Bid Sheet 2026 Bag Wall District 11 and 12.xlsx
XLSX spreadsheet 16 KB Posted
- Solicitation number
- RFB 605 2600000683 3
- Issued by
- Kentucky
About this file
This is a bid sheet for RFB 605 2600000683 for Polypropylene Barrier Wall Construction in Districts 11 and 12 in Kentucky. The solicitation requests vendors to submit bids for the mobilization, foundation preparation, and installation of polypropylene barrier walls with varying heights (2 feet through 6 feet), along with supporting services including concrete placement, traffic control, and erosion control. District 11 requires 2,215 linear feet of barrier wall installation across multiple height specifications, while District 12 requires 2,415 linear feet. Additional line items include mobilization (15 lump sum units for each district), foundation preparation work (10-15 linear feet of non-yielding and 5 linear feet of yielding for each district), concrete placement using transfer pumps or pump trucks (75-100 hours each district), traffic control (15-25 days each district), 6-inch minus stone aggregate (1,500 tons each district), Class III channel lining (150 tons each district), Class B concrete (1,000 cubic yards each district), and long reach trackhoe equipment rental (50 hours each district). Vendors are instructed to enter actual bid prices and response times on the sheet and upload responses into the e-procurement system.
Vendors must bid all line items for each district in which they wish to provide services and are not required to bid all districts. The bid sheet requires vendors to specify their years of experience in providing similar services. All materials, equipment, and labor are included in the respective bid line items, with specifications requiring compliance with current KYTC standards and MUTCD requirements where applicable. Concrete must meet the most current edition of KYTC Standard Specifications, and the state reserves the right to supply fill material using other master agreements. No specific bid submission deadline, award date, contract term, or funding source information is provided on this bid sheet.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFB 605 2600000683 Polypropylene Barrier Wall Construction | |
| Vendor: | Vendor Rep: |
Instructions: Actual bid prices and response time must be entered on this bid sheet and uploaded into the e-procurement system. Vendors shall bid all line items for each district for which they wish to provide services. A vendor is not required to bid all districts.
| Vendor guarantees ___ years of experience in providing similar services as requested in this solicitation. | ||||||||||
| District 11 | District 12 | |||||||||
| Bid Item | Extended Description | Estimated Qty | UOM | Unit Price | Ext Price | Estimated Qty | UOM | Unit Price | Ext Price | |
| Line 1 | Mobilization | This item will be for mobiliizing all materials and equipment to construct barrier wall as required in the specs. | 15 | LS | 15 | LS | ||||
| Line 2 | Foundation Preparation-Non-Yeilding | This item includes all equipment, labor and materials needed to excavate project site necessary to install barrier wall. If a hoe ram is needed, it will be incidental to this bid item. Any tree removal will be incidental to this bid item. | 10 | LNFT | 10 | LNFT | ||||
| Line 3 | Foundation Preparation-Yeilding | This item includes all equipment, labor and materials needed to excavate project site necessary to install barrier wall. If a hoe ram is needed, it will be incidental to this bid item. Any tree removal will be incidental to this bid item. | 5 | LNFT | 5 | LNFT | ||||
| Line 4 | 2' Bags | This item will include all equipment, labor and materials needed to install barrier wall on project site. Includes but not limited to materials for bags, ties to tie bags together when needed. All labor needed to install bags. All equipment necessary to install bags include sled (any apparatus to hold bags in place while concrete is poured in them). | 1000 | LNFT | 1000 | LNFT | ||||
| Line 5 | 3' Bags | This item will include all equipment, labor and materials needed to install barrier wall on project site. Includes but not limited to materials for bags, ties to tie bags together when needed. All labor needed to install bags. All equipment necessary to install bags include sled (any apparatus to hold bags in place while concrete is poured in them). | 200 | LNFT | 500 | LNFT | ||||
| Line 6 | 4' Bags | This item will include all equipment, labor and materials needed to install barrier wall on project site. Includes but not limited to materials for bags, ties to tie bags together when needed. All labor needed to install bags. All equipment necessary to install bags include sled (any apparatus to hold bags in place while concrete is poured in them). | 600 | LNFT | 500 | LNFT | ||||
| Line 7 | 5' Bags | This item will include all equipment, labor and materials needed to install barrier wall on project site. Includes but not limited to materials for bags, ties to tie bags together when needed. All labor needed to install bags. All equipment necessary to install bags include sled (any apparatus to hold bags in place while concrete is poured in them). | 200 | LNFT | 200 | LNFT | ||||
| Line 8 | 6' Bags | This item will include all equipment, labor and materials needed to install barrier wall on project site. Includes but not limited to materials for bags, ties to tie bags together when needed. All labor needed to install bags. All equipment necessary to install bags include sled (any apparatus to hold bags in place while concrete is poured in them). | 200 | LNFT | 200 | LNFT | ||||
| Line 9 | Concrete Placement-Transfer Pump or Other Mechanical Support | This item is for any mechanical means of support to place Class B Concrete such as a transfer line truck, conveyor belt or other mechanical. A pump truck will be paid as a separate line item. Minimum of 8 hours per delivery order. | 75 | HR | 100 | HR | ||||
| Line 10 | Concrete Placement-Pump Truck | This item will be for a pump truck to place Class B Concrete. This item also includes all material, labor, and oversight necessary for operating the pump truck and discharging the material into the polypropylene barrier wall apparatus. Minimum of 8 hours per delivery order will be paid. | 75 | HR | 75 | HR | ||||
| Line 11 | Traffic Control | Provide traffic control that meets most current standards in the KYTC Specifications, MUTCD and Standard Drawing. Flaggers will be incidental to this bid item. Any flaggers must have flagger certification. While traffic is still driving through workzone, vendor shall keep roadway clear of debris. | 15 | DAY | 25 | DAY | ||||
| Line 12 | 6" Minus Stone | aggregate that must pass through a six inch opening. | 1500 | TON | 1500 | TON | ||||
| Line 13 | Class III Channel Lining | Will be used for erosion control. Item includes material, labor and equipment to install channel lining. | 150 | TON | 150 | TON | ||||
| Line 14 | Class B Concrete | Must meet most current edition of KYTC Standard Specifications. Item will include materal and coordination for supplying concrete to project site. KYTC still reserves the right to opt to supply the fill material using other master agreements. | 1000 | CY | 1000 | CY | ||||
| Line 15 | Long Reach Trackhoe | Shall be a CAT 320 or equivalent. Shall be capable of reaching at least 40 feet. 8 hour minimum per delivery order will be paid. | 50 | HR | 50 | HR | ||||
| TOTAL | $0.00 | TOTAL | $0.00 |
# of Days to Start Work: # of Days to Start Work:
Sheet2
Sheet3
File details come from the government source that posted it. Updated .