Bid Tab Sheet (Unofficial).pdf

PDF 85 KB Posted

Attached to
GDC-23-HAYS-SP-002R, Hays State Prison Kitchen and Dining Ren.
Solicitation number
PE-40900-RFQ-2025-000000118
Issued by
Candler County, Georgia

About this file

This is a bid tabulation sheet for the Hays State Prison Kitchen & Dining Renovation project (GDC-23-HAYS-SP-002R) managed by the Georgia State Financing and Investment Commission, with a bid opening date of January 22, 2025, at 2:00 PM. The project involves a complete kitchen and dining renovation, with two contractors submitting bids: Iugis Construction Corporation and J&J Contractors, Inc.

The base bid amounts show Iugis Construction Corporation at $12,977,000.00 and J&J Contractors, Inc. at $18,125,000.00. The document includes five deductive alternates, which for J&J Contractors total $5,000,000.00 in potential deductions, covering: removal of roof access door and louver relocation ($500,000), exterior loop piping replacement ($1,000,000), water heater and storage tank replacement ($500,000), AHU replacement in Building A ($2,000,000), and boiler replacement with pump relocation ($1,000,000). Iugis Construction Corporation listed $0.00 for all deductive alternates. The bidder qualification notes indicate Iugis Construction Corporation's experience with secure environments and correctional facility construction.

View the file

Other files

File Type Posted
Pre_Bid Sign_In Sheet.pdf PDF
Invitation To Bid.pdf PDF
eBuilder Registration _ Bid Submittal User Gu.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project:

Bid Open Date:

Description Unit Cost Total Cost Unit Cost Total Cost

1 Base Bid - Kitchen & Dining Renovation 0.00 12,977,000.00 0.00 18,125,000.00 12,977,000.00 18,125,000.00

Remove roof access door, ladder and relocation of louver for Bldgs.

D & K from scope 0.00 0.00 0.00 -500,000.00

Remove exterior loop piping replacement on dormitory roof from scope 0.00 0.00 0.00 -1,000,000.00

Remove water heater and water storage tank replacement from scope 0.00 0.00 0.00 -500,000.00

4 Remove replacement of AHU's, etc. in Building A from scope 0.00 0.00 0.00 -2,000,000.00

5 Remove boiler replacement and boiler pump relocation from scope 0.00 0.00 0.00 -1,000,000.00

0.00 -5,000,000.00

12,977,000.00 18,125,000.00

Bidder Qualification Notes iugis Construction Corporation is pleased to submit our qualifications for the General Contractor role for the Hays State Prison project. With extensive experience in secure environments, we are uniquely equipped to deliver excellence for this critical facility. Our expertise in correctional facility construction ensures we meet the stringent safety, security, and operational requirements inherent to such projects.

Bid Summary Base Bid Total

Deductive Alternates

Deductive Alternates Cost Total

Base Bid

Base Bid Cost Total

Iugis Construction Corporation J&J Contractors, Inc GDC-23-HAYS-SP-002R, Hays State Prison Kitchen & Dining Ren. Brian Hwang Aaron Pack

01.22.2025 2:00 PM bhwang@iugiscorp.com aaron@jjcontractors.com

4232669038

GDC-23-HAYS-SP-002R, Hays State