This is a Bid Notice for a Bridge Rehabilitation project in McIntosh and Pittsburg Counties, Oklahoma, involving the Indian Nation Turnpike/SH-375 over the South Canadian River and its overflow, located 8.6 miles south of the SH-9 interchange near Vernon. The project encompasses two separate work areas (IN-MC-78 and IN-MC-80) with a combined project length of 0.894 miles and a let date of November 19, 2026. The scope includes extensive roadway rehabilitation, bridge reconstruction, traffic control, and associated infrastructure work. Roadway items include clearing and grubbing, excavation, pavement removal and replacement, superpave asphalt placement totaling 2,993 tons across both locations, rumble strip installation, and guardrail installation and removal. Bridge work consists of concrete placement (class AA, A, and C concrete totaling approximately 1,900 cubic yards), prestressed concrete beams, structural steel, bearing assemblies, epoxy-coated reinforcing steel totaling over 338,000 pounds, expansion joint systems, carbon fiber-reinforced polymer repairs, and various concrete repair and protective coating applications. Additional work includes traffic control measures, traffic signing and striping, cable barrier installation and removal spanning 6,164 linear feet, construction staking, and SWPPP documentation and management.
The bid notice does not specify pricing terms, set-aside requirements, or incumbent contractor information within the document. The project is funded through state and local sources in Oklahoma and requires comprehensive coordination across multiple work categories, including traffic management, structural repairs, and environmental controls. Mobilization and construction staking are required as part of the contract scope. The extensive quantities of materials—including over 43,000 square yards of asphalt pavement removal, nearly 2,100 square yards of sodding and vegetative work, and multiple concrete finishing and coating applications—indicate a substantial rehabilitation effort requiring specialized expertise in bridge reconstruction and roadway restoration.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
260303Proposal: Let Date: Call Order:November 19, 2026 044
J/P Num: Proj. Num:36893(04)
38909(04)
IN-MC-78
IN-MC-80
Counties:MCINTOSH, PITTSBURG
BRIDGE REHABILITATION
INDIAN NATION TURNPIKE/SH-375 (OTA ACCESS): OVER SOUTH
CANADIAN RIVER AND OVERFLOW, 8.6 MILES SOUTH OF THE
SH-9 INTERCHANGE NEAR VERNON.
PROJECT LENGTH = 0.894 MILES
Description:
Line # Item Description Quantity Unit
0001 ROADWAY - IN-MC-78
0010 201(A)1200 CLEARING AND GRUBBING 1.000 LSUM
0020 202(A)2200 UNCLASSIFIED EXCAVATION 400.000 CY
0030 202(D)2500 UNCLASSIFIED BORROW 530.000 CY
0040 205(A)6200 TYPE A-SALVAGED TOPSOIL 1.000 LSUM
0050 221(B)2300 TEMPORARY SILT FENCE 990.000 LF
0060 230(A)7200 SOLID SLAB SODDING 2,105.000 SY
0070 233(A)0200 VEGETATIVE MULCHING 0.350 AC
0080 241 3100 MOWING 0.700 AC
0090 307(K)4200 STABILIZED SUBGRADE 604.000 SY
0100 310(B)5300 SUBGRADE, METHOD B 100.000 SY
0110 407(B)7300 TACK COAT 77.000 GAL
0120 408 8100 PRIME COAT 335.000 GAL
0130 411(B)1330 SUPERPAVE, TYPE S3(PG 64-22 OK) 187.000 TON
0140 411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK) 115.000 TON
0150 413(A)4200 RUMBLE STRIP-METHOD HMA-CON 453.000 LF
0160 413(C)4400 RUMBLE STRIP-METHOD PCC-CON 120.000 LF
0170 414(A)5200 P.C.CONCRETE PAVEMENT(PLACEMENT) 100.000 SY
0180 414(G)5800 P.C. CONCRETE FOR PAVEMENT 14.000 CY
0190 619(B)6360 REMOVAL OF CONCRETE PAVEMENT 100.000 SY
0200 619(B)6364 REMOVAL OF ASPHALT PAVEMENT 4,530.000 SY
0210 619(B)6396 REMOVAL OF GUARDRAIL 430.000 LF
0220 623(A)1200 BEAM GUARDRAIL W-BEAM SINGLE 325.000 LF
0230 623(G)1820 GUARDRAIL END TREATMENT (31") 1.000 EA
0240 623(I)2050 GUARDRAIL BRIDGE CONN-THRIE BEAM (31") 3.000 EA
0250 625(B)4300 REMOVE AND RECONSTRUCT FENCE 240.000 LF
0260 853 5170 GUARDRAIL DELINEATORS(TYPE 1, CODE 1) 14.000 EA
38909(04)
IN-MC-78
IN-MC-80
Counties:MCINTOSH, PITTSBURG
BRIDGE REHABILITATION
INDIAN NATION TURNPIKE/SH-375 (OTA ACCESS): OVER SOUTH
CANADIAN RIVER AND OVERFLOW, 8.6 MILES SOUTH OF THE
SH-9 INTERCHANGE NEAR VERNON.
