Bid Packet 07.09.2025.pdf

PDF 3 MB Posted

Attached to
COVERSION OF ALTERNATIVE FUEL STATION
Solicitation number
P25-06
Issued by
Bossier Parish, Louisiana

About this file

The document is a comprehensive bid packet for the City of Bossier City, Louisiana, soliciting bids for the Conversion of Alternative Fuel Stations (Bid #P25-06). The project involves converting two existing alternative fuel stations located at 2250 East Texas Street and 4520 Barksdale Boulevard from E85 and CNG fuels to regular unleaded gasoline and diesel, including the installation of an above-ground diesel tank. Sealed bids will be received until 2:30 p.m. on August 12, 2025, with a public bid opening at 3:00 p.m. in the Council Chambers. A mandatory pre-bid meeting is scheduled for July 17, 2025, at 10:00 A.M. at the Bossier City Engineering Conference Room, and bidders must attend to be eligible to submit a proposal. The project has a completion timeline of 215 calendar days, with liquidated damages of $500 per day for delays.

The bid requires contractors to be licensed in Louisiana for Municipal and Public Works Construction, with specific qualifications for handling hazardous waste and underground storage tanks. Bidders must submit a bid bond or certified check for 5% of the total bid amount, and the successful contractor will be required to provide performance and payment bonds equal to 100% of the contract price, plus a 10% maintenance bond. The project involves comprehensive work including demolition of existing CNG equipment, tank removal, installation of new diesel tanks and dispensers, updating fuel management software, and site restoration. Contractors must comply with OSHA, EPA, and local environmental regulations, implement safety plans, and provide spill prevention and emergency response protocols. The bid emphasizes the need for experienced contractors with at least three similar fuel system conversions in the past five years.

View the file

Other files

File Type Posted
SampleBidEnvelope.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONVERSION OF ALTERNATIVE

FUEL STATIONS

BID# P25-06

DUE: AUGUST 12, 2025

2:30 P.M.

INDEX

Conversion of Alternative Fuel Stations

Bid #P25-06

Section A – Legal Notice to Bidders A-1

Section B – Instructions to Bidders B-1 – B-4

Section C – Bid Form/Bid Bond C-1 – C-3

Section D – Contract Agreement/Affidavit/ D-1 – D-6 Resolution of Board of Directors/ Designation of Construction contractor as Agent Governmental Entity and Exemption Certificate And Attestation of Felony Conviction Statement with E-Verify of Employees

Section E – Performance/Payment/Maintenance Bonds E -1 – E-2

Section F – General Conditions F-1 – F-15

Section G - Standard Terms G-1 – G-3

Section H – Specifications & Map Views H-1 – H-13

LEGAL NOTICE TO BIDDERS

BID #P25-06 Conversion of Alternative Fuel Stations

SEALED BIDS, electronic or paper, addressed to the Purchasing Agent of the City of

Bossier City, at 620 Benton Road, Bossier City, Louisiana, 71111 will be received until

2:30 p.m., August 12, 2025 for Bid #P25-06 Conversion of Alternative Fuel Stations.

The bids will then be publicly opened and read aloud in the Council Chambers at 3:00 p.m.

This project is for the conversion for two alternative fuel stations from E85 and CNG fuels to regular unleaded and addition of an above ground tank for diesel fuel.

In accordance with the Louisiana Public Bid Law, RS:38:2212 Act No. 590, 2008, contractors shall be provided the option to submit bids for Public Work projects through either a secure electronic interactive system or by submitting a paper bid. Use www.bidnetdirect.com to submit an electronic bid.

Specifications, Plans, and Contract Documents may be obtained from the office of the

Purchasing Agent, 620 Benton Road, Bossier City, LA, 71111 for $0.00.

There will be a Mandatory Pre-Bid Meeting held Thursday, July 17, 2025 at

10:00A.M. at the Bossier City Engineering Conference Room, 2nd Floor, 620 Benton

Road, Bossier City, LA. All prospective bidders shall be present at the beginning of the pre-bid conference and shall remain in attendance for the duration of the pre-bid conference. Any prospective bidder who fails to attend the conference or remain for the duration shall be prohibited from submitting a bid for the project.

Bids shall be submitted on the official Bid Form furnished with the bid package and those submitted otherwise will not be considered or accepted. Although any addenda issued will be transmitted to all prime bidders who request bid documents, it shall be the Bidder’s responsibility to make inquiry as to any Addenda issued in accordance with LA 38:2212.

C(2)(a). Each proposal must be accompanied by a bid security, which may be a certified check, cashier’s check, or bid bond, for an amount not less than 5% of the amount of the bid, made payable to the City of Bossier City, Louisiana. An acceptable performance/payment bond equal to 100% of the contract price along with a maintenance bond equal to 10% of the contract price will be required of the successful bidder.

Only the lowest responsive bidder will be required to submit the Attestation Form (Felony

Conviction Statement and E-Verify) within ten days after the bid opening.

The successful bidder will agree to commence work under this contract on or before a date to be specified in the Notice to Proceed and fully complete the project within Two Hundred

Fifteen (215) Calendar days. Bidder will pay as liquidated damages, the sum of $500.00 for each consecutive day thereafter.

On any bids submitted in the amount of $50,000 or more, the Contractor shall be licensed under Louisiana Revised Statutes 37:2150-2163 and show his license number on the bid and on the envelope in which it is submitted. Any Subs being Electrical, Mechanical, or

Plumbing (plumbers bidding Mechanical work) shall be licensed under Louisiana Revised

Statute 37:2156 for bids submitted in the amount of $10,000 or more.

