BID_TAB_ITB_11-25.pdf
PDF 107 KB Posted
- Attached to
- ITB 11-25 Warehouse Storage Building
- Solicitation number
- ITB 11-25
- Issued by
- Volusia County, Florida
About this file
The document is a bid tabulation (Bid Tab) for Invitation to Bid (ITB) 11-25 by New Smyrna Beach Utilities for a Warehouse Storage Building project in Volusia County, Florida. The solicitation seeks a licensed General Contractor to design and construct a four-bay, three-sided metal building with specific technical requirements, including a 26-gauge clear span structure, single slope roof, and 145 MPH wind speed compliance. The project involves constructing a building with bay openings 27 feet wide, a total building width between 108-115 feet, and a 35-foot depth, with each bay capable of supporting up to 60,000 pounds.
The bid tabulation shows four contractors submitted proposals: AccuTech Construction Inc. ($305,244.00), P.A.V.C.O Contracting Group ($260,765.00), KBT Contracting Group ($389,736.00), and FSV Construction Company ($244,200.00). FSV Construction Company was awarded the contract, with the lowest total bid. The project includes line items for mobilization/demobilization, clearing/grubbing, grading, metal building construction, rust inhibitor, drawings, pad drawings, and a $10,000 project contingency. The bid demonstrates a comprehensive approach to evaluating contractor proposals based on detailed line-item pricing and specific project requirements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB 11-25 Warehouse Storage Building Quantity
AccuTech Construction
Inc.
P.A.V.C.O Contracting
Group KBT Contracting
Group
FSV
Construction
Company
Mobilization/Demobilization 1 LS $19,024.00 $13,000.00 $123,691.00 $25,000.00
Clearing/Grubbing 1 LS $16,374.00 $9,915.00 N/A $10,600.00
Grading 1 LS $6,320.00 $13,750.00 $12,825.00 $14,750.00
Three Sided, Four (4) Bay, Clear Span Metal Building and Concret Pad 1 LS $244,426.00 $178,600.00 $233,590.00 $135,000.00
Rust Inhibitor 1 LS included in line
4 price $8,500.00 included in line
4 price $36,850.00
Drawings 1 LS $4,600.00 $12,500.00 $7,500.00 $7,000.00
Pad Drawings 1 LS $4,600.00 $14,500.00 $2,130.00 $5,000.00
Project Contingency $10,000 $10,000.00 $10,000.00 $10,000.00 $10,000.00
Total Cost $305,244.00 $260,765.00 $389,736.00 $244,200.00
AWARDED
Sheet1
File details come from the government source that posted it. Updated .