BID2023-104 Bid Tabs.xlsx
XLSX spreadsheet 27 KB Posted
- Solicitation number
- S-73000-00009074
- Issued by
- Harney County, Oregon
About this file
BID2023-104 Curb Ramp at Naef Rd and Harold Ave - Bid Tabs Summary
This document is a bid tabulation sheet for BID2023-104, a curb ramp construction project located at Naef Road and Harold Avenue. The project encompasses site preparation, traffic control, excavation, grading, asphalt paving, concrete work including curbs and walks, accessibility improvements such as curb ramps and truncated domes, and landscaping. The work includes 25 active line items with quantities ranging from 2 curb ramps to 650 cubic yards of topsoil. Ten contractors submitted bids: Colton Construction, Duke Construction and Excavation, Turney Excavation, Freedom Builders, D&D Concrete & Utilities, Don Burke Excavation, Angelo Underground, KNL Industries, Lee Contractors, and Brown Contracting. The lowest responsive bid total is $61,235.00 submitted by Angelo Underground, while the highest is $127,825.00 from Lee Contractors. The average bid across all contractors is $93,448.93.
Pricing analysis reveals significant variation among bidders, particularly on labor-intensive items such as flagging at $240 to $24,000 for 240 hours, temporary work zone fencing from $570 to $4,940 for 95 feet, and concrete work ranging considerably by contractor. Several line items (39-74) containing water quality seeding and additional topsoil work contain formula errors and zero pricing across most bids, indicating potential scope clarification issues. The flagging rate shows base plus fringe at $48.19 per hour. Two bid totals were submitted separately at $113,820.00 and $58,335.00, suggesting possible bid corrections or alternative pricing scenarios. No set-asides, incumbent information, or specific award dates are indicated in this tabulation document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESB_fnl_RFCQ_279B_Services.docx | DOCX document | |
| ESB_fnl_RFCQ_Attachments_279B_Services.docx | DOCX document | |
| 35891 Intent To Award.xlsx | XLSX spreadsheet | |
| Exhibit 1 (Technical Specifications)~4.docx | DOCX document | |
| 35891 Preliminary Results.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Tabs BID 2023-104 Curb Ramp at Naef Rd and Harold Ave
| Contractor #1 - Colton Construction | Contractor #2 - Duke Construction and Excavation | Contractor #3 - Turney Excavation | Contractor #4 - Freedom Builders | Contractor #5 - D&D Concrete & Utilities | Contractor #6 - Don Burke Excavation | Contractor #7 - Angelo Underground | Contractor #8 - KNL Industries | Contractor #9 - Lee Contractors | Contractor #10 - Brown Contracting | ||||||||||||||||||
| Bid Item | Unit | Quantity | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Unit Price | Total | Low | High | Average Unit Price | Average Total | |
| 1 | WORKPLACE HARASSMENT PREVENTION PLAN | LS | 1 | $1,000.00 | $1,000.00 | $463.22 | $463.22 | $250.00 | $250.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | $200.00 | $200.00 | $1,000.00 | $1,000.00 | $200.00 | $200.00 | $500.00 | $500.00 | $200.00 | $1,000.00 | $580.00 | $580.00 |
| 2 | EXTRA WORK AS AUTHORIZED | FA | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 3 | MOBILIZATION | LS | 1 | $5,000.00 | $5,000.00 | $4,554.64 | $4,554.64 | $2,850.00 | $2,850.00 | $5,000.00 | $5,000.00 | $8,000.00 | $8,000.00 | $4,500.00 | $4,500.00 | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 | $12,000.00 | $12,000.00 | $9,000.00 | $9,000.00 | $4,000.00 | $12,000.00 | $7,000.00 | $7,000.00 |
| 4 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | LS | 1 | $1,000.00 | $1,000.00 | $2,605.56 | $2,605.56 | $1,300.00 | $1,300.00 | $5,000.00 | $5,000.00 | $6,000.00 | $6,000.00 | $4,400.00 | $4,400.00 | $1,800.00 | $1,800.00 | $10,000.00 | $10,000.00 | $5,000.00 | $5,000.00 | $3,300.00 | $3,300.00 | $1,000.00 | $10,000.00 | $4,220.00 | $4,220.00 |
| 5 | FLAGGERS | HR | 240 | $70.00 | $16,800.00 | $73.82 | $17,716.80 | $86.00 | $20,640.00 | $80.00 | $19,200.00 | $63.00 | $15,120.00 | $95.00 | $22,800.00 | $59.00 | $14,160.00 | $100.00 | $24,000.00 | $45.00 | $10,800.00 | $1.00 | $240.00 | $240.00 | $24,000.00 | $55.00 | $13,200.00 |