The City of Bossier City reserves the right to reject any/or all bids in accordance with R.S.

38:2214.

ANGELA WILLIAMSON

DIRECTOR OF FINANCE

CITY OF BOSSIER CITY, LOUISIANA

INSTRUCTIONS TO BIDDERS

1.0 BID FORMS

1.1 All bids must be made on the form provided with this copy of the contract documents.

All bids must be legibly written in ink or type print, with all prices given in words and figures.

No alterations in bids or in the printed forms will be permitted by erasures or interlineations.

Each bid shall be enclosed in a sealed envelope, addressed to the Purchasing Agent of the City of Bossier City, Louisiana, and identified on the outside of the envelope with the appropriate title of the project as indicated on the plans.

1.2 Bids shall be strictly in accordance with the prescribed form. Any modifications thereof or deviations therefrom may be considered as sufficient cause for rejection.

1.3 Bids carrying riders or qualifications to the bid as submitted may be rejected as irregular.

2.0 BID GUARANTEE

2.1 Each bid shall, as a guarantee of good faith on the part of the bidder, be accompanied by either a cashier’s check or a certified check drawn on an acceptable bank, or an acceptable bidder’s bond with an authorized surety company in an amount of not less than 5% of the total bid.

2.2 The bid guarantee shall be made payable with conditions to the City of Bossier City, Louisiana and the amount of the check or bond may be retained by and forfeited to said City of Bossier City, Louisiana, hereinafter referred to as Owner, as liquidated damage if such bid is accepted and the contract is awarded, and the bidder fails to enter into a contract in the form prescribed, with legally responsible sureties, within ten days after such award is made by the Owner.

3.0 SIGNATURE OF BIDDERS

3.1 Each bid must be signed in ink by the bidder with his full name, title and business address. In the case of a firm, the name of the firm must be inserted. A bid submitted by, or on behalf of a corporation must be signed in the name of such corporation by an official authorized to bind the corporation. Failure to include a copy of the appropriate signature authorization, if required, may result in the rejection of the bid unless bidder has complied with LA R.S.

38:2212(A)(1)(c) or RS 38:2212(O).

4.0 ONLY ONE BID

4.1 No bidder may submit more than one bid. Two bids under different names will not be received from one firm or association.

5.0 RESPONSIBILITY OF AGENT

5.1 Any person signing a bid as the agent of another, or of others, may be required to submit satisfactory evidence of authority to do so. (See 3.1, above)

5.2 The title of the person executing the bid or contract will be clearly indicated beneath his signature.

6.0 QUALIFICATIONS OF BIDDERS

6.1 Bidders on projects in the amount of fifty thousand dollars ($50,000) or more shall be required to have a Louisiana contractor's license for Municipal and Public Works Construction and/or any other classification applicable to the work in compliance with Louisiana State Licensing Board for Contractors and in compliance with Louisiana Revised Statutes.

6.2 Contractors who would like to provide a bid on this project shall be licensed as a Commercial Contractor with Specialty Certification for Hazardous Waste Treatment or Removal and Underground Storage Tanks by the State of Louisiana. Contractors must also have a Current UST Certified Worker Certificate with the Louisiana Department of Environmental Quality.

Pricing shall include ALL materials, hardware, equipment, labor, etcetera to complete the project.

6.3 Bidders may be required to submit satisfactory evidence that they have a practical knowledge and experience in the particular work bid upon, and that they have the necessary financial resources to complete the proposed work. Inexperience in the type or size of the job bid upon shall be sufficient cause for rejection of the bid. The opinion of the Owner in this regard shall be final. In determining the lowest responsible bid, the following elements will be considered: Whether the bidder involved maintains a permanent place of business, has adequate plant equipment to do the work properly and expeditiously, has a suitable financial status to meet obligations incidental to the work, and has appropriate technical experience.

6.4 Each bidder may be required to show that former work performed by him has been handled in such manner that there are not just or proper claims pending against such work. No bidder will be acceptable if he is engaged in other work which impairs his ability to finance this contract or provide proper equipment for the proper execution of same. Each bidder shall demonstrate his ability by meeting all requirements herein stipulated.

6.5 The lowest responsive bidder will be required to submit the Attestation Form (Felony Conviction Statement and E-Verify) within 10 days after the bid opening. Bidder shall submit a completed and signed Felony Conviction Statement to attest that he has not been convicted of, or has not entered a plea of guilty or nolo contendere to any of the crimes or equivalent federal crimes listed in Subsection B of LA R.S. 38:2227. A copy of the Attestation statement for use is included in the Invitation to Bid. This form also includes the E-Verify. The Attestation form can be mailed, faxed, or e-mailed.

7.0 LOCAL CONDITIONS AFFEC TING WORK

7.1 Each bidder shall visit the site of the work and thoroughly and fully inform himself relative to construction hazards and procedure, labor, and all other conditions and factors, local and otherwise, which would affect the prosecution and completion of the work and the cost thereof, including the arrangement and conditions of existing structures or pipelines affecting or which are affected by the proposed work, sub-surface conditions affecting excavating work, the procedure necessary for maintenance or uninterrupted operation and the prosecution of the work, the availability and cost of labor, and facilities for transportation, handling and storage of materials and equipment. It must be understood and agreed that all such factors have been properly investigated and considered in the preparation of every proposal submitted, as there will be no subsequent financial adjustment to any contract awarded thereunder which is based on the lack of such prior information or its effect on the cost of the work.

