This is a Bid Notice (RFQ) issued by the City of Dixon, California for the Competition Pool Replaster Project #100597. The project involves obtaining all required permits and replastering the competition pool at the Pat Granucci Aquatics Center. The scope of work includes stripping existing plaster down to the concrete substrate and removal, followed by replacement of multiple components including floor return caps, 6-inch by 6-inch standard waterline tile, A-7250 gutter cap tile, eight 12-inch racing lanes, VGB-compliant main drain covers, sixteen 12-inch targets, stainless-steel gutter caps, waterline depth markers on the cantilever face, deck depth-marker mosaics, 8-inch by 8-inch international "No Diving" markers, the 4-inch tile band at the 4-foot-6-inch depth, tile surrounding the floor returns, three wall steps, trim tile on the shallow-end steps, and all tile on the top step. Existing pool lights and handrails will be carefully removed and reinstalled, with the gutter resealed and new white plaster applied in accordance with project requirements. Bids are being accepted from November 5, 2026 at 9:00 p.m. through November 19, 2026 at 3:00 p.m. Contact Austin George at the City of Dixon at (707) 678-7441.
The estimated project cost is $225,000.00. The scope of work is to be verified by the contractor prior to bid submission. No information regarding set-asides, incumbents, site visits, prebid meetings, award dates, or contract term is provided in the bid notice.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ - COMPETITION POOL REPLASTER PROJECT #100597
The work will consist of obtaining all required permits and replastering the competition pool at the Pat Granucci Aquatics Center. The existing plaster will be stripped down to the concrete substrate and removed. The contractor will remove and replace the floor return caps, 6-inch by 6-inch standard waterline tile, A-7250 gutter cap tile, eight 12-inch racing lanes, VGB-compliant main drain covers, sixteen 12- inch targets, stainless-steel gutter caps, waterline depth markers on the cantilever face, deck depth-marker mosaics, 8-inch by 8-inch international “No Diving” markers, the 4- inch tile band at the 4-foot-6-inch depth, tile surrounding the floor returns, three wall steps, trim tile on the shallow-end steps, and all tile on the top step. Existing pool lights and handrails will be carefully removed and reinstalled. The gutter will be resealed, and the pool will receive new white plaster in accordance with the project requirements. Scope of work to be verified by contractor. The estimated cost for this project is $225,000.00
Status Accepting Bids
11/5/26 9:00pm 11/19/26 3:00pm
Company & Contacts City of Dixon Austin George
(707) 678-7441
Location Dixon
Prebid Date Bid Date