| 6 | TEMPORARY WORK ZONE FENCING INCLUDING POSTS | FT | 95 | $10.00 | $950.00 | $12.19 | $1,158.05 | $6.00 | $570.00 | $30.00 | $2,850.00 | $20.00 | $1,900.00 | $6.00 | $570.00 | $10.00 | $950.00 | $52.00 | $4,940.00 | $40.00 | $3,800.00 | $15.00 | $1,425.00 | $950.00 | $4,940.00 | $25.40 | $2,413.00 |
| 7 | EROSION CONTROL | LS | 1 | $1,000.00 | $1,000.00 | $1,017.99 | $1,017.99 | $1,150.00 | $1,150.00 | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $1,780.00 | $1,780.00 | $500.00 | $500.00 | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $350.00 | $350.00 | $350.00 | $2,000.00 | $1,070.00 | $1,070.00 |
| 8 | SEDIMENT BARRIER, TYPE 8 | FT | 95 | $6.00 | $570.00 | $7.14 | $678.30 | $4.00 | $380.00 | $10.00 | $950.00 | $8.00 | $760.00 | $3.20 | $304.00 | $10.00 | $950.00 | $7.50 | $712.50 | $5.00 | $475.00 | $5.00 | $475.00 | $475.00 | $950.00 | $6.70 | $636.50 |
| 9 | POLLUTION CONTROL PLAN | LS | 1 | $1,000.00 | $1,000.00 | $463.22 | $463.22 | $250.00 | $250.00 | $1,500.00 | $1,500.00 | $500.00 | $500.00 | $500.00 | $500.00 | $200.00 | $200.00 | $1,000.00 | $1,000.00 | $100.00 | $100.00 | $250.00 | $250.00 | $100.00 | $1,000.00 | $510.00 | $510.00 |
| 10 | CONSTRUCTION SURVEY WORK | LS | 1 | $1,000.00 | $1,000.00 | $2,895.06 | $2,895.06 | $4,650.00 | $4,650.00 | $5,000.00 | $5,000.00 | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | $2,700.00 | $2,700.00 | $4,000.00 | $4,000.00 | $2,000.00 | $2,000.00 | $6,000.00 | $6,000.00 | $1,000.00 | $6,000.00 | $3,140.00 | $3,140.00 |
| 11 | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | LS | 1 | $3,000.00 | $3,000.00 | $5,176.96 | $5,176.96 | $4,100.00 | $4,100.00 | $7,500.00 | $7,500.00 | $3,000.00 | $3,000.00 | $8,216.00 | $8,216.00 | $2,000.00 | $2,000.00 | $4,000.00 | $4,000.00 | $15,000.00 | $15,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $15,000.00 | $5,200.00 | $5,200.00 |
| 12 | CLEARING AND GRUBBING | LS | 1 | $6,000.00 | $6,000.00 | $2,298.99 | $2,298.99 | $800.00 | $800.00 | $2,500.00 | $2,500.00 | $3,000.00 | $3,000.00 | $4,930.00 | $4,930.00 | $2,000.00 | $2,000.00 | $4,500.00 | $4,500.00 | $1,000.00 | $1,000.00 | $1,600.00 | $1,600.00 | $1,000.00 | $6,000.00 | $3,020.00 | $3,020.00 |
| 13 | GENERAL EXCAVATION | LS | 1 | $3,000.00 | $3,000.00 | $3,431.08 | $3,431.08 | $4,200.00 | $4,200.00 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | $9,540.00 | $9,540.00 | $2,000.00 | $2,000.00 | $4,000.00 | $4,000.00 | $3,000.00 | $3,000.00 | $9,500.00 | $9,500.00 | $2,000.00 | $9,500.00 | $4,300.00 | $4,300.00 |
| 14 | SUBGRADE GEOTEXTILE | SY | 85 | $5.00 | $425.00 | $4.09 | $347.65 | $3.75 | $318.75 | $10.00 | $850.00 | $1.00 | $85.00 | $5.00 | $425.00 | $10.00 | $850.00 | $10.00 | $850.00 | $10.00 | $850.00 | $4.00 | $340.00 | $340.00 | $850.00 | $7.80 | $663.00 |
| 15 | AGGREGATE BASE AND SHOULDERS | TON | 80 | $40.00 | $3,200.00 | $26.06 | $2,084.80 | $58.00 | $4,640.00 | $75.00 | $6,000.00 | $100.00 | $8,000.00 | $59.30 | $4,744.00 | $30.00 | $2,400.00 | $50.00 | $4,000.00 | $250.00 | $20,000.00 | $124.00 | $9,920.00 | $2,400.00 | $20,000.00 | $98.80 | $7,904.00 |
| 16 | LEVEL 3, 1/2 INCH DENSE ACP MIXTURE | TON | 35 | $200.00 | $7,000.00 | $410.35 | $14,362.25 | $360.00 | $12,600.00 | $250.00 | $8,750.00 | $400.00 | $14,000.00 | $343.00 | $12,005.00 | $125.00 | $4,375.00 | $250.00 | $8,750.00 | $400.00 | $14,000.00 | $265.00 | $9,275.00 | $4,375.00 | $14,000.00 | $248.00 | $8,680.00 |
| 17 | EXTRA FOR THICKENED EDGE SIDEWALK | FT | 35 | $80.00 | $2,800.00 | $96.73 | $3,385.55 | $55.00 | $1,925.00 | $70.00 | $2,450.00 | $40.00 | $1,400.00 | $86.00 | $3,010.00 | $20.00 | $700.00 | $50.00 | $1,750.00 | $40.00 | $1,400.00 | $120.00 | $4,200.00 | $700.00 | $4,200.00 | $62.00 | $2,170.00 |
| 18 | CONCRETE CURBS, CURB AND GUTTER | FT | 90 | $140.00 | $12,600.00 | $99.53 | $8,957.70 | $80.00 | $7,200.00 | $40.00 | $3,600.00 | $60.00 | $5,400.00 | $75.00 | $6,750.00 | $20.00 | $1,800.00 | $80.00 | $7,200.00 | $100.00 | $9,000.00 | $69.00 | $6,210.00 | $1,800.00 | $12,600.00 | $81.80 | $7,362.00 |
| 19 | CONCRETE WALKS | SF | 550 | $35.00 | $19,250.00 | $31.72 | $17,446.00 | $14.50 | $7,975.00 | $15.00 | $8,250.00 | $16.00 | $8,800.00 | $11.50 | $6,325.00 | $13.00 | $7,150.00 | $35.00 | $19,250.00 | $25.00 | $13,750.00 | $31.00 | $17,050.00 | $7,150.00 | $19,250.00 | $27.80 | $15,290.00 |
