Bid Notice-Construction Demolition _ Industrial Waste Hauling.pdf

PDF 469 KB Posted

Attached to
Construction Demolition & Industrial Waste Hauling
Solicitation number
WC27024
Issued by
San Joaquin County, Sunnyvale City, California

About this file

Summary

This is a Bid Notice for Special Provisions issued by the City of Stockton Public Works Department for a Sidewalk Repairs and ADA Curb Ramp Installation project (Project No. WC27024). The project encompasses sidewalk repairs, curb and gutter installation, and ADA-compliant curb ramp installation at approximately 20 citywide locations. The work includes removal and replacement of concrete sidewalks, curbs, gutters, driveway aprons, and asphalt concrete pavement, with an estimated 114 ADA curb ramps to be installed across various standard and modified designs. Key bid items include mobilization, traffic control, water pollution control, curb-ramp installations per multiple City of Stockton standard details (R-64, R-65, R-66, and modified designs), concrete sidewalk removal and replacement (23,480 square feet), vertical and rolled curb and gutter removal and replacement (680 and 870 linear feet respectively), driveway apron removal and replacement (520 square feet), and additional asphalt pavement work (300 square feet). The bid opening is scheduled for Thursday, October 22, 2026, at 2:00 p.m. The successful contractor must complete all work within 140 working days from the Notice to Proceed, with liquidated damages of $5,200 per day assessed for delays beyond the contract completion date.

The contract requires a Class A California Contractor License, City of Stockton business license, and various permits including encroachment permits, construction notification with the San Joaquin Valley Air Pollution Control District, and Construction and Demolition Debris Recycling Reports. All submittals must be completed within 30 calendar days of the Notice of Award, with 15 calendar days allowed for Engineer review and approval. A pre-construction conference will be scheduled following contract award, and a post-construction conference is required prior to final payment. The contractor must maintain performance and faithful performance bonds, with the faithful performance bond retained for 12 months following recordation of the Notice of Completion and potentially reduced to 10 percent of actual constructed improvement costs thereafter. The contractor is responsible for all labor, materials, equipment, permits, and fees, with compensation included in the bid prices. No separate payment is provided for materials furnished but not yet installed, and failure to submit a complete bid on the City's required forms or to bid all items may result in the bid being deemed non-responsive.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PUBLIC WORKS DEPARTMENT

SPECIAL PROVISIONS

FOR

SIDEWALK REPAIRS AND ADA CURB

RAMP INSTALLATION

PROJECT NO. WC27024

BID OPENING: Thursday, October 22, 2026, 2:00 p.m.

