BID_S-1-27_Question_&_Answer_Report.pdf
PDF 81 KB Posted
- Attached to
- Cahill and Lions Park Pavement Restoration
- Solicitation number
- S-1-27
- Issued by
- Niobrara County, Wyoming
About this file
This Question & Answer Report document pertains to IFB No. S-1-27 issued by the City of Cheyenne, Wyoming Purchasing Department for the Cahill and Lions Park Pavement Restoration project. The project encompasses cold milling of existing asphalt across 23,026 square yards, placement of 2,773 tons of new asphalt paving, localized patching of 1,361 square yards, unclassified excavation of 100 cubic yards, adjustment of utility structures, and waterborne striping restoration. The report addresses three clarification questions submitted by prospective bidders prior to the August 11, 2026 response deadline at 2:00 p.m. A non-mandatory pre-bid meeting was held on July 27, 2026 via Zoom, with the question submission deadline set for July 31, 2026. Contract award is estimated for September 14-15, 2026, with Notice to Proceed by September 21, 2026 and final completion required by October 31, 2026. Work at Cahill Park must be substantially completed before commencing at Lions Park.
Key clarifications provided in the Q&A report address asphalt quantity specifications of approximately 1,500 tons based on 13,345 square yards at Lions Park, confirmation that the City will provide a loader for stockpiling asphalt millings at the North Park facility, and approval for complete lot closures during active work phases. Bidders must submit a 5% bid guarantee with performance and payment bonds equal to 100% of the contract amount. Wyoming's resident contractor preference statute applies with a 5% cost preference for certified resident bidders, subject to restrictions limiting resident subcontracting to no more than 30% of contract work. Commercial General Liability insurance of $1,000,000 per occurrence and Business Automobile Liability of $1,000,000 combined single limit are required. Liquidated damages range from $250 to $3,500 per calendar day based on the original contract amount, with the City retaining 5% of work value throughout the contract term and a two-year warranty period required upon completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Cheyenne
Purchasing TJ Barttelbort, Purchasing Manager
2101 O'Neil Ave., Room 309, Cheyenne, WY 82001
(307) 773-1045
QUESTION & ANSWER REPORT
Invitation For Bid - Cahill and Lions Park Pavement Restoration
QUESTION & ANSWER REPORT
IFB No. S-1-27
Cahill and Lions Park Pavement Restoration
RESPONSE DEADLINE: August 11, 2026 at 2:00 pm
Monday, August 3, 2026
Approved, Unanswered Questions
Approved, Answers Provided
1. Asphalt Qty
Jul 21, 2026 10:16 AM
Question: I come up with closer to 1500 TN based on the 13,345 Sy for all the lions park lots. Can this be looked at?
Jul 21, 2026 10:16 AM
Answered by TJ Barttelbort: We have reviewed the quantities, and they will remain as published. Those quantities account for a small percentage of overage and are based on an average weight using granite aggregate. Some suppliers only use granite, and we do not want to be short.
Aug 3, 2026 3:57 PM
2. Loader
Jul 30, 2026 2:32 PM
Question: Will a loader need to be provided to stockpile at the location the millings were dropped off?
Jul 30, 2026 2:32 PM
Answered by TJ Barttelbort: The City will provide a loader to pile the asphalt millings.
3. Traffic control
QUESTION & ANSWER REPORT
IFB No. S-1-27 Cahill and Lions Park Pavement Restoration
Jul 30, 2026 2:32 PM
Question: Can the lots be completely shut down while we are working in them?
Jul 30, 2026 2:32 PM
Answered by TJ Barttelbort: Yes, we’ll completely shut down each lot while they are working on them.
| QUESTION & ANSWER REPORT |
| IFB No. S-1-27 Cahill and Lions Park Pavement Restoration |
| RESPONSE DEADLINE: August 11, 2026 at 2:00 pm |
| Approved, Unanswered Questions |
| Approved, Answers Provided |
File details come from the government source that posted it. Updated .