Bid Notice-CTSI EV Charging Project.pdf
PDF 360 KB Posted
- Attached to
- CTSI EV Fast Charging Network Project
- Solicitation number
- CTSI-PLAN-EV-2026-01
- Issued by
- Klamath County, Oregon
About this file
This Request for Proposals (RFP) issued by the Confederated Tribes of Siletz Indians (CTSI) Planning Department seeks turnkey design-build services for a regional electric vehicle charging network consisting of up to thirty-two (32) DC Fast Charging ports across multiple sites throughout Lincoln County, Oregon. The project encompasses design, permitting, procurement, installation, commissioning, and maintenance of Level 3 DC fast charging stations capable of serving public, tribal government, fleet, transit, and emergency response vehicles. The RFP was issued on June 15, 2026, with questions due by July 1, 2026, and proposals due on July 15, 2026. The anticipated locations include multiple CTSI facilities in Siletz and Lincoln City, including the Tribal Administration Campus, Clinic Campus, USDA Campus, Public Works Facility, Emergency Operations Center, Tribal Housing Areas, and Chinook Winds Casino and Resort, with the option for CTSI to identify additional sites during implementation. The Notice of Intent to Award is scheduled for July 28, 2026, contingent upon Tribal Council approval.
The contract is structured as a fixed-price design-build engagement divided into five phases: Planning & Engineering, Equipment Procurement, Construction, Commissioning, and optional maintenance services spanning years two through five following a one-year warranty period. Proposers must submit a detailed cost proposal broken down by engineering, equipment, construction, commissioning, and optional services for solar integration and battery storage. All proposals require a bid guarantee equivalent to 5 percent of the bid price, and successful contractors must provide performance and payment bonds totaling 100 percent of the total contract price or alternative assurance methods within ten days of award. Indian Preference, as defined under Siletz Tribal Code 2.001, shall be applied to qualified entities documenting 51 percent or more ownership by enrolled Native Americans or tribes, with fifteen points allocated under the evaluation criteria for this preference. The project is anticipated to be funded through federal infrastructure opportunities including ODOE Community Renewable Energy, FHWA NEVI, EPA Clean Communities, and BIA Energy programs. Minimum qualifications include demonstrated EV charging experience, licensed electrical contractor status, Oregon-licensed engineering support, and public-sector project experience, with preferred qualifications including tribal project experience and Federal grant experience.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS (RFP)
CTSI EV FAST CHARGING NETWORK PROJECT
Design, Permitting, Procurement, Installation, Commissioning, and Maintenance of
Up to Thirty-Two (32) DC Fast Charging Ports in Lincoln County, Oregon
Issued By: Confederated Tribes of Siletz Indians (CTSI) – Planning Department
Project Location: Multiple CTSI sites within Lincoln County, Oregon
RFP Number: CTSI-PLAN-EV-2026-01
Issue Date: 06/15/2026
Proposal Due Date: 07/15/2026
Contract Type: Fixed Price Design-Build Contract
1. INVITATION
The Confederated Tribes of Siletz Indians (CTSI) seeks proposals from qualified firms to provide turnkey design-build services for a regional electric vehicle (EV) charging network consisting of up to thirty-two (32) DC Fast Charging ports throughout Lincoln
County, Oregon.
The final configuration may consist of any combination of single-port and dual-port
Level 3 charging stations capable of serving public, tribal government, fleet, transit, and emergency response vehicles.
CTSI intends to establish a countywide EV charging network supporting:
• Tribal government operations
• Tribal transit vehicles
• Community charging access
• Emergency management resilience
• Economic development
• Tourism and regional travel
• Future fleet electrification
The selected proposer shall provide all labor, equipment, materials, engineering, permitting, utility coordination, construction, commissioning, software integration, warranty support, and optional maintenance services.
This procurement shall be conducted in accordance with CTSI Procurement Policies, Indian Preference requirements, applicable Federal grant requirements, and applicable
Oregon laws. Indian preference shall be applied to the greatest extent feasible.
2. PROJECT OBJECTIVES
CTSI desires to:
Objective 1
Construct a countywide EV charging network.
Objective 2
Provide a minimum of 32 charging ports.