7.2 It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to become familiar with local conditions that may in any manner affect cost, progress, performance or furnishing of the Work, (c) consider federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress, performance or furnishing of the Work; (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Owner of all conflicts, errors or discrepancies in the Contract Documents requiring correction, clarification, or interpretation.

7.2 The Contractor to whom the work is awarded shall conduct his work in strict conformance with state and parish laws and City ordinances relative to labor, sanitary requirements and traffic safety regulations.

8.0 TAXES

8.1 Bids shall not include sales/use tax. When Form R-1020 from Louisiana Department of Revenue is properly executed by both the contractor and the governmental entity, it shall serve as evidence of the sales tax exempt status that has been conferred onto the contractor. This designation of agency shall be effective for purchases of component construction materials, taxable services and leases and rental of tangible personal property.

9.0 INTERPRETATION OF CONTRACT DOCUMENTS

9.1 No oral interpretation will be made to any bidder as to the meaning of the contract documents or any part thereof. Every request for such interpretation shall be made in writing to the City of Bossier City, City Engineer, P.O. Box 5337, Bossier City, Louisiana, 71171-5337.

Any inquiry received five days or more prior to the date fixed for the opening of bids will be given consideration. Every interpretation made to a bidder will be in the form of an addendum to the contract document and when issued will be on file in the City’s Purchasing Department at least five days before bids are opened. In addition, all addenda will be mailed to each person holding contract documents, but it shall be the bidder’s responsibility to make inquiry as to the addenda issued. All such addenda shall become part of the contract documents and all bidders shall be bound by such addenda, whether or not received by the bidders.

10. WITHDRAWAL OF BID

10.1 Bids may be withdrawn by the bidder at any time prior to the bid opening deadline. Bids containing patently obvious, unintentional, and substantial mechanical, clerical, or mathematical errors, or errors of unintentional omission of a substantial quantity of work, labor, material, or services made directly in the compilation of the bid, may be withdrawn by the contractor if clear and convincing sworn, written evidence of such errors is furnished to the public entity within forty-eight hours of the bid opening excluding Saturdays, Sundays, and legal holidays.( LA R.S.38:2214C). Under no circumstances will any bid be accepted or opened if it is received after date and time it is due but instead will be returned unopened to the bidder.

11.0 ACCEPTANCE AND REJECTION OF BIDS

11.1 The Owner reserves the right to accept the bid which, in its judgment, is the lowest responsive bid on and for the work covered by the proposal and to reject any and all bids for just cause as provided for by LA R.S. 38:2214.

12.0 WAGES

12.1 It is the intent of the City of Bossier City that all workers on City public works contracts be properly skilled in their respective trades and that they be paid wages which fairly reflect labor costs in the Bossier City/Bossier Parish area. To reduce the administrative burden and expense of entering into a contract with the City of Bossier and to allow wages to be paid which accurately represent equilibrium levels in the local area, the provisions of the Davis Bacon Act are not applicable to this City funded project.

13.0 BOSSIER CITY COUNCIL RESOLUTION #15 OF 1984 is shown below for information and consideration:

A RESOLUTION SUPPORTING THE PREFERENCE OF BOSSIER PARISH

CONTRACTORS AND/OR LABORERS ON ALL CONTRACTS WITH THE CITY OF

BOSSIER CITY

WHEREAS, the Bossier City Council has adopted an Ordinance to amend Section 23A- 2(b), of the Procurement Code, to delete the requirements of complying with the provisions of Louisiana Revised Statute 38:2301 which pertains to the payment of prevailing wages for public works contracts, and;

WHEREAS, the Bossier City Council desires that locally generated funds expended on contracts in addition to improving the facilities in this area will add to the employment and aid the local economy, through the enactment of this Resolution;

NOW, THEREFORE,

SECTION I: BE IT RESOLVED by the City Council of the City of Bossier City, that Primary Contractors awarded contracts with the City of Bossier City shall give preference to Bossier City skilled craftsman and laborers in performing said contracts.

SECTION II: BE IT FURTHER RESOLVED that a copy of this Resolution shall be included in every construction bid package offered by the City of Bossier City.

This Resolution, having been submitted to a vote and declared adopted on motion of Mrs.

Miller and seconded by Mr. Carpenter, on this 3rd day of July, 1984, by the following vote, shall be in full force and effect from and after its adoption:

AYES: Mr. Carpenter, Mr. Mercer, Mr. Provenza, Mrs. Bennett, Mrs. Miller, Mr. Maddox

NAYS: None

ABSENT: Mr. Wojecki

ABSTAIN: None

/s/A.L. Maddox, Vice President /s/Jewel Lewis, City Clerk

LOUISIANA UNIFORM PUBLIC WORK BID FORM

TO: City of Bossier City Office of Purchasing 2nd Floor Municipal Building 620 Benton Rd.

Bossier City, LA 71111

BID FOR: Conversion of Alternative Fuel Stations Bid # P25-06 Calendar Days –215 Days Liquidated Damages - $500.00/day Plans – $0.00

The undersigned bidder hereby declares and represents that she/he; a) has carefully examined and understands the Bidding Documents, b) has not received, relied on, or based his bid on any verbal instructions contrary to the Bidding Documents or any addenda, c) has personally inspected and is familiar with the project site, and hereby proposes to provide all labor, materials, tools, appliances and facilities as required to perform, in a workmanlike manner, all work and services for the construction and completion of the referenced project, all in strict accordance with the Bidding Documents prepared by:

City of Bossier City and dated:

(Owner to provide name of entity preparing bidding documents.)

