This is a bid solicitation package issued by the California Department of Parks and Recreation (DPR), Monterey District, for septic tank and vault pumping services across multiple state park facilities in Monterey County. The contractor shall furnish all labor, materials, tools, and equipment necessary to provide septic pumping services for vaults and holding tanks, as well as emergency pumping services, at twenty-eight service locations spanning Marina State Beach, Point Lobos State Natural Reserve, Andrew Molera State Park, Pfeiffer Big Sur State Park, Julia Pfeiffer Burns State Park, John Little State Natural Reserve, and Limekiln State Park. The contract encompasses a 36-month term commencing March 1, 2026, or upon Department of General Services (DGS) Office of Legal Services (OLS) approval, whichever is later. Bids must be submitted electronically in PDF format to monterey.contractbids@parks.ca.gov no later than 11:00 a.m. on Friday, January 16, 2026, with bid opening scheduled for 1:00 p.m. the same day via conference call. Prospective bidders may submit questions no later than 2:00 p.m., seven calendar days prior to bid opening, with answers provided by addendum on the CaleProcure website. The contract will be awarded to the lowest responsible bidder whose bid complies with all prescribed requirements, and all bids shall remain valid for 30 calendar days following the bid opening date.
The bid solicitation specifies a fixed rate structure across three 12-month service periods with rates remaining constant throughout the 36-month contract term. The DVBE participation requirement has been waived; however, the DVBE incentive program still applies, offering a dollar cap of $100,000 for all combined incentives and preferences. A 5% Small Business Preference is available to California-certified small businesses, and Target Area Contract Preference Act (TACPA) preferences between 5-9% may apply for contracts exceeding $100,000. Contractors must possess and maintain a current and valid Liquid Waste Hauler Permit issued by the County of Monterey Health Department throughout the contract term. Service technicians must be trained and certified, with copies of certifications provided upon request. The contractor is responsible for all miscellaneous materials incidental to service, including safety materials, with no additional charges to the State. Standard workdays are Monday through Friday from 8:00 a.m. to 5:00 p.m., excluding weekends and state-observed holidays; however, emergency call-outs require 24-hour response, seven days a week, with a mandatory 4-hour response time. Insurance requirements include general liability coverage of $1,000,000 per occurrence with $2,000,000 aggregates, motor vehicle liability of $1,000,000 combined single limit, statutory workers' compensation coverage, and pollution liability insurance of $1,000,000 per incident and $2,000,000 aggregate, with the State named as additional insured.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of California – The Resources Agency
DEPARTMENT OF PARKS AND RECREATION
Invitation for Bid – C25720005
Septic Tank & Vault Pumping Services
Monterey District Monterey County, California
Bids Due by Friday, January 16, 2026, at 11:00 a.m.
Bid Opening on Friday, January 16, 2026, at 1:00 p.m.
Term: 36 months
Proposed Start Date: March 1, 2026, or upon DGS – OLS approval, whichever is later
The DVBE Participation Requirement for this solicitation has been waived – however, the DVBE Incentive still applies.
STATE OF CALIFORNIA – NATURAL RESOURCES AGENCY
Department of Parks and Recreation
Monterey District
Septic Tank & Vault Pumping Services C25720005
Table of Contents
ITEM PAGE NUMBER
Cover Page 1 Table of Contents 2 Notice to Contractors 3 Small Business Preference and TACPA Notices (DPR 478) 6 Commercially Useful Function – Bidder Certification (DPR 87) 9 Disabled Veteran Business Enterprise Notice (DPR 479IW) 10 Disabled Veterans Business Enterprise Declarations (DGS PD 843) 15 Standard Agreement (STD 213) (SAMPLE) 16 Exhibit A, Scope of Work 18 Exhibit A, Attachment 1, Schedule of Services 24 Exhibit A, Attachment 2, Site Map 29 Exhibit B, Budget Detail and Payment Provisions 31 Exhibit B, Attachment 1, Service Contracts Bid Form (DPR 940B) and Cost Sheets 33 Exhibit C, General Terms and Conditions (view and download) https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List- Folder/Standard-Contract-Language Via Internet Exhibit D, Services Standard Agreement with Pollution Liability 44 Darfur Contracting Act Certification (DPR 74) 50 Bidder Declaration (GSPD-05-105) 52 California Civil Rights Laws Attachment (DGS OLS 4) 54 Contractor’s Certification Clauses (CCC 04/2017) 55 Payee Data Record Supplement w/ Instructions Goods vs Services (DPR 88) 59 Payee Data Record (STD 204) 61 Payee Data Record Supplement (STD 205) 63 Artificial Intelligence (AI) Disclosure Form (DPR 97B) 65 https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language
State of California - Natural Resources Agency
NOTICE TO CONTRACTORS
MONTEREY DISTRICT
SEPTIC TANK & VAULT PUMPING SERVICES
Bid Number: C25720005
Bids must be submitted electronically with all necessary fully executed bid submission documents as an attachment in Portable Document Format (PDF) to monterey.contractbids@parks.ca.gov no later than 11:00 a.m. on Friday, January 16, 2026. Bid submission time will be as of the electronic time stamp associated with when the electronic email submission was received. Submissions with attached PDF documents more than 10 Megabytes in size risk being rejected and can be deemed unresponsive. DPR will provide an individual electronic email response confirming receipt of each submission received. If a confirmation receipt is not received within 30 minutes of submission, please contact Jeannie Lopez at the email address above to confirm your bid was received. Confirmation receipt is not a representation by DPR that the submitted bid is responsive and complete. Bidders are responsible for ensuring that the electronic submission that contains the attachment is fully responsive and lacks any deficiency prior to submitting to the email address above. Failure to do so risks the bid being deemed unresponsive. It is recommended that Bidders submit bids at least one (1) hour in advance from the bid submission deadline to allow for confirmation of bid submission. Bids will be opened publicly over conference call at 1:00 p.m. on January 16, 2026.
Individuals interested in calling in to the Bid Opening must send their request into monterey.contractbids@parks.ca.gov to receive a conference participation access code. Please ensure a request for a conference call is submitted 24 hours in advance to allow DPR adequate time to accommodate all Bidders. Bids will be submitted to perform the work as follows:
Furnish all labor, materials, tools and equipment necessary to provide pumping services for septic vaults and holding tanks, as well as emergency pumping services in accordance with the specifications therefore and such addenda thereto may be issued prior to bid opening date.