PROJECT LENGTH = 0.894 MILES
Description:
Line # Item Description Quantity Unit
0002 BRIDGE - IN-MC-78
0270 501(G)1800 CLSM BACKFILL 10.000 CY
0280 504(A)5200 APPROACH SLAB 76.200 SY
0290 504(B)5300 SAW-CUT GROOVING 3,038.500 SY
0300 504(E)5500 CONCRETE PARAPET 61.350 LF
0310 509 0100 SPECIAL CONCRETE FINISH 1,323.000 SY
0320 509(A)0210 CLASS AA CONCRETE 691.700 CY
0330 509(B)0320 CLASS A CONCRETE 20.000 CY
0340 509(D)0510 CLASS C CONCRETE 12.000 CY
0350 511(B)2310 EPOXY COATED REINFORCING STEEL 165,650.000 LB
0360 512(A)3200 PAINTING EXISTING STRUCTURES 1.000 LSUM
0370 515(A)7200 WATER REPELLENT (VISUALLY INSPECTED) 31,806.000 SY
0380 517 9110 ELASTOMERIC COATING 6,068.000 SF
0390 518(B)0310 EXPANSION JOINT SYSTEM 580.000 LF
0400 520(A)1200 PREPARATION OF CRACKS, ABOVE WATER 550.000 LF
0410 520(C)1400 EPOXY RESIN, ABOVE WATER 48.000 GAL
0420 521(A)2200 PNEUMATICALLY PLACED MORTAR 182.000 SY
0430 523(A)3200 SEALER CRACK PREPARATION 4,011.000 LF
0440 523(B)3300 SEALER RESIN 47.000 GAL
0450 524(A)4200 (SP) CARBON FIBER-REINFORCED POLYMER 3,040.000 SF
0460 535 7100 CORROSION INHIBITOR(SURFACE APPLIED) 74.000 SY
0470 540 8120 (PL)REPAIR BRIDGE ITEM (TYPE A) 4.000 EA
0480 619(B)6304 REMOVAL OF BRIDGE ITEMS 1.000 LSUM
38909(04)
IN-MC-78
IN-MC-80
Counties:MCINTOSH, PITTSBURG
BRIDGE REHABILITATION
INDIAN NATION TURNPIKE/SH-375 (OTA ACCESS): OVER SOUTH
CANADIAN RIVER AND OVERFLOW, 8.6 MILES SOUTH OF THE
SH-9 INTERCHANGE NEAR VERNON.
