This specification document is for the City of Minneapolis's rental of heavy equipment without operator services for various city departments and the Park Board. The City is accepting bids for multiple types of heavy equipment including dump trucks, tandems, tractors, cranes, log loaders, skidders, chippers, and haulers on an as-needed basis. The contract is non-exclusive, and the City reserves the right to award multiple contractors to serve its best interests. The initial contract term is one year beginning around March 2027, with the option for the City to renew and extend the contract for four additional 12-month periods if agreeable to both parties. Equipment requests will be made by City personnel with an average notice of two working days prior to the start of work, though shorter notice may occur. City personnel will specify the type and size of equipment needed, and substitutions will not be permitted without prior written authorization. Delivery is required within 24 hours of equipment request unless otherwise agreed upon, with delivery coordination and mileage charges based on Google Maps calculations.

Bid prices shall remain firm for the initial contract year. After the initial period, price escalation may be allowed upon renewal based on demonstrable industry-wide, regional, or operational cost increases, with requests for escalation requiring documentary evidence submitted 60 days prior to contract year end. Escalation increases are capped at the Consumer Price Index or five percent, whichever is higher. The City will award contracts to the lowest responsive and responsible bidders. All on-road vehicles must meet 2010 or newer emission standards, and all off-road equipment must meet Tier 3 or newer emission standards. The contractor must maintain equipment in good running condition with major parts replacement and all fuel, filters, and lubrication service provided by the contractor, while the City assumes liability for minor parts, daily greasing, and damage caused by accident, fire, or vandalism unrelated to equipment malfunction. Invoicing requires itemized billing for actual rental time with no minimum charges, and payment is rendered within 30 days of invoice receipt and material acceptance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

RENTAL OF HEAVY EQUIPMENT WITHOUT OPERATOR

EVENT NO.: 4351

SCOPE OF WORK:

The City of Minneapolis is accepting bids for the rental of heavy equipment without operator for various City of Minneapolis departments (“City”) and boards (“Park Board”) projects on an as needed basis. The various needs include dump trucks, tandems, tractors, cranes, etc. and other equipment such as log loaders, skidders, chippers and haulers as needed, all in accordance with the specifications as follows.

CONTRACT TERM:

It is the intent of the City to award multiple contracts. The successful Contractor(s) will be awarded an initial one (1) year contract starting on or around March 2027. Bid prices shall remain firm for the initial contract term. This contract may be renewed at the expiration of the initial term at the request of the City. The City reserves the right to extend these contracts for four (4) additional 12-month periods if agreeable to both parties.

The bid will be awarded to the lowest responsive and responsible bidders based on the Bid Forms submitted. The City reserves the right to award multiple bidders to serve the best interest of the City. This contract could be used by any City Department but most likely will be Fleet or Park Board.

NON-EXCLUSIVE:

Any contract(s) resulting from this Call for Bid will not be an exclusive contract and the City reserves the right to hire other contractors and seek bids from other vendors.

PRICE ESCALATION:

Prices shall be firm for the first year of the contract. After the initial contract period, an escalation may be allowed for any extensions based upon a demonstrable industry-wide, regional, or operational increases in the contractor’s costs. For documentary evidence to be considered, it must be submitted to the City of Minneapolis Purchasing Department sixty (60) days prior to the end of the current contract year. The exact amount of escalation, if any, will be governed by the validity of the documentary evidence submitted. No price increase will be effective until approved by the City of Minneapolis Purchasing Department. With the exception of extraordinary circumstances, the amount of any increase shall not exceed the Consumer Price Index (CPI) or five (5) percent, whichever is higher.

RIGHTS OF THE CITY:

The City reserves the right to reject all or any part of any bid, waive informalities, and award the contract to the lowest responsive and responsible bidder(s) to best serve the interest of the City.

Informality shall mean a minor defect or variation of a bid from the exact requirements of the Request for Bid which does not affect the price, quality, quantity, or delivery schedule for the goods, services or construction being procured.

QUANTITIES:

The quantities specified in this Contract are estimated only. They may not indicate the actual quantity which will be ordered, since such volume will depend upon requirements which develop during the Contract period.

Quantities shown shall not be construed to represent any amount which the City shall be obligated to purchase under the Contract or relieve the Contractor of its obligation to fill all orders placed by the City.

REQUESTS FOR EQUIPMENT:

City personnel will call the vendor to request type of equipment needed. The average notice is two working days prior to the start of work, but shorter notice may sometimes occur. The request will be made for a specific piece of equipment and substitutions will not be allowed unless prior authorization is given in writing (email is satisfactory). The City personnel have determined the size and type of equipment needed. If other equipment is to be considered, a prior on-site meeting with City personnel with be necessary.

The City may require equipment that is not specifically called for on this bid. Each bidder is encouraged to list and bid all equipment they can provide in addition to what is requested. Any additional equipment bid will be covered under this contract with the same terms and conditions.