Estimated Contract Start Date: March 1, 2026, or upon Department of General Services (DGS)
– Office of Legal Services (OLS) approval, whichever is later.
Contract Performance Period: 36 months from contract approval.
Instructions to Download Bid Package: Prospective bidders may examine and obtain the bid forms, specifications, plans and addenda (if any) by downloading this bid package from the Department of General Services’ (DGS) website at https://caleprocure.ca.gov/pages/Events- BS3/event-search.aspx. On the website, go to Quick Links, Find Bid Opportunities, and enter Bid Number “C25720005” in the “Event Name” field. Click on the “Search” button to view the full advertisement and bid documents.
Questions and Answers: Any discrepancies, omissions, ambiguities, or conflicts in or among the contract documents or doubts as to meaning shall be brought to the State's attention by emailing your questions directly to monterey.contractbids@parks.ca.gov NO LATER THAN 2 p.m., seven (7) calendar days prior to bid opening date. Answers will be provided by Addendum which will be posted within the Bid Solicitation located on the CaleProcure website stated above. It is the responsibility of the bidders to download any addenda as needed.
mailto:monterey.contractbids@parks.ca.gov mailto:monterey.contractbids@parks.ca.gov https://caleprocure.ca.gov/pages/Events-BS3/event-search.aspx https://caleprocure.ca.gov/pages/Events-BS3/event-search.aspx mailto:monterey.contractbids@parks.ca.gov
Notice to Contractors
Bidding Requirements: No bids will be accepted after the date and time set for bid due date.
No bids will be considered unless it is made on a standard bid form furnished by the Department of Parks and Recreation and is made in accordance with the "Instructions to Bidders".
Bids must be submitted for the entire work as described herein. The Department of Parks and Recreation reserves the right to waive any irregularity in a bid or to reject any or all bids.
Bids shall take into consideration all such conditions as may affect the work. Bidder should carefully examine the entire bid documents and become fully aware of the nature and location of the work, the quantities of work, and conditions to be encountered in performing the work.
Prices shown on the Bid Form shall include all applicable taxes and other items of expense incident to the bid price.
Any bid may be withdrawn prior to the hour fixed above, provided that the written request for withdrawal is submitted by the bidder or his/her duly authorized representative and e-mailed to the place shown above. An oral or other form of request to withdraw a bid is not acceptable.
If the contract is awarded, it will be awarded to the lowest responsible bidder whose bid complies with the prescribed requirements. The apparent low bidder will be required to execute a contractual agreement in the form of a "Standard Agreement - Form 213" which shall be binding upon the State of California only upon approval by the State.
In the case of a tie bid, the determination of a successful bidder will be made by a coin toss in the presence of all interested bidders, at a time and date set by the originating office.
All bids shall remain valid for 30 calendar days after the bid opening date.
The contract shall be signed by the successful bidder and returned within five (5) working days after the bidder receives notice that the contract has been awarded.
Procedure for Protesting an Award: Upon written request by any bidder who has submitted a bid, the agency must post a notice of the proposed contract award in a place accessible by the general public including any internet site identified in the IFB at least five days prior to awarding the contract.
If contract is not awarded to the low bidder, the low bidder shall be notified by FAX, overnight courier, e-mail, or personal delivery five (5) working days prior to the award of contract.
Inspection of bids is permitted after the bid opening. At that time, all bids shall be available for public inspection.
There are time limits in which to file a protest. A protest must be filed with the agency and DGS after notice of intent to award the contract, but before the actual award. Once a protest is filed the contract may not be awarded until the protest is withdrawn or DGS has rendered a decision.
After filing a protest, the protestant has five calendar days to file a detailed written statement of the protest grounds if the original protest did not contain the complete grounds for the protest.
Notice to Contractors
Protests of award shall be in writing and filed with:
Department of General Services Office of Legal Services
Attention: Protest Coordinator 707 Third Street, 7th Floor
West Sacramento, CA 95605
A copy of the written protest should be sent to:
Department of Parks and Recreation Administrative Services Division Manager, Contract Services Unit
P.O. Box 942896 Sacramento, CA 94296-0001
Bid Submission: In order for a bid to be considered responsive, Bidder must submit the following documents in a single PDF document by the due date above:
DPR 87 – Commercially Useful Function – Bidder Certification (if applicable) (Page 9) DGS PD 843 – DVBE Declarations (if applicable) (Page 15) Exhibit B, Attachment 1 – Service Contract Bid Form/Cost Sheets (Pages 33-43) DPR 74 – Darfur Contracting Act Certification (if applicable) (Page 50-51) GSPD-05-105 – Bidder Declaration (Pages 52-53) CCC 04/2017 – Contractor Certification Clauses (Pages 55-58) DPR 88 Payee Data Record Supplement w/ Instructions, Goods vs Services (Pages 59-60) STD 204 Payee Data Record (Pages 61-62) STD 205 Payee Data Record Supplement (if applicable) (Pages 63-64) DPR 97B Artificial Intelligence (AI) Disclosure Form (Pages 65-67)
Contractor must include with the bid documents a current and valid Liquid Waste Hauler Permit issued by the County of Monterey Health Department (see Attachment A, Scope of Work, page 3).
All forms requiring a signature can be completed either manually, or by use of electronic signature (e-signature). E-signatures are legally binding and equivalent to handwritten signatures to signify an agreement. The use of e-signature is optional and will be at the expense of the Bidder.
5% SMALL BUSINESS PREFERENCE PROGRAM
Bidder
DPR 478 (Rev. 9/2023)(Excel 9/20/2023)(Page 1 of 3)
$29,870 $28,421
Small Business Status
Claims small business status, but is not CA certified
Does not claim to be a small business Claims small business status, but their CA certification has expired
Claims small business and is CA Certified
$28,975 $28,975
$29,520 $29,520
Bid Amount Bid After 5% Preference
$30,750 $30,750
SMALL BUSINESS PREFERENCE AND TACPA NOTICES
5% Small Business Preference / Target Area Contract Preference Act (TACPA) (page 3)
What is a California Certified Small Business (SB)?