Bidders must acknowledge all addenda. The Bidder acknowledges receipt of the following ADDENDA: (Enter the number the Designer has assigned to each of the addenda that the Bidder is acknowledging) ____________________________________________________

TOTAL BASE BID: For all work required by the Bidding Documents (including any and all unit prices designated “Base Bid” but not alternates) the sum of:

Dollars ($ )

ALTERNATES: For any and all work required by the Bidding Documents for Alternates including any and all unit prices designated as alternates in the unit price description.

Alternate No. 1 Deduction for 10,000 GAL DISEL TANK IN LIEU OF 12,000 for the lump sum of:

Dollars ($ )

Alternate No. 2 Deduction for 8,000 GAL DISEL TANK IN LIEU OF 12,000 for the lump sum of:

Dollars ($ )

Alternate No. 3 Increase for REMOVAL OF SIGNS AT BOTH LOCATIONS for the lump sum of:

Dollars ($ )

NAME OF BIDDER:

ADDRESS OF BIDDER:

LOUISIANA CONTRACTOR’S LICENSE NUMBER:

NAME OF AUTHORIZED SIGNATORY OF BIDDER:

TITLE OF AUTHORIZED SIGNATORY OF BIDDER:

SIGNATURE OF AUTHORIZED SIGNATORY OF BIDDER **:

DATE:

THE FOLLOWING ITEMS ARE TO BE INCLUDED WITH THE SUBMISSION OF THIS LOUISIANA UNIFORM PUBLIC WORK BID

FORM:

* The Unit Price Form shall be used if the contract includes unit prices. Otherwise it is not required and need not be included with the form. The number of unit prices that may be included is not limited and additional sheets may be included if needed.

** A CORPORATE RESOLUTION OR WRITTEN EVIDENCE of the authority of the person signing the bid for the public work as prescribed by LA R.S. 38:2212(B)(5).

BID SECURITY in the form of a bid bond, certified check or cashier’s check as prescribed by LA R.S. 38:2218.(A) is attached to and made a part of this bid.

LOUISIANA UNIFORM PUBLIC WORK BID FORM

UNIT PRICE FORM

TO: City of Bossier City Office of Purchasing 2nd Floor Municipal Building 620 Benton Rd.

Bossier City, LA 71111

BID FOR: Conversion of Alternative Fuel Stations Bid # P25-06 Calendar Days –215 Days Liquidated Damages - $500.00/day Plans – $0.00

UNIT PRICES: This form shall be used for any and all work required by the Bidding Documents and described as unit prices.

Amounts shall be stated in figures and only in figures.

DESCRIPTION: Base Bid or Alt.# DEMOLITON (TOTAL FOR BOTH ALTERNATIVE FUEL LOCATIONS) REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

001 1 LUMP SUM

DESCRIPTION: Base Bid or Alt.#______ TOTAL TO UPDATE E85 SUPPLY/INSTALLATION/START-UP REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

002 2 EACH

DESCRIPTION: Base Bid or Alt.# 8,000 GAL DIESEL TANK SUPPLY/INSTALLATION/START-UP REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

003 2 EACH

DESCRIPTION: Base Bid or Alt.# E.TEXAS (HWY 80) REPLACE FUEL SUMP AT FILL AREA REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

004 1 LUMP SUM

DESCRIPTION: Base Bid or Alt.# TANK REMOVAL (3) UG TANKS AT 620 BENTON ROAD REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

005 1 LUMP SUM

DESCRIPTION: Base Bid or Alt.# GILBARCO VEEDER-ROOT TANK GAUGES-SUPPLY/INSTALL/START-UP REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

006 2 EACH

DESCRIPTION: Base Bid or Alt.# ____ SYNTECH FUELMASTER PEDESTALS-SUPPLY/INSTALL/START-UP REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

2 EACH

DESCRIPTION: Base Bid or Alt# REMOVAL OF SIGNS AT BOTH LOCATIONS REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

1 LUMP SUM

DESCRIPTION: Base Bid or Alt REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)

All quantities are estimated. The contractor will be paid based upon actual quantities as verified by the Owner and Engineer.

C-3

CITY OF BOSSIER CITY BID FORM

BID BOND

(For a paper bid, one original required of all Bidders with Power of Attorney attached. For an electronic bid, an electronic bid bond or a paper bond will still be accepted if received before the bid opening)

Date , 2025

KNOW ALL MEN BY THESE PRESENTS:

That of , as Principal, and _____________________________________________, as Surety, are held and firmly bound unto the City of Bossier in the full and just sum of five (5%) percent of the total amount of this bid, including all alternates, lawful money of the United States, for payment of which sum, well and truly be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally firmly by these presents.

Surety represents that it is listed on the current U. S. Department of the Treasury Financial Management Service list of approved bonding companies as approved for an amount equal to or greater that the amount for which it obligates itself in this instrument or that it is a Louisiana domiciled insurance company with at least an A - rating in the latest printing of the A. M. Best's Key Rating Guide. If surety qualifies by virtue of its Best's listing, the Bond amount may not exceed ten percent of policyholders' surplus as shown in the latest A. M. Best's Key Rating Guide.