I

Table of Contents

DIVISION I – GENERAL PROVISIONS

SECTION 1 – GENERAL

1-1.01 TERMS AND DEFINITIONS

1-1.02 SPECIFICATIONS

1-1.03 PLANS

SECTION 2 – BIDDING

2-1.01 GENERAL

2-1.02 BID PROTEST

SECTION 3 – CONTRACT AWARD AND EXECUTION

3-1.01 CONTRACT AWARD

3-1.02 CONTRACT EXECUTION

3-1.03 CONTRACT BONDS

SECTION 4 – SCOPE OF WORK

4-1.01 DIFFERING SITE CONDITIONS

4-1.01 EXTRA WORK

4-1.02 CLEANUP

SECTION 5 – CONTROL OF WORK

5-1.01 PERMITS

5-1.02 SUBMITTALS

5-1.03 RECORDS

5-1.04 JOB SITE APPEARANCE

5-1.05 PROPERTY PRESERVATION/EXISTING FACILITIES

5-1.06 PRE-CONSTRUCTION SURVEY

5-1.07 PRESERVING AND PERPETUATING SURVEY MONUMENTS

5-1.08 CONSTRUCTION SURVEY

5-1.09 REQUEST FOR INFORMATION

5-1.10 NOTICE OF POTENTIAL CLAIM

5-1.11 INSPECTIONS

5-1.12 AS-BUILT/RECORD DRAWINGS

5-1.13 SURFACE RESTORATION

5-1.14 RIGHTS IN LAND

5-1.15 STAGING AREA

5-1.16 SITE MAINTENANCE AND CLEANUP

5-1.17 DISPOSAL OF MATERIALS

5-1.18 ENVIRONMENTAL PROTECTION

5-1.19 CONSTRUCTION CONTROL

SECTION 6 – CONTROL OF MATERIALS

II

6-1.01 CITY-FURNISHED MATERIALS

6-1.02 STATE-FURNISHED MATERIALS

6-1.03 BUY AMERICA REQUIREMENTS

6-1.04 QUALITY ASSURANCE PROGRAM

6-1.05 TESTING

6-1.06 PRE-QUALIFIED AND TESTED SIGNING AND DELINEATION MATERIAL

SECTION 7 – LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

7-1.01 PUBLIC CONVENIENCE

7-1.02 PUBLIC SAFETY

7-1.03 PUBLIC NOTIFICATION

SECTION 8 – PROSECUTION AND PROGRESS

8-1.01 SCHEDULE

8-1.02 PRE-CONSTRUCTION CONFERENCE

8-1.03 POST CONSTRUCTION CONFERENCE

8-1.04 BEGINNING OF WORK

8-1.05 TIME OF COMPLETION

8-1.06 LIQUIDATED DAMAGES

8-1.07 CITY OF STOCKTON HOLIDAY SCHEDULE FOR 2026

SECTION 9 – PAYMENT

9-1.01 GENERAL

9-1.02 PAYMENTS

9-1.03 INCREASE OR DECREASE QUANTITIES

9-1.04 MOBILIZATION

9-1.05 STOP NOTICE

9-1.06 DESCRIPTION OF WORK

9-1.07 PROSECUTION AND PROGRESS

9-1.08 QUANTITIES

DIVISION II – GENERAL CONSTRUCTION

SECTION 10 – GENERAL

10-1.01 ORDER OF WORK

10-1.02 MONUMENTS

SECTION 11 – BLANK

SECTION 12 – TEMPORARY TRAFFIC CONTROL

12-1.01 MAINTAINING TRAFFIC

12-1.02 TRAFFIC CONTROL SYSTEM FOR LANE AND ROAD CLOSURE

SECTION 13 – WATER POLLUTION CONTROL

13-1.01 WATER POLLUTION CONTROL

SECTION 14 – ENVIRONMENTAL STEWARDSHIP

III

14-1.01 HAZARDOUS WASTE AND CONTAINMENT

14-1.02 DUST CONTROL

14-1.03 NOISE CONTROL REQUIREMENTS

14-1.04 PRE-CONSTRUCTION MIGRATORY BIRD SURVEY

SECTION15 – EARTHWORK

15-1.01 ROADWAY EXCAVATION

15-1.02 RELATIVE COMPACTION

SECTION 16 – EROSION CONTROL AND HIGHWAY PLANTING

16-1.01 LANDSCAPE REPAIR

16-1.02 EXISTING IMPROVEMENTS

16-1.03 SPRINKLER SYSTEMS, SERVICE WATER LINES AND FENCES

16-1.04 LAWN TURF

16-1.05 REPAIR OF TURFED AREAS

SECTION 17 – HOT MIX ASPHALT

SECTION 18 – MISCELLANEOUS FACILITIES

SECTION 19 – MINOR CONCRETE

SECTION 20 – CURB-RAMP

SECTION 21 – ELECTRICAL

21-1.01 FOUNDATIONS

21-1.02 STANDARDS, STEEL PEDESTALS AND POSTS

Standards, steel pedestals and posts shall conform to the provisions in Section 56-3 “Standards, Poles, Pedestals, and Posts”, and Section 87-1.03J “Standards, Poles, Pedestals, and Posts” of the Caltrans Specifications and these Special Provisions

21-1.03 CONDUIT

21-1.04 COLORED CONTROLLED DENSITY FILL (CDF)

21-1.05 PULL BOXES

SPECIAL PROVISIONS

FOR

SIDEWALK REPAIR AND ADA CURB RAMP INSTALLATION

PROJECT NO. WC27024

DIVISION I – GENERAL PROVISIONS

SECTION 1 – GENERAL

1-1.01 TERMS AND DEFINITIONS

Wherever in the Standard Specifications, Special Provisions, Notice to Contractors, Proposal, Contract, or other contract documents the following terms are used; the intent and meaning shall be interpreted as follows:

City or Owner - City of Stockton

Director - Director of Public Works, City of Stockton

Standard Specifications - City of Stockton, Standard Plans and Specifications, and any amendments or revisions thereto (Revised 9/27/16)

Caltrans Specifications - State of California, Department of Transportation, 2025

Standard Plans and Specifications and any amendments or revisions thereto.

Laboratory - City of Stockton's Department of Public Works or consultant laboratory.

Department - Department of Public Works, City of Stockton Engineer - City Engineer, City of Stockton, acting either directly or through properly authorized Engineer agents and consultants.

MUTCD - Latest edition of California Manual on Uniform Traffic

Control Devices (MUTCD), and any amendments and revisions thereto

1-1.02 SPECIFICATIONS

The work described herein shall be done in accordance with the current City of Stockton, Department of Public Works Standard Specifications and Plans, and the latest Editions of the State of California, Department of Transportation Standard Specifications and Standard Plans, California MUTCD, as referenced therein, and in accordance with the following Special Provisions. To the extent the California Department of Transportation Standard Specifications implement the STATE CONTRACT ACT, they shall not be applicable since the City of Stockton is not subject to said ACT.

In case of conflict or discrepancy between any of the Contract Documents, the order of documents listed below shall be the order of precedence, with the first item listed having the highest precedence.

a. Contract Change Order

b. Contract

c. Project Special Provisions

d. Project Plans

e. City’s Standard Specifications

f. City’s Standard Drawings

g. Revised Caltrans Standard Specifications

h. Caltrans Standard Specifications

i. Revised Caltrans Standard Plans

j. Caltrans Standard Plans

k. Supplemental Project Information

With regards to discrepancies or conflicts between written dimensions given on drawings and the scaled measurements, the written dimensions shall govern.

With regards to discrepancies or conflicts between large-scale drawings and small-scale drawings, the larger scale shall govern.

With regards to discrepancies or conflicts between detailed drawings and referenced standard drawings or plans, the detailed drawings shall govern.

In the event where provisions of codes, safety orders, contract documents, referenced manufacturer’s specifications or industry standards are in conflict, the more restrictive and higher quality shall govern.

Should it appear that the work to be done or any of the matters relative thereto are not sufficiently detailed or explained in these specifications, the special provisions, or the plans, the Contractor shall apply to the Engineer in writing for such further explanations as may be necessary and shall conform to them as part of the contract. All responses from the Engineer shall be in writing. In the event of any doubt or question arising respecting the true meaning of these specifications, the special provisions or the plans, reference shall be made to the Engineer, whose decision thereon shall be final.

