About this file

This document is an Invitation to Bid (ITB) for pavement maintenance and repair projects at four airports in Southern Oregon: Chiloquin State Airport, Christmas Valley Airport, Lake County Airport, and Malin Airport. The project, referred to as PMP Region 3 - Southern Airports, requires various work including crack sealing, joint repair, and pavement marking. The bid items, estimated quantities, and unit prices are detailed for each airport location. Bids are due on January 10, 2024 at 2:00 pm.

The bid summary sheet shows four bidders and their proposed pricing for the work at each airport. The total bid amounts range from $171,607.67 to $396,922.00. No other pricing details or terms are provided. This appears to be a standard competitive bid for state and local government infrastructure projects, with the contract awarded to the lowest responsive and responsible bidder.

View the file

Other files

File Type Posted
00008116_Att C_Plans.pdf PDF
00008116_ITB.docx DOCX document
ITBAttD - Bid Submittal Form~2.pdf PDF
2023 PMP Pre bid attendees~2.docx DOCX document
00008116_Att A_Bid Schedule.pdf PDF
00008116_Att B_Technical Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:1/10/24
RFB No.:S-10900-00008166BIDDER
NAME:Hybrid Construction LLCKNL Industries IncC.R. ContractingO'Malley Brothers Corporation
Bids due:1/10/2024 2:00 pm
Description:PMP Region 3 - Southern Airports
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

SCHEDULE A - CHILOQUIN STATE AIRPORT
1Mobilization1LS$ 7,400.00$ 7,400.00$ 15,000.00$ 15,000.00$ 23,750.00$ 23,750.00NO
2Crack Sealing4,866LF$ 2.67$ 12,992.22$ 1.54$ 7,493.64$ 3.25$ 15,814.50BID
3Joint Repair973LF$ 25.00$ 24,325.00$ 19.02$ 18,506.46$ 56.50$ 54,974.50FORM
4Pavement Marking6,045SF$ 1.33$ 8,039.85$ 3.87$ 23,394.15$ 2.25$ 13,601.25ATTACHED
TOTAL$ 52,757.07$ 64,394.25$ 108,140.25
SCHEDULE B - CHRISTMAS VALLEY AIRPORT
1Mobilization1LS$ 7,400.00$ 7,400.00$ 15,000.00$ 15,000.00$ 22,890.00$ 22,890.00$ - 0
2Crack Sealing2,976LF$ 3.75$ 11,160.00$ 2.52$ 7,499.52$ 3.75$ 11,160.00$ - 0
3Joint Repair473LF$ 29.00$ 13,717.00$ 31.72$ 15,003.56$ 98.65$ 46,661.45$ - 0
TOTAL$ 32,277.00$ 37,503.08$ 80,711.45$ - 0
SCHEDULE C - LAKE COUNTY AIRPORT
1Mobilization1LS$ 7,400.00$ 7,400.00$ 15,000.00$ 15,000.00$ 22,775.00$ 22,775.00$ - 0
2Crack Sealing4,539LF$ 3.11$ 14,116.29$ 2.20$ 9,985.80$ 3.50$ 15,886.50$ - 0
3Joint Repair152LF$ 71.00$ 10,792.00$ 98.69$ 15,000.88$ 255.00$ 38,760.00$ - 0
4Pavement Marking1,113SF$ 4.00$ 4,452.00$ 9.16$ 10,195.08$ 5.50$ 6,121.50$ - 0
TOTAL$ 36,760.29$ 50,181.76$ 83,543.00$ - 0
SCHEDULE D - MALIN AIRPORT
1Mobilization1LS$ 7,400.00$ 7,400.00$ 15,000.00$ 15,000.00$ 24,465.00$ 24,465.00$ - 0
2Crack Sealing3,501LF$ 3.35$ 11,728.35$ 2.15$ 7,527.15$ 3.75$ 13,128.75$ - 0
3Joint Repair1,787LF$ 15.00$ 26,805.00$ 16.80$ 30,021.60$ 38.75$ 69,246.25$ - 0
4Pavement Marking651SF$ 5.96$ 3,879.96$ 10.67$ 6,946.17$ 8.00$ 5,208.00$ - 0
TOTAL$ 49,813.31$ 59,494.92$ 112,048.00$ - 0
GRAND TOTAL$ 171,607.67$ 211,574.01$ 384,442.70$ 396,922.00