PROJECT LENGTH = 0.894 MILES
Description:
Line # Item Description Quantity Unit
0009 ROADWAY - IN-MC-80
0490 201(A)1200 CLEARING AND GRUBBING 1.000 LSUM
0500 202(A)2200 UNCLASSIFIED EXCAVATION 400.000 CY
0510 202(D)2500 UNCLASSIFIED BORROW 2,150.000 CY
0520 205(A)6200 TYPE A-SALVAGED TOPSOIL 1.000 LSUM
0530 221(B)2300 TEMPORARY SILT FENCE 4,701.000 LF
0540 230(A)7200 SOLID SLAB SODDING 6,229.000 SY
0550 233(A)0200 VEGETATIVE MULCHING 1.200 AC
0560 241 3100 MOWING 2.400 AC
0570 307(K)4200 STABILIZED SUBGRADE 7,285.000 SY
0580 310(B)5300 SUBGRADE, METHOD B 476.000 SY
0590 407(B)7300 TACK COAT 728.000 GAL
0600 408 8100 PRIME COAT 3,873.000 GAL
0610 411(B)1330 SUPERPAVE, TYPE S3(PG 64-22 OK) 1,921.000 TON
0620 411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK) 1,072.000 TON
0630 413(A)4200 RUMBLE STRIP-METHOD HMA-CON 4,323.000 LF
0640 413(C)4400 RUMBLE STRIP-METHOD PCC-CON 571.000 LF
0650 414(A)5200 P.C.CONCRETE PAVEMENT(PLACEMENT) 476.000 SY
0660 414(B)5300 DOWEL JOINTED P.C.C.PAVT.(PLACEMENT) 1,521.000 SY
0670 414(G)5800 P.C. CONCRETE FOR PAVEMENT 447.000 CY
0680 619(B)6360 REMOVAL OF CONCRETE PAVEMENT 1,996.000 SY
0690 619(B)6364 REMOVAL OF ASPHALT PAVEMENT 43,230.000 SY
0700 619(B)6396 REMOVAL OF GUARDRAIL 4,175.000 LF
0710 623(A)1200 BEAM GUARDRAIL W-BEAM SINGLE 3,975.000 LF
0720 623(G)1820 GUARDRAIL END TREATMENT (31") 1.000 EA
0730 623(I)2050 GUARDRAIL BRIDGE CONN-THRIE BEAM (31") 3.000 EA
0740 625(B)4300 REMOVE AND RECONSTRUCT FENCE 765.000 LF
0750 853 5170 GUARDRAIL DELINEATORS(TYPE 1, CODE 1) 52.000 EA
38909(04)
IN-MC-78
IN-MC-80
Counties:MCINTOSH, PITTSBURG
BRIDGE REHABILITATION
INDIAN NATION TURNPIKE/SH-375 (OTA ACCESS): OVER SOUTH
CANADIAN RIVER AND OVERFLOW, 8.6 MILES SOUTH OF THE
SH-9 INTERCHANGE NEAR VERNON.
PROJECT LENGTH = 0.894 MILES
Description:
Line # Item Description Quantity Unit
0010 BRIDGE - IN-MC-80
0760 501(B)1300 SUBSTRUCTURE EXCAVATION COMMON 120.000 CY
0770 501(G)1800 CLSM BACKFILL 240.000 CY
0780 503(A)4240 PRESTRESSED CONCRETE BEAMS (TYPE IV) 3,983.350 LF
0790 504(A)5200 APPROACH SLAB 358.400 SY
0800 504(B)5300 SAW-CUT GROOVING 3,500.000 SY
0810 504(E)5520 42" F-SHAPED PARAPET 886.000 LF
0820 506(A)7225 STRUCTURAL STEEL M270 GRADE 50W 4,350.000 LB
0830 507(A)8210 WEATHERING STEEL FIXED BEARING ASSEMBLY 60.000 EA
0840 507(B)8310 WEATHERING STL EXP. BEARING ASSEMBLY 30.000 EA
0850 509(A)0210 CLASS AA CONCRETE 908.600 CY
0860 509(B)0320 CLASS A CONCRETE 20.000 CY
0870 509(D)0510 CLASS C CONCRETE 12.000 CY