Objective 3
Support future electric:
• Tribal fleet vehicles
• Transit vehicles
• Government vehicles
• Emergency response vehicles
Objective 4
Improve transportation resilience during disasters.
Objective 5
Create charging opportunities for residents and visitors.
Objective 6
Support future renewable energy integration and battery storage.
3. ANTICIPATED LOCATIONS
Potential locations may include:
Siletz
• Tribal Administration Campus
• Clinic Campus (Siletz and Lincoln City Campus)
• USDA Campus
• Public Works Facility
• Emergency Operations Center
Lincoln City
• Tribal Housing Areas
• Chinook Winds Casino and Resort
Additional Sites
As identified by CTSI during implementation.
CTSI reserves the right to modify locations before award.
Projected locations :
https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R263688 https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R17619 https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R112783 https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R523211 https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R503282 https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R503276 https://propertyweb.co.lincoln.or.us/Property-Detail/PropertyQuickRefID/R229779
4. PROJECT SCOPE OF WORK
Phase 1 – Planning & Engineering
Contractor shall:
• Conduct site evaluations
• Utility load assessments
• Electrical engineering
• Geotechnical review as necessary
• Civil engineering
• ADA compliance review
• Traffic circulation analysis
• Prepare construction drawings
• Obtain permits
• Coordinate with utilities
Phase 2 – Equipment Procurement
Contractor shall provide all equipment including:
DC Fast Chargers
Minimum requirements:
• CCS charging standard
• NACS compatibility or adapter capability
• OCPP compliant
• Networked chargers
• RFID capable
• Credit card capable
• Fleet management capability
• Load balancing capability
• Remote diagnostics
• UL listed equipment
Minimum Charger Output
One or more of:
• 250 kW+
• 350 kW+
• 500 kW+
Port Configuration
Any combination of:
• 32 single ports
• 16 dual-port chargers
• Mixed configuration provided the total installed charging ports equals or exceeds 32 total ports.
Phase 3 – Construction
Contractor shall provide:
• Site preparation
• Trenching
• Conduit installation
• Utility upgrades
• Concrete foundations
• Equipment installation
• Striping
• Signage
• Lighting
• ADA improvements
• Landscaping restoration
Phase 4 – Commissioning
Contractor shall:
• Perform startup testing
• Utility coordination
• Network integration
• User acceptance testing
• Staff training
• Final commissioning
Phase 5 – Optional Maintenance
Proposers shall provide pricing for:
Year 1
Warranty support
Years 2–5
Optional maintenance agreement
Including:
• Preventative maintenance
• Software updates
• Repairs
• Annual inspections
5. FUTURE RESILIENCE OPTIONS
Proposers are encouraged to submit optional pricing for:
Solar Integration
• Solar canopies
• Carport systems
Battery Storage
• BESS systems
• Microgrid integration
Emergency Operations
• Backup generation integration
• Emergency vehicle charging priority
6. DELIVERABLES
Selected contractor shall provide:
Design Documents
• 30%
• 60%
• 90%
• Final Construction Documents
Permitting Package
Utility Coordination Package
Construction Schedule
QA/QC Plan
Safety Plan
Training Materials
Warranty Documents
As-Built Drawings
GIS Data
Provide GIS-compatible data including:
• Charger locations
• Utility connections
• Asset inventory
7. PROPOSAL FORMAT
Proposals shall include:
Section 1
Cover Letter
Section 2
Firm Qualifications
Section 3
Project Team
Section 4
Relevant Experience
Minimum three comparable projects.
Section 5
Technical Approach
Section 6
Schedule
Section 7
Indian Preference Plan
Required.
Must describe:
• Employment opportunities
• Subcontracting opportunities
• Tribal partnerships
• Workforce development
Failure to submit may result in rejection.
Section 8
Cost Proposal
Provide:
• Engineering
• Equipment
• Construction
• Commissioning
• Maintenance
• Optional solar
• Optional battery storage
Section 9
References
Minimum three.
Section 10
Litigation Disclosure
Section 11
Insurance Certificates
8. MINIMUM QUALIFICATIONS
Proposers must demonstrate:
• EV charging experience
• Licensed electrical contractor
• Oregon licensed engineering support
• Ability to perform utility coordination
• Financial capability
• Experience with public-sector projects
Preferred:
• Tribal project experience
• Federal grant experience
• NEVI program experience
9. EVALUATION CRITERIA
Criteria
Technical Approach
Relevant Experience
Project Team
Cost Proposal
Schedule
Operations & Maintenance
Indian Preference
Total
Indian Preference points shall be awarded in accordance with CTSI procurement requirements.
