Bid Tabulation Lite_N_Tie.pdf
PDF 20 KB Posted
- Attached to
- Lite-N-Tie Elevated Water Storage Tank
- Solicitation number
- PE-68400-NONST-2024-000000007
- Issued by
- Jefferson County, Georgia
About this file
This document is a bid tabulation for the Lite-N-Tie Elevated Water Storage Tank project, which is being solicited by the Jones County Board of Commissioners in Georgia. The project involves the construction of a 750,000-gallon elevated water storage tank, including the tank, foundations, labor, materials, painting, and any necessary appurtenances. The bid tabulation provides unit prices and total costs for three alternates: a single pedestal tank, a multi-column tank, and a composite tank. The bids were due on March 22nd, and the contract will be awarded based on the lowest responsive and responsible bid.
The bid tabulation also includes line items for additional work, such as fencing, electrical, geotechnical services, piping, SCADA system, site work, and testing. Pricing for these items is provided by the three bidders: Caldwell Tanks Inc., Lite-N-Tie, and Phoenix Fabricators and Erectors LLC. The bid prices range from approximately $2.6 million to $3.8 million for the base bid items. The document indicates that some mathematical errors were made in the bid submissions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1_Addendum 1.pdf | ||
| Lite_N_Tie Elevated Water Storage Tank.pdf | ||
| Bid Award _Lite_n_Tie Elevated Water Tank.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIDDER: BIDDER: BIDDER:
Louisville, KY 40219 Fort Worth, TX 76177 ph: 502-964-3361 ph: 817-439-8888 Avon, IN 46123 ph: 317-271-7002
UNIT TOTAL UNIT TOTAL UNIT TOTAL
PRICE PRICE PRICE PRICE PRICE PRICE
1 1 LS
Bidder agrees to furnish all materials and equipment and to perform all labor necessary for the construction of a 750,000-gallon elevated water storage tank (single pedestal) in place and in permanent operation for the Jones County BOC. The work consists of a 750,000-gallon elevated water storage tank with a height as specified on the drawings from the top of the concrete foundation to the tank overflow. Included in work is the elevated tank, foundations, labor, freight, materials, painting of tank, and any additional appurtenances necessary for a complete and operational tank.
3,628,097.00$ 3,628,097.00$
-$ -$ 2,976,513.00$ 2,976,513.00$
2 400 LF 6’ Chain Link Fence including 1A each – 16-foot double gate 77.00$ 30,800.00$
35.00$ 14,000.00$ 45.00$ 18,000.00$
3 1 LS
Electrical including electrical service to building includes 100 amp service in weather proof enclosure mounted as per the electrical drawings. Enclosure to include 3 – 20 amp breakers, and weather proof duplex receptacle.
1.00$ 1.00$
150,000.00$ 150,000.00$ -$ -$
4 1 LS Geotechnical as needed for Foundation Design. 5,000.00$ 5,000.00$ * 2,000.00$ 2,000.00$ 5,000.00$ 5,000.00$
5 1 LS
Install 18-inch Ductile Iron Pipe from the Elevated Tank to the
County’s Water Main. This is to include 18-inch Gate Valve with
Box; 18-inch Ductile Iron Piping; Connection to County’s 16-inch
Water Main; 18-inch x 18-inch D.I. Tee; 18 inch x 16 inch D.I.
Reducer (2); 16 inch Gate Value with Box; 16 inch x 6 inch
Hydrant Tee; 6 inch D.I. Fire Hydrant Lead; New 3 Way Fire
Hydrant (Mueller or M&H); 6 inch Gate Value with box; 16 inch x 2 inch Tapping Saddle and Value with Box. +/- 20 LF 2-inch
Class 200 pvc Water Main One (1) Non-Freeze Yard Hydrant, and tank overflow discharge piping.
