This document is a Bidders Questions and Answers record for Idaho Invitation to Bid (ITB) #1114 for Statewide Practice Ammunition. The State of Idaho is procuring practice ammunition for state agencies and eligible political subdivisions through a competitive bidding process. The ITB includes 15 line items across multiple ammunition calibers and types, with awards to be made on a per-line-item basis to at least two lowest responsive and responsible bidders per item. The original bid closing date of April 23, 2026, has been extended by ten business days to May 7, 2026, with the public bid opening scheduled for May 8, 2026, at 10:30 AM MT. Bidders are not required to submit pricing for all ammunition category tables; however, if bidding within a category table, all line items within that table must receive pricing. The contract will be a firm-price statewide arrangement with specific performance requirements and renewal options executed by mutual written agreement in compliance with State of Idaho Contract Terms and Conditions.
Ammunition specifications must meet or exceed performance requirements in Exhibit 3 and comply with SAAMI standards; NATO STANAG-compliant and SAAMI-compliant products are both acceptable, and NATO headstamp markings are no longer required. Contractors must maintain a 90% quarterly fill rate for all orders placed under the contract, though failure to meet this benchmark is discretionary grounds for non-renewal or termination. Pricing submissions may be provided via manufacturer specification sheets, public catalog links, or online MSRP listings with contact instructions for quotes, and renewal-period price adjustments utilize the BLS Producer Price Index for Ammunition as the primary benchmark, supplemented by manufacturer documentation at the State's discretion. Additional requirements include F.O.B. Destination delivery with risk of loss remaining with the Contractor until acceptance, standard fulfillment within 90 days (extendable by mutual written agreement for documented supply chain constraints), mixed-lot deliveries with lot number documentation per manufacturer packaging, and a maximum misfire rate of five per 10,000 rounds. The document does not reference set-asides, incumbents, or specific funding sources.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 2 Admin Doc - ITB #1114.docx | DOCX document | |
| Bidder Questions 2 - ITB #1114.docx | DOCX document | |
| Modifications & Exceptions - ITB #1114.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidder Questions ITB #1114 – Practice Ammunition
| No |
| ITB Section |
| ITB Page |
| Question |
| Response |
NATO Specification Requirement: For Line Items requesting "5.56mm NATO" and "9mm NATO," does the State require ammunition manufactured in strict compliance with NATO STANAG standards (STANAG 4172 and STANAG 4090, respectively), including:
- NATO headstamp with the cross symbol (⊗)
- Proof testing to NATO pressure specifications (430 MPa for 5.56mm; 235 MPa for 9mm)
- Full interchangeability certification per NATO Technical Performance Specifications The State does not require ammunition manufactured in strict compliance with NATO STANAG specifications for Line Items referencing 9mm NATO and 5.56 NATO. Both STANAG‑compliant and SAAMI‑compliant products that meet or exceed the performance specifications in Exhibit 3 are acceptable. A NATO headstamp, NATO proofing, or interchangeability certification is not required.
Separately from the NATO-specific question above, Bidders should note that the former Exhibit 3, Section 1.4,which required all cartridges to be headstamped with caliber designation and manufacturer name or trademark, has been removed in this amendment. Headstamp markings are no longer a requirement for any line item under this solicitation.
Ordering agencies remain responsible for confirming firearm compatibility under Exhibit 3, Section 2.3.
| Does the State require specific environmental testing documentation (e.g., salt spray, thermal cycling) beyond standard EPVAT (pressure/velocity/accuracy) data to qualify as 'NATO' or 'or equal'?" |
| No. The State does not require environmental testing documentation of any kind. SAAMI compliance, as set forth in Exhibit 3, Section 2.2, is the applicable quality and performance standard. No supplemental environmental qualification testing is required. |
"Or Equal" Definition: If a product is not manufactured to STANAG specifications but meets SAAMI standards and achieves comparable ballistic performance, would it qualify as an "or equal" product? Could you please confirm whether the State requires:
- True NATO-spec ammunition (STANAG-compliant with NATO headstamp), OR
- SAAMI-compliant commercial ammunition that meets NATO-level ballistic performance?