10. INDIAN PREFERENCE
CTSI shall provide Indian Preference to the greatest extent feasible in accordance with
CTSI Tribal Code and applicable federal requirements.
Offerors shall submit:
Indian Ownership Documentation
If applicable.
Employment Plan
Including:
• Number of tribal members employed
• Training opportunities
• Apprenticeships
Subcontracting Plan
Including use of:
• Tribal firms
• Native-owned firms
• Local businesses
• PART II: MINIMUM QUALIFICATIONS AND SERVICES TO BE
PERFORMED
• All submitters shall, at a minimum, include the following in their proposal pursuant to this RFP:
• 1. Submitter must have proven experience in [insert expertise desired for this project].
• 2. The proposal must clearly detail the costs associated with the services being proposed.
• 3. Submitter must summarize its understanding of the scope of services being requested by the CTSI. Submitter shall describe its approach to meeting
CTSI’s deliverables and objectives in a cost-effective manner.
• 4. Submitter shall provide proof of Indian preference should it apply to the business entity or individual who will be providing the services proposed in this
RFP. Indian preference is provided in accordance with the methods in the Siletz
Tribal Code §2.001. Indian preference applies to a qualified entity documenting
51% or more ownership of a business entity by an enrolled Native
American/Tribe.
• Bonds
• All Proposals must be accompanied by a bid guarantee equivalent to 5% of the bid price. The bid guarantee can be in the form of a bid bond, certified check, bank draft, U.S. Government bonds at par value, or other negotiable instrument.
Failure to submit a bid guarantee with the bid shall result in the rejection of the bid. Bid guarantees submitted by unsuccessful bidders shall be returned as soon as practicable after Proposal evaluation.
• A successful Submitter must submit one of the following forms of assurance of completion within 10 days after contract award and as a condition of any contract:
• (1) Performance and payment bonds in a penal sum of 100% of the total contract price;
• (2) Separate performance and payment bonds, each for 50% or more of the contract price;
• (3) Cash escrow deposited with CTSI of not less than 20% of the total contract price; or
• (4) An irrevocable letter of credit for 25% of the total contract price unconditionally payable upon demand of CTSI.
• Bonds must be obtained from guarantee or surety companies acceptable to the
United States Government. Each bond shall clearly state the rate of premium and the total amount of premium charged. The effective date of the bond shall be on or after the execution date of the contract.
• PART III: EVALUATION FACTORS
• CTSI shall award the contract to the Submitter(s) whose proposal is most advantageous to CTSI, as based on the criteria below:
• Proposals meeting minimum qualifications shall be evaluated on the four criteria listed below. Each proposal shall be scored based on the points allotted to each category, 100 combined points maximum. The number of points assigned to a proposal does not necessarily determine the award of a contract; rather it establishes benchmarks to assist in the overall evaluation of the proposal.
• Experience and Capability Maximum Points: 50
• Submitter’s skill, knowledge and experience advising on Tribal healthcare matters as outlined in this proposal. Relevant experience and qualifications of person(s) who will perform the actual work will be considered under this evaluation factor. If applicable, this rating will focus on those persons assigned to the CTSI contract, rather than the characteristics of the Submitter firm.
• Proposal Format and Criteria Maximum Points: 5
• Submitter’s proposal must be professional, readable, and meet the minimum criteria as listed in Part III and Part V of this document.
• Indian Preference Maximum Points: 15
• CTSI welcomes proposals from all interested persons and businesses. However, in evaluating the relative merit of each proposal and ultimately awarding the contract, CTSI will give an Indian Preference according to the Siletz Tribal Code §
2.001. Fifteen points to businesses documenting 51% or more ownership of business entity by an enrolled Native American/Tribe.
• Fees Maximum Points: 30
• Overall projected costs will be evaluated under this category. Submitter’s proposal should include a detailed list of fees, fee structures and/or fee schedules.
