Bid Notice-Bridge Painting - I-35.pdf
PDF 1 MB Posted
- Attached to
- Bridge Painting - I-35
- Solicitation number
- 260143
- Issued by
- Carter County, Asher Town, Oklahoma
About this file
This is a bid notice issued by the Oklahoma Department of Transportation for a bridge painting project in Carter County. The project involves painting an existing structure on I-35 over Caddo Creek, located 3.0 miles north of the SH-142 intersection near Ardmore, Oklahoma. The scope of work includes painting existing structures, collection and handling of waste materials, traffic control measures, traffic striping, and mobilization. Bidding proposals will be available beginning May 21, 2026, with a deadline for submission of June 10, 2026 at 10:30 a.m. The bid opening is scheduled for Thursday, June 11, 2026 at 10:30 a.m. via the Bid Express internet bidding system. The estimated contract time for completion is 45 calendar days, with a flexible start date no later than November 2, 2026. The project is designated as State Aid Project SSP-210F(128)PM with JP No. 30079(10). Pre-bid questions will be accepted through May 29, 2026, with responses posted to the ODOT website. Upon award, the successful contractor must execute and return the contract within ten working days, and the Department will complete its execution within fourteen working days.
The bid proposal cost is $50.00 plus tax, with State Standard Specifications available for purchase through the ODOT Business Services Center. All bids must include a proposal guaranty equal to 5 percent of the bid total. The DBE goal for this proposal is zero. The project includes multiple bid items covering traffic control (construction traffic stripes, pavement marking removal, pavement markers, construction zone impact attenuators, truck-mounted attenuators, portable longitudinal barriers, construction signs, warning lights, drums, channelizer cones, and portable changeable message signs), traffic striping with plural-component materials, and mobilization. Traffic surveillance by the Oklahoma Highway Patrol is included at a non-bid fixed rate of $77.00 per hour for estimated 100 hours. Lane rental fees of $5,000 per lane per hour will apply for restrictions to less than two lanes during specified peak periods, including weekdays (7:00 a.m. to 7:00 p.m.), weekends, and major holidays. Liquidated damages are assessed daily based on contract amount, ranging from $300 for contracts under $200,000 to $1,800 for contracts exceeding $10 million. Minimum wage requirements apply at $7.25 per hour for all labor classifications on this state-funded project.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID RIGGING IS A SERIOUS CRIME. IF YOU HAVE ANY INFORMATION CONCERNING COLLUSIVE BIDDING, EVEN A REQUEST TO SUBMIT A COMPLIMENTARY BID, PLEASE CALL THE OKLAHOMA ATTORNEY GENERAL'S OFFICE AT TELEPHONE NO. 405-521-3921.
PROPOSAL 260143
CALL ORDER 105
TO BE LET ON
THURSDAY, JUNE 11, 2026 AT 10:30 A.M.
STANDARD PROPOSAL
BIDX WILL BE ACCEPTED.
CARTER COUNTY
STATE AID PROJECT
BRIDGE PAINTING
I-35: OVER CADDO CREEK, 3.0 MILES NORTH OF THE SH-142 INTERSECTION NEAR
ARDMORE.
PROJECT LENGTH = 0.00 MILES
SSP-210F(128)PM, 30079(10)
CONTRACT TIME ESTIMATED FOR PROPOSAL IS 45 CALENDAR DAYS
FLEX START - SEE SPECIAL PROVISION 108-23
THE DBE GOAL IS ZERO FOR THIS PROPOSAL.
CREATION OF THIS DOCUMENT WAS ON MONDAY, MAY 11, 2026 AT 8:40 AM.
CREATED: 5/11/2026 8:40 AM
S T A T E O F O K L A H O M A D E P A R T M E N T O F T R A N S P O R T A T I O N
Advertisement to Contractors – June 11, 2026 10:30 A.M. Bid Opening
SHEET 1 OF 1
Plans and proposals for this bid opening will be available on May 21, 2026. No bidding proposals will be issued to any Contractor after June 10, 2026 10:30 A.M.. The cost for each bidding proposal is $ 50.00 + tax. State Standard Specifications may be purchased by contacting ODOT Business Services Center Branch (405) 521-4509. No refunds will be made for bidding documents or specification books purchased.
Sample proposals, preliminary plans, long form and short form notices, order forms, bid tabs and awards, can be accessed on ODOT's Web site: https://oklahoma.gov/odot/business-center/contracts-and-proposals.html
Bids must be prepared in accordance with the State Standard Specifications. Unless otherwise specified, bids for all projects must be submitted over the internet to Bid Express(https://www.bidx.com) using AASHTOware Project Bids.
Instructions for using Bid Express, Project Bids, and the electronicbidding process are available from the Office Engineer Division. When written bids are allowed, sealed proposals may be delivered directly to the Office Engineer Division prior to the scheduled bid opening. For written bids, do not disassemble the bidding proposal in any way.
Any firm bidding a project as a joint venture, that has not been previously approved by the department, must complete the ‘Request for Joint Venture’ form, which is posted on the ODOT website, prior to bidding.
Unless otherwise specified in the proposal, all bids must be submitted with a proposal guaranty equal to 5 % of the bid total.
Questions and comments regarding the June 11, 2026 bid opening will be accepted until May 29, 2026. Please submit your questions through the ODOT pre-bid email address: ODOT-Prebid.Question@odot.org. Responses will be posted to the “Pre-bid Questions and Answers” section of the ODOT Contracts & Proposals webpage as they are received. It is recommended that interested contractors visit the “Pre-Bid Questions and Answers” link regularly in order to stay informed of the latest information: https://oklahoma.gov/odot/business-center/contracts-and-proposals.html.
Unless otherwise noted in the proposal, upon award of the contract to the successful bidder, the contract will be completely and correctly executed by the contractor and returned to the Department within ten(10) working days from the date of award. The Department will have fourteen(14) working days from the date of award to complete it's execution of the contract.
The Oklahoma Department of Transportation(ODOT) and the Oklahoma Turnpike Authority(OTA) ensures that no person or groups of persons shall, on the grounds of race, color, sex, religion, national origin,age, disability, retaliation or genetic information, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination underany and all programs, services, or activities administered by ODOT or OTA, their recipients, sub -recipients, and contractors. To request an accommodation please contact the ADA Coordinator at (405)521-4140 or the Oklahoma Relay Service at 1-800-722-0353. If you have any ADA or Title VI questions email ODOT-ada-titlevi@odot.org
Description of work and location of project: Call Order: 105 SSP-210F(128)PM I-35 CARTER JP No.30079(10)
BRIDGE PAINTING
I-35: OVER CADDO CREEK, 3.0 MILES NORTH
OF THE SH-142 INTERSECTION NEAR ARDMORE.
STATE OF OKLAHOMA, OKLAHOMA DEPARTMENT OF TRANSPORTATION - By: TIM J. GATZ, Director.
PAGE 1 OF 51PROPOSAL ID : 260143
S U M M A R Y O F T I M E
CONTRACT TIME
CONTRACT TIME ESTIMATED FOR PROPOSAL IS 45 CALENDAR DAYS
NOTICE
THE DEPARTMENT WILL CONSIDER A PROPOSAL NONRESPONSIVE AND REJECT IT IN ACCORDANCE
WITH SUBSECTIONS 102.08 AND/OR 102.14 OF THE CURRENT OKLAHOMA DEPARTMENT OF
TRANSPORTATION STANDARD SPECIFICATIONS.
PAGE 2 OF 51PROPOSAL ID : 260143
S U M M A R Y O F I T E M S
SHEET 1 OF 2
LINE ITEM DESCRIPTION APPROX. QTY UNIT PRICE BID AMOUNT
UNITS DOLLARS CTS DOLLARS CTS
SECTION 0001 BRIDGE A
0010 512(A)3200
PAINTING EXISTING STRUCTURES
1.000 LSUM
0020 512(B)3300
COLLECTION AND HANDLING OF
WASTE
1.000 LSUM
SECTION 0001 SUB TOTAL
SECTION 0002 TRAFFIC CONTROL
0030 857(A)9205
CONSTRUCTION TRAFFIC
STR.(PAINT)(6" WIDE)
7,860.000 LF
0040 857(F)9700
PAVEMENT
MRKNG.REMOVAL(TRAF.STRP)
14,410.000 LF
0050 858(A)0212
PAVE.MARKERS CLASS A TYPE 2
600.000 EA
0060 871(B)2300
CONST.ZONE IMPACT ATTEN.