The City will normally contact the lowest bid item first, the second lowest bid item next and so forth depending on availability. Notwithstanding this, the City may contact a higher bid item if in the opinion of the City the machine and/or operator provided by an alternative Contractor is better suited for the project. A lower priced Contractor, working for the City will not be allowed to bump a higher priced Contractor, also working for the City, in the middle of a project.

Specific information regarding the job location, work hours, possible special conditions, and other job information will be provided at the time of request.

Period of usage shall be given at the time of request to the best of the City’s estimation.

Equipment may be scheduled anytime. When a need is determined, and the vendor is contacted, vendors are expected to respond in a timely manner. If an effort is made to contact a vendor and the vendor does not respond or cannot respond within the time allotted by a department, the department may contact another vendor on the contract list for their rental equipment and operator needs.

Bidders must provide a telephone number that is active during normal working hours. Many City and/or Park Board needs arise that are of urgent nature. The Contractor shall provide his/her current business telephone number, cell phone number and e-mail address for contact.

The City will make a reasonable attempt to contact the Contractor to initiate a contract. A lack of response from the Contractor or an inability to contact the Contractor in a 30-minute period may constitute a rejection on the part of the Contractor to accept the contract. If a Contractor cannot be contacted, the City and/or Park Board will make alternative arrangements for which neither the City nor the Park Board will be financially liable. If in a calendar year, a Contractor has not accepted a contract after six (6) attempts by the City,the Contractor's bid may be considered invalid for future contracts.

All equipment provided must be available for inspection at any time by the City or Park Board Personnel. In order to help meet the City’s goals of reducing Greenhouse Gasses, all on road vehicles must meet 2010 or newer emission standards, and all off road equipment must meet Tier 3 or newer emission standards.

DELIVERY REQUIREMENTS:

Delivery shall occur within 24 hours after receipt of the equipment(s) unless otherwise agreed to by the City if the delivery cannot happen within the 24-hour time frame. Coordination of the delivery time and delivery method shall be agreed upon by both City and Contractor.

Mileage distance will be the distance from the starting delivery point to the City’s destination point. Mileage distance will be determined by using google maps. The City may use the Contractor’s delivery, may pick up the equipment, or may contract for delivery with a provider.

Upon request by the City, Contractor shall provide the contact information (i.e. Name, Telephone, Email, and Rate) for their delivery provider.

EQUIPMENT REQUIREMENTS:

The City shall furnish:

1. Qualified operators to operate the equipment.

2. Minor parts replacement and installation. Minor parts defined as throw away parts – light bulbs, bucket teeth, etc. and those parts which normally can be expected to wear out during normal usage.

3. Daily greasing.

4. Responsibility to the Contractor for personal and property damage caused at the job site by accident, fire, vandalism or other destruction provided such as personal or property damage was not caused by malfunction of the machine or negligence on the part of its owner. Certificate of Self Insurance available upon request.

5. Any necessary repairs, parts, labor and mileage charge that the City of Minneapolis is liable for and the Contractor performs shall be billed to the City/Park Board.

A sample of the itemized invoice shall include the following information:

a. Labor (per hour) $

b. Minimum labor charge $

c. Mileage (per mile) $

d. Parts % off list or % over cost (indicate which)

6. Contractor shall furnish:

a. Equipment in good running condition with fresh oil and filters changed. Must perform work for which it is intended

b. Major parts replacement and installation. Major parts defined as those parts that would not normally break under normal usage - hydraulic pumps and systems, transmission and engine failure, etc.

c. Changing of filters, greases, etc. to maintain warranty

d. All fuel, filters and lubrication service, including installation on a schedule basis – and including adding hydraulic fluids, transmission fluids, transmission fluids and the like as needed between changes.

e. Where available, vandal proofing panels for glass areas, lockable exhaust stacks, lockable fuel and water intake openings and tire valve protectors

All equipment with operator will be rented on an hourly basis and must be in excellent operating condition and be complete with proper licenses, insurance, fuel and necessary operating supplies.

INVOICING REQUIREMENTS:

Vendors shall submit an itemized invoice that contains billing for actual rental time; no minimum charges are allowed.

To ensure accurate and timely processing, each invoice must include:

1. PO Number assigned at the time equipment is rented.

2. Dispatcher’s Name given to the vendor when the rental is arranged.

3. Department Name: Fleet or Park Board Fleet

All work requested under this Contract shall be placed on a City issued Purchase Order. Bidder shall make all reasonable efforts to submit invoices and documentation in an electronic format, such as PDF or other format compatible with City software capabilities, in lieu of paper invoices and documentation, when so requested by City. Upon delivery and acceptance of the materials, the Bidder shall submit an invoice detailing the appropriate charges.

Invoices shall be submitted to:

City of Minneapolis – Accounts Payable 505 Fourth Ave. S, Room 310 Minneapolis, MN 55415 Email: submitinvoices@minneapolismn.gov

Upon receipt of invoice and final inspection and acceptance of the materials, the City will render payment within thirty (30) days unless any items thereon are questioned, in which event payment will be withheld pending verification of the amount claimed and the validity of the claim. The Supplier shall provide complete cooperation during any such investigation.