1) For a business to be considered a Small Business (SB), they must be certified with the State of California - Department of General Services in accordance with California Code of Regulations, Title 2, Section 1896.94.
2) Your business may be eligible if it meets all of the following*:
a. Must be independently owned and operated.
b. Cannot be dominant in its field of operation.
c. Must have its principal office located in California.
d. Must have its owners (or officers in the case of a corporation) domiciled in California.
e. Together with its affiliates, be either:
• A business with 100 or fewer employees, and an average annual gross receipts of $16 million or less over the previous three tax years, or
• A manufacturer with 100 or fewer employees.
f. Microbusiness: A small business will automatically be designated as a microbusiness if gross annual receipts, together with all affiliates, are less than $5,000,000 or, the small business is a manufacturer with 25 or fewer employees.
* For additional details visit the Department of General Services (DGS) website.
State of California - Natural Resources Agency
DEPARTMENT OF PARKS AND RECREATION
What is the Small Business Preference?
5% Small Business Preference: State law allows certified small business (SB) and microbusiness (MB) firms to receive a 5% bidding preference on applicable state solicitations. The 5% preference is also available for non-certified businesses who subcontract 25% of contract amount with a certified SB/MB. In no event shall the SB preference or non-SB subcontracting preference exceed $50,000 in any single bid.
The effect of the preference is to help SBs/MBs be more competitive in the bid process, thereby enhancing state contract awards directly or indirectly to SB/MB. The preference is only used for computation purposes to determine the winning bidder, the contract is awarded at the actual bid amount.
1. How does the 5% Small Business (SB) Preference Work?
a) The following example shows how the 5% preference computation works, and how it is used to determine a successful bidder.
https://www.dgs.ca.gov/PD/Services/Page-Content/Procurement-Division-Services-List-Folder/Certify-or-Re-apply-as-Small-Business-Disabled-Veteran-Business-Enterprise https://www.dgs.ca.gov/PD/Services/Page-Content/Procurement-Division-Services-List-Folder/Certify-or-Re-apply-as-Small-Business-Disabled-Veteran-Business-Enterprise
The State of California www.dgs.ca.gov/PD/Contact Department of General Services Receptionist: (916) 375-4940 Office of Small Business and DVBE Services 24-hour recording: (916) 322-5060 707 Third Street, First Floor – Room 400 FAX: (916) 375-4950 West Sacramento, CA 95605 OSDSHelp@dgs.ca.gov
DPR 478 (Rev. 9/2023)(Page 2 of 3)
b) Computation Method for example 4-a:
1. Five percent is applied to the lowest (non-certified small business) responsible bid ([Bidder 2] $28,975 x .05 = $1448.75).
2. The preference amount ($1,448.75) is subtracted from the certified small business (Bidder 4’s) bid amount ($29,870 - $1,448.75 = $28,421.25).
3. Bidder 4’s computed total is $28,421.25, making them the lowest bidder.
4. The contract is awarded to Bidder 4 for $29,870.
c) NOTE: The 5% SB preference is applied to currently certified and registered small businesses and is used for bid evaluation purposes and does not alter the bid's actual amount.
2. Documentation
a) Bidders must provide a printout from the State's SB/DVBE vendor system showing your certification and expiration date from the following web site. www.Caleprocure.ca.gov
b) If a non-certified firm is claiming the SB Preference based on subcontracting at least 25% of the contract to a certified SB/MB, you must include a complete GSPD 05-105 with your bid. An evaluated bid under the 25% SB subcontracting qualification cannot displace a certiffied and registered SB.
c) At completion of peformance and when SB participation was included toward SB goals under this contract, then the contractor must complete and submit form DPR 489 to the State's designated representative under this contract and within the time specified within the contracting documents or within 60 days of receipt of final payment, which ever is sooner.
3. Verification Information submitted by the bidders to claim the SB Preference will be verified by the State. If evidence of an alleged violation is found during the verification process, the State shall initiate an investigation, in accordance with the requirements of the PCC §10115, et seq., and MVC §999 et seq., and follow the investigatory procedures required by the 2 CCR §1896.80. Contractors found to be in violation of certain provisions may be subject to loss of certification, penalties and/or contract termination.
4. To locate SB/MB contractors:
a) Contact the department’s contracting official named in this solicitation for any SB/MB contractors who may have identified themselves as potential subcontractors, and to obtain suggestions for search criteria to possibly identify SB/MB contractors for the solicitation. You may also contact the department’s SB/DVBE Advocate for assistance: www.parks.ca.gov/advocate.
b) Access the list of all certified SB/MBs by using the Department of General Services, Procurement Division (DGS-PD) online certified firm database at: www.Caleprocure.ca.gov
c) Search by “Keywords” or United Nations Standard Products and Services Codes (UNSPSC) that apply to the elements of work you want to subcontract to a SB/MB.
d) Check for subcontractor ads that may be placed on the California State Contracts Register (CSCR) for this solicitation prior to the closing date. You may access the CSCR at: www.Caleprocure.ca.gov
5. Information The State of California, Department of General Services, Procurement Division, Office of Small Business and DVBE Services (OSDS) offers many services that assist contractor/business owners with a variety of information designed to streamline the State contracting process. OSDS also certifies SB/MB contractors. For more information, please contact http://www.dgs.ca.gov/PD/Contact mailto:OSDSHelp@dgs.ca.gov http://www.caleprocure.ca.gov/
TARGET AREA CONTRACT PREFERENCE ACT (TACPA)
Information regarding TACPA including bidder questions about eligibility, please contact:
The State of California Receptionist: (916) 375-4940 Department of General Services Procurement Division - Dispute Resolution Unit 707 Third Street, Second Floor Worksite Eligibility Determinations:
West Sacramento, CA 95605 TACPA@dgs.ca.gov
DPR 478 (Rev. 9/2023)(Page 3 of 3)
Any vendor whose bid is over $100,000 may apply for Target Area Contract Preference Act (TACPA) preference. TACPA provides 5 to 9 percent preferences for a California business that is located in the qualified zone.
How does the TACPA Preference Work?
