About this file

This is a Bid Set and Project Manual for a water main replacement project issued by the City of Umatilla, Florida, in conjunction with the Florida Department of Environmental Protection (DEP). The project, designated ITB-26-PW-001 and DEP Agreement No. L0360, involves furnishing all labor, equipment, and materials to construct approximately 2,540 linear feet of 6-inch PVC water main and 1,450 linear feet of 10-inch PVC/FPVC water main (utilizing both conventional installation and directional drilling methods), install fire hydrants and associated appurtenances, cut and cap existing mains, reconnect existing water services, and complete associated restoration work. A mandatory pre-bid conference is scheduled for October 15, 2026, at 2:00 PM at Umatilla City Hall. Sealed bids must be received by 2:00 PM on Thursday, October 29, 2026, at the City of Umatilla, 1 South Central Avenue, Umatilla, Florida 32784. The bid opening will occur immediately thereafter on the same date. The City of Umatilla Council is scheduled to award the contract on November 17, 2026. The work must be substantially completed within 120 days and fully completed and ready for final payment within 150 days after the contract effective date. Bidders must attend the pre-bid conference to be eligible to submit a bid.

Bidders must be licensed by the Florida Construction Industry Licensing Board and must have successfully completed a minimum of three similar water main installation and/or replacement projects within the past five years as the prime contractor, each with a minimum contract value of $500,000, with at least one project exceeding $750,000. Bid security equal to 5 percent of the maximum bid price (base bid plus all additive alternates) must be submitted in the form of a bid bond. Progress payments will be made monthly at 95 percent of completed work value with 5 percent retainage, and payment will be made by approximately the 25th of each month. Upon substantial completion, the contractor will receive payment bringing total payments to 95 percent of work completed, less any retainage and punch list items. Interest accrues on unpaid amounts at the rate of 1/12th of the federal prime interest rate per month. Liquidated damages are assessed at $400 per day for delays beyond the 120-day substantial completion deadline and $250 per day for delays beyond the 150-day final completion deadline. The bid form includes unit price line items for mobilization, water main installation (conventional and directional drill methods), fittings, valves, fire hydrants, tapping sleeves, cutting and capping existing mains, service reconnections, pavement and concrete restoration, grassing and seeding, and testing and disinfection, with an additive alternate for GPR (Ground Penetrating Radar) service. Bidding documents are available through the issuing office, CPH Consulting, LLC, and through myVendorlink.com as of September 24, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida License No. 3215

Project Manual

DEP Water Main Replacements, Phase II

DEP Agreement No. L0360

City of Umatilla, Florida

Project No. 2501913

Client No. 1402-07-1

September 2026

BID SET

Prepared by:

PROJECT MANUAL

FOR

DEP WATER MAIN REPLACEMENTS, PHASE II

DEP AGREEMENT NO. L0360

CITY OF UMATILLA, FLORIDA

Florida License No. 3215

Orange Park, Florida Project No. 2501913 Client No. 1402-07-1

September 2026

1402-07-1 ii Table of Contents

DEP AGREEMENT NO. LPA0400

TABLE OF CONTENTS

DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS

00111 Advertisement for Bids

00200 Instructions to Bidders

00410 Bid Form

00430 Bid Bond

00520 Standard Form of Agreement

00610 Performance Bond

00615 Payment Bond

00620 Contractor's Application for Payment

00700 General Conditions

00800 Supplementary Conditions

00814 Sworn Statement Under Section 287.133(3)(a), Florida Statutes, on

Public Entity Crimes

00900 Addenda and Modifications

DIVISION 1 - GENERAL REQUIREMENTS

01060 Regulatory Requirements

01150 Measurement and Payment

01300 Submittals

01301 Administrative Requirements

1402-07-1 iii Table of Contents

01391 Visual Documentation

01400 Quality Control

01500 Construction Facilities

01570 Temporary Traffic Control

01700 Project Closeout

DIVISION 2 - SITE WORK

02230 Site Clearing, Stripping, and Grubbing

02240 Dewatering

02300 Earthwork

02310 Finish Grading

02370 Erosion and Sedimentation Control

02441 Directional Drill

02510 Pipe Work - Water Distribution System

02590 Underground Facilities

02750 Concrete Paving, Sidewalk, and Curb

02921 Grassing, Seeding, and Sodding

02960 Asphaltic Pavement and Concrete Replacement

DIVISION 3 - CONCRETE

Not Applicable

DIVISION 4 - MASONRY

1402-07-1 iv Table of Contents

DIVISION 5 - METALS

DIVISION 6 - WOOD AND PLASTICS

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

DIVISION 8 - DOORS AND WINDOWS

DIVISION 9 - FINISHES

DIVISION 10 - SPECIALTIES

DIVISION 11 - EQUIPMENT

DIVISION 12 - FURNISHINGS

12345 Metal Laboratory Casework

DIVISION 13 - SPECIAL CONSTRUCTION

1402-07-1 v Table of Contents

DIVISION 14 - CONVEYING SYSTEMS

DIVISION 15 - MECHANICAL

DIVISION 16 - ELECTRICAL

1402-07-1 00111-1 Invitation to Bid

CITY OF UMATILLA

DEP WATER MAIN REPLACEMENTS, PHASE 2, DEP AGREEMENT NO. L0360

INVITATION TO BID

PROJECT NAME: DEP WATER MAIN REPLACEMENTS, PHASE II, DEP AGREEMENT NO. L0360

CITY BID NO: ITB-26-PW-001

OWNER: CITY OF UMATILLA, FLORIDA

SCOPE OF WORK: Furnishing all labor, equipment, and materials necessary to construct approximately 2,540 LF of 6” PVC water main, 1,450 LF of 10” PVC/FPVC (conventional installation/directional drill) water main, fire hydrants, associated appurtenances, cutting and capping existing mains; reconnection of existing water services; connection to existing mains; and associated restoration.

MANDATORY PRE-BID CONFERENCE: October 15, 2026, 2:00 PM. Umatilla City Hall. 1 S. Central Ave., Umatilla, FL 32784

RECEIPT OF BIDS: Sealed bids marked “DEP Water Main Replacements, Phase 2” for the work described herein shall be received until 2 p.m., on Thursday, October 29, 2026, at the City of Umatilla, 1 South Central Avenue, Umatilla, Florida 32784, at which time and place bids will be publicly opened and read aloud. ALL BIDS, WHETHER HAND DELIVERED OR MAILED, MUST BE AT UMATILLA CITY HALL BEFORE THE ABOVE-STATED DEADLINE TO BE CONSIDERED. PLEASE PROVIDE ONE (1) ORIGINAL BID AND BID SECURITY. ELECTRONIC OR

FACSIMILE SUBMITTALS WILL NOT BE ACCEPTED.

INFORMATION REGARDING BIDDING MATERIAL, ETC: The Issuing Office for the Bidding Documents is CPH Consulting, LLC., 580-1 Wells Road, Orange Park, Florida 32073, (904) 278-0030. Prospective Bidders may examine the Bidding Documents at the Issuing Office, Monday through Friday (excluding holidays), or Umatilla City Hall, 1 South Central Avenue, Umatilla, Florida 32784.

Prospective Bidders may access and download the Bidding Documents online at www.cphcorp.com upon submission of contact information and registering as a Plan Holder. Partial sets of Bidding Documents will not be available from the Issuing Office. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including addenda, if any, obtained from sources other than the Issuing Office.

Complete plans and specifications may also be obtained from myVendorlink.com. These plans and specifications will be available on September 24, 2026.

Bid security shall be furnished in accordance with the Instructions to Bidders.

To be considered qualified, Bidder must be licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board and must have successfully completed, as prime contractor, a minimum of

(3) projects of a similar nature, involving water main installation and/or replacement within the past (5) years, each having a minimum contract value of $500,000, with at least one project having a contract value in excess of $750,000.

PROJECTED TIMELINE:

ADVERTISEMENT PUBLISHED: September 24, 2026 MANDATORY PRE-BID MEETING: October 15, 2026, 2:00 PM. Umatilla City Hall. 1 S. Central Ave., Umatilla, FL 32784 DEADLINE FOR REQUEST FOR INFORMATION BY PLANHOLDERS: October 15, 2026 BID DEADLINE: October 29, 2026, 2:00 p.m.

BID OPENING: October 29, 2026 BID AWARD BY UMATILLA CITY COUNCIL: November 17, 2026

The City reserves the right to waive informalities in any bid, to reject any and all Bids or portions of Bids, with or without cause, and to accept the bid that in its judgment will be for the best interest of the City.

The City of Umatilla, Florida is an Equal Opportunity Employer.

Modified per CPH Consulting, LLC EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-1 Instructions to Bidders

SECTION 00200

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1 — Defined Terms

Article 2— Bidding Documents

Article 3 — Qualifications of Bidders

Article 4 — Pre-Bid Conference

Article 5 — Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6 — Bidder’s Representations and Certifications

Article 7 — Interpretations and Addenda

Article 8 — Bid Security

Article 9 — Contract Times

Article 10 — Substitute and “Or Equal” Items

Article 11 — Subcontractors, Suppliers, and Others

Article 12 — Preparation of Bid

Article 13 — Basis of Bid

Article 14 — Submittal of Bid

Article 15 — Modification and Withdrawal of Bid

Article 16 — Opening of Bids

Article 17 — Bids to Remain Subject to Acceptance

Article 18 — Evaluation of Bids and Award of Contract

Article 19 — Bonds and Insurance

Article 20 — Signing of Agreement

Article 21 — Sales and Use Taxes

Article 22 — Contracts to Be Assigned

Article 23 — Wage Rates

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-2 Instructions to Bidders

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued and which registers plan holders.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Engineer has established a Bidding Documents Website as indicated in the Advertisement for Bids.

Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by (Engineer) (Owner).

2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents or make them available for examination.

Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.

2.05 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe Portable Document Format (.pdf). It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-3 Instructions to Bidders

Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

C. After the Contract is awarded, the Owner will provide or direct the Engineer to provide for the use of the Contractor documents that were developed by Engineer as part of the Project design process, as Electronic Documents in native file formats.

1. Electronic Documents that are available in native file format include:

a. CAD Drawings

2. Release of such documents will be solely for the convenience of the Contractor. No such document is a Contract Document.

3. Unless the Contract Documents explicitly identify that such information will be available to the Successful Bidder (Contractor), nothing herein will create an obligation on the part of the Owner or Engineer to provide or create such information, and the Contractor is not entitled to rely on the availability of such information in the preparation of its Bid or pricing of the Work. In all cases, the Contractor shall take appropriate measures to verify that any electronic/digital information provided in Electronic Documents is appropriate and adequate for the Contractor’s specific purposes.

4. In no case will the Contractor be entitled to additional compensation or time for completion due to any differences between the actual Contract Documents and any related document in native file format.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 To be considered qualified, bidder shall be licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board. Additionally, a qualified bidder shall have successfully completed as prime contractor, a minimum of (3) projects of a similar nature, involving water main installation and/or replacement, within the past (5) years, each having a minimum contract value of $500,000, with at least one (1) project having a contract value in excess of $750,000. To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within five (5) days of Owner’s request, Bidder must submit the following information:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. Evidence that Bidder is authorized to do business in the state where the Project is located.

C. Bidder’s State of Florida contractor license number.

D. Subcontractor and Supplier qualification information.

E. List of similar projects completed within the most recent five (5) years. Provide brief description of project, date completed, original contract amount, final contract amount, contact names and phone numbers of Owners and Engineers.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-4 Instructions to Bidders

F. List of currently active projects with project description, contract amount, percent complete, contact names and phone numbers of Owners and Engineers.

G. Other required information regarding qualifications.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A mandatory pre-bid conference will be held at the time and location indicated in the Advertisement for Bids. Representatives of Owner and Engineer will be present to discuss the Project. Proposals will not be accepted from Bidders who do not attend the conference. It is each Bidder’s responsibility to sign in at the pre-bid conference to verify its participation. Bidders must sign in using the name of the organization that will be submitting a Bid. A list of qualified Bidders that attended the pre-bid conference and are eligible to submit a Bid for this Project will be issued in an Addendum. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions – No Reports Available

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-5 Instructions to Bidders

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

4. Geotechnical Report: The Bidding Documents do not contain a Geotechnical Report

(GR).

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. A site visit has not been pre-scheduled outside of the mandatory pre-bid meeting. Bidders shall use contact information in Paragraph 5.04 D to arrange access.

C. Bidders visiting the Site are required to arrange their own transportation to the Site.

D. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner contact for visiting the Site: Aaron Mercer, City Manager, (352) 669-3125. Bidder must conduct the required Site visit during normal working hours.

E. Bidder is not required to conduct any subsurface testing or exhaustive investigations of Site conditions.

F. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

G. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-6 Instructions to Bidders schedule, access, existing operations, security, liability insurance, and applicable safety programs.

H. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program – Not Applicable

5.06 Other Work at the Site – Not Applicable

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner, on its own initiative, may issue Addenda to clarify, correct, supplement, or change non-technical aspects of the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:

A. Jarrod P. Petrohovich, P.E., jarrod.petrohovich@cphcorp.com; Amanda Bourke, amanda.bourke@cphcorp.com

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven (7) days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5% of Bidder’s maximum Bid price (determined by adding the base bid and all additive alternates) and in the form of a Bid Bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid Bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid mailto:jarrod.petrohovich@cphcorp.com mailto:amanda.bourke@cphcorp.com

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-7 Instructions to Bidders security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 business days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum Bid Bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.03 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for all major component and construction disciplines of the Work within five (5) days after Bid opening.

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-8 Instructions to Bidders information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in non-erasable ink and the Bid Form signed in non-erasable ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½-inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature). The corporate address and state of incorporation must be shown.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature). The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-9 Instructions to Bidders

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located in the form of a valid business license number, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 After bid opening, Owner may request evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract.