Surety further represents that it is licensed to do business in the State of Louisiana and that this Bond is signed by surety's agent or attorney-in-fact. This Bid Bond is accompanied by appropriate power of attorney.

THE CONDITION OF THIS OBLIGATION IS SUCH that, whereas said Principal is herewith submitting its bid to the Obligee on a Contract for:

NOW, THEREFORE, if the said Contract be awarded to the Principal and the Principal shall, within such time as may be specified, enter into the Contract in writing and give a good and sufficient bond to secure the performance of the terms and conditions of the Contract with surety acceptable to the Obligee, then this obligation shall be void; otherwise this obligation shall become due and payable.

PRINCIPAL (BIDDER) SURETY

BY: BY:

AUTHORIZED OFFICER-OWNER-PARTNER AGENT OR ATTORNEY-IN-FACT (SEAL)

D-1

CONTRACT AGREEMENT

This contract Agreement, made and entered into this day of 20 , by and between

The City of Bossier City, Louisiana, acting through its Mayor thereunto duly authorized to do so, Party of the First Part and hereinafter called the OWNER and _______________________ of of the Second Part and hereinafter called the CONTRACTOR.

WITNESSETH: That, in consideration for the payment to be made to the CONTRACTOR and of the mutual agreements herein contained; the Parties to the presents hereby agree, the OWNER for itself and its successors, and the CONTRACTOR for itself, himself, or themselves, or its, his, or their successors and assigns or its, his, or their executors and administrators, as follows:

ARTICLE I. The CONTRACTOR shall furnish all tools, equipment, supplies, superintendence, transportation, and other construction accessories, services and facilities, furnish all material supplies and equipment specified and required to be incorporated in and form a permanent part of the completed work;

provide and perform all necessary labor; and in a good, substantial, and workmanlike manner and in full accordance with the provisions of the Proposal, General Conditions, Detailed Specifications, and Special Conditions and in full conformity with Contract Plans and Specifications all of which are a part of this contract, for the Project of: Project P25-05 Conversion of Alternate Fuel Stations

ARTICLE II. That the OWNER shall pay to the CONTRACTOR for the performance of the work embraced in this contract, and the CONTRACTOR will accept as full compensation therefor, the sum (subject to adjustments by change orders as provided by the contract and quantities reconciliation) of:

($ ) for all work included in the contract and designated in the foregoing ARTICLE I, payment to be made in the manner described in the General Conditions section of this contract.

ARTICLE III. That the CONTRACTOR shall start on, or within the (10) days following the date of the issuance of a Notice to Proceed and the CONTRACTOR shall complete said work within Two Hundred Fifteen (215) Calendar Days from and after the said date of the Notice to Proceed. The contractor will have 72 hours to begin work once notified concerning a repair location by the Public Works Department. Bidder further agrees to pay as liquidated damages, the sum of Five Hundred Dollars ($500.00) for each consecutive day thereafter.

IN WITNESS WHEREOF, the Parties hereto have executed this contract as of the date shown hereon.

WITNESS: CITY OF BOSSIER CITY

PRINT NAME: _________________________ Thomas H. Chandler, Mayor

PRINT NAME: _________________________ Date Signed

WITNESS:

PRINT NAME: _________________________ Contractor (Company Name)

PRINT NAME: _________________________ Signature, Title Date Signed

D-2

AFFIDAVIT ATTESTING THAT PUBLIC CONTRACT

WAS NOT SECURED

THROUGH EMPLOYMENT OR PAYMENT OF SOLICITOR

Attachment 1. Contract Agreement

All architects, engineers, contractors, subcontractors, or any person, corporation, firm, association, or other organization receiving value for services rendered in connection with this contract shall execute the following affidavit:

BEFORE ME, the undersigned Notary Public, duly qualified and commissioned, came and appeared authorized representative of who does hereby state as follows, to-wit:

1) that I employed no person, corporation, firm, association, or other organization, either directly or indirectly, to secure the public contract under which he received payment, other than persons regularly employed by me whose services in connection with the construction of the public building or project or in securing the public contract in the regular course of their duties for me; and

2) that no part of the contract price received by me was paid or will be paid to any person, corporation, firm, association, or other organization for soliciting the contract, other than the payment of their normal compensation to persons regularly employed by me whose services in connection with the construction of the public building or project were in the regular course of their duties for me.

THUS D O N E A N D PASSED before me, Notary, on this 20 .

day of

By:

Signature and Title

Notary Public

D-3

CORPORATE RESOLUTION

Name of Company: _______________________________________________________

Be it resolved by the Board of Directors/Members/Managers of _________________, a corporation/limited liability company (“Company”) organized and existing under the laws of the State of ________________________ and domiciled in _______________________, do hereby resolve that __________________________ is hereby authorized to sign any and all contracts and/or agreements with the City of Bossier City and to do any and all things necessary to execute the contracts and/or agreements on behalf of the Company.

That I, ________________________, ______________________ hereby certify that

(Name) (Position of Authority) the above and forgoing resolution is a true and correct copy of a resolution of the Board of

Directors/Members of the Company which was passed at a meeting, duly called on

____________________, at which a quorum was present. The foregoing resolution has been entered into the records of the Company, has not been rescinded or modified, and remains in full force and effect on this date.