The Contractor shall examine carefully the site of the work and the plans and specifications therefore. He/She shall investigate and satisfy himself/herself as to conditions to be encountered, the character, quality and quantity of surface, subsurface materials or obstacles to be encountered, the work to be performed, materials to be furnished, and as to the requirements of the bid, plans and specifications of the contract.

1-1.03 PLANS

The bidder's attention is directed to the provisions in Section 1-1.03, “Definitions” of the Standard Specifications and Section 1-1.07 of the Caltrans Specifications.

See Instructions to Bidders for complete instructions and documentation forms.

SECTION 2 – BIDDING

2-1.01 GENERAL

The bidder's attention is directed to the "Notice to Contractors" for the date, time and location of the mandatory pre-bid meeting, if applicable. Refer to the City of Stockton’s Bid Flash webpage:

https://www.stocktonca.gov/business/contracts___purchasing/bidflash/public_works.php

The bidder's attention is directed to the provisions in Section 2, "Bidding," of the Standard Specifications and these special provisions for the requirements and conditions which the bidder must observe in the preparation for the submission of the bid.

The Bidder's Bond form mentioned in the last paragraph in Section 2-1.34, "Bidder’s Security," of the Standard Specifications will be found following the signature page of the Proposal.

In conformance with Public Contract Code Section 7106, a Non-collusion Affidavit is included in the Proposal. Signing the Proposal shall also constitute the signature of the Non-collusion Affidavit.

The contractor, sub-recipient, or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of Title 49 CFR (Code of Federal Regulations) part 26 in the award and administration of US DOT-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate.

Each subcontract signed by the bidder must include this assurance.

2-1.02 BID PROTEST

In case of Bid protests, attention is directed to the provisions in Section 2-1.51, “Bid Protests” of the Standard Specifications. The party filing the protest must have submitted a bid for the work. A subcontractor of a bidder may not submit a bid protest.

A copy of bid protests is to be sent to the following address:

Attention: Adriana Garibay

City of Stockton Public Works Department

1465 South Lincoln St Stockton, CA 95206

SECTION 3 – CONTRACT AWARD AND EXECUTION

3-1.01 CONTRACT AWARD

The bidder's attention is directed to the provisions in Section 3, " Contract Award and Execution," of the Standard Specifications and these special provisions for the requirements and conditions concerning award and execution of contract.

https://www.stocktonca.gov/business/contracts___purchasing/bidflash/public_works.php

Bid protests are to be delivered to the following address: Department of Public Works, 1465 South Lincoln Street, Stockton CA Attn: Adriana Garibay. The award of the contract, if it be awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed.

3-1.02 CONTRACT EXECUTION

The contract shall be executed by the successful bidder and shall be returned, together with the contract bonds, to the Agency so that it is received within 10 days, not including Saturdays, Sundays and legal holidays, after the bidder has received the contract for execution. Failure to do so shall be just cause for forfeiture of the proposal guaranty. The executed contract documents shall be delivered to:

City of Stockton Public Works Department

Attn: Adriana Garibay 1465 South Lincoln Street

Stockton, CA 95206

3-1.03 CONTRACT BONDS

Contract Bonds shall conform to the requirements set forth in Section 3-1.05, "Contract Bonds", of the Standard Specifications, except for the second paragraph which shall be replaced with the following:

"The Faithful Performance bond will be retained by the City of Stockton for twelve

(12) months following recordation of the Notice of Completion (or partial completion) to guarantee correction of failure attributed to workmanship and materials. Upon recordation of the Notice of Completion (or partial completion), the amount of the Faithful Performance bond may be reduced to ten percent (10%) of the actual cost of the constructed improvements”.

SECTION 4 – SCOPE OF WORK

4-1.01 DIFFERING SITE CONDITIONS

Attention is directed to the provisions in Section 4-1.06, "Differing Site Conditions," of the Caltrans Specifications and the Standard Specifications. Contractor shall notify the Engineer if he/she finds physical conditions differing materially from contract documents.

4-1.01 EXTRA WORK

Section 4-1.05, “Changes and Extra Work” of the Caltrans Specifications is amended by adding the following between the second and third paragraphs:

“If, in the opinion of the Engineer, such work cannot reasonably be performed concurrently with other items of work, and if a controlling item of work is delayed thereby, an adjustment of contract time will be made.”

4-1.02 CLEANUP

The Contractor’s attention is directed to Sections 4-1.13, “Cleanup,” of the Caltrans Specifications.

The Contractor shall conduct and cause all working forces at the site to maintain the site in a neat orderly manner throughout the construction operations. The work shall be conducted in a manner that will control the dust. When ordered to provide dust control, the Contractor shall use water to reduce the dusty conditions all to the satisfaction of the Engineer. During construction, the Contractor shall remove all rubbish and debris as it is generated. Upon completion of the work, the Contractor shall remove all equipment, debris, and shall leave the site in a neat, clean condition all to the satisfaction of the Engineer.

SECTION 5 – CONTROL OF WORK

5-1.01 PERMITS

The Contractor’s attention is directed to Sections 5-1.20B, “Permits, Licenses, Agreements, and Certifications,” of the Caltrans Specifications.

The following is not an all-inclusive list of the required permits and/or licenses, if applicable:

• Contractor’s License – A valid California Class A Contractor License.

• Business License – Contractor shall possess prior to the execution of the contract and maintain throughout the duration of the contract, a valid City of Stockton business license.

• City of Stockton Encroachment Permit – Contractor is responsible for obtaining a permit and paying fees.

