Bid_Schedule.doc

DOC document 77 KB Posted

Attached to
BLM FY25 BROADCAST SEEDING BOISE DISTRICT Federal contract opportunity
Solicitation number
140L2625Q0002
Issued by
Department of the Interior Bureau of Land Management Idaho Region

About this file

This is a bid schedule for a broadcast seeding project for the Bureau of Land Management (BLM) Idaho Region, scheduled to begin around February 3, 2025. The project is divided into two schedules: Schedule A covers 25,395 acres across 5 different seeding areas (Mary, Sugar, Jump, Table, and Valley) requiring 104,600 bulk pounds of seed, while Schedule B encompasses 95,094 acres across 6 areas (Paddock Mix 1-4, Mineral, and Lava) requiring 281,860 bulk pounds of seed.

The total project covers 120,489 acres and requires 386,460 bulk pounds of seed with varying application rates from 1.0 to 19.4 pounds per acre depending on the mix type (sagebrush, grass, and forb combinations). The performance period is 17 days, and the contractor must begin work within three days of notification from the Contracting Officer's Representative. The actual start date will depend on seed availability from the government, with an approximate start date of February 3, 2025.

View the file

Other files for this federal contract opportunity

Other files attached to BLM FY25 BROADCAST SEEDING BOISE DISTRICT, newest first.
File Type Posted
work_location_maps.pdf PDF
Specifications.docx DOCX document
wage_determination.pdf PDF
Sol_140L2625Q0002.pdf PDF
statement_of_work.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

BDO BLM FY25 BROADCAST SEEDING #1

Schedule A

Item No.
Description
Percent Coverage
Estimated Quantity (Acres)
Estimated Bulk Pounds of Seed
Estimated Bulk Rate (Lbs/Acre)
Unit Price

($/Acre) Total Cost

1
Mary (Sagebrush)
100
2,958
3,040
1.0
2
Sugar (Sagebrush)
100
7,449
7,480
1.0
3
Jump (Sagebrush)
100
6,452
7,800
1.2
4
Table (Grass/Sagebrush)
100
5,803
33,380
5.8
5
Valley (Grass/Forb/Sagebrush)
100
2,733
52,900
19.4

SCHEDULE A TOTALS

25,395
104,600

Schedule B

Item No.
Description
Percent Coverage
Estimated Quantity (Acres)
Estimated Bulk Pounds of Seed
Estimated Bulk Rate (Lbs/Acre)
Unit Price

($/Acre) Total Cost

6
Paddock Mix 1 (Sagebrush/Forb)
100
48,170
61,240
1.3
7
Paddock Mix 2 (Sagebrush/Forb)
100
10,709
11,880
1.1
8
Paddock Mix 3 (Sagebrush/Grass/Forb)
100
11,879
63,900
5.4
9
Paddock Mix 4 (Sagebrush/Grass/Forb)
100
8,627
44,310
5.1
10
Mineral (Grass/Sagebrush)
100
5,811
37,080
6.4
11
Lava (Grass/Sagebrush)
100
9,898
63,450
6.4

SCHEDULE B TOTALS

95,094
281,860

Schedule A Total Estimated Acres: 25,395

Approximate Start Date: 2/3/2025 Schedule B

Total Estimated Acres: 95,094

Approximate Start Date: 2/3/2025 Total Performance Time: 17 days

Actual start date is dependent on when government-provided seed will be available, approximated date as listed above. The contractor shall be required to start work within three days after being notified by the Contracting Officer’s Representative.