IN WITNESS WHEREOF, the undersigned have executed this consent this

_________ day of ____________________, 2025.

WITNESSES:

Printed name: _________________ SIGNATURE

Printed name: _________________

NOTARY PUBLIC

D-4

Acceptance of Agency Signature of Contractor or Subcontractor Authorized Acceptor Date (mm/dd/yyyy)

Name of Contractor’s or Subcontractor’s Acceptor

Name of Contractor

Address

City State ZIP

R-1020 (4/12)

Designation of Construction Contractor as Agent of a Governmental Entity

Sales Tax Exemption Certificate

City of Bossier City , an agency of the United Legal Name of Governmental Entity

States government, or an agency, board, commission, or instrumentality of the State of Louisiana or its political subdivisions, including parishes, municipalities and school boards, does hereby designate the following contractor as its agent for the purpose of making sales tax exempt purchases on behalf of the governmental body:

Name of Contractor

Address

City State ZIP

This designation of agency shall be effective for purchases of component construction materials, taxable services and leases and rentals of tangible personal property for the following named construction project:

Construction Project Contract Number

This designation and acceptance of agency is effective for the period

Beginning Date (mm/dd/yyyy) End Date (mm/dd/yyyy)

Purchases for the named project during this period by the designated contractor shall be considered as the legal equivalent of purchases directly by the governmental body. Any materials purchased by this agent shall immediately, upon the vendor’s delivery to the agent, become the property of this government entity. This government entity, as principal, assumes direct liability to the vendor for the payment of any property, services, leases, or rentals made by this designated agent. This agreement does not void or supersede the obligations of any party created under any construction contract related to this project, including specifically any contractual obligation of the construc-tion contractor to submit payment to the vendors of materials or services for the project.

This contractor-agent is not authorized to delegate this purchasing agency to others; separate designations of agency by this governmental entity are required for each contractor or sub-contractor who is to purchase on behalf of this governmental entity.

The undersigned hereby certify that this designation is the entirety of the agency designation agreement between them. In order for a purchase for an eligible governmental entity through a designated agent to be eligible for sales tax exemption, the designation of agency must be made, accepted, and disclosed to the vendor before or at the time of the purchase transaction.

This designation of agency form, when properly executed by both the contractor and the governmental entity, shall serve as evidence of the sales tax exempt status that has been conferred onto the contractor. No other exemption certificate form is necessary to claim exemption from sales taxes. The agency agreement evidenced by this sales tax exemption certificate must be implemented at the time of contract execution with the governmental entity. The contract between the governmental entity and his agent must contain provisions to authenticate the conferment of agency.

Designation of Agency Signature of Authorized Designator Date (mm/dd/yyyy)

Name of Authorized Designator

Name of Governmental Entity City of Bossier City Address

620 Benton Road City

Bossier City State

LA

ZIP

71111

D-5

Name of Project Project No.

STATE OF _____________________

PARISH OF ____________________

ATTESTATIONS AFFIDAVIT

Before me, the undersigned notary public, duly commissioned and qualified in and for the parish and state aforesaid, personally came and appeared Affiant, who after being duly sworn, attested as follows:

LA. R.S. 38:2227 PAST CRIMINAL CONVICTIONS OF BIDDERS

A. No sole proprietor or individual partner, incorporator, director, manager, officer, organizer, or member who has a minimum of a ten percent (10%) ownership in the bidding entity named below has been convicted of, or has entered a plea of guilty or nolo contendere to any of the following state crimes or equivalent federal crimes:

(a) Public bribery (R.S. 14:118) (c) Extortion (R.S. 14:66)

(b) Corrupt influencing (R.S. 14:120) (d) Money laundering (R.S. 14:230)

B. Within the past five years from the project bid date, no sole proprietor or individual partner, incorporator, director, manager, officer, organizer, or member who has a minimum of a ten percent (10%) ownership in the bidding entity named below has been convicted of, or has entered a plea of guilty or nolo contendere to any of the following state crimes or equivalent federal crimes, during the solicitation or execution of a contract or bid awarded pursuant to the provisions of Chapter 10 of Title 38 of the Louisiana Revised Statutes:

(a) Theft (R.S. 14:67)

(b) Identity Theft (R.S.

14:67.16)

(c) Theft of a business record (R.S.14:67.20)

(d) False accounting (R.S.

14:70)

(e) Issuing worthless checks

(R.S. 14:71)

(f) Bank fraud (R.S. 14:71.1)

(g) Forgery (R.S. 14:72)

(h) Contractors; misapplication of payments (R.S. 14:202)

(i) Malfeasance in office (R.S. 14:134)

LA. R.S. 38:2212.10 VERIFICATION OF EMPLOYEES

A. At the time of bidding, Appearer is registered and participates in a status verification system to verify that all new hires in the state of Louisiana are legal citizens of the United States or are legal aliens.

B. If awarded the contract, Appearer shall continue, during the term of the contract, to utilize a status verification system to verify the legal status of all new employees in the state of Louisiana.

C. If awarded the contract, Appearer shall require all subcontractors to submit to it a sworn affidavit verifying compliance with Paragraphs (A) and (B) of this Subsection.

D-6

Name of Project Project No.

LA. R.S. 23:1726(B) CERTIFICATION REGARDING UNPAID WORKERS COMPENSATION

INSURANCE

A. R.S. 23:1726 (B) prohibits any entity against whom an assessment under Part X of Chapter 11 of Title 23 of the Louisiana Revised Statutes of 1950 (Alternative Collection Procedures & Assessments) is in effect, and whose right to appeal that assessment is exhausted, from submitting a bid or proposal for or obtaining any contract pursuant to Chapter 10 of Title 38 of the Louisiana Revised Statutes of 1950 and Chapters 16 and 17 of Title 39 of the Louisiana Revised Statutes of 1950.