• Construction Notification, Dust Control – The Contractor is responsible for the preparation and submittal of the San Joaquin Valley Air Pollution Control District Construction Notification Form. More information can be found at the following web site: http://www.valleyair.org.

• Construction Water – The Contractor is responsible for obtaining a permit for water from California Water Service or City of Stockton, as applicable, for construction water obtained from a City hydrant. This permit shall be approved by the City of Stockton Fire Department.

• Construction and Demolition (C&D) Debris Recycling Report – Submit report within 14 days of construction or demolition project completion. The completed form must be accompanied by the official weight tags or receipts verifying the information provided in the report and must be submitted to the City of Stockton Public Works Department, Solid Waste Division, 505 W. Weber Ave.

Building 2, Stockton, CA 95203. Failure to provide the C&D Debris Recycling Report form will result in a 5% withholding of the contract amount.

Full compensation for conforming to the provisions in this section including applicable permit fees, shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed, therefore.

5-1.02 SUBMITTALS

The following is a list of anticipated submittals for the project. The list is provided to aid the Contractor in determining the scope of work, but is not intended to be all-inclusive, and additional submittals may be required:

http://www.valleyair.org/

• List of submittals

• DAS-140 & DAS-142

• Shop Drawings

• Material Submittals

• Product Submittals

• Local Hire Employment Ordinance – Good Faith Effort

• Monthly Local Employment Ordinance Compliance Report (During Construction)

• Pre-construction Survey of entire project (dated photos, identified locations, etc.)

• Emergency Contacts/Authorized Representatives

• Traffic Control Plan and Pedestrian Detour Plans

• Water Pollution Control Program (WPCP) by a QSD, Best Management Practices

• Project Schedule (Critical Path Method)

• Public Notifications (Flyers, News Release Letter, etc.)

• City of Stockton Construction and Demolition Debris Recycling Report (within 14 days of construction)

• City of Stockton Encroachment Permit

• City of Stockton Business License

• Staging Agreements with Private Property Owner (if applicable)

• Acknowledgements of Monument Preservation

• Concrete Mix Design

• HMA Mix Design

The Contractor shall transmit each submittal to the Engineer for review and approval.

Submittals shall be sequentially numbered on the submittal list form. Resubmittals shall be identified with the original number and a sequential resubmittal suffix letter. The original submittal shall be numbered X. The first resubmittal shall be numbered X-a and so on. Identify on the form the date of the submittal, and Contractor, Subcontractor or supplier. Any incomplete submittals will be returned for resubmittal.

Schedule submittals to expedite the Project, and deliver to Engineer at the Engineer’s office, see Section 10-1.01, “Order of Work,” of these Special Provisions.

For each submittal for review, allow 15 calendar days excluding delivery time to and from the Contractor.

When revised for resubmission, identify all changes made since previous submission.

Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

Within 10 calendar days after Notice of Award submit a complete list of all submittals to be submitted and the dates when they will be submitted.

All submittals shall be submitted within 30 calendar days from the date of the Notice of Award; otherwise, project working days will commence, with or without issuance of the Notice to Proceed.

Wherever called for in the Contract Documents, or where required by the Engineer, the Contractor shall furnish to the Engineer for review, 1 set, plus one reproducible copy, of each shop drawing submittal. The term “Shop Drawings” as used herein shall be understood to include detail design calculations, shop drawings, fabrication and installation drawings, erection drawings, list, graphs, catalog sheets, data sheets, and similar items. Whenever the Contractor is required to submit design calculations as part of a submittal, such calculations shall bear the signature and seal of an engineer registered in the appropriate branch and in the state of California, unless otherwise directed.

Normally, a separate submittal form shall be used for each specific item or class of material or equipment for which a submittal is required. Transmittal of a submittal of various items using a single form will be permitted only when the items taken together constitute a manufacturer’s “package” or are so functionally related that expediency indicates review of the group or package as a whole. A multi-page submittal shall be collated into sets, and each set shall be stapled or bound, as appropriate, prior to transmittal to the Engineer.

Except as may otherwise be indicated herein, the Engineer will return prints of each submittal to the Contractor with their comments noted on the submittal. The Contractor shall make complete and acceptable submittals to the Engineer by the second submission of a submittal item. The City reserves the right to withhold monies due to the Contractor to cover additional costs of the Engineer’s review beyond the second submittal.

If a submittal is returned to the Contractor marked “NO EXCEPTIONS TAKEN”, formal revision and resubmission of said submittal will not be required.

If a submittal is returned to the Contractor marked “MAKE CORRECTIONS NOTED”, formal revision and resubmission of said submittal will not be required.

5-1.03 RECORDS

The Contractor’s attention is directed to Sections 5-1.27, “Records,” of the Caltrans Specifications.

The cost accounting records for the contract shall be maintained separately from other contracts, during the life of the contract, and for a period of not less than 3 years after the date of acceptance of the contract. If the Contractor intends to file claims against the City, the Contractor shall keep the cost accounting records specified above until complete resolution of all claims has been reached.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.04 JOB SITE APPEARANCE

The Contractor shall maintain a neat appearance to the work.

Debris developed during construction shall be disposed of concurrently with its generation. The Contractor shall pay to the City of Stockton the sum of Two Hundred

Fifty Dollars ($250) for every calendar day where debris has remained on the job site overnight.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work and no additional compensation will be allowed therefore.

5-1.05 PROPERTY PRESERVATION/EXISTING FACILITIES

The Contractor’s attention is directed to Sections 5-1.36, “Property and Facility Preservation,” and Section 15, “Existing Facilities,” of the Caltrans Specifications.