12.13 Bidder must be licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board. Bidder’s state contractor license number must be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

13.02 Allowances - Not applicable

ARTICLE 14—SUBMITTAL OF BID

14.01 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement for Bids and must be enclosed in a plainly marked package with the Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the City of Umatilla, 1 South Central Avenue, Umatilla, FL 32784

14.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-10 Instructions to Bidders correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

14.03 Bids may not be submitted electronically.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the Advertisement for Bids and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00200-11 Instructions to Bidders

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE (TYPE “NOT APPLICABLE” IF BONDS NOT REQUIRED)

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing Bid Bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one (1) fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES – NOT APPLICABLE

ARTICLE 22—CONTRACTS TO BE ASSIGNED – NOT APPLICABLE

ARTICLE 23 – WAGE RATES – NOT APPLICABLE

END OF SECTION

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00410-1 Bid Form

SECTION 00410

BID FORM

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—BIDDER

SUBMITTED BY: DATE:

Company Name (printed or typed)

Address

City, State, Zip

BIDDER’S CONTACT:

Name

PHONE NO.:

EMAIL ADDRESS:

CONTRACTOR’S FLORIDA LICENSE NO.:

ARTICLE 2—OWNER

2.01 This Bid is submitted to:

City of Umatilla 1 South Central Avenue Umatilla, FL 32784

2.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 3—ATTACHMENTS TO THIS BID

3.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign;

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00410-2 Bid Form

ARTICLE 4—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

4.01 Unit Price Bids

A. Bidder will perform the following Work at the indicated unit prices:

Item No.

Description

Est.

Qty

Unit

Bid Unit Price

Bid Amount

1 Mobilization & General Conditions 1 LS $

2 Water Main, Conventional Install a 6” PVC 2,540 LF $ b 10” PVC 580 LF $

3 Water Main, Horizontal Directional Drill a 10” FPVC 870 LF $

4 Ductile Iron Fittings, Cement Lined 900 LBS $

5 Gate Valve and Box a 10” Gate Valve 1 EA $

6 2” Line Stop 1 EA $

7 Fire Hydrant Assembly 2 EA $

8 Tapping Sleeve and Valve a 6” x 6” 5 EA $ b 10” x 10” 2 EA $

9 Cut & Cap Existing Mains a 2” 9 EA $

10 Water Main Branch Connection a 2” Type B 1 EA $

11 Reconnect Existing Water Services a Short 11 EA $ b Long 15 EA $

12 Asphaltic Pavement Restoration 190 LF $

13 Asphaltic Driveway Restoration 40 SY $

14 1” Asphaltic Roadway & Mill Overlay 40 SY $

15 Concrete Curb/Driveway/Sidewalk Restoration 120 LF $

16 Stabilized Roadway/Driveway Restoration 430 LF $

17 Grassing a Seeding 2,000 LF $ b Sodding 2,000 LF $

18 Removal of Unsuitable Materials 25 LF $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00410-3 Bid Form

Item No.

Description

Est.

Qty

Unit

Bid Unit Price

Bid Amount

19 Flushing, Pressure Testing, Disinfection 1 LS $

20 Demobilization 1 LS $

BASE BID TOTAL $

21 Additive Alternate No. 1 – GPR Service 1 LS $

TOTAL BID (Base Bid Total + Additive Alternate No. 1) $

B. Bidder acknowledges that:

1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and

2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.

ARTICLE 5—TIME OF COMPLETION

5.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

5.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 6—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

6.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

6.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

6.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 7—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

7.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00410-4 Bid Form

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

12. Bidder is licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board.

7.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00410-5 Bid Form

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 7.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By: Attest:

(individual’s signature) (individual’s signature)

Name: Name:

(typed or printed) (typed or printed)

Title: Title:

Date: Date:

Address for giving notices:

Bidder’s Business License No. _____________________________________________________________

Affix corporate seal, if applicable.

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00430-1 Bid Bond

SECTION 00430

BID BOND (PENAL SUM FORM)

Bidder Surety

Address (principal place of business): Address (principal place of business):

Owner Bid

Name: City of Umatilla, Florida Project (name and location):

Address (principal place of business): DEP Water Main Replacements, Phase II DEP Agreement No. L0360 Umatilla, Florida

1 South Central Avenue Umatilla, FL 32784

Bid Due Date:

Bond: 5% of Maximum Bid (Base Bid plus Alternates)

Bond No.:

Penal Sum:

Date of Bond:

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of Attorney)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest: Attest:

(Signature) (Signature) Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1402-07-1 00430-2 Bid Bond

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors,…