45.000 SD
0070 876(A)3210
(PL)TRUCK MOUNTED ATTENUATOR
45.000 SD
0080 877(B)4300
DELIVER PORTABLE LONGITUDINAL
BARRIER
430.000 LF
0090 880(B)6300
CONSTRUCTION SIGNS 0 TO 6.25 SF
400.000 SD
0100 880(B)6310
CONSTRUCTION SIGNS 6.26 SF TO 15.99
SF
200.000 SD
0110 880(B)6320
CONSTRUCTION SIGNS 16.0 SF TO 32.99
SF
900.000 SD
0120 880(E)6607
WARNING LIGHTS(TYPE B)
450.000 SD
0130 880(E)6616
WARNING LIGHTS(TYPE D)
3,200.000 SD
PAGE 3 OF 51PROPOSAL ID : 260143
S U M M A R Y O F I T E M S
SHEET 2 OF 2
LINE ITEM DESCRIPTION APPROX. QTY UNIT PRICE BID AMOUNT
UNITS DOLLARS CTS DOLLARS CTS
0140 880(F)6700
DRUMS
1,700.000 SD
0150 880(G)6805
CHANNELIZER CONES
1,500.000 SD
0160 880(L)7310
(SP) TRAFFIC SURVEILLANCE, OHP
(NON-BID)
100.000 HOUR $ 77.00 $ 7,700.00
0170 882(A)8210
PORT.CHANGEABLE MESSAGE SIGN
177.000 SD
SECTION 0002 SUB TOTAL
SECTION 0003 TRAFFIC STRIPING
0180 856(A)8207
(SP) TRAFFIC STRIPE(PLURAL-
COMPONENT)(6" WIDE)
6,550.000 LF
SECTION 0003 SUB TOTAL
SECTION 0004 CONSTRUCTION
0190 641 2100
MOBILIZATION
1.000 LSUM
SECTION 0004 SUB TOTAL
TOTAL
PAGE 4 OF 51PROPOSAL ID : 260143
D E P A R T M E N T O F T R A N S P O R T A T I O N
I N D E X O F P R O V I S I O N S FOR JPN(s) : SSP-210F(128)PM, 30079(10)
CARTER COUNTY
PROPOSAL PROVISIONS
102-013(a-b)19 BIDDING PROCEDURES 103-004(a-b)19 SUBCONTRACTS FOR STATE FUNDED CONSTRUCTION CONTRACTS 106-006(a)19 BUY AMERICA 108-023(a)19 FLEXIBLE NOTICE TO PROCEED 108-080(a)19 LIQUIDATED DAMAGES 108-417(a-c)19 LANE RENTAL 109-014(a)19 MATERIAL ON HAND 711-003(a-h)19 TRAFFIC STRIPE 856-003(a-j)19 TRAFFIC STRIPE (PLURAL-COMPONENT) 880-010(a-b)19 TRAFFIC SURVEILLANCE
CS000300 REQUIRED LABOR PROVISIONS SAP PROJECTS
CS000350 SPECIAL LABOR PROVISIONS FOR PROJECTS FINANCED W/STATE
FUNDS
CS001600 SAMPLE MAINTENANCE BOND
CZ002300 CONTRACT DISPUTE RESOLUTION PROCEDURE
CZ002850 NO.2 PROPOSAL SHEET
CZ002975 * BIDDER'S AFFIDAVIT - STATEMENT UNDER PENALTY OF PERJURY
PAGE 5 OF 51PROPOSAL ID : 260143
102-13(a-b)19 11/20/2020
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
BIDDING PROCEDURES
These special provisions amend and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction, English and Metric.
102.07 PREPARATION OF PROPOSAL (Revise to amend as follows:)
Submit the Proposal in the format required by the Bid Notice. For each item on the Proposal Forms, type or write (in ink) the unit price and the product of the unit price and estimated quantity on the Proposal Forms in the space provided. Show the total Proposal amount by adding the products of the unit prices and the estimated quantities. Acknowledge any change to a unit price, the product of a unit price and quantity, or the total Proposal amount with the initials of the person signing the Proposal, adjacent to each change.
If a discrepancy occurs on the Proposal, between the unit price and the product of the unit price and quantity, the Department will use the unit price. If a unit price or the product of a unit price and quantity is omitted or is entered as zero ($0) for any item listed on the Proposal Forms, the Department will consider the Proposal non-responsive and will reject the Proposal. If there is a discrepancy between the submitted electronic media and written Proposal, the Department will use the written Proposal. If the Department requires a printout of electronic media and a discrepancy occurs between the printout and the electronic media, the Department will use the printout.
An individual, all members of a partnership, a duly authorized officer of a corporation, or all members of a joint venture shall sign the Proposal in black or blue ink. For Proposals submitted by a corporation, show the name of the corporation and business address. For Proposals submitted by the internet bidding process, the Department will require an electronic signature only. Include a Non-Collusive Bidding Certification with the Proposal in accordance with Subsection 102.16, “Non- Collusive Bidding Certification.”
102.08 NONRESPONSIVE PROPOSALS (Revise to amend as follows:)
The Department will consider a proposal nonresponsive and may reject it for any of the following reasons:
• The bidder submits a Proposal on an unapproved form (or format, if computer-generated), or the form is altered, incomplete, or disassembled.
• The bidder submits a Proposal using a form other than the latest approved Proposal Form.
• The Department determines that Proposal irregularities (such as unauthorized additions and
PAGE 6 OF 51PROPOSAL ID : 260143
102-13(b-b)19 11/20/2020 conditional or alternate bids) may tend to make the Proposal incomplete, indefinite, or ambiguous.
• The Proposal does not contain a unit price for each item listed, except for authorized alternate items.
• The