The Contractor's attention is directed to the existence of certain underground facilities that may require special precautions be taken by the Contractor to protect the health, safety, and welfare of workers and of the public. Facilities requiring special precautions include, but are not limited to, conductors of petroleum products, oxygen, chlorine, and toxic or flammable gases, natural gas in pipelines six (6) inches or greater in diameter, or pipelines operating at pressures greater than60 psi (gage); underground electric supply system conductors or cables with potential to ground of more than 300 V, either directly buried or in duct or conduit, which do not have concentric grounded or other effectively grounded metal shields or sheaths.

The Contractor shall notify the Engineer and the appropriate regional notification center for operators of subsurface installations at least two (2) working days, prior to performing any excavation or other work close to any underground pipeline, conduit, duct, wire, or other structure. Regional notification centers include, but are not limited to, the following:

Notification Center Telephone Number Underground Service Alert – Northern California (USA)

(800) 227-2600

Immediately upon encountering unknown existing facilities, the Contractor shall notify the Engineer in writing of the situation, request coverage of the work as extra work, and aid the Engineer in determining due diligence. Failure to do so may result in forfeiture of any rights to receive extra work compensation under Section 8-1.07, “Delays,” of the Caltrans Specifications. Should the Contractor stop work, no compensation will be made for any "down time" prior to written notifications being received by the Engineer or his representative.

Delays due to encountering unexpected facilities shall be determined and compensated in accordance with the provisions of Section 8-1.07, “Delays,” of the Caltrans Specifications, and as herein modified. Delays due to encountering unexpected facilities shall be compensated as additional contract working days to the contractor. Contractor shall submit a written request to the Engineer requesting time extension due to the delay.

No other compensation is allowed.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.06 PRE-CONSTRUCTION SURVEY

The Contractor shall perform pre‐construction and post‐construction survey of all existing driveways, mailboxes, fences, structures, pavements, and other above-ground facilities within the project limits prior to beginning any work, noting their condition by means of dated photographs and video.

Color photographs shall be taken with a digital camera at locations (property sites) that are appropriate to show pre‐existing conditions and after-constructed conditions. Each photograph shall show the date and time the photograph was taken and clearly be labeled showing the location, viewing direction, and any special features noted. Digital copies of photographs and video shall be submitted to the City prior to approval of the project.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.07 PRESERVING AND PERPETUATING SURVEY MONUMENTS

Action by: Action:

Contractor's Land Surveyor 1. Identifies existing survey monuments.

2. Lists all existing survey monuments.

3. Ties out / performs construction staking of survey monuments.

4. Indicates survey monuments on construction plans.

5. Files all pre-construction Corner Records or

Records of Survey with San Joaquin County. The Corner Records or Record of Survey will show monuments within the area of construction reasonably subject to removal or disturbance not shown on a recent record document (recent record document is a filed survey map or corner record document completed with acceptable modern survey methods that includes survey ties from monuments within the construction area to monuments outside of the construction area).

6. Submits copies of pre-construction Corner Records or Records of Survey filed with San Joaquin County to City Engineer/Project Manager

Contractor 7. Preserves/perpetuates all survey monumentation during construction, including, but not limited to, those listed.

8. Restores survey monuments disturbed by construction.

Contractor's Land Surveyor, 9. Files all post-construction Corner Records and Records of Survey with San Joaquin County for all monuments disturbed during construction

10. Submits copies of Corner Records or Records of Survey filed with San Joaquin County to City Engineer/Project Manager.

Monuments set shall be sufficient in number and durability and efficiently placed so as not to be readily disturbed, to assure, together with monuments already existing, the perpetuation or facile reestablishment of any point or line of the survey.

When monuments exist that control the location of subdivisions, tracts, boundaries, roads, streets, or highways, or provide horizontal or vertical survey control, the monuments shall be located and referenced by or under the direction of a licensed land surveyor or registered civil engineer prior to the time when any streets, highways, other rights-of-way, or easements are improved, constructed, reconstructed, maintained, resurfaced, or relocated, and a corner record or record of survey of the references shall be filed with the county surveyor. They shall be reset in the surface of the new construction, a suitable monument box placed thereon, or permanent witness monuments set to perpetuate their location if any monument could be destroyed, damaged, covered, or otherwise obliterated, and a corner record or record of survey filed with the county surveyor prior to the recording of a certificate of completion for the project. Sufficient controlling monuments shall be retained or replaced in their original positions to enable property, right-of-way and easement lines, property corners, and subdivision and tract boundaries to be reestablished without devious surveys necessarily originating on monuments differing from those that currently control the area. It shall be the responsibility of the governmental agency or others performing construction work to provide for the monumentation required by this section. It shall be the duty of every land surveyor or civil engineer to cooperate with the governmental agency in matters of maps, field notes, and other pertinent records. Monuments set to mark the limiting lines of highways, roads, streets, or right-of-way or easement lines shall not be deemed adequate for this purpose unless specifically noted on the corner record or record of survey of the improvement works with direct ties in bearing or azimuth and distance between these and other monuments of record.

The decision to file either the required corner record or a record of survey pursuant to subdivision shall be at the election of the licensed land surveyor or registered civil engineer submitting the document.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.08 CONSTRUCTION SURVEY

Section 5-1.26, "Construction Surveys", of the Standard Specifications is deleted, and replaced with the following:

1. The Contractor shall be responsible for all construction survey stakes necessary to construct the project in accordance with the lines, grades, sections, stage construction/traffic handling, and traffic signalization, pavement delineation plan described in the plans and specifications.