TACPA will be granted to California-based firms in accordance with Government Code §4530 whenever contracts for goods or services are in excess of $100,000 and the bidder meets certain requirements as defined in the California Administrative Code (Title 2, §1896.30 et seq.) regarding labor needed to produce the goods or provide the services being procured. The TACPA is optional on the part of the bidder (not mandatory), is for bidder evaluation purposes only, and does not alter the amount of the awarded Contract.
Bidders seeking to take advantage of this preference will need to review the DGS Procurement website and submit the appropriate response forms with their bid. The bidder may omit these forms if there is no intention to claim this preference.
Please carefully review the forms and requirements. Bidders are not required to apply for these preferences.
Denial of the TACPA preference request is not a basis for rejection of a bid.
The required applications/forms are as follows:
• STD. 830, TACPA Preference Request for Goods and Services Solicitations
• DGS/PD 525, Manufacturer’s Summary of Contract Activities and Labor Hours
• DGS/PD 526, Bidder’s Summary of Contract Activities and Labor Hours
These forms can be found on the California Statewide Forms Directory at:
https://forms.dgs.ca.gov/content/DGSFormsPortal/california-state-forms-directory.html
Contracts awarded with applied preferences will be monitored throughout the life of the contract for compliance with statutory, regulatory, and contractual requirements. The State will take appropriate corrective action and apply sanctions as necessary to enforce preference programs.
Note: You do not need to be a certified Small Business to apply for the TACPA Preference.
mailto:TACPA@dgs.ca.gov https://www.dgs.ca.gov/PD/Services/Page-Content/Procurement-Division-Services-List-Folder/Request-a-Target-Area-Contract-Preference http://www.documents.dgs.ca.gov/dgs/fmc/pdf/std830.pdf https://www.documents.dgs.ca.gov/dgs/fmc/gs/pd/gspd0525.pdf https://www.documents.dgs.ca.gov/dgs/fmc/gs/pd/gspd0526.pdf https://forms.dgs.ca.gov/content/DGSFormsPortal/california-state-forms-directory.html
State of California � Natural Resources Agency
COMMERCIALLY USEFUL FUNCTION � BIDDER CERTIFICATION
All California Certified Small Business (SB), Micro Business (MB), and Disabled Veteran Business Enterprise (DVBE) suppliers contracting and subcontracting must complete this certification form.
LEGAL BUSINESS NAME (including �Doing Business As� DBA name) DPR REFERENCE/AGREEMENT NUMBER
CERTIFICATIONS (mark all that apply)
Small Business Micro Business DVBE
DGS CERTIFICATION NUMBER
(OSDS)
EXPIRATION DATE
For this agreement, this business is the: Prime Contractor Subcontractor
All Certified Small Business, Micro Business, and/or DVBE prime contractors, subcontractors or suppliers must meet the commercially useful function requirements under Government Code Section 14837(d)(4)(A) for Small and Micro Businesses, and Military and Veterans Code Section 999(b)(5)(B)(i) for DVBEs.
A. Is the GSPD-05-105, Bidder Declaration attached? Yes No
B. Is the DGS PD 843, Disabled Veteran Business Enterprise Declarations form attached if applicable?
Yes No N/A
Please answer the following 5 questions as they apply to your company for the goods and/or services being acquired in this solicitation:
Will your business be responsible for the execution of a distinct element of the resulting work?
Yes No
Will your business carry out the obligation of the contract by actually performing, managing or supervising the work involved?
Yes No
3 Will you perform work that is normal for your business, service and functions? Yes No
Will your business be responsible for products, inventories, materials, suppliers required for the contract, negotiating price, determining quality and quantity, ordering, installing (if applicable) and making payment?
(Note: This only applies to GOODS. If this is a service, mark N/A and skip to #5.)
Goods Services
Yes No N/A
If subcontracting a portion of the work, is it a normal portion as expected by current industry practices? (Also answer Yes if not subcontracting any portion.)
Yes No
A response of �No� may result in your quote being deemed non-responsive and disqualified.
BIDDER�S CERTIFICATION
The signatory of this document must be the certified business owner (or authorized representative in the case of a corporation) and as such, hereby certifies under penalty of perjury under the laws of the State of California that all information provided herein is truthful and accurate.
PRINTED NAME AND TITLE OF AUTHORIZED SIGNER SIGNATURE DATE
DEPARTMENT OF PARKS AND RECREATION USE
APPROVED DENIED
DPR BUYER/EVALUATOR PRINTED NAME SIGNATURE DATE
DPR 87 (Rev. 5/2025)(Word to PDF 5/28/2025)
DPR 479IW (Rev. 10/2025)(Excel 10/28/2025)(Page 1 of 5)
1. Bidder's attention is directed to the Disabled Veteran Business Enterprise (DVBE) Participation Requirement for bidders, as outlined in the accompanying bid package.
Disabled Veteran Business Enterprise (DVBE) Notice
2. What is a Disabled Veteran Business Enterprise (DVBE)?
a. For a business to be considered a Disabled Veteran Business Enterprise (DVBE), they must be certified with the State of California - Department of General Services in accordance with California Code of Regulations, Title 2, Section 1896.94. Please see the following website for more information about DVBE certification benefits and eligibility requirements:
www.dgs.ca.gov/PD/Services/Page-Content/Procurement-Division-Services-List-Folder/Certify-or- Re-apply-as-Small-Business-Disabled-Veteran-Business-Enterprise
b. Only DVBEs who perform a commercially useful function relevant to this solicitation, may be used to satisfy the DVBE incentive program requirements.
3. Commercially Useful Function Definition
a. California Code of Regulations, Title 2, § 1896.61(l): The term "DVBE contractor, subcontractor or supplier" means any person or entity that satisfies the ownership (or management) and control requirements of §1896.61(f); is certified in accordance with §1896.70;
and provides services or goods that contribute to the fulfillment of the contract requirements by performing a commercially useful function.
b. A person or entity must perform a commercially useful function (CUF) as defined under Military and Veterans Code (MVC) §999.
c. A contractor, subcontractor, or supplier will not be considered to perform a commercially useful function if the contractor's, subcontractor's, or supplier's role is limited to that of an extra participant in a transaction, contract, or project through which funds are passed in order to obtain the appearance of disabled veteran business enterprise participation.
