Bid_Scope_Materials_List.docx

DOCX document 18 KB Posted

Attached to
NED Home Rehab - 28 Archer Ave
Solicitation number
NED-S-28-031626
Issued by
Escambia County, Florida

About this file

This is a Bid Scope Materials List for a residential rehabilitation project issued by Escambia County, Florida's Neighborhood Enterprise Division under the State Housing Initiatives Partnership (SHIP) program for 28 Archer Avenue. The scope specifies detailed product requirements across kitchen, bathroom, flooring, mechanical, electrical, and structural categories, including branded items such as Delta faucets, GE appliances, Whirlpool refrigerator, American Standard bathroom fixtures, Shaw flooring, Hunter ceiling fan, Broan ventilation units, and CertainTeed roofing materials. The project includes mandatory work on plumbing fixtures with new braided supply lines and shutoff valves, drywall repairs with complete finishing (tape, mud, texture, and paint), electrical repairs, and optional flooring replacement with luxury vinyl plank. A mandatory pre-bid meeting is scheduled for March 31, 2026, at 10:00 AM at the project site, with questions due by April 8, 2026, at 1:00 PM and bids due by April 9, 2026, at 1:00 PM through the OpenGov portal only. Contractor selection is anticipated for April 10, 2026, and all bids must remain valid for 180 days from submission.

Pricing must be submitted as a lump sum with firm unit pricing itemized by line item, including all labor, overhead, permits, insurance, and profit. The contract specifies that contractors may use like, similar, or equal valued products as approved alternatives to the specified materials. Payment is structured as 100% upon completion for projects under $15,000; for projects exceeding $15,000, contractors receive a 40% draw upon NED confirmation of 50% work completion, a substantial completion draw of 150% minus uncompleted line-item costs within 20 business days, and final payment upon satisfaction of completion, inspections, homeowner acceptance, and warranty provisions. All work must comply with Escambia County Building Code with a mandatory 60-day completion timeline and liquidated damages assessed at $150 per day for delays. Eligible contractors must be licensed, insured, and in good standing with the County; projects valued at $25,000 or higher require 100% Performance and Payment Bonds. Required qualifications include state contractor licenses, county competency and business licenses, current Worker's Compensation and Commercial General Liability coverage of at least $1,000,000, EPA RRP certification, verification of non-debarred status through sam.gov, E-Verify enrollment, and drug-free workplace certification. No set-asides or incumbent vendors are identified.

View the file

Other files

File Type Posted
NED_Home_Rehab_-_28_Archer_Ave.pdf PDF
SCOPE_-_SHIP_-_28_Archer_Ave_-_Oliver_L.docx DOCX document
Bid_Scope_Materials_List.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Scope Materials List

Kitchen SinkDouble bowl aluminum drop-in.
Kitchen FaucetDelta, Savile pull-down
RangeGE, JB645RKSS
CooktopGE, JP3030DJBB
Micro-VentedGE, JVM3160RFSS
Hood VentBroan, BCSEK 30-in, 250cfm
RefrigeratorWhirlpool, WRT348FMES
Vanity SinkRound ceramic drop-in
Bathroom FaucetDelta, Woodhurst 1.5-gpm centerset
Tub FaucetDelta, T13420-SS
Shower FaucetDelta, T13220-SS
TubAmerican Standard Solar, (60x30)
Tub SurroundSterling, 61044100-0 (60x31.5) with corresponding tub
ShowerAquatic, AX160304PS-WH
ToiletAmerican Standard Cadet 3, comfort height, elongated 1.28-GPF
Bathroom FanBroan QK60s, 60cfm
Flooring – LVPShaw, Torino Plus Floorte 500RG
CarpetShaw, Burghley 2 - 60oz. – 6lbs. Pad
Hot Water HeaterA.O. Smith Signature 900, 50-gallon
Ceiling FanHunter, Anisten 52-in
Kitchen LightCommercial Electric, 54663141
Bathroom LightHampton Bay, V1124-79
Hall LightHampton Bay, FZP8012-A
Coach LightHampton Bay, 245 746
Ext. Ceiling LightHampton Bay, WB0325
Light BulbsLED
RoofingCertainTeed, Landmark
Gutter6” Aluminum with 4” downspouts

Windows HVAC seer

· When repairing or replacing plumbing fixtures always use new braded supply lines.

· When repairing or replacing trim always putty, caulk, and paint.

· When repairing or replacing drywall always tape, mud, texture, and paint.

· When repairing or replacing electrical wiring always repair the drywall.

· Counter tops are to be square-edged, laminate with a 4” backsplash.

· Cabinetry shall be constructed of ½” plywood or better with ¾” solid hardwood fronts and frames, no particle board. All exposed ends will be finished and have side-mounted drawer guides.

· Moving furniture is the contractor’s responsibility, its contents are the homeowners.

· All electrical appliances are to be EnergyStar approved with LED bulbs.

· Protect all surfaces, furniture, decorations, and the homeowner’s property from damage.

“Contractors are obligated to use like, similar, or equal valued products”.

File details come from the government source that posted it. Updated .