2. Contractor shall be responsible for referencing all existing monumentation within the limits of the project prior to removal of any existing monuments. Monument referencing shall be reviewed and approved by the engineer prior to commencing of the work.

3. The Contractor shall employ a Land Surveyor registered in the State of California or an appropriately registered Civil Engineer to perform such survey work. All stakes and marks set by the Contractor's Land Surveyor or Civil Engineer shall be carefully preserved by the Contractor. In case such stakes and marks are destroyed or damaged, they will be promptly replaced, at the direction of the Engineer, at no additional cost to the City. Copies of all field notes and cut sheets shall be provided to the City at no additional cost to the City.

included in prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.09 REQUEST FOR INFORMATION

The Contractor’s attention is directed to Sections 5-1.42, “Request for Information” of the Caltrans Specifications.

Contractor shall submit a request for information upon recognition of any event or question of fact arising under the contract. The Engineer shall respond to the request for information within 5 working days.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.10 NOTICE OF POTENTIAL CLAIM

The Contractor shall not be entitled to the payment of any additional compensation for any cause, or for the happening of any event, thing or occurrence, including any act or failure to act, by the Engineer, unless he has given the Engineer due written notice of potential claim as herein specified, provided, however, that compliance with this section shall not be a prerequisite for matters within the scope of the protest provisions under “Changes and Extra Work”, “Time of Completion” or within the notice provisions in “Liquidated Damages” not to any claim which is based on differences in measurements of errors of computation as to Contract quantities. The written notice of potential claim shall set forth the items and reasons which the Contractor believes to be eligible for additional compensation, the description of work, the nature of the additional costs, and the total amount of the potential claim. If based on an act or failure to act by the Engineer, written notice for potential claim must be given to the Engineer prior to the Contractor commencing work; in all other cases, written notice for potential claims must be given to the Engineer within 15 days after the happening of the event, thing or occurrence giving rise to the potential claim.

It is the intention of this Section that potential differences between the parties of this Contract be brought to the attention of the Engineer at the earliest possible time appropriate action may be taken and settlement may be reached. The Contractor hereby agrees that he shall have no right to additional compensation for any claim that may be based on any act or failure by the Engineer or any event, thing or occurrence for which no written notice of potential claim was filed.

5-1.11 INSPECTIONS

All work under this contract shall be under the control and inspection of the City Engineer or his/her appointed representative. The Contractor shall notify the City of Stockton Public Works Department forty-eight (48) hours in advance of any construction. Contractor shall pay for overtime for inspection during City holidays, weekends and non-business hours.

5-1.12 AS-BUILT/RECORD DRAWINGS

The Contractor shall maintain a complete set of drawings on site for the purpose of keeping up to date all field modifications. This plan set shall be available for review by the project Inspector or the Engineer. These plans shall be provided to the Inspector after the completion of construction at the Post Construction Meeting and prior to the final payment. All revisions, modifications and/or changes shall be marked clearly. Notes and dimensions shall be in red and be clear and legible. These plans will be used by the Design Engineer to mark up the original plan sheets with the revisions made during construction.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.13 SURFACE RESTORATION

Surface restoration shall consist of restoring all areas within the limits of work to their original existing condition prior to construction.

The Contractor shall restore all paved areas, such as driveways, curb and gutter, roadway surfaces, ditches, landscaped areas, etc., and all other improvements disturbed or damaged by his operations.

Full compensation for conforming to the provisions in this section shall be considered as included in the prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.14 RIGHTS IN LAND

The following is added to Section 5-1.32, “Areas for Use" of the Caltrans Specifications:

"All work, equipment parking, or any other activity associated with the project shall be confined to the project limits within the street rights-of-way. The Contractor's use of any other property exclusively in connection with this project shall be by a written agreement between the property owner and the Contractor. A certified copy of any such agreement shall be furnished to the Engineer prior to the use of such property by the Contractor."

compensation will be allowed therefore.

5-1.15 STAGING AREA

Attention is directed to the requirements specified in Section 5-1.32, ”Areas for Use” of the Caltrans Specifications and these Special Provisions.

The street right-of-way shall be used only for activities that are necessary to perform the required work. The Contractor shall not occupy the right-of-way or allow others to occupy the right-of-way for material storage or other purposes that are not necessary to perform the required work.

The Contractor shall secure at his own expense any area required for plant sites, storage of equipment or materials, or for other purposes.

Full compensation for conforming to the provisions in this section shall be considered as included in prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

5-1.16 SITE MAINTENANCE AND CLEANUP

The Contractor shall maintain the work sites in a neat and orderly manner throughout construction. Removed broken concrete shall be disposed of immediately. If, in the determination of the Engineer, the Contractor has not adequately maintained a clean, neat and orderly work site, the Contractor may be required to pay to the City of Stockton the sum of two hundred fifty dollars ($250) per work site. The work shall be conducted in a manner that will control dust. When ordered to provide dust control, the Contractor shall provide a vacuum sweeper to reduce the dusty conditions to the satisfaction of the Project Engineer. A permit shall be obtained from both the City Permit Center and California Water Service Company for construction water that is obtained from a fire hydrant. During and upon completion of construction, the Contractor shall remove all equipment, debris, and shall leave the site in a neat and clean condition to the satisfaction of the Project Engineer. Full compensation for Site Maintenance and Cleanup shall be considered as included in the price paid for the various items of work and no separate payment will be made therefore.

