About this file

This is a bid tabulation sheet for Oregon State Bridge Construction project S-73000-00010964, the MP35 Bridge Rail Repair project in McMinnville, administered by the State of Oregon. The project encompasses bridge rail repair work including mobilization, temporary work zone traffic control, portable changeable message signs, pollution control planning, work containment planning, temporary work access and containment, architectural treatment, concrete repair location and execution, bridge removal work, ornamental bridge rail installation, and salvaging and stockpiling of bridge materials. The tabulation presents cost estimates across 12 distinct bid items with quantities ranging from 1 lump-sum item to 26 square yards for architectural treatment and 3 square yards for concrete repair work.

Four contractors submitted bids for the project: Lee Contractors LLC with a total bid of $143,950.00, Oregon State Bridge Construction Inc at $150,500.00, HP Civil Inc at $153,524.88, and Wildish Standard Paving Co at $251,553.00. Lee Contractors LLC submitted the lowest total bid price. Significant cost variations exist among bidders on individual line items, particularly on ornamental bridge rail installation (ranging from $35,000 to $70,000), concrete repair ($1,500 to $24,000), and temporary work access and containment ($15,000 to $25,000). The bid tabulation does not identify prevailing wage requirements, bonding requirements, project timelines, or contract award dates within the document itself.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00010964 OR99W MP35 Bridge Rail Repair (McMinnville)
BID TABULATIONLee Contractors LLCOregon State Bridge Construction IncHP Civil IncWildish Standard Paving Co
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1MOBILIZATION1LS$ 13900.00$ 13,900.00$ 15,050.00$ 15,050.00$ 15,384.88$ 15,384.88$ 46653.00$ 46,653.00
2TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE1LS$ 16,600.00$ 16,600.00$ 25,000.00$ 25,000.00$ 25,000.00$ 25,000.00$ 50,000.00$ 50,000.00
3PORTABLE CHANGEABLE MESSAGE SIGN2EACH$ 2,200.00$ 4,400.00$ 3,000.00$ 6,000.00$ 500.00$ 1,000.00$ 3,000.00$ 6,000.00
4POLLUTION CONTROL PLAN1LS$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 500.00$ 500.00$ 500.00$ 500.00
5WORK CONTAINMENT PLAN1LS$ 500.00$ 500.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 500.00$ 500.00
6TEMPORARY WORK ACCESS AND CONTAINMENT1LS$ 15000.00$ 15,000.00$ 25,000.00$ 25,000.00$ 24,000.00$ 24,000.00$ 25000.00$ 25,000.00
7ARCHITECTURAL TREATMENT26SQYD$ 225.00$ 5,850.00$ 100.00$ 2,600.00$ 140.00$ 3,640.00$ 150.00$ 3,900.00
8LOCATE CONCRETE REPAIR1LS$ 5200.00$ 5,200.00$ 5,000.00$ 5,000.00$ 500.00$ 500.00$ 3000.00$ 3,000.00
9CONCRETE REPAIR3SQYD$ 13500.00$ 40,500.00$ 500.00$ 1,500.00$ 6,000.00$ 18,000.00$ 8000.00$ 24,000.00
10BRIDGE REMOVAL WORK1LS$ 5500.00$ 5,500.00$ 15,000.00$ 15,000.00$ 10,000.00$ 10,000.00$ 20000.00$ 20,000.00
11ORNAMENTAL BRIDGE RAIL1LS$ 35000.00$ 35,000.00$ 44,350.00$ 44,350.00$ 50,000.00$ 50,000.00$ 70000.00$ 70,000.00
12EXTRA FOR SALVAGING AND STOCKPILING BRIDGE1LS$ 1,000.00$ 1,000.00$ 5,000.00$ 5,000.00$ 500.00$ 500.00$ 2,000.00$ 2,000.00
TOTAL$ 143,950.00$ 150,500.00$ 153,524.88$ 251,553.00