B. By signing this bid/proposal, Affiant certifies that no such assessment is in effect against the bidding / proposing entity.

NAME OF BIDDER NAME OF AUTHORIZED SIGNATORY OF BIDDER

DATE TITLE OF AUTHORIZED SIGNATORY OF BIDDER

SIGNATURE OF

AUTHORIZED SIGNATORY

OF BIDDER

Sworn to and subscribed before me by Affiant on the day of , 20 .

Notary Public

FAX: (318) 741-8970

E-MAIL – beauchemind@bossiercity.org

E-1

PERFORMANCE/PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS that of hereinafter called Principal, and hereinafter called Surety, are held and firmly bound unto the City of Bossier City, State of Louisiana, hereinafter called OWNER, in the penal sum of ($ ) in lawful money of the United States, for payment of which sum well and truly to be made, we bind ourselves, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the OWNER, dated day of 20 , a copy of which is hereto attached and made a part hereof for the construction of:

NOW, THEREFORE, if the Principal shall promptly make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor the prosecution of WORK provided for in such contract, and any authorized extension or modification thereof, including, but not limited to, all amounts due for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such WORK, and all insurance premiums on said WORK, and for all labor, performed in such WORK whether by SUBCONTRACTOR or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

AND THEREFORE, if the Principal shall well, truly, and faithfully perform its duties, all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term thereof, and any extensions thereof which may be granted by the OWNER, with or without notice to the Surety and during the one year guaranty period, and if he shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless the OWNER from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the OWNER all outlay and expense which the OWNER may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the WORK to be performed thereunder or the SPECIFICATION accompanying the same shall in any way affect its obligation on this BOND, and it does hereby waive notice of any such change, extension of time, alteration, or addition to the terms of the contract or to the WORK or to the SPECIFICATIONS.

PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

IN WITNESS WHEREOF, this instrument is executed in counterparts, each one of which shall be deemed an original, this day of , 20 .

ATTEST:

PRINCIPAL

BY:

SURETY

BY:

Note: Date of bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute bond.

Important: Surety companies must meet the requirements outlined in LA RS 38:2219 to write surety bonds and insurance for the public works project.

MAINTENANCE BOND

E-2

MAINTENANCE BOND

(Only if required in the Legal Notice to Bidders)

Bond No.

KNOW ALL MEN BY THESE PRESENTS:

That of as Principal, hereinafter called CONTRACTOR, and a Corporation duly existing under the laws of the State of Louisiana and hereinafter called SURETY, are held and firmly bound unto the CITY OF BOSSIER CITY as obligee, hereinafter called CITY, for 10% of the contract price in the amount of ($ ) for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, Contractor, by written agreement dated _________________________ entered into a contract with the City of Bossier City for:

which contract is by reference made a part hereof, and is hereinafter referred to as the CONTRACT.

NOW THEREFORE, the condition of this obligation is such that if the Contractor upon receiving notice within a period of from the date of final acceptance of said Contract of any defects in the work performed under said Contract which are directly attributed to defective materials or workmanship, shall promptly correct said defects, then this obligation shall be null and void; otherwise, it shall remain in full force and effect. No right of action shall accrue on this bond to or for the use of any person or corporation other than the CITY named herein.

SIGNED AND SEALED this day of 20

ATTEST:

(CONTRACTOR/PRINCIPAL)

(SURETY)

GENERAL CONDITIONS

G-1

1.1 INSURANCE/BOND/INDEMNIFICATION REQUIREMENTS OF

CONSTRUCTION/PUBLIC WORKS CONTRACTORS

(Give a copy of these requirements to your agent)

1.2 INSURANCE DEFINITIONS:

1.2.1 Insurance Company: The company or firm which will protect the Contractor from claims which may arise out of or result from the Contractor’s operations and for which the Contractor may be legally liable. An acceptable insurance company is defined as one licensed in the State of Louisiana or an “approved non-admitted” carrier. Generally, as a minimum, the company issuing a bond must have a current A.M. Best rating of A- or better. Companies providing insurance coverage other than bonds must have a current A.M. Best rating of A-, Financial Size Category VII or better. This rating requirement will be waived for the Workers’ Compensation only on Admitted insurers offering statutory benefits This waiver shall not apply to Self-Insured Funds without prior, written consent of the City.

1.2.2 Surety: The bondsman, party or parties who may guarantee the fulfillment of the contract by bond. An “acceptable surety company” is defined to be a company that is either domiciled in Louisiana or owned by Louisiana residents and is licensed to write surety bonds or appears on the current “Treasury List” (i.e., U.S. Department of the Treasury Circular 570, Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies) and approved for an amount equal to or greater than the amount of contract, licensed in the State of Louisiana and qualified to write bonds in the State of Louisiana.

1.3 SURETY AND CONTRACT BONDS:

1.3.1 Proposal Guaranty: The bid must be accompanied by a bid bond in an amount not less than 5% of the total bid amount including additive alternates. The proposal guaranty shall be a check certified by the cashier of a National or State Bank, or a bid bond guaranteed by an acceptable surety company. The certified check or bid bond shall be made payable to the City of Bossier, Louisiana. A cashier’s check or money order will be accepted; however, currency will not be accepted.

1.3.2 Procurement of Surety Bonds and Insurance: Surety bonds written for public works project shall be written by a surety or insurance company currently on the U.S.

