BID_REQUEST_FORM_9-23-25.pdf

PDF 439 KB Posted

Attached to
ADA Path of Travel Upgrades at 11 Preschool Playgrounds
Solicitation number
25/26-0026i
Issued by
San Bernardino County, California

About this file

This is a Bid Request Form from the Fontana Unified School District (FUSD) for ADA Path of Travel Upgrades at Preschool Playgrounds. The project involves ADA upgrades for path of travel to playgrounds, with an estimated construction cost of $180,000. The project is scheduled to start on 12/22/25, with an estimated completion date of 2/20/26, spanning 60 calendar days. The project will be processed as an informal bid, with a liquidated damages rate of $500 per day. The license class required is B, and the architect is Lionakis.

The project will be funded through local sources, with no federal funding indicated. It requires a construction schedule and will be awarded as a base bid with a GC (Prime Contractor) approach. The DSA Inspector will be Cremo Inspection, and the District Project Manager is Keith Bacosa. The bid was completed by Noel Garcia from M&O/Facilities Planner and authorized by the Director of Facilities on 9-23-25. No testing consultant or construction management firm is currently specified for the project.

View the file

Other files

Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FONTANA UNIFIED SCHOOL DISTRICT

UNIFORM PUBLIC CONSTTRUCTION COST ACCOUNTING ACT

BID REQUEST FORM

The following information is needed prior to bid process. The information on this checklist must be must be accurate and complete in order to provide an accurate Notice of Inviting Bids to our contractors. If the Board requires prior authorization to bid, please attach board item.

Date: _______________ Attachments needed: Scope, DSA Letter, Estimated Budget Cost and Project Schedule

PROJECT NAME:

District Project Manager: (Process req after Board Approval: email purchasing REQ #)

Labor Compliance Firm: Yes No Contact: Architect:

License Class: DSA Approval Date: Est. Start Date:

Est. Completion Date: Duration: calendar days

Liquidated Damages: /day Est. Construction Cost: Construction Schedule Attached: Yes No

*Note: Civil Code required payment bond for projects over $25,000 Informal Bid ($75,001-

$220,000) Formal Bid (over $220,000) Under $75,000

(3 quotes required)

GC (Prime Contractor)

Attach Multi-line description with category and allowance and / or alternatives Award as: Base Bid Multi-lines Allowances Alternates (include in NIB) Detailed

Scope of Work (detailed paragraph) Required for Publication and complete scope of work to be attached:

Testing Consultant:

Email/Phone:

Time: Location:

Time:

Time:

Time: Location:

DSA Inspector:

CM Firm:

Contact Name:

Plans & Specs Host Location:

Public Advertisement Information:

Adv Dates:

Jobwalk Date:

RFI Deadline:

Prequalification Date:

Bid Submittal Date:

Board Date: Due:

Completed by M&O/Facilities Planner Date

Authorized by Director of Facilities Date

Budget Approval Date

FUSD 1/27/25 bc

Bid No: ______________________

Check all that apply:

Bond: State/Local (Circle One) Other M&O/ DM/ RM (Circle One)

Funding:________________ Federal: Yes No

Bid No:
Other:
Date: 9-23-25
PROJECT NAME: ADA Path of Travel Upgrades at ____ Preschool Playgrounds
District Project Manager: Keith Bacosa
Yes: Off
No Contact: On
Process req after Board Approval email purchasing REQ: N/A
Architect: Lionakis
License Class: B
DSA Approval Date:
Est Start Date: 12/22/25
EstCompletion Date: 2/20/26
Duration: 60
Liquidated Damages: 500
Est Construction Cost: $180,000
Construction Schedule Attached: No
Under 60000: Off
Informal Bid 60001: On
Formal Bid over 200000: On
GC Prime Contractor: On
Base Bid: On
Multilines: Off
Allowances: On
Alternates include in NIB Detailed: Off
Scope of Work detailed paragraph Required for Publication and complete scope of work to be attached 1: ADA upgrades for path of travel to playgrounds.
Scope of Work detailed paragraph Required for Publication and complete scope of work to be attached 2:
Scope of Work detailed paragraph Required for Publication and complete scope of work to be attached 3:
Scope of Work detailed paragraph Required for Publication and complete scope of work to be attached 4:
DSA Inspector: Cremo Inspection
Testing Consultant: N/A
CM Firm: N/A
Contact Name: N/A
EmailPhone: N/A
Plans Specs Host Location:
Public Advertisement Information:
Time:
Location:
1:
2:
Time_2:
Prequalification Date:
Time_3:
Time_4:
Location_2:
Bid Submittal Date 1:
Bid Submittal Date 2:
Due:
Completed by MOConstruction ManagerPlanning Development: Keith Bacosa
Date_2: 9-23-25
Authorized by Director Planning Development: Noel Garcia
Date_3: 9-23-25
Budget Approval:
Date_4:
Authorized by Director Risk Management:
Date_5:
Check Box2: Yes
Check Box3: Off
Check Box4: Off

File details come from the government source that posted it. Updated .