• PART IV: PROPOSAL FORMAT AND INSTRUCTIONS TO SUBMITTER
• Proposals submitted to CTSI must, at a minimum, contain the following information and shall be organized as follows:
• A. Letter of Transmittal to include the following information:
• a. Name, address and telephone number of Submitter and/or Submitting
Firm;
• b. A signature of the Submitter or of any partner, officer or employee who certifies that he or she has the authority to bind the Submitter;
• c. Date of Proposal;
• d. A statement that the Submitter’s proposal is valid for ninety (90) days after the deadline for submission of proposals.
• B. Names and resumes of the key personnel including support staff to be assigned to the account. Resumes describing the qualifications of personnel to be utilized in the performance of this contract must show, at a minimum, the person’s name, education, position, and total years and types of experience relevant to the performance of the contract.
• C. References. Submitter shall include two references, preferably of clients who have worked directly with the primary personnel that will be assigned to
CTSI.
• D. Submitter’s proposal for delivering services that will be provided, including organization of responsibilities, approach, and the availability of personnel for consultation and discussion as necessary to serve the needs of
CTSI.
• E. Detailed cost breakdown. Fee schedule for services and expenses must be included in the proposal. Rates for added alternatives and additional scope of work shall be negotiated at the same rate schedule.
• F. Conflict of Interest Disclosure. Please provide a statement disclosing any current or proposed business transaction between Submitter and any CTSI member, officer, employee or any other potential conflict which may give rise to a claim of conflict of interest. Submitter shall warrant that it has no interest, direct or indirect, which would conflict in any manner or degree with the performance of services under this contract.
• G. Litigation disclosure. Describe any material, current or pending litigation, administrative proceedings or investigations that could impact the reputation or financial viability of your firm.
• H. CTSI requires that Submitter be an Equal Opportunity Employer. Provide a statement that Submitter complies fully with all government regulations regarding nondiscriminatory employment practices and provide a copy of any written EEO, ADA or affirmative action policies presently followed by Submitter.
• I. Proof of Indian Preference, if applicable. Preference will be provided in accordance with the methods set forth in Siletz Tribal Code §2.001. To the greatest extent feasible, preference shall be given to a qualified entity documenting 51% or more ownership of a business entity by an enrolled Native
American/Tribe.
11. INSURANCE REQUIREMENTS
Prior to award:
Commercial General Liability
$2,000,000
Automobile Liability
$1,000,000
Workers Compensation
Statutory Limits
Professional Liability
$2,000,000
Umbrella Coverage
$5,000,000
12. CONTRACT REQUIREMENTS
The resulting contract shall include:
• Federal grant compliance provisions
• Davis-Bacon (if applicable)
• Buy America requirements (if applicable)
• Non-discrimination requirements
• Debarment certification
• Drug-free workplace certification
• Conflict of interest certification
13. SOVEREIGN IMMUNITY
Nothing in this RFP, any proposal, negotiations, contract, or resulting agreement shall be construed as a waiver of the sovereign immunity of the Confederated Tribes of Siletz
Indians. Any waiver must be expressly approved by Tribal Council through formal resolution.
14. CTSI RIGHTS
CTSI reserves the right to:
• Reject any or all proposals
• Waive minor irregularities
• Request clarifications
• Conduct interviews
• Negotiate scope and pricing
• Award without discussions
• Cancel the solicitation
• Reissue the solicitation
• Award multiple contracts
Consistent with tribal procurement authority and competitive procurement requirements.
15. TENTATIVE SCHEDULE
Milestone
RFP Issued – 06/15/2026
Questions Due 07/01/2026
Proposals Due 07/15/2026
Interviews
Notice of Intent to Award 07/28/2026
Tribal Council Approval (Unk eta)
Notice to Proceed (unk eta)
APPENDIX A – PROPOSED SYSTEM CONCEPT
Target Buildout: 32 DC Fast Charging Ports
Example configuration:
• 8 dual-port 350 kW chargers = 16 ports
• 4 dual-port 180 kW chargers = 8 ports
• 8 single-port 150 kW chargers = 8 ports
Total = 32 ports
ODOE Community Renewable Energy, FHWA NEVI, EPA Clean Communities, BIA
Energy, and other federal infrastructure funding opportunities.
File details come from the government source that posted it. Updated .