| 20 | EXTRA FOR NEW CURB RAMPS | EACH | 2 | $2,000.00 | $4,000.00 | $881.24 | $1,762.48 | $2,500.00 | $5,000.00 | $800.00 | $1,600.00 | $2,000.00 | $4,000.00 | $3,162.50 | $6,325.00 | $2,500.00 | $5,000.00 | $1,500.00 | $3,000.00 | $1,500.00 | $3,000.00 | $1,300.00 | $2,600.00 | $2,600.00 | $5,000.00 | $1,760.00 | $3,520.00 |
| 21 | TRUNCATED DOMES ON NEW SURFACES | SF | 60 | $30.00 | $1,800.00 | $2.90 | $174.00 | $17.00 | $1,020.00 | $30.00 | $1,800.00 | $50.00 | $3,000.00 | $0.00 | $0.00 | $40.00 | $2,400.00 | $50.00 | $3,000.00 | $50.00 | $3,000.00 | $45.00 | $2,700.00 | $1,800.00 | $3,000.00 | $43.00 | $2,580.00 |
| 22 | PAVEMENT BAR, TYPE STOP BAR | SF | 15 | $70.00 | $1,050.00 | $115.80 | $1,737.00 | $100.00 | $1,500.00 | $40.00 | $600.00 | $30.00 | $450.00 | $33.40 | $501.00 | $100.00 | $1,500.00 | $66.50 | $997.50 | $30.00 | $450.00 | $150.00 | $2,250.00 | $450.00 | $2,250.00 | $83.30 | $1,249.50 |
| 23 | REMOVE AND REINSTALL EXISTING SIGNS | LS | 1 | $500.00 | $500.00 | $579.01 | $579.01 | $770.00 | $770.00 | $300.00 | $300.00 | $600.00 | $600.00 | $500.00 | $500.00 | $100.00 | $100.00 | $1,000.00 | $1,000.00 | $2,000.00 | $2,000.00 | $500.00 | $500.00 | $100.00 | $2,000.00 | $820.00 | $820.00 |
| 24 | TOPSOIL | CY | 5 | $100.00 | $500.00 | $210.99 | $1,054.95 | $150.00 | $750.00 | $150.00 | $750.00 | $100.00 | $500.00 | $138.00 | $690.00 | $50.00 | $250.00 | $150.00 | $750.00 | $200.00 | $1,000.00 | $169.00 | $845.00 | $250.00 | $1,000.00 | $133.80 | $669.00 |
| 25 | BARK MULCH | CY | 5 | $100.00 | $500.00 | $210.99 | $1,054.95 | $150.00 | $750.00 | $100.00 | $500.00 | $100.00 | $500.00 | $138.00 | $690.00 | $50.00 | $250.00 | $150.00 | $750.00 | $200.00 | $1,000.00 | $170.00 | $850.00 | $250.00 | $1,000.00 | $134.00 | $670.00 |
| 39 | WATER QUALITY SEEDING, LOW GROW SEED MIX | ACRE | 0.08 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! |
| 40 | TOPSOIL | CY | 650 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! |
| 41 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 42 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 43 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 44 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 45 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 46 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 47 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 48 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 49 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 50 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 51 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 52 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 53 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 54 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 55 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 56 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 57 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 58 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 59 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 60 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 61 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 62 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 63 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 64 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 65 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 66 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 67 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 68 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 69 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 70 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 71 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 72 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 73 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| 74 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | ERROR:#REF! | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ERROR:#REF! | |||
| $96,945.00 | $98,406.21 | $88,588.75 | $93,450.00 | $95,515.00 | $104,505.00 | $61,235.00 | $118,950.00 | $127,825.00 | $94,380.00 | $61,235.00 | $127,825.00 | ||||||||||||||||
| Submitted bid total $113,820.00 | Submitted bid total $58,335.00 | ||||||||||||||||||||||||||
| Base+Fringe for flagger is $48.19 |