS NOT funded by any Federal monies.

C.6 LICENSES, TAXES, PERMITS, AND FEES

The Contractor shall, without additional expense to the District, be responsible for obtaining any necessary licenses and permits (including City of Colorado Springs Drainage and Right of Way permits), and for complying with any Federal, State, and municipal laws, codes, and regulations, taxes applicable to the performance of the work. The Contractor shall perform all work in accordance with laws, ordinances, codes, etc., in force in the city, county, and state where the project is located. The Contractor shall pay all applicable taxes, including payroll taxes and all other expenses in connection with the performance of the work. Cost of these items will be included in the Contract price.

C.7 SALES TAX

Colorado Springs School District 11 is a public governmental non-profit entity that is tax exempt under Section 115 of the Internal Revenue Code. The District’s Federal tax number is FIN 84-6001179 and the State of Colorado tax number is 98-02922-0000. Federal and State taxes shall not be assessed on purchases for District projects.

C.8 VENUE AND JURISDICTION

Exclusive venue and jurisdiction over any dispute relating in any way to the Contract shall be in the District Court, El Paso County, and State of Colorado.

C.9 COLORADO GOVERNMENTAL IMMUNITY ACT

Except as expressly provided herein, Colorado Springs School District 11 retains all of its rights under the Colorado Governmental Immunity act, C.R.S. §24-10-101, et. Seq. This Contract shall not be construed to create any right or benefit for any person who is not a party to this Contract.

C.10 APPROPRIATION OF FUNDS

In accordance with District governing Board and C.R.S. §24-103-503 entitled “Multi-year Contracts”, performance of the District’s obligations under this Agreement are expressly subject to the appropriation of funds by the Colorado Springs School District 11 Board of Education. Further, in the event that funds are not appropriated in whole or in part sufficient for performance of the District’s obligations under this Agreement, or appropriated funds may not be expended due to Board spending limitations, then the District may terminate this Agreement without compensation to the Contractor. If funds are not available in a fiscal year to continue the Contract, the Contract will be terminated at no cost to the District, upon a 30-day written notice. Upon termination, any materials, supplies, or items of equipment, which have not been fully paid for by the district will be returned to the vendor at the vendor’s expense. The District will not purchase similar materials, supplies, or items of equipment during the anticipated life of the terminated Contract without notification of the terminated Contractor and consideration of reinstating the terminated Contract.

C.11 CHANGE ORDERS

The Contracting Officer, at any time, by written order, may make changes in or additions to the services to be performed by this Agreement, issue additional instructions, require modified or additional work or services within the general scope of the Agreement, or vary the amount of District-furnished property. If any of said changes cause any increase or decrease in the cost of, or in the time required for, performance of this Agreement, an equitable adjustment will be made in the Agreement price or term of performance, or both, and the agreement will be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty calendar days from the date of receipt by the District of the notification of changes provided, however, that the Contracting Officer, if he or she decides that the facts justify such action, may receive and act on any such claim asserted at any time prior to final payment under this Agreement. Failure to agree to any adjustment will be a dispute concerning a question of fact within the meaning of the clause of this Agreement titled "Disputes." However, nothing in this clause excuses the Contractor from proceeding with the agreement as changed, and it is limited to proceeding with its appeal pursuant to the provision titled "Disputes."

C.12 PROTECTION OF DISTRICT PROPERTY

The Contractor shall take all necessary precautions and care to avoid damaging existing buildings, equipment, materials, and vegetation on District property. If the Contractor’s failure to take the necessary precautions or negligence results in damage to any of the District’s property, the Contractor shall replace or satisfactorily repair the damage at no expense to the District. If the Contractor refuses to make such repairs or replacement, the District will have the right to repair by whatever means necessary and deduct the cost from the Contract price.

C.13 DELAY CAUTION - CMAS TESTING

Contractors shall prepare and understand the need for special work planning schedules that the District may require if work could interfere with student scholastic activities, including test taking for Colorado Measures of Academic Success (CMAS) that occurs each year and starts for 3rd graders in February and continues through 10th graders until Mid-April.

C.13.3 Work stoppage could occur prior to test taking time as students prepare for the tests. District will provide exact dates of the testing and/or work stoppage times for a particular school and grade level. Contractor must take these stoppages into consideration for their proposal offer and, if awarded, for the actual work schedules.

C.14 DISTRICT CALENDAR

Colorado Springs School District 11 calendar showing school start and end times, scheduled holidays, and early release dates for the current fiscal school year are hereby furnished and should be taken into consideration by all Offerors to prepare their estimates for scheduling purposes. The calendar and school start and end times are furnished as an estimating tool only. Days and times may change due to unforeseeable circumstances during the actual school year. Therefore, the District is not responsible for any Contractor delays or damages due to any applicable changes. Current school year calendar can be accessed at: http://www.d11.org and click on “Calendar” on the left side of page.

C.15 ACCESS TO DISTRICT BUILDINGS

C.15.3 Normal Working Hours “Normal working hours” for District personnel is defined as 7:30 a.m. to 4:30 p.m., Monday http://www.d11.org/ through Friday, and excludes State and Federal holidays. At the District’s option, a School District employee may be required to be in the buildings during times that the building is occupied by private Contractors. If access to the buildings is required by the Contractor during other than normal working hours, then the Contractor must reimburse the District for overtime pay for one employee for the entire time that the employee is required to be in the building in excess of normal working hours. The Contractor must give written notice to the District at least two (2) days in advance of such requirement for access to the buildings during other than normal working hours. Reimbursement, if applicable, will be deducted from amounts owed by the District to the Contractor.

C.15.4 Pre-Construction Authorization Prior to entering a District site or facility, the Contractor must have completed pre-construction procedures and a safety meeting with the District Project Manager. A Notice to Proceed (issued only by the District Contracting Officer) or receipt of a District Purchase Order does provide the Contractor with an assumed right to enter District facilities to perform work. The Notice to Proceed is issued only after receipt of the signed contract, appropriate insurance certificate and endorsements, and performance and/or material payment bonds, if required. The District Project Manager will schedule the Pre-Construction Safety meeting, which may be on site or at another designated office. The Project Manager, also known as the Contracting Officer’s Technical Representative (COTR), is responsible for the daily coordination involving ordering, site supervision, scheduling, receiving, shipment inspection, product and/or service quality assurance, reviewing of invoices, recommendation for payment and other matters of a technical nature. Contractors must always sign in with the main school office prior to beginning any work in District facilities. The District reserves the right not to issue facility internal or external keys or access codes. Even if a District building is unlocked, especially around loading/unloading docks, and access is easily obtained, a Contractor must first sign in with the school main office, prior to beginning any work. Date and time of first Pre-Construction meeting will be determined after Contract signing.

C.16 INSPECTION AND ACCEPTANCE (SERVICES)

The District’s Requirement office through the COTR is responsible for performing inspection and acceptance of services rendered, including inspection of any records maintained by the Contractor.

C.17 INSPECTION/TESTING (SUPPLIES AND MATERIALS)

Payment for the goods delivered hereunder shall not constitute acceptance thereof. The District shall have the right to inspect such goods and to reject any or all of said goods which are in District’s judgment defective or nonconforming. Goods rejected and goods supplied in excess of quantities called for herein may be returned to Seller at its expense, in addition to District’s other rights. The District may charge Seller all expenses of unpacking, examining, repacking and reshipping such goods. In the event District receives goods whose defects or nonconformity is not apparent on examination, the District reserves the right to require replacement, as well as payment of damages. Nothing contained in this purchase order shall relieve, in any way, the Seller from the obligation of testing, inspection, and quality control.

C.18 INDEMNIFICATION AND HOLD HARMLESS

C.18.3 The Contractor agrees to defend, indemnify, and hold the District harmless from and against any and all liabilities, costs, damages, or losses (collectively the “Damages”) that the District may sustain arising out of any and all claims, demands, costs, or judgments, relating to the management services provided by the Contractor under this Contract, except for those Damages that are legally caused by the negligence of the District or its employee(s). The term “Damages” includes without limitation those sustained by the District under its self-insurance policies and those caused by a third person, an Act of God, collision, vandalism, fire, or theft.

C.18.4 The term “claims” includes without limitation those asserted against the District’s insurance and self-insurance policies, as well as those resulting from any other cause, including without limitation a third person, accident, collision, vandalism, fire, or theft, except as provided in this Section.

C.18.5 The District shall notify the Contractor of any Claim as soon as practicable, and shall cooperate with the Contractor in the defense…

This is the start of the file's text. The full file is on GovTribe.