75,900.00$ 75,900.00$
45,000.00$ 45,000.00$ 120,526.00$ 120,526.00$
6 1 EA
SCADA Panel complete with tap; tapping; valves; panel;
antenna; installation and testing. 1.00$ 1.00$
25,000.00$ 25,000.00$ -$ -$
7 1 LS
Site Work including Grubbing; Stump Removal; Grading;
Grassing as Specified; Silt Fence; All Erosion Control and any additional appurtenances necessary for a complete and Operational Tank Site. 15,000.00$ 15,000.00$
100,000.00$ 100,000.00$ 76,930.00$ 76,930.00$
4000 Tower Road
INGRAM & ASSOCIATES
CONSULTING ENGINEERS
332 NEW STREET
MACON, GA 31201
Caldwell Tanks Inc.
Lite-N-Tie Elevated Water Tank
ITEM #
I&A Project No.: 1160-111-01 fx: 317-273-1154
1665 Harmon Road
UNIT DESCRIPTIONQUANT.
BID TABULATION FOR ALL BIDDERS
JONES COUNTY BOARD OF COMMISSIONERS
Phoenix Fabricators and
Erectors LLC.
182 South County Road 900 East
Landmark Structures
8 1 LS Testing Allowances (paid on invoices) 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$
9 1 LS
Modification to the Master Control Panel at Jones County Water Department to accept this new signal. 1.00$ 1.00$ 5,000.00$ 5,000.00$ -$ -$
10 360 SY Graded Aggregate Base Construction (GABC) Drive. 45.00$ 16,200.00$ * 30.00$ 10,800.00$ 26.00$ 9,360.00$
11 1 LS
Tank overflow pond including pond grading, drop inlet, piping, flared end section (FES), perforated riser pipe, riprap, and rock ring around riser. 12,000.00$ 12,000.00$
23,200.00$ 23,200.00$ 28,000.00$ 28,000.00$
TOTAL BASE BID *
UNIT TOTAL UNIT TOTAL UNIT TOTAL
PRICE PRICE PRICE PRICE PRICE PRICE
1 1 LS
Bidder agrees to furnish all materials and equipment and to perform all labor necessary for the construction of a 750,000-gallon elevated water storage tank (multi-column) in place and in permanent operation for the Jones County BOC. The work consists of a 750,000-gallon elevated water storage tank with a height as specified on the drawings the top of the concrete foundation to the tank overflow. Included in work is the elevated tank, foundations, labor, freight, materials, painting of tank and logo, and any additional appurtenances necessary for a complete and operational tank. 3,218,097.00$ 3,218,097.00$ no bid no bid 2,587,019.00$ 2,587,019.00$
UNIT TOTAL UNIT TOTAL UNIT TOTAL
PRICE PRICE PRICE PRICE PRICE PRICE
100 1 LS
Bidder agrees to furnish all materials and equipment and to perform all labor necessary for the construction of a 750,000-gallon elevated water storage tank (composite) in place and in permanent operation for the Jones County BOC. The work consists of a 750,000-gallon elevated water storage tank with a height as specified on the drawings the top of the concrete foundation to the tank overflow. Included in work is the elevated tank, foundations, labor, freight, materials, painting of tank and logo, and any additional appurtenances necessary for a complete and operational tank. 3,490,097.00$ 3,490,097.00$ 3,742,000.00$ 3,742,000.00$ 3,786,676.00$ 3,786,676.00$
I hereby certify that this is a true and accurate record of all unit prices received on March 22, 2024.
* Indicates a mathmatical error in bid submitted
3,793,000.00$ 3,244,329.00$ no bid
Tim Ingram, P.E. #20644
ALTERNATE BID No. 2
ITEM # QUANT. UNIT
ALTERNATE BID No. 3
ITEM # QUANT. UNIT DESCRIPTION
BID COST for Alternate No.3. If chosen this will replace Bid Base Item 1. 3,490,097.00$ 3,742,000.00$ 3,786,676.00$
2,587,019.00$
DESCRIPTION
BID COST for Aleternate No. 2. If chosen this will replace Base Bid Item 1. 3,218,097.00$ -$