4. What is the DVBE Incentive Program?
a. The DVBE Incentive Program was established by statute and applies to contracts solely financed by State funds. This program is separate from the DVBE Participation Program. The incentive is designed to encourage bidders to partner with DVBE subcontractors.
The DVBE Participation Requirement for this solicitation has been waived – however the DVBE Incentive still applies.
There is no minimum DVBE participation requirement for this solicitation.
DVBE Incentive for Invitation For Bid (IFB) (Participation Requirement Waived)
State of California - Natural Resources Agency https://www.dgs.ca.gov/PD/Services/Page-Content/Procurement-Division-Services-List-Folder/Apply-for-or-Re-apply-as-Small-Business-Disabled-Veteran-Business-Enterprise
DPR 479IW (Rev. 10/2025)(Page 2 of 5)
b. The incentive may be combined with other incentives and preferences up to an established cap of $100,000.00. The incentive is used only for evaluation purposes and does not alter the amounts of the actual bids.
5. Reporting Requirement
a. If, for this agreement, a contractor made a commitment to achieve disabled veteran business enterprise (DVBE) participation, within 60 days of receiving final payment under this agreement (or within such other time period as may be specified elsewhere in this agreement) the contractor must certify in a report to the awarding department:
i) the total amount the prime contractor received under the contract
ii) the name and address of the DVBE(s) that participated in the performance of the contract
iii) the amount each DVBE received from the prime contractor
iv) that all payments under the contract have been made to the DVBE(s)
v) the actual percentage of DVBE participation that was achieved
b. You will be required to report to DPR the actual dollars spent with each DVBE subcontractor on form STD. 817. If awarded the contract you will receive this form at the completion of the contract. A person or entity that knowingly provides false information shall be subject to a civil penalty for each violation. (Military & Veterans Code (M&VC) § 999.5(d)).
6. Who is eligible to receive the incentive?
a. Any responsive and responsible bidder who has attained .01% DVBE participation or higher with a registered and certified DVBE.
7. Documentation
a. Bidders must document DVBE participation commitment by completing and submitting the following forms:
1) GSPD 05-105, Bidder Declaration: The GSPD 05-105 is used to document the proposed prime contractor and subcontractors, including their roles and responsibilities. The form must be submitted with the bid package. If there is a discrepancy between the dollar amount and percentage of bid for DVBE participation then the percentage shall prevail.
2) DGS PD 843, DVBE Declaration: All disabled veteran owners and disabled veteran managers of the DVBE must complete the form and submit it with the bid package. A DGS A DGS PD 843 needs to be submitted by every DVBE supplier who is part of a bid whether they are the prime contractor or subcontractor.
b. Bids that fail to submit the completed required forms to confirm the level of DVBE participation will not be eligible to receive the DVBE incentive. Clerical and typographical errors on these forms may be corrected at the State’s sole discretion.
c. Information submitted by the bidders to claim the DVBE incentive(s) will be verified by the State. If evidence of an alleged violation is found during the verification process, the State shall initiate an investigation, in accordance with the requirements of the PCC §10115, et seq., and MVC §999 et seq., and follow the investigatory procedures required by the 2 CCR §1896.80.
Contractors found to be in violation of certain provisions may be subject to loss of certification, penalties and/or contract termination.
c. Table A – Invitation For Bid (IFB) (aka Low Price Method)
a. Low Price Method
A B C
$98,000.00 $102,100.00 $100,000.00
0% 8% 4.5%
1 3 2 n/a 5% 4% n/a $4,900.00
(5% x $98,000) $3,920.00
(4% x $98,000) n/a 97,100.00
($102,100 - $4,900) 96,080.00
($100,000 - $3,920)
3 2 1
DPR 479IW (Rev. 10/2025)(Page 3 of 5)
Final Rank:
DVBE Incentive (from Table A) Incentive Amount (% x Lowest Responsive and Responsible Bid Price) Adjusted Bid Price (Bidder's Price - Bidder's Incentive Amount)
Bidder Name
Original Bid Price
DVBE Participation for certified DVBE Prime or Subcontractors
Initial Ranking
2% - 2.99% .01% - 1.99%
5% of lowest responsive and responsible bid 4% of lowest responsive and responsible bid 3% of lowest responsive and responsible bid 2% of lowest responsive and responsible bid 1% of lowest responsive and responsible bid
Confirmed DVBE Participation of DVBE Incentive Amount for IFB
5% or more 4% - 4.99% 3% - 3.99%
8. How does the DVBE Incentive Program Work?
a. The DVBE incentive is used only for evaluation purposes to determine the successful bidder and does not alter the amounts of the actual bids. A dollar cap of $100,000.00 is set for all combined incentives and preferences.
b. For contracts to be awarded based on the Low Price Method, the incentive amount is equal to a percentage of the lowest responsive and responsible bid based on the amount of DVBE participation in the bid being evaluated per Table A below. The Computation Method does not include the small business preference; however, the small business preference may be applied and may affect the application of the incentive and the outcome of the ranking.
9. Computation Method
The State of California www.dgs.ca.gov/PD Department of General Services Receptionist: (916) 375-4940 Office of Small Business and DVBE Services 24-hour recording: (916) 322-5060 707 Third Street, First Floor – Room 400 FAX: (916) 375-4950 West Sacramento, CA 95605 OSDSHelp@dgs.ca.gov
DPR 479IW (Rev. 10/2025)(Page 4 of 5)
10. Substitution of Proposed DVBE
a. If awarded the contract, the DVBE subcontractors and/or contractors proposed by bidder must be used unless prior written notice of substitution is provided to the state and the state approves such substitution.
b. The notice must include a minimum of: (1) a written explanation of the reason for the substitution; and (2) an updated GSPD 05-105 must be submitted to the award office of Department of Parks and Recreation. The substitution request must before approved before the substitution can take place.
c. Failure to adhere to at least the DVBE participation proposed by the successful bidder may be cause for contract termination and recovery of damages under the rights and remedies due the state under the default section of the contract.
d. Contractor understands and agrees that should award of this contract be based in part on their commitment to use the Disabled Veteran Business Enterprise (DVBE) subcontractor(s) identified in their bid or offer, per Military and Veterans Code 999.5 (e), a DVBE subcontractor may only be replaced by another DVBE subcontractor and must be approved by the State. Changes to the scope of work that impact the DVBE subcontractor(s) identified in the bid or offer and approved DVBE substitutions will be documented by contract amendment.
e. Failure of Contractor to seek substitution and adhere to the DVBE participation level identified in the bid or offer may be cause for contract termination, recovery of damages under rights and remedies due to the State, and penalties as outlined in M&VC § 999.9; Public Contract Code (PCC) § 10115.10, or PCC § 4110 (applies to public works only).
11. To locate DVBE contractors:
a. Contact the department’s contracting official named in this solicitation for any DVBE contractors who may have identified themselves as potential subcontractors, and to obtain suggestions for search criteria to possibly identify DVBE contractors for the solicitation. You may also contact the department’s SB/DVBE Advocate for assistance – www.parks.ca.gov/advocate.
b. Access the list of all certified DVBEs by using the Department of General Services, Procurement Division (DGS-PD) online certified firm database at:
https://caleprocure.ca.gov/pages/PublicSearch/supplier-search.aspx?psNewWin=true
Search by “Keywords” or United Nations Standard Products and Services Codes (UNSPSC), that apply to the elements of work you want to subcontract to a DVBE.
c. Check for subcontractor ads that may be placed on the California State Contracts Register (CSCR) for this solicitation prior to the closing date. You may access the CSCR at:
www.Caleprocure.ca.gov
d. The State of California, Department of General Services, Procurement Division, Office of Small Business and DVBE Services (OSDS) offers many services that assist contractor/business owners with a variety of information designed to streamline the State contracting process. OSDS also certifies http://www.dgs.ca.gov/PD mailto:OSDSHelp@dgs.ca.gov http://www.parks.ca.gov/advocate https://caleprocure.ca.gov/pages/PublicSearch/supplier-search.aspx?psNewWin=true http://www.caleprocure.ca.gov/
b. DGS PD 843, DVBE Declaration
DPR 479IW (Rev. 10/2025)(Page 5 of 5)
a. GSPD 05-105, Bidder Declaration
DISABLED VETERAN BUSINESS ENTERPRISE (DVBE)
DVBE Documentation Checklist
1. The State of California acknowledges the service and sacrifice of its disabled veterans, in part, through the “Disabled Veteran Business Enterprise (DVBE) Participation Program.” As mandated bylaw, state agencies have a goal to award at least 3% of their annual contract dollars to certifiedDVBE’s.
2. When a firm bids on a state DPR contract that contains DVBE participation, the firm may benefit from the DVBE Incentive program. We encourage all suppliers to obtain as much DVBE participation as possible.
3. INCOMPLETE DOCUMENTATION (GSPD 05-105 AND DGS PD 843) WILL RESULT IN
DISQUALIFICATION FROM FURTHER PARTICIPATION IN THE SELECTION PROCESS FOR THE
CONTRACT.
4. The following checklist is provided to assist bidders with their DVBE participation documentation:
All DVBE participation is indicated.
The names of each participating DVBE company is listed with the corresponding percentage of the total bid price for the services/goods to be provided by each subcontractor.
A copy of the printout from eProcurement system showing the company’s DVBE certification status.
The DVBE participation percentage listed agrees with the dollar value claimed.
A completed and signed DGS PD 843 is included with the bid for every DVBE (whether prime contractor or subcontractor) included.
SCO ID: 3790 - C25720005
STATE OF CALIFORNIA - DEPARTMENT OF GENERAL SERVICES
STANDARD AGREEMENT
STD 213 (Rev. 04/2020)
1. This Agreement is entered into between the Contracting Agency and the Contractor named below:
CONTRACTING AGENCY NAME
CONTRACTOR NAME
2. The term of this Agreement is:
START DATE
THROUGH END DATE
3. The maximum amount of this Agreement is:
4. The parties agree to comply with the terms and conditions of the following exhibits, which are by this reference made a part of the Agreement.
Exhibits Title Pages
Exhibit A Scope of Work
Exhibit B Budget Detail and Payment Provisions
Exhibit C * General Terms and Conditions
Items shown with an asterisk (*), are hereby incorporated by reference and made part of this agreement as if attached hereto.
These documents can be viewed at https://www.dgs.ca.gov/OLS/Resources
IN WITNESS WHEREOF, THIS AGREEMENT HAS BEEN EXECUTED BY THE PARTIES HERETO.
CONTRACTOR
CONTRACTOR NAME (if other than an individual, state whether a corporation, partnership, etc.)
CONTRACTOR BUSINESS ADDRESS CITY STATE ZIP
PRINTED NAME OF PERSON SIGNING TITLE
CONTRACTOR AUTHORIZED SIGNATURE DATE SIGNED
STATE OF CALIFORNIA
CONTRACTING AGENCY NAME
Form Print Form
C25720005
Exhibit D Special Terms and Conditionns http://www.dgs.ca.gov/OLS/Resources
SCO ID: 3790 - C25720005 Form Print Form
STATE OF CALIFORNIA - DEPARTMENT OF GENERAL SERVICES
STANDARD AGREEMENT
STATE CONTRACTING AGENCY ADDRESS CITY
PRINTED NAME OF PERSON SIGNING
CONTRACTING AGENCY AUTHORIZED SIGNATURE DATE SIGNED
ZIP
EXEMPTION (If Applicable)
TITLE
CALIFORNIA DEPARTMENT OF GENERAL SERVICES APPROVAL
Contractor Name: TBD Contract #: C25720005
Exhibit A – Scope of Work
EXHIBIT A
SCOPE OF WORK
1. PROJECT SUMMARY
A. Contractor shall provide all labor, equipment, and materials required to provide septic pumping services (See Exhibit A, Attachment 1) in accordance with the work specifications. Services include:
1. Septic pumping for vaults and holding tanks
2. Emergency septic pumping
B. The Contractor shall coordinate with the State Representative by phone or email one (1) hour before arrival to the first site.
C. Term: The term of this contract is 36 months. If awarded, contract shall commence upon DGS - OLS approval, and terminate 36 months from approval, whichever is later.
D. The services will be performed at the following location(s):
Marina State Beach Restroom 200 Reservation Road, Marina, CA 93933
Marina State Beach Resources Office 61 Reservation Road, Marina, CA 93933
Marina State Beach Residence 71 Reservation Road, Marina, CA 93933
Carmel River State Beach – Monastery Beach 26478 Carmelo St, Carmel, CA 93923
Ishxenta State Park – Point Lobos Ranch entrance 53 Riley Ranch Road, Carmel, CA 93923
Ishxenta State Park – Gould Residence 54 Riley Ranch Road, Carmel, CA 93923
Ishxenta State Park – San Jose Creek 27953 San Jose Creek Canyon Road, Carmel, CA 93923
Residence 1 Residence 3
Exhibit A – Scope of Work
Point Lobos State Natural Reserve 62 CA-1 Carmel, CA 93923
Hudson House Entrance Kiosk Rat Hill Residence Whalers Cove Whalers Cabin Sea Lion Point Piney Woods Bird Island
Andrew Molera State Park 45500 CA-1, Big Sur, CA 93920
Day Use Trail Camp 1 Trail Camp 2 Residence #1 Bunkhouse Ranch House
Pfeiffer Big Sur State Park 47555 CA-1, Big Sur, CA 93920
Wastewater Treatment Plant
Julia Pfeiffer Burns State Park 52801 CA-1 Big Sur, CA 93920
Day Use Lot Residence
John Little State Natural Reserve 55420 CA-1, Big Sur, CA 93920
*Limekiln State Park 63025 CA-1 Big Sur, CA 93920
Lower Restroom Upper Restroom Residence/Shop
E. The rates specified in Exhibit B, Attachment 1 - Cost Sheet, shall stay in effect for the entire contract term.
F. Amendment: This contract shall be amended by mutual consent of both parties for additional time or money in the event of unforeseen circumstances.
Exhibit A – Scope of Work
Costs incurred shall be at the same rates as described in Exhibit B, Attachment 1 – Cost Sheet.
2. PROJECT REPRESENTATIVE(S)
A. The Contract Representative(s) during the term of this contract will be:
Representatives DPR State Representative Contractor’s Contract Administrator
Agency / Contractor Monterey District Contractor Name
Name and Title:
Jim Doran, District Facilities Chief
Address: 2211 Garden Road City, State, Zip: Monterey, CA, 93940 Phone Number: (831) xxx-xxxx E-mail Address
B. The State reserves the right to identify a State Representative or Designee in the absence of the DPR Contract Administrator.
C. Any changes in the Contractor’s Contract Administrator shall be immediately reported in writing no later than 5 business days to the DPR Contract Administrator or State Representative.
3. QUALIFICATION REQUIREMENTS
A. Contractor and/or Subcontractor must possess and maintain at all times during the term of this contract a valid Liquid Waste Hauler permit issued by the County of Monterey Health Department.
B. Services on equipment shall be performed by Trained and Certified Service Technicians. The contractor shall provide copies of Certifications upon request.
4. PERFORMANCE DETAILS
A. Contractor is responsible for supplying miscellaneous materials incidental to service, including safety materials needed or required to perform service at no additional charge to the State.
B. Any damage to existing facilities, utilities, or any State Park equipment (SCADA equipment) resulting from this work shall be reported immediately or within 24 hours of damage discovery to the DPR Contract Administrator or State Representative and must be repaired immediately by the Contractor to the satisfaction of the DPR Contract Administrator or State Representative at no cost to the State. Such repairs shall comply with all applicable provisions of this Agreement. The Contractor shall be responsible for any damage to their equipment caused by objects, garbage, or debris during pumping of the septic tank/vault and will be responsible for the repair/replacement of said equipment.
5. SERVICE DETAILS
A. Workdays, Hours, and State Holidays – Services shall be performed Monday – Friday from 8:00 am – 5:00 pm, excluding weekends and State observed holidays. Current State observed holidays are New Year’s Day, Martin Luther King Jr. Day, President’s Day, Cesar Chavez Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Indigenous People’s Day, Diwali, Veteran’s Day, Thanksgiving Day, Day after Thanksgiving Day, and Christmas Day. Emergency call-outs may require 24-hour response, 7 days a week.
B. Scheduling of Work: After the Agreement has been approved and accepted by both the State and Contractor, Contractor shall confer with the DPR Contract Administrator or State Representative to create a schedule of work.
C. During the term of this Agreement, and notwithstanding the described hours and calendar schedule, the DPR Contract Administrator or State Representative and Contractor shall mutually agree in writing to modify workdays or hours to reasonably accommodate the completion of the work.
6. WORK SPECIFICATIONS
Pumping Services
A. Pumping service is to be performed for each of the vaults and holding tanks listed in Exhibit A, Attachment 1 – Schedule of Services according to the specified schedule. Each service shall consist of completely pumping out the tank and appropriately hauling and discharging the sewage at the designated site specified in the Exhibit A – Scope of Work. Pumping and hauling discharge shall be done in such a manner to prevent spillage of any waste on the ground surrounding the units and shall meet all requirements of the Health and Safety Code of the State of California.
B. All objects, garbage and debris must be removed from holding tanks each time the tanks are pumped. Contractor is responsible for filtering and removal/disposal
C. of all non-waste items from inside tanks, vaults, and pit tanks on or upon pumping and cleaning unrelated to sewage, such as diapers, rags, rocks, syringes, small plastics, etc.
D. Tanks must be washed down with a high-pressure stream of water so compacted waste and toilet paper are broken down, and holding tanks cleaned out to prevent buildup of solids, scum, or sand/soil concentrations. State Parks provide the water by connecting to a nearby water source.
E. Servicing days shall be in accordance with Exhibit A, Attachment 1 or as requested in writing by the State Representative or Designee. When any regular service day falls on a State holiday, service shall be required the next business day. Services shall be completed by 5:00 PM on the scheduled days.
F. Pumped waste from tanks and/or vaults serviced shall be transported by the Contractor to their designated discharge site as required by law.
7. EMERGENCY SERVICE CALLS
A. When contacted by the State Representative or Designee, the Contractor shall respond as soon as possible to the service site with all necessary labor, tools, and equipment to perform pumping when the service is identified as an emergency.
An emergency is defined as a tank that is full or when there is an imminent threat of raw sewage exposure.
B. The Contractor shall furnish the State Representative with telephone number(s) for 24-hour contact.
C. The Contractor must respond to emergencies within 4 (four) hours of the initial State Representative’s phone call.
D. Emergency services shall be paid at the rates specified in Exhibit B, Attachment 1
– Cost Sheet Table 2.
E. Additional “emergency” services may be requested by the State Representative or Designee. Payment for such emergency service will be in accordance with Exhibit B, Attachment 1 – Cost Sheet
8. ADDITIONAL SPECIFICATIONS
A. Any spillage must be cleaned up and affected areas disinfected by the Contractor prior to leaving the job site.
B. The Contractor shall conduct their operations in a safe and responsible manner so as not to jeopardize the health and safety of themselves, their employees, park visitors or State employees. The Contractor shall follow OSHA regulations as they apply to accomplishing the services of this contract.
9. INSPECTIONS BY STATE AND RECORD OF SERVICE
A. At completion of each service, the Contractor or their service agent shall provide the State Representative with a signed statement verifying the date and time services were completed. The Contractor or their service agent may at his/her option make the statement in duplicate and obtain signature of the State Representative to verify the preparation and submission of the statement to the State Representative.
B. Service equipment shall meet all requirements of the Health and Safety Code of the State of California and of any local code in which the equipment operates.
Exhibit A, Attachment 1 - Schedule of Services
EXHIBIT A, ATTACHMENT 1
SCHEDULE OF SERVICES
Servicing of septic vault/tank pumping under this agreement shall be performed at the following locations, in accordance with Exhibit A – Scope of Work, at the rates listed in Exhibit B, Attachment 1 – Cost Sheet. This Schedule of Services lists the regularly scheduled services to be performed during the term of this agreement. Additional services may be requested as needed by the State’s Representative at the rates provided on Exhibit B, Attachment 1 – Cost Sheet, Section 2.
Location within Park Unit: Monterey
Vault Size
Service Frequency for 36 Months
Contract Marina State Beach - Pump Lift Station
1,000 Gallons (2 Pump Lift Station)
Marina State Beach - Resources Office and Residence Building
500 Gallons (1 Pump Lift Station)
Carmel River State Beach - Monastery Beach
4,000 Gallons
Ishxenta State Park - Lift Station Main Pumps
500 Gallons
Ishxenta State Park – Gould Residence Septic Line
1500 Gallons (Septic Line)
Ishxenta State Park - San Jose Creek Residence #1 Septic Line
1,500 Gallons
Ishxenta State Park - San Jose Creek Residence #3 Septic
Point Lobos State Natural Reserve - Hudson House Lift Station
200 Gallons
Point Lobos State Natural Reserve - Kiosk Lift Station
3,000 Gallons
Point Lobos State Natural Reserve - Rat Hill Residence Septic
Point Lobos State Natural Reserve - Whalers Cove Lift Station
1,000 Gallons
Point Lobos State Natural Reserve – Whalers Cabin Septic
Point Lobos State Natural Reserve - Sea Lion Point Lift Station
2,500 Gallons
Point Lobos State Natural Reserve - Piney Woods Lift Station
Point Lobos State Natural Reserve - Bird Island Lift Station
Location within Park Unit: Big Sur Vault Size
Service Frequency for 36 Months
Contract Andrew Molera State Park - Day Use Septic
Andrew Molera State Park – Trail Camp # 1
Andrew Molera State Park – Trail Camp # 2
Andrew Molera State Park - Residence #1
2,800 Gallons
Andrew Molera State Park – Bunkhouse
Andrew Molera State Park – Ranch House
Pfeiffer Big Sur State Park Lift Station
(Lift Station)
Pfeiffer Big Sur State Park – Wastewater Treatment Plant Digester
10,000 Gallons (Septic Digester)
Julia Pfeiffer Burns State Park – Day Use
(Septic line)
Julia Pfeiffer Burns State Park Residence
John Little State Natural Reserve – Residence Septic
*Limekiln State Park – Lower Restroom
*Limekiln State Park – Upper Restroom
*Limekiln State Park – Residence/Shop
2,000 Gallons
*The CA-1 highway closure in Big Sur, Regent’s landslide, is anticipated to re-open in March 2026. Currently, direct southbound access to Limekiln State Park is not possible. Limekiln State Park can be accessed from CA-1 northbound from San Luis Obispo County. Check DOT (Department of Transportation/Caltrans) District 5 for current road conditions. See map below.
Exhibit A, Attachment 2 - Site Map
EXHIBIT A, ATTACHMENT 2
SITE MAP
MONTEREY LOCATIONS
Marina State Beach (2 locations)
Carmel River State Beach
Ishxenta State Park (4 locations)
Point Lobos State Natural Reserve (8 locations)
Exhibit A, Attachment 2 - Site Map
BIG SUR LOCATIONS
Andrew Molera State Park (6 locations)
Pfeiffer Big Sur State Park (2 locations)
Julia Pfeiffer Burns State Park (2 locations)
John Little State Natural Reserve
Limekiln State Park (3 locations) *The CA-1 highway closure, Regent’s landslide, is anticipated to re-open in March 2026. Currently, direct southbound access to Limekiln State Park is not possible. Limekiln State Park can be accessed from CA-1 northbound from San Luis Obispo County. Check DOT (Department of Transportation/Caltrans) District 5 for current road conditions. Refer to map on Exhibit A, Attachment 1 – Schedule of Services, Page 5).
Exhibit B – Budget Detail and Payment Provisions
EXHIBIT B
BUDGET DETAIL AND PAYMENT PROVISIONS
1. INVOICING AND PAYMENT
A. For services satisfactorily rendered, and upon receipt and approval of the invoices, the State agrees to compensate the Contractor in accordance with the rates specified in Exhibit B, Attachment 1, Chemical Toilet Rental and/or Service Bid Form, which is attached hereto and made part of this agreement.
B. Invoices shall include the Agreement number and shall be submitted not more frequently than monthly in arrears to:
Department of Parks and Recreation
Attention: Accounting Office
2211 Garden Road Monterey, CA 93940
Monterey.AdminStaff@parks.ca.gov
Should an invoice be disputed, Contractor will correct any/all disputed items on the invoice and resubmit the invoice as indicated above. Failure to provide and resubmit corrected invoice will result in a delay of payment.
2. BUDGET CONTINGENCY…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .