Bid Tabulation-Award

21 KB Posted

Attached to
Darien DDA Dock Repairs
Solicitation number
66136-22-DDDADockRepair
Issued by
Miller County, Georgia

About this file

This is a Bid Tabulation and Award document for the Darien Downtown Development Authority (DDDA) dock repair project in Georgia. The DDDA solicited sealed bids from qualified dock building contractors to repair the downtown development authority docks. Sealed bids were due by October 21, 2022, at 5:00 PM and were opened on November 1, 2022, at 5:30 PM in a public forum at City Hall, with Aaron Carpenter, Director of Planning, overseeing the bid opening. The project was divided into multiple sections (A through G) covering mobilization, various repair components, and material selection options. On December 6, 2022, at the DDDA meeting, CWA Development was selected as the awarded contractor. The project has an estimated completion time of 8 to 12 weeks, and bonding and insurance were required from all bidders.

CWA Development submitted the lowest compliant bid totaling $376,258.00 for the Wear Deck material option, which was selected for award. The competing bids were from Marineco at $396,839.00 (Trex option) and Drury Land & Marine Inc. at $583,362.00. CWA Development's bid included performance bonds and insurance as required. Key project specifications noted in the award included that the Wear Deck commercial application requires stringers at 16 inches on center, while existing stringers are spaced at 24 inches on center with varying spans. The Trex deck alternative would have required stringers at 12 inches on center. All three bidding contractors included performance bonds and submitted insurance documentation with their bids.

Text of this file

December 6, 2022 @ the Darien Downtown Development Meeting, CWA Development was chosen as the bid to be awarded contract for the Darien Downton Dock Repairs (BID NUMBER 66136-22-DDDADockRepair). This bid was the lowest bid meeting all requirements of the RFP.

$376,258.00 (Wear Deck Material)

BID TABULATION- Darien Downtown Development Authority Dock Repairs BID NUMBER 66136-22-DDDADockRepair Date of Opening of Sealed Bids: November 1, 2022 Time: 5:30pm City Hall Bids Opened by: Aaron Carpenter, Director of Planning CRC

Marineco
CWA, Development
Drury Land & Marine Inc.
Section: A
$55,800.00
$34,733.00
$117,750.00

$18,362.00 (Bond) $37,000 Mobilization

Section: B
$47,700.00
$59,404.00
$62,500.00
Section: C
$51,800.00
$42,768.00
$99,750.00
Section: E
$126,500.00
$18,369.60
$85,000.00
Section: F
$71,100.00
$141,900.00
$124,000.00
Section: G
$22,050.00
$70,083.40
$39,000.00

Total Cost of Repairs

$390,950.00

1. $376,258.00 (Wear Deck)

2. $396,839.00 (Trex) $583,362.00

Estimated Completion Time

8-12 Weeks

110 Business Days

2 Months

Performance Bonds

Included in Total/Issued Upon Award of Contract
Included in Total/Issued Upon Award of Contract
Included in Total/Issued Upon Award of Contract

Insurance Included

Stated Yes-No Copy of Insurance Included in Bid Package
Yes
Yes

Comments

Section E:

Marineco

· Cost Plus if Stringers are Needed/Cannot determine how many are needed until Removing the Decking

Section F:

CWA Development, Inc.

· Wear Deck: Commercial Application Needs Stingers 16” O.C.

· Existing Stringers: 24” O.C. & Varying Spans.

· Trex Deck: Commercial Application Needs Stringers 12” O.C.

https://ssl.doas.state.ga.us/gpr//eventDetails?eSourceNumber=236613666136-22-DDDADockRepair&sourceSystemType=doas

Other files

File Type Posted
RFQ-Dock Repair —
DDDA Conceptual Dock Plans —
Award Information —
DNR Letter of Permission —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .