McKay Bay Waste to Energy (WTE) Facility Tile/Refractory Work, Bid# 25-P-00198
Bid Response for Division I: Labor Cost for Outages
Each Outage has a time frame of (Estimated twelve (12) -12-hour Shifts of twelve (12) workers = 1728 hrs. per outage)
| a. | Boiler 1 February (Tuesday 0700 – Monday 0700): 1728 hrs. | | |
| b. | Boiler 3 February (Tuesday 0700 – Monday 0700): 1728 hrs. | |
| c. | | Boiler 2 March (Tuesday 0700 – Monday 0700): 1728 hrs. | |
| d. | Boiler 4 April (Tuesday 0700 – Monday 0700): 1728 hrs. | | |
| e. | Boiler 1 August (Monday 0700 – Sunday 0700): 1728 hrs. | | |
| f. | | Boiler 3 August (Monday 0700 – Sunday 0700): 1728 hrs. |
| g. | Boiler 2 September (Monday 0700 – Sunday 0700): 1728 hrs. | |
| h. | Boiler 4 September (Monday 0700 – Sunday 0700): 1728 hrs. | |
Total # of Hours: 13,824 hours
Provide breakdown in below table.
| Straight Time Rate |
| Overtime Rate |
| Double Time Rate |
| Labor Classification |
| Straight Time Rate |
| Estimate# of Hrs |
| Total Labor $ |
| Overtime Rate |
| Estimate# of Hrs |
| Total Labor $ |
| Double Time Rate |
| Estimate# of Hrs |
| Total Labor $ |
Supervisor
Foreman
Mason Welder
Mason Tender
Other:
Other:
Other:
2. Mobilization and Demobilization (for all outages in this Division): $
3. PPE (for all outages in this division): $_____________
4. Per Diem (for all outages in this division): $
Total Amount for Division I: $__________________________________
Bid Response for Division II: Labor Cost for Emergency Work/Unplanned Outages
The Department is estimating four (4) 12-hour Consecutive Shifts of four (4) workers x four (4) unplanned outages = 768 hrs. Use OT rate for calculating this labor cost.
Total # of Hours: 768 hours Provide breakdown in below table.
| Straight Time Rate |
| Overtime Rate |
| Double Time Rate |
| Labor Classification |
| Straight Time Rate |
| Estimate# of Hrs |
| Total Labor $ |
| Overtime Rate |
| Estimate# of Hrs |
| Total Labor $ |
| Double Time Rate |
| Estimate# of Hrs |
| Total Labor $ |
Supervisor
Foreman
Mason Welder
Mason Tender
Other:
Other:
Other:
2. Mobilization and Demobilization (for all outages in this Division): $_________________
3. PPE (for all outages in this division): $_________________
4. Per Diem (for all outages in this division): $
Total Amount for Division II: $_________________________________
Bid Response for Division III: Tile/Refractory List
| Material |
| Quantity |
| UOM |
| Price |
| Total |
| 8 "Hidden Clip Nitride Tile T-25932 |
| 5000 |
| Each |
| 9" T SLOT BRICK SIC |
| 500 |
| Each |
| 8" Beveled Repair Tile |
| 700 |
| Each |
| 4" V- Anchor 310SS |
| 300 |
| Each |
| SIC Surebond Mortar |
| 320 |
| Bags |
| SIC V-Bond Mortar |
| 200 |
| Bags |
| 2.5" Y Membrane Anchor Inconel 601 |
| 2500 |
| Each |
| 2.25" x 3/8" Inconel 600 Stud |
| 1500 |
| Each |
| 2.5" x 3/8" Inconel 600 Stud |
| 1500 |
| Each |
| 2 3/8" x 3/8" Inconel 600 Stud |
| 4000 |
| Each |
| 1" Steer Horn Inconel 601 |
| 5000 |
| Each |
| 2" Y Membrane Anchor Inconel 601 |
| 7500 |
| Each |
| Left Side Grate Blocks T28181 |
| 60 |
| Each |
| Right Side Grate Blocks T28191 |
| 60 |
| Each |
| Threaded Washers Stainless |
| 4500 |
| Each |
| Ceramic Fiber Blanket 2" 6# |
| 60 |
| Box |
| 3/32" 112 Inconel Weld Rod |
| 800 |
| LBS |
| 1/8" 309SS Weld Rod |
| 150 |
| LBS |
| Black Beauty Sandblast Material |
| 800 |
| Bags |
| T&G Slot Brick 12" |
| 130 |
| Each |
| 8" Back Cast Tile |
| 550 |
| Each |
Total Amount for Division III: Tile/Refractory List: $_________________________________________
Bid Response for Division IV: Materials Cost
Other refractory materials not listed in the above table:
MATERIALS COST MARKUP PERCENTAGE (Not to exceed 10%): ______% of $50,000: $__________ Example: $3,500 (10% of $35,000) + $35,000 = $38,500
Bid Response for Division V: Rental Equipment
The listed rental equipment is the total needed for all eight (8) scheduled outages, please include all associated cost including mark up and freight in the total cost.
| Rental Equipment |
| Quantity |
| UOM |
| Price |
| Total |
| Sand Blast Equipment (2 Pots) |
| 8 |
| LOT |
| Dryer-Water Separator |
| 8 |
| LOT |
| Saw Blade SIC RS-30 |
| 8 |
| LOT |
Total Amount for Division V: Rental Equipment $_________________________________________
Grand Total of All Divisions (I, II, III, IV, V): $__________________________________________