5-1.17 DISPOSAL OF MATERIALS

All materials designated to be removed and not salvaged shall become the property of the Contractor and shall be disposed of in accordance with Federal, State, and local laws, and ordinances. The Contractor shall file: 1) Construction and Demolition Debris Materials Checklist at the time of permit application, and 2) Construction and Demolition Debris Recycling Report within fourteen (14) days of job completion. Full compensation for conforming to the requirements of this section shall be considered included in the various bid items of work and no additional compensation will be considered therefore.

5-1.18 ENVIRONMENTAL PROTECTION

The Contractor shall be responsible for all applicable permits, licenses and fees required for the construction and completion of the project.

Any Contractor or person engaged in activities that will or may result in pollutants entering the City storm drainage system shall undertake all practicable measures to reduce the introduction of such pollutants. The Contractor shall be fully responsible for removing the materials out of the storm system irrespective of its condition before the construction work.

The Contractor shall follow Caltrans’ best management practices regarding environmental protection and comply with all City regulations, ordinances, and City Storm Water Quality Control Criteria Plan. It is available for download at:

https://www.stocktonca.gov/services/water,_sewer___stormwater/stormwater/index.php #collapse1313b0

The Contractor shall winterize the project and apply the proper protected measures at all existing drain inlets within the project boundary and maintain them through the winter season.

Full compensation for furnishing all labor, materials, tools, equipment, and incidentals for doing all work involved in environmental protection shall be included in the various bid items and no additional compensation will be made therefore.

5-1.19 CONSTRUCTION CONTROL

The City reserves the right to order discontinuance of any equipment in use. This will be determined at the discretion of the Engineer on the basis that the use of said equipment would prohibit obtaining the best possible result.

Additional operated equipment may be requested by the Engineer for the above reasons. Failure to comply with the Engineer's request concerning equipment use or removal will be deemed sufficient cause for shutting down all work until the requirements are met. Days lost for this type of shutdown will be charged as workable days.

SECTION 6 – CONTROL OF MATERIALS

Attention is directed to the provisions in Section 6, "Control of Materials," of the Standard Specifications, and these Special Provisions.

6-1.01 CITY-FURNISHED MATERIALS

There are no City-furnished materials for this project.

6-1.02 STATE-FURNISHED MATERIALS

The are no State-furnished materials for this project.

6-1.03 BUY AMERICA REQUIREMENTS

Attention is directed to the "Buy America" requirements of the Surface Transportation https://www.stocktonca.gov/services/water,_sewer___stormwater/stormwater/index.php#collapse1313b0 https://www.stocktonca.gov/services/water,_sewer___stormwater/stormwater/index.php#collapse1313b0

Assistance Act of 1982 (Section 165) and the regulations adopted pursuant thereto.

Furnish steel and iron materials to be incorporated into the work with certificates of compliance. Steel and iron materials must be produced in the U.S. except:

1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials

[60 Fed Reg 15478 (03/24/1995)];

2. If the total combined cost of the materials does not exceed the greater of 0.1 percent of the total bid or $2,500, materials produced outside the U.S. may be used.

Production includes:

1. Processing steel and iron materials, including smelting or other processes that alter the physical form or shape (such as rolling, extruding, machining, bending, grinding, and drilling) or chemical composition;

2. Coating application, including epoxy coating, galvanizing, and painting, that protects or enhances the value of steel and iron materials.

6-1.04 QUALITY ASSURANCE PROGRAM

Refer to Instruction to Bidders document.

6-1.05 TESTING

Testing of materials and work shall conform to the provisions in Section 6, "Control of Materials" of the Caltrans Specifications and these special provisions. Whenever the provisions of Section 6 of the Caltrans Standard Specifications refer to tests or testing, it shall mean tests to assure the quality and to determine the acceptability of the materials and work. Contractor’s attention is directed to the City’s Quality Assurance Program in Instructions to Bidder Package.

Contractor shall hire a certified, independent from contractor’s company, laboratory to conduct compaction and material testing. Testing includes and not limited to compaction testing and material testing. A relative compaction of 95% is expected on AC overlay, roadway sub grade and sidewalk areas.

Compaction testing will be required for subsoil, AB, and hot mix asphalt. For AB, sieve analysis, cleanness value, and R value may be provided by the vendor if the source is consistent.

For Asphalt Concrete, certificate of compliance, one sieve analysis, and one oil content test per day is required from supplier.

For concrete, certificate of compliance for Curb Gutter/Sidewalk, driveway, and ADA ramp or ASTM C39 compaction test, 4 cylinders per day, with a required 28 day strength of 3,000 psi is required.

Full compensation for performing the work in these specifications shall be included in the prices paid for the various contract items of work, and no additional compensation will be allowed therefore.

6-1.06 PRE-QUALIFIED AND TESTED SIGNING AND DELINEATION MATERIAL

The California Department of Transportation maintains the list of Prequalified and Tested signing and delineation materials and products. Approval of pre-qualified and tested products and materials shall not preclude the Engineer from sampling and testing any of the signing and delineation materials or products at any time.

None of the listed signing and delineation materials and products shall be used in the work unless such material or product is listed on the California Department of Transportation's List of Approved Traffic Products. A Certificate of Compliance shall be furnished as specified in Section 6, "Control of Materials", of the Caltrans Specifications for signing and delineation materials and products. Said certificate shall also certify that the signing and delineation material or product conforms to the pre-qualified testing and approval of the California Department of Transportation, Division of Traffic Operations, and was manufactured in accordance with the approved quality control program.

