Bid tab~63.xlsx
XLSX spreadsheet 17 KB Posted
- Solicitation number
- S-73000-00011907
- Issued by
- Clatsop County, Oregon
About this file
This is a bid tabulation document for the Skipanon River Bridge (BR1400) Span 2 Replacement project in Oregon, managed by ODOT in Clatsop County. The project involves replacing the center span of the Skipanon River Bridge in Warrenton and includes various construction elements such as mobilization, temporary traffic control, pollution control, bridge removal work, installation of steel rolled beams, timber components, and pavement work. The bid tabulation shows detailed line items for 22 different components of work, including specific quantities and unit prices.
The bid tabulation compares pricing from five contractors: Lee Contractors LLC (listed as non-responsive), Bergerson Construction Inc ($463,402.00), HP Civil Inc ($579,768.33), Stellar J Corporation ($665,058.50), and Oregon State Bridge Construction Inc ($724,626.33). Major cost items include steel rolled beam work ranging from $98,500 to $210,000, bridge removal work ranging from $40,100 to $172,500, and glued laminated timber with quantities of 5 MBFM ranging from $45,985.40 to $75,000 among responsive bidders.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BR01400-ExistingDrawings.pdf | ||
| 00011907_ITB~1.docx | DOCX document | |
| 00011907_Att B_Special Provisions.docx | DOCX document | |
| 00011907_Att A_Plans_Rev Add 1.pdf | ||
| GZ_M23004_rpt_01.pdf | ||
| 00011907_Att C_Bid Pricing Form.xlsx | XLSX spreadsheet | |
| NOI Structured Juniper 2.pdf | ||
| Q and A 11.18.2024.docx | DOCX document | |
| 00011907_Att A_Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| S-73000-00011907 Skipanon River Bridge (BR1400) Span 2 Replacement | ||||||||
| BID TABULATION | Lee Contractors LLC | Bergerson Construction Inc | HP Civil Inc | Stellar J Corporation | Oregon State Bridge Construction Inc | |||
| Bid Item # | Description | Est | ||||||
| QTY | UNIT | UNIT | ||||||
| PRICE | TOTAL | |||||||
| PRICE | UNIT | |||||||
| PRICE | TOTAL | |||||||
| PRICE | UNIT | |||||||
| PRICE | TOTAL | |||||||
| PRICE | UNIT | |||||||
| PRICE | TOTAL | |||||||
| PRICE | UNIT | |||||||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | NON-RESPONSIVE | $ 52,350.00 | $ 52,350.00 | $ 57,976.83 | $ 57,976.83 | $ 66,000.00 | $ 66,000.00 | $ 72,300.00 | $ 72,300.00 | |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | 1 | LS | $ - 0 | $ 25,300.00 | $ 25,300.00 | $ 10,000.00 | $ 10,000.00 | $ 12,000.00 | $ 12,000.00 | $ 65,000.00 | $ 65,000.00 | |
| 3 | PORTABLE CHANGEABLE MESSAGE SIGNS | 2 | EACH | $ - 0 | $ 7,950.00 | $ 15,900.00 | $ 2,500.00 | $ 5,000.00 | $ 4,000.00 | $ 8,000.00 | $ 10,000.00 | $ 20,000.00 | |
| 4 | POLLUTION CONTROL PLAN | 1 | LS | $ - 0 | $ 2,045.00 | $ 2,045.00 | $ 500.00 | $ 500.00 | $ 1,000.00 | $ 1,000.00 | $ 2,000.00 | $ 2,000.00 | |
| 5 | WORK CONTAINMENT PLAN | 1 | LS | $ - 0 | $ 2,045.00 | $ 2,045.00 | $ 500.00 | $ 500.00 | $ 1,000.00 | $ 1,000.00 | $ 2,000.00 | $ 2,000.00 | |
| 6 | TEMPORARY WORK ACCESS AND CONTAINMENT | 1 | LS | $ - 0 | $ 8,200.00 | $ 8,200.00 | $ 7,500.00 | $ 7,500.00 | $ 50,000.00 | $ 50,000.00 | $ 75,000.00 | $ 75,000.00 | |
| 7 | PAINTED WOOD | 2 | TON | $ - 0 | $ 925.00 | $ 1,850.00 | $ 500.00 | $ 1,000.00 | $ 300.00 | $ 600.00 | $ 6,000.00 | $ 12,000.00 | |
| 8 | BRIDGE REMOVAL WORK | 1 | LS | $ - 0 | $ 40,100.00 | $ 40,100.00 | $ 172,500.00 | $ 172,500.00 | $ 100,000.00 | $ 100,000.00 | $ 58,500.00 | $ 58,500.00 | |
| 9 | BRIDGE DECK COLD PLANE PAVEMENT REMOVAL,4-5 INCHES DEEP | 245 | SQYD | $ - 0 | $ 43.00 | $ 10,535.00 | $ 40.00 | $ 9,800.00 | $ 50.00 | $ 12,250.00 | $ 53.00 | $ 12,985.00 | |
| 10 | CLASS 2 PREPARATION | 25 | SQYD | $ - 0 | $ 250.00 | $ 6,250.00 | $ 200.00 | $ 5,000.00 | $ 200.00 | $ 5,000.00 | $ 200.00 | $ 5,000.00 | |
| 11 | REINFORCEMENT - GRADE 60 | 1 | LS | $ - 0 | $ 13,500.00 | $ 13,500.00 | $ 10,000.00 | $ 10,000.00 | $ 3,000.00 | $ 3,000.00 | $ 10,000.00 | $ 10,000.00 | |
| 12 | STEEL ROLLED BEAM | 1 | LS | $ - 0 | $ 98,500.00 | $ 98,500.00 | $ 117,500.00 | $ 117,500.00 | $ 202,202.00 | $ 202,202.00 | $ 210,000.00 | $ 210,000.00 | |
| 13 | TIMBER AND LUMBER | 0.8 | MBFM | $ - 0 | $ 19,060.00 | $ 15,248.00 | $ 10,000.00 | $ 8,000.00 | $ 15,000.00 | $ 12,000.00 | $ 19,681.54 | $ 15,745.23 | |
| 14 | GLUED LAMINATED TIMBER | 5 | MBFM | $ - 0 | $ 9,600.00 | $ 48,000.00 | $ 10,000.00 | $ 50,000.00 | $ 15,000.00 | $ 75,000.00 | $ 9,197.08 | $ 45,985.40 | |
| 15 | BEARING DEVICES, ELASTOMERIC | 4 | EACH | $ - 0 | $ 290.00 | $ 1,160.00 | $ 1,500.00 | $ 6,000.00 | $ 150.00 | $ 600.00 | $ 4,500.00 | $ 18,000.00 | |
| 16 | ASPHALTIC PLUG JOINT SEALS | 52 | FOOT | $ - 0 | $ 242.00 | $ 12,584.00 | $ 175.00 | $ 9,100.00 | $ 170.00 | $ 8,840.00 | $ 170.00 | $ 8,840.00 | |
| 17 | TIMBER DECK MOUNTED THRIE BEAM RAIL | 1 | LS | $ - 0 | $ 54,680.00 | $ 54,680.00 | $ 65,000.00 | $ 65,000.00 | $ 60,000.00 | $ 60,000.00 | $ 39,104.20 | $ 39,104.20 | |
| 18 | BRIDGE IDENTIFICATION MARKERS | 1 | EACH | $ - 0 | $ 975.00 | $ 975.00 | $ 500.00 | $ 500.00 | $ 500.00 | $ 500.00 | $ 300.00 | $ 300.00 | |
| 19 | POLYMER MEMBRANE | 2200 | SQFT | $ - 0 | $ 6.00 | $ 13,200.00 | $ 5.50 | $ 12,100.00 | $ 5.33 | $ 11,726.00 | $ 5.33 | $ 11,726.00 | |
| 20 | ROLLED WATERPROOF MEMBRANE | 910 | SQFT | $ - 0 | $ 6.00 | $ 5,460.00 | $ 4.65 | $ 4,231.50 | $ 4.55 | $ 4,140.50 | $ 4.55 | $ 4,140.50 | |
| 21 | LEVEL 3 ACP, 1/2" DENSE | 100 | TON | $ - 0 | $ 324.00 | $ 32,400.00 | $ 260.00 | $ 26,000.00 | $ 260.00 | $ 26,000.00 | $ 256.00 | $ 25,600.00 | |
| 22 | LONGITUDINAL PAVEMENT MARKINGS - PAINT | 520 | FOOT | $ - 0 | $ 6.00 | $ 3,120.00 | $ 3.00 | $ 1,560.00 | $ 10.00 | $ 5,200.00 | $ 20.00 | $ 10,400.00 | |
| TOTAL | $ - 0 | $ 463,402.00 | $ 579,768.33 | $ 665,058.50 | $ 724,626.33 |