0880 511(B)2310 EPOXY COATED REINFORCING STEEL 173,238.000 LB
0890 513(B)4300 CLASS B BRIDGE DECK REPAIR 35.000 SY
0900 515(A)7200 WATER REPELLENT (VISUALLY INSPECTED) 8,937.000 SY
0910 517 9110 ELASTOMERIC COATING 1,984.000 SF
0920 518(B)0310 EXPANSION JOINT SYSTEM 144.000 LF
0930 520(A)1200 PREPARATION OF CRACKS, ABOVE WATER 184.000 LF
0940 520(C)1400 EPOXY RESIN, ABOVE WATER 17.500 GAL
0950 521(A)2200 PNEUMATICALLY PLACED MORTAR 98.000 SY
0960 523(A)3200 SEALER CRACK PREPARATION 1,015.000 LF
0970 523(B)3300 SEALER RESIN 12.000 GAL
0980 524(A)4200 (SP) CARBON FIBER-REINFORCED POLYMER 35.000 SF
0990 535 7100 CORROSION INHIBITOR(SURFACE APPLIED) 258.000 SY
1000 619(B)6304 REMOVAL OF BRIDGE ITEMS 1.000 LSUM
0011 TRAFFIC CONTROL - IN-MC-80
1010 857(A)9205 CONSTRUCTION TRAFFIC STR.(PAINT)(6" WIDE) 45,180.000 LF
1020 857(F)9700 PAVEMENT MRKNG.REMOVAL(TRAF.STRP) 45,180.000 LF
1030 871(B)2300 CONST.ZONE IMPACT ATTEN. 2,210.000 SD
1040 877(B)4300 DELIVER PORTABLE LONGITUDINAL BARRIER 9,850.000 LF
1050 877(C)4400 RELOCATION OF PORT. LONGITUDINAL BARRIER 9,850.000 LF
1060 880(A)6220 ARROW DISPLAY(TYPE C) 1,860.000 SD
1070 880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF 3,150.000 SD
1080 880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 6,880.000 SD
1090 880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 7,200.000 SD
1100 880(C)6410 CONSTRUCTION BARRICADES(TYPE III) 8,820.000 SD
1110 880(E)6600 WARNING LIGHTS(TYPE A) 16,000.000 SD
1120 880(F)6700 DRUMS 51,824.000 SD
1130 880(L)7310 (SP) TRAFFIC SURVEILLANCE, OHP (NON-BID) 480.000 HOUR
1140 882(A)8210 PORT.CHANGEABLE MESSAGE SIGN 640.000 SD
0012 TRAFFIC SIGNING AND STRIPING - IN-MC-80
1150 856(A)8207 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE) 61,224.000 LF
38909(04)
IN-MC-78
IN-MC-80
Counties:MCINTOSH, PITTSBURG
BRIDGE REHABILITATION
INDIAN NATION TURNPIKE/SH-375 (OTA ACCESS): OVER SOUTH
CANADIAN RIVER AND OVERFLOW, 8.6 MILES SOUTH OF THE
SH-9 INTERCHANGE NEAR VERNON.
PROJECT LENGTH = 0.894 MILES
Description:
Line # Item Description Quantity Unit
0013 TRAFFIC CABLE BARRIER - IN-MC-80
1160 509(A)0200 CLASS AA CONCRETE 51.230 CY
1170 619(B)6432 REMOVAL OF CABLE BARRIER 6,164.000 LF
1180 628(B)7300 HIGH-TENSION CABLE BARRIER(TL-4) 6,164.000 LF
1190 628(C)7400 END ANCHORS 4.000 EA
0014 STAKING - IN-MC-80
1200 642(B)3300 CONSTRUCTION STAKING LEVEL II 1.000 LSUM
0015 CONSTRUCTION - IN-MC-80
1210 220 1100 SWPPP DOCUMENTATION AND MANAGEMENT 1.000 LSUM
1220 641 2100 MOBILIZATION 1.000 LSUM