Bid Schedule.pdf
PDF 125 KB Posted
- Attached to
- Detroit Floating Plant Drydocking
- Solicitation number
- W911XK21B0004
About this file
This bid schedule outlines work requirements and pricing for the repair and alteration of two vessels, the Tug DEMOLEN and the associated Crane Barge VELER. The work includes cleaning and inspecting hulls, replacing doors, pumps, valves and other components, performing structural and plumbing modifications, and applying new exterior coatings. A total of 75 line items are specified, covering tasks such as drydocking, inspections, mechanical work, tank work and other repairs. Pricing is provided for each task using unit rates as well as total projected pricing. The bid schedule also includes options for additional work like extra lay days, welding hours and plate repair. The solicitation specifies a total not-to-exceed amount of $100,000 for potential unforeseen conditions work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION B – SUPPLIES OR SERVICES AND PRICES
Detroit Floating Plant Drydocking Bid Schedule Line Items Description of Work Quantity Unit Unit Price Total Price
Base-TUG DEMOLEN 0001 Dry Dock and Undocking 1 Job 0002 Clean Hull for Inspection 1 Job 0003 Inspection of Transducer Well 1 Job 0004 Inspection of Rudder 1 Job 0005 Inspection of Propeller 1 Job 0006 Remove and Replace Prop Shaft Packing 1 Job 0007 Replace ON/OFF Fresh Water Valve 1 Job 0008 Remove and Replace Ballast Tank Vents 3 Job
Remove all Fenders 0009 Replace all Support Pipe 1 Job 0010 Add Fender for High Water Ops. 1 Job 0011 Repaint Draft Markings and Name 1 Job 0012 Final Paint Coat 1 Job 0013 Ultrasonic Testing 75 CI 0014 Replace Chain Locker Valve 1 Job 0015 Open and Recondition Sea Chests 3 Job 0016 Inspect and Repair Front Ballast and Fuel Tank 1 Job 0017 Remove and Replace Lazarette Hatch 1 Job 0018 Remove and Replace Emergency Bow Hatch 1 job 0019 Remove and Replace Stern Deck Hatch 1 Job 0020 Replace Floor in Both Heads 1 Job 0021 Add Anchor Box and Replace Chain 1 Job 0022 Clean and Inspect Fuel Tanks 4 Job
Base Total - TUG DEMOLEN Base-Crane Barge Veler
0022 Dry Dock and Undocking 1 Job 0023 Clean Hull for Inspection 1 Job 0024 Remove Two Spugs and Replace 1 Job 0025 Remove and Replace Cabin Door 1 Job 0026 Remove and Replace Engine Room Door 1 Job 0027 Replace Heater Boiler 1 Job 0028 Replace All Mast Flag Lines 1 Job 0029 Sandblast and Paint Entire Hull 1 Job
Facilities Plumbing Modifications 0030 Remove Black Tank. Pump, and Vent 1 Job 0031 Plumb Grey Water Drain to Black Tank Drain 1 Job 0032 Plumb Existing Black Water Drain to New Black Tank 1 Job 0033 Remove all Existing Grey Water/Black Water Discharge Pipe 1 Job 0034 Install New Black Water Pump and Drain 1 Job
0035 Repaint Draft Markings and Name 1 Job 0036 Sandblast and Paint Deck With Non-Skid 3,800 SQFT
Base Total - CRANE BARGE VELER Options-TUG DEMOLEN
0037 Additional lay Days 5 Day 0038 Miscellaneous Welding 100 HRS 0039 Spot Sandblast and Spot Paint Hull 400 SQFT 0040 Hull Plate Repair 120 IN
Hull Plate Renewal 0041 Flat Hull Plate 200 LB 0042 Curved Hull Plate 200 LB 0043 Replace Zinc Anodes 10 PC
Options Total - TUG DEMOLEN Options-Crane Barge Veler
0044 Additional lay Days 5 Day 0045 Miscellaneous Welding 100 HRS 0046 Hull Plate Repair 120 IN
Hull Plate Renewal 0047 Flat Hull Plate 200 LB 0048 Curved Hull Plate 200 LB
Options Total - CRANE BARGE VELER
Total for Base – Tug Demolen Total for Base – Crane Barge Veler Overall Total for Base Items
Total for Options – Tug Demolen Total for Options – Crane Barge Veler Overall Total for Option Items
Unforeseen Conditions Cost (Time & Materials) – TUG DEMOLEN $50,000.00 Unforeseen Conditions Cost (Time & Materials) – CRANE BARGE VELER $50.000.00 Total for Time and Materials $100,000.00
Overall Contract Total