SAAMI-compliant commercial ammunition that meets or exceeds the performance specifications in Exhibit 3 qualifies as an "or equal" for Line Items 1 and 11. The State does not require true NATO-specification ammunition bearing a NATO headstamp. Both STANAG-compliant and SAAMI-compliant products are acceptable; neither is required to the exclusion of the other. Ordering agencies are responsible for confirming firearm compatibility with the specific ammunition ordered prior to placing orders, consistent with Exhibit 3, Section 2.3.
| What technical documentation must a bidder provide to demonstrate that a non-STANAG product qualifies as "equal"? Would a manufacturer specification sheet of functional equivalence suffice? Would functional equivalence require NATO pressure standards or SAAMI pressure standards, as they can be considered contradictory? |
| A manufacturer specification sheet demonstrating that the offered product meets or exceeds the specifications in Exhibit 3 is sufficient documentation for any product offered as an "or equal." No independent laboratory certification or third-party testing report is required at bid submission. For non-STANAG products offered on Line Items 1 and 11, SAAMI pressure standards are the applicable benchmark, not NATO pressure specifications. The two standards are not simultaneously required, and bidders need not demonstrate NATO pressure compliance to qualify a SAAMI-compliant product. The ordering agency retains the right to determine final acceptability of any "or equal" product consistent with Exhibit 2, Section 11. |
Will the State of Idaho award this contract to:
- A Single Vendor — Where one bidder receives the contract for all 15 line items (if they are the lowest responsible bidder on the aggregate total), OR
- Multiple Vendors by Line Item — Where each line item is evaluated and awarded separately to the lowest responsible bidder for that specific item (meaning different vendors could receive awards for different calibers/types)?
Awards will be made on a per-line-item basis. The State will not evaluate bids on an aggregate total and will not award the entire contract to a single vendor. For each line item, the State intends to award to at least two (2) lowest responsive and responsible Bidders, as set forth in ITB Section 3.6. A single Bidder may receive award on one or more line items, and different vendors may be awarded different line items or categories. Additionally, this amendment revises Submittal Form B to clarify that Bidders are not required to submit pricing for all four (4) ammunition category tables.
| Will the State consider modifying the contract language to clarify that third-party carrier or manufacturer-provided transportation and cargo insurance may be used to cover in-transit risk, provided that the Contractor maintains general? |
| No contract modification is needed. Under Article 2, Section 2.5 of the State of Idaho Contract Terms and Conditions, all property is delivered on an F.O.B. Destination basis, meaning risk of loss remains with the Contractor until acceptance by the State, consistent with Article 2, Section 2.6. How the Contractor satisfies that obligation, whether through third-party carrier insurance, manufacturer-provided coverage, or any other arrangement, is the Contractor's determination. The contract does not prescribe the form of transit coverage. The separately required insurance coverages set forth in the Insurance Requirements (Commercial General Liability and Commercial Automobile Liability at $1,000,000 each) remain applicable regardless. |
For line items specifying FMJ construction, will the State accept alternative projectile types and grain that meet SAAMI specifications and function reliably in standard duty platforms, provided they are intended for training and meet performance use
The "or equal" standard is a performance standard. Any alternative product must meet or exceed all applicable specifications in Exhibit 3, including the construction requirements in Section 1.3 (FMJ or TMJ for training-grade line items), SAAMI compliance, and the misfire rate standard in Section 4. Whether a specific alternative, including one with a different projectile type or grain weight, meets those specifications is determined by the ordering agency at the time of order, consistent with Exhibit 2, Section 11. Bidders offering alternatives are strongly encouraged to include manufacturer specification documentation with their bid to support that determination.
| 8 |
| Section 1; 1.2 |
| 2 |
| Is the State open to extending deadlines to both submit questions and the bid closing date by (2) two weeks each? |
Answers to the questions below may require additional clarification questions, and another round of Q&A is strongly requested to provide appropriate follow-up clarifications or exception requests.
This amendment extends the bid closing date by ten (10) business days. The closing date of April 23, 2026 is revised to May 7, 2026. The public bid opening is revised to May 8, 2026, at 10:30 AM MT. Bidders are directed to IPRO for the updated schedule. The question submission deadline has passed; all questions received prior to that deadline are being addressed through this document. The State may issue an additional Q&A period in connection with this amendment; if one is offered, it will be announced via IPRO.
| 9 |
| Section 1; 1.6 |
| 3 |
| Upon mutual written agreement, can you confirm each renewal option will be extended in compliance with STATE OF IDAHO CONTRACT TERMS AND CONDITIONS, Section 1.2.2. (Renewal Options)? |
| Confirmed. Each renewal or extension will be executed by mutual written agreement of the parties and will fully incorporate the State of Idaho Contract Terms and Conditions, including the Renewal Options provision at Section 1.2.2. No terms or conditions of the original contract are modified by a renewal unless expressly changed by written amendment. |
| 10 |
| Exhibit 2; 2.2 |
| 11 |
| Is the State open to accepting a letter from the manufacturer instead of a BLS index to justify a price adjustment? |
Since COVID, in this market, manufacturer price adjustments rarely overlap directly (year-to-year) with PPI/BLS indexes. Over a five-year period, this significantly increases the contract’s risk profile, which negatively impacts competitive bid responses.
The BLS Producer Price Index for Ammunition (PCU332992332992) remains the primary benchmark for renewal-period price adjustment requests. However, Contractors may submit supplementary documentation, such as a manufacturer cost letter, commodity pricing data, or other verifiable market evidence, alongside the required BLS index data. The State will review such documentation and may consider it at its sole discretion; submission does not guarantee approval of any adjustment request. If the BLS index series is discontinued during the contract term, the State will designate an appropriate successor index at that time.
| 11 |
| Exhibit 2; 2.2 |
| 11 |
| If the Bureau of Labor Statistics (BLS) Producer Price Index for Ammunition (PCU332992332992) is discontinued, is the State open for price adjustment justifications to be determined via mutual written agreement between State and Contractor? |
As currently written, it is presumed “the most appropriate BLS successor index” will be chosen at sole discretion of the State, which triggers further contract uncertainty/risk.
If the BLS Producer Price Index for Ammunition (PCU332992332992) is discontinued, the State will designate an appropriate successor index. The existing ITB language, providing for "the most appropriate BLS successor index", reflects this intent. The State retains discretion to make that designation consistent with its fiscal obligations. As noted in the response to Question 10, Contractors may also submit supplementary documentation in support of renewal-period adjustment requests, which the State will consider at its sole discretion.
| 12 |
| Exhibit 2; 3 |
| 11-12 |
| To clarify, does it satisfy the requirements of this section to provide a public link to an online catalog (Manufacturer Suggested Retail Price; MSRP List) with instructions to call the Contractor for a discounted pricing quote to be sent via email? |
Heavy percentage discounts are often applied to catalog products for general catalog orders (MSRP list).
Yes. Providing a public link to an online catalog with instructions to contact the Contractor for a pricing quote satisfies the requirements of Exhibit 2, Section 3, which expressly permits price lists in the form of a public website or online catalog. The State's requirement is that a current, accessible price listing exist and be shareable with ordering agencies for posting on the Division of Purchasing's procurement website. The State notes that awarded unit prices on Submittal Form B are the governing prices for all purchases under this contract; a catalog or MSRP list is a reference document, not the pricing instrument.
| 13 |
| Exhibit 2; 6.3, 6.4, 6.5 |
| 12 |
| Is the State open to changing the order fulfillment timeframe from (90) ninety days to (180) one hundred eighty days? |
Given ongoing market uncertainty, current wars, and general global unrest (aside from supply chain issues), a (90) ninety-day timeframe is not a realistic request for all Line Items requested in this solicitation, which will negatively impact competitive responses The State declines this request. The existing language in Exhibit 2 already provides the flexibility the vendor is seeking. Section 6.4 expressly permits the Contractor and ordering agency to mutually agree in writing to a longer lead time where justified by documented supply chain constraints or cost savings, subject to Division of Purchasing approval. Section 5 establishes the process for the Contractor to communicate fulfillment challenges promptly, after which the parties can jointly determine the appropriate path. Contractors are encouraged to use these provisions when circumstances warrant a deviation from the standard lead time.
| 14 |
| Exhibit 2; 3, 10 |
| 11, 13 |
| To clarify, are ammunition orders off a catalog price list subject to the 90% Fill Rate requirement? |
It is strongly discouraged to apply a Fill Rate requirement to products generally listed in a catalog (MSRP list) since some of these products are low volume are either not consistently stocked and/or may have inconsistent/cancelled production.
Yes. The 90% quarterly fill rate in Exhibit 2, Section 10 applies to all purchase orders placed under this contract for the line items on Submittal Form B. This is a statewide firm-price contract for specifically identified ammunition types, not a general catalog arrangement, and all orders are subject to the fill rate standard regardless of how pricing is communicated. The State notes that the existing language is discretionary with respect to consequences, failure to meet the fill rate "may be cause for non-renewal or termination, at the sole discretion of the Division of Purchasing." The fill rate is a performance benchmark; it does not trigger automatic corrective action.
| 15 |
| Exhibit 2; 10 |
| 13 |
| Is the State open to removing the 90% Fill Rate as a condition for non-renewal or termination of the Contract? |
Given ongoing market uncertainty, current wars, and general global unrest (aside from supply chain issues), a 90% Fill Rate across all ordering agencies and eligible public agencies across all line items is not a realistic request in this solicitation and is contrary to industry norms.
The 90% quarterly fill rate requirement is retained. A performance benchmark is necessary to ensure product availability across the statewide user base and to support the integrity of the multiple-award structure, which exists specifically to mitigate supply disruption risk. As noted in response to Question 14, the existing language in Exhibit 2, Section 10 is already expressly discretionary, failure to meet the fill rate "may be cause for non-renewal or termination, at the sole discretion of the Division of Purchasing." DOP will evaluate any shortfall in the context of all relevant circumstances, including market conditions and contractor communication.
| 16 |
| Exhibit 3; 3.4 |
| 16 |
| Is the State open to removing Exhibit 3, Section 3.4 from the ITB? |
When shipped directly from the manufacturer to law enforcement agencies, it is not standard operating procedure for the manufacturer to record all lot numbers for all shipments. Thus, Section 3.4 would require, specifically for this contract, all ordered ammunition to be warehoused before delivery to record lot numbers. Then, when there are multiple lot numbers per order (which is common), each separate lot number may require to be shipped separately as multiple shipments. This would significantly increase shipping estimates/costs, add administrative burdens from the ordering agencies to accept orders, add administrative costs to the Contractor for this contract, and would further delay delivery timeframes.
The State agrees that the current language in Exhibit 3, Section 3.4 creates fulfillment burdens not aligned with standard industry practice, particularly for large-volume or direct-from-manufacturer shipments. The State's interest in lot number information is limited to post-delivery traceability in the event a defect or safety issue is identified after receipt. Accordingly, this amendment revises Exhibit 3, Section 3.4 to permit mixed-lot deliveries, provided each case or box bears the applicable lot number per the manufacturer's standard factory packaging. This amendment removes the advance notification requirement and the associated right to reject shipments for undisclosed mixed lots.
| 17 |
| Exhibit 3; 4 |
| 16 |
| Is the State open to removing Exhibit 3, Section 4 from the ITB? |
It’s not clear how a misfire ratio would be determined, or who would make that determination. Factors unrelated to ammunition quality at delivery may contribute to a high misfire rate, not limited to (but including) malfunctions stemming from weapon maintenance or improper storage. Reputable ammunition manufacturers generally operate with high reliability, and deviations from the norm are generally specific to a manufacturer’s lot.
The misfire rate standard in Exhibit 3, Section 4 is retained. A threshold of five (5) misfires per ten thousand (10,000) rounds is a minimum quality baseline consistent with expectations for new production, factory-loaded, SAAMI-compliant ammunition. Regarding how determinations are made: Exhibit 2, Section 11 establishes the ordering agency's right to test shipments for compliance with Exhibit 3 specifications, including misfire rates, through its established testing protocols. Any remediation is handled under the procedures in Exhibit 2, Sections 8 and 9. These provisions establish a process for resolution, not an automatic enforcement mechanism.
| 18 |
| SUBMITTAL FORM B; INSTRUCTIONS, Form B tabs |
| N/A |
| To clarify, since the State intends to make multiple awards and contracts will be awarded per line item, is it a requirement to complete all 15 Line Items on the Bid Schedule? |
Given the concerns outlined in the previous questions, allowing bidders the option to only bid Line Items that provide maximum opportunity for contract success will positively impact competitive responses.
No. This amendment revises the Submittal Form B Instructions tab to clarify that Bidders are not required to submit pricing for all four (4) ammunition category tables. A Bidder may elect to bid on one or more category tables.
However, if a Bidder submits pricing for any line item within a category table, pricing must be provided for all line items within that table, partial category bids will be considered non-responsive for that category. The Mandatory Submission Requirements in ITB Section 3.1 (which require a complete Submittal Form B) are satisfied by completing all line items within each category table on which the Bidder elects to bid.