For those categories of materials included on the list of Prequalified and Tested Signing and Delineation Materials, only those products shown within the listing may be used in the work. Other categories of products, not included on the list of Prequalified and Tested Signing and Delineation Materials, may be used in the work provided they conform to the requirements of the Standard Specifications.

Materials and products will be considered for addition to said approved pre-qualified and tested list if the manufacturer of the material or product submits to the Division of Traffic Operations of the California Department of Transportation a sample of the material or product. The sample shall be sufficient to permit performance of all required tests.

Approval of such materials or products will be dependent upon a determination as to compliance with the Specifications and any test the California Department of Transportation may elect to perform. The list of approved pre-qualified and tested signing and delineation materials and products can be found at the California Department of Transportation Website:

https://dot.ca.gov/-/media/dot-media/programs/engineering/documents/mets/2627-signing-delineation-materials-a11y.pdf

SECTION 7 – LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

7-1.01 PUBLIC CONVENIENCE

Contractor’s attention is directed to Section 12-1.02, “Maintaining Traffic” of these Special Provisions.

The Contractor shall notify San Joaquin Regional Transit District (SJRTD) (dispatcher

(209) 948-0642) a minimum of five (5) working days prior beginning Work. Contractor shall coordinate with SJRTD if any bus stops and bus routes are affected.

The Contractor shall inform the City Fire Department, City Police Department, City Traffic Department, Municipal Utilities Department (MUD), Stockton Unified School District, and https://dot.ca.gov/-/media/dot-media/programs/engineering/documents/mets/2627-signing-delineation-materials-a11y.pdf https://dot.ca.gov/-/media/dot-media/programs/engineering/documents/mets/2627-signing-delineation-materials-a11y.pdf all affected utilities no later than seventy-two (72) hours before work is to begin. The Contractor shall provide the City with the name and telephone number (business, home, and mobile) of three (3) representatives available at all times during the duration of the contract. Said names and telephone numbers shall be provided to the City of Stockton Public Works, Fire and Police Departments.

The Contractor shall circulate printed form letters, approved by the Engineer, explaining the project to be constructed and the length of time inconvenience will be caused by the project and deliver same to the residents and businesses to be affected at least seventy-two (72) hours before work is to commence. In addition, the Contractor shall provide temporary “No Parking” signs posted seventy-two (72) hours in advance of the work. Such signs shall be placed no further than fifty (50) feet apart. The additional “No-Parking” signs shall be removed on completion of the work and the opening of the street to traffic.

The Contractor is responsible for the removal of any vehicles obstructing his operations.

Full compensation for conforming to the provisions in this section shall be considered as included in prices paid for the various contract items of work involved, and no additional compensation will be allowed therefore.

7-1.02 PUBLIC SAFETY

The Contractor’s attention is directed to Section 12-1.02, “Maintaining Traffic” of these Special Provisions. Nothing in the specifications voids the Contractor’s public safety responsibilities.

All safety devices, their maintenance, and use shall conform to the latest requirements of OSHA and shall conform to the applicable provisions of Part 6 "Temporary Traffic Control", latest MUTCD California Supplement, the current edition of the “Manual on Uniform Traffic Control Devices (MUTCD)” and the latest “Work Area Traffic Control Handbook (WATCH)”. It shall be the complete responsibility of the Contractor to protect persons from injury and to avoid property damage.' Adequate barricades, construction signs, flashers, and other such safety devices, as required, shall be placed and maintained during the progress of the construction work, until the project is completed.

Whenever required, flagmen shall be provided to control traffic.

The Contractor shall provide for the proper routing of vehicles, bicyclists, and pedestrians in a manner that will hold congestion and delay of such traffic to practicable minimum by furnishing, installing, and maintaining all necessary temporary signs, barricades, and other devices and facilities, as approved by the City Traffic Engineer. As the work progresses, the Contractor shall relocate, subject to the City Traffic Engineer's approval, such devices and facilities as necessary to maintain proper routing. The Contractor shall maintain Americans with Disabilities Act (ADA) compliance through the work site (or approved alternate route) at all times during all phases of construction. The Contractor shall notify the City Traffic Engineer via the inspector a minimum of three (3) working days prior to the relocation of any traffic control devices.

Full compensation for furnishing, installing, moving, and removing of all necessary traffic control devices including, but not limited to, signing, striping, barricades, arrow boards, CMS, and flagging shall be included in the contract prices for “Traffic Control” and no additional compensation will be allowed therefore. Section 12-1.04, "Payment,” of the Caltrans Specifications is deleted.

7-1.03 PUBLIC NOTIFICATION

The Contractor shall circulate printed form letters/door hangers, approved by the Engineer, explaining the project and the length of time inconvenience will be caused by the project, and deliver same to the residents and/or businesses to be affected no earlier than 48 hours, nor later than 24 hours, before work is to commence. An additional four

(4) construction information signs shall be placed at various locations warning about pending construction and delays. The Contractor shall install “Road Closed,” arrows, Detour signs, and barricades as necessary.

In addition, the Contractor shall provide temporary "Tow-away, No Parking" signs posted in advance of the work which signs shall be removed upon completion of the work and the opening of the street to traffic. The signs shall not be less than 12”x18” size, “Tow-away, No Parking” words shall be in white letters on red background, and must have Stockton Municipal Code 10.04.310, California Vehicle Code 22651(l)(n), Stockton Police Department telephone number 937-8354, and date and time of parking restriction clearly indicated on it. Such signs shall be placed no farther than fifty (50) feet apart. It shall be the Contractor's responsibility to arrange for the removal of any vehicles obstructing his/her operations.

The Contractor shall…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .