Bid sheet.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Contractor shall remove and replace 4 fan coil units at the Clinton Indian Health Center
- Solicitation number
- 246-23-Q-0045
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF25A-16d (1).pdf | ||
| SF24-16d (1).pdf | ||
| ok70.txt | TXT text file | |
| SF25-16d1 (1).pdf | ||
| OF306AddendumToDeclarationForFederalEmployment-04.2025.pdf | ||
| RFQ - Commercial Clauses updated JE 2-10-23.docx | DOCX document | |
| OF306.pdf | ||
| SF1449-Commercial Solicitation-Award.pdf | ||
| SOW_Clinton FCU Replacement 2023 r1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IGCE
| HHS IGCE TEMPLATE | |
| PROJECT TITLE: | Replace 4 Split Systems in Server Room at Clinton HIS |
| Detailed Price Summary | 2/2/23 |
| Contract Line Item Description | Base Period | ||||
| Quantity | Unit | Unit Price | Total Price | ||
| Commercial service to remove and replace condenser units and air handlers per the SOW | |||||
| 6 | Materials: | EA | |||
| 7 | Condensing units | 4.00 | EA | ||
| 8 | Fan coil units | 4.00 | EA | ||
| 9 | line sets wit insulation | 1.00 | EA | ||
| 10 | refrigerant | 1.00 | EA | ||
| 11 | disconnects | 1.00 | EA | ||
| 12 | breakers | 4.00 | EA | ||
| 13 | wiring | 1.00 | EA | ||
| 14 | drain pans | 1.00 | EA | ||
| 15 | insulation | 1.00 | EA | ||
| 16 | wet switches | 1.00 | EA | ||
| 17 | low ambient controls | 1.00 | EA | ||
| 18 | fan cycling switches | 1.00 | EA | ||
| install condensing nits on adjustable risers units must not be installed in direct contact with roof | 1.00 | EA | |||
| Crene for removal and replacement of units | 1.00 | EA | |||
| drain pans | 1.00 | EA | |||
| wet switches for all coil units | 1.00 | EA | |||
| flush existing condensate drains prior to use | 1.00 | EA | |||
| Integrare existing WebCtrl sensors into new units | 1.00 | EA |
| 19 | |||
| Line Item Subtotal | $ - 0 | ||
| Fringe Benefits | ERROR:#REF! | ||
| Subtotal Line Item & Fringe | ERROR:#REF! | ||
| Overhead/Fringe Benefits | $ - 0 | ||
| Subtotal Line Items, Fringe and Overhead | ERROR:#REF! | ||
| $ - 0 | |||
| $ - 0 | |||
| $ - 0 | |||
| $ - 0 | |||
| Subtotal - All Costs | ERROR:#REF! | ||
| Fee/Profit | |||
| Total Cost | |||
| Bonds | |||
| Total Estimated Yearly Values | |||
| TOTAL ESTIMATED VALUE OF CONTRACT | ERROR:#REF! |