Department of Treasury Financial Management Service list of approved bonding companies which is published annually in the Federal Register or by an insurance company that is either domiciled in Louisiana or owned by Louisiana residents and is licensed to write surety bonds. For any public works project, no surety or insurance company shall write a bond which is in excess the amount indicated as approved by the U.S. Department of the Treasury Financial Management Service list; companies authorized by this Paragraph who are not on the treasury list shall not write a bond when the penalty exceeds 15 percent of its capital and surplus, such capital and surplus being the amount by which the company’s assets exceed its liabilities as reflected by the most

G-2 recent financial statements filed by the company with the Department of Insurance. In addition, any surety bond written for a public works project shall be written by a surety or insurance company that is currently licensed to do business in the State of Louisiana.

1.3.3 Performance/Payment Bond: The Contractor shall furnish a Corporate Surety Bond in an amount at least equal to 100% of the contract price, guaranteeing the faithful performance of this contract and the payment of all persons performing labor and furnishing equipment and material in connection with this contract. Prior to the execution of the contract, the Contractor shall file the bond with the City with an acceptable surety company, as defined herein. The bond must be signed by both the Contractor and Surety.

1.3.4 Maintenance Bond: When required the Contractor shall furnish a Maintenance Bond equal to 10% of the contract price for the maintenance and repair of any and all structural defects which may develop or occur due to defective material and/or workmanship for a period specified under this contract beginning the date the Certificate of Substantial Completion for the project is issued by the Owner.

1.3.5 The insurance required shall be written for not less than limits of liability specified herein. Coverages shall be written on forms which include contractual liability and independent contractor coverage on an occurrence basis and products/completed operations coverage. Products/completed operations coverage shall be maintained for a two-year period from the date of final payment. The coverage shall be maintained without interruption from date of commencement of the work until date of final payment and termination of any coverage required to be maintained after final payment.

1.4 PROPERTY INSURANCE

1.4.1 Contractor shall obtain at Contractor’s cost such Property insurance covering the work as may be specified in special provisions of the contract.

1.4.2 Certificates of Insurance shall be filed with the City prior to commencement of the work.

The City has the right to require certified copies of the policies included with the certificates. Evidence that the Authorized Representative signing the Certificate is authorized to bind the insurance company or companies affording coverage may also be required. These certificate and insurance policies required by this shall contain a provision that coverages afforded under the policies will not be materially changed or canceled until at least a 30-day prior written notice has been given to the City by the insurance company. In the event the polices are canceled due to nonpayment of premium, only a 10-day notice will be required. If any of the foregoing insurance coverages are required to remain in force after final payment and are reasonably available, an additional certificate evidencing continuation of such coverages shall be submitted with the final Application for Payment information concerning reduction of coverage shall be furnished by the Contractor with reasonable promptness in accordance with the Contractor’s information and belief.

G-3

1.5 INDEMNIFICATION

1.5.1 To the fullest extent permitted by law, the Contractor shall indemnify, defend, and hold harmless the City and its agents and employees from and against claims, damages, losses and expenses, including but not limited to Attorney’s fees, arising out of or resulting from performance of the work, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury or destruction of tangible property (other than work itself) including loss of use resulting therefrom, but only to the extent caused in whole or in part by negligent acts or omissions of the Contractor, a subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity which would otherwise exist as to a party or person described in this Paragraph.

1.5.2 In claims against any person or entity indemnified under this Paragraph by an employee of the Contractor, a subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under this shall not be limited by a restriction on amount or type of damages, compensation or benefits payable by or for the Contractor or a subcontractor under workers’ or workmen compensation acts, disability benefit acts or other employee benefit acts.

1.6 USE OF LANDS

1.6.1 Preservation and Restoration of Railway Property: The provision given elsewhere herein, which require the Contractor to protect property against damage, and which place upon the Contractor all responsibility for damage to property, injury to person, and loss, expense, inconvenience and delay to the owners of property and others, shall be understood to apply in connection with railway lines or railroads the same as in connection with other kinds of property. In the protection of railway lines and railroad, however, the Contractor will be required to exercise particular care to avoid any damage which might result in train wrecks or in delays in train service. In the performance of work in close proximity to railroad tracks, the Contractor shall consult with the railroad owners or officials in regard to means and methods of conducting the work, and, unless the City orders otherwise, he shall use in the performance of the work means and methods which are not unsatisfactory to said owners or officials, and he shall at his own expense provide such track walkers and flag men as the said owners and officials may deem necessary for the adequate protection of the railroad property and train services. The Contractor shall be solely and directly responsible to the owners and operators of such properties for any damage, injury, expense, loss, inconvenience or delay which may result from carrying out of the work to be done under this contract, and, if the special provisions so specify, he shall give bond or insurance in the amount therein specified to each corporation, company, partnership, or individual owning or operating any of the properties affected, in guarantee of this responsibility. Any extension of time granted the Contractor in which to complete the contract shall not relieve him or his surety from this responsibility.

G-4

1.7 RESPONSIBILITY FOR DAMAGE CLAIMS

1.7.1 Contractor’s Responsibility: Until final written acceptance of the project by the City, the

Contractor shall have the change and care thereof and shall take every precaution against injury or damage to any part thereof by the action of the elements, or from any other cause, whether arising from the execution or from the non-execution of the work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof except damage to the work due to unforeseeable causes beyond the control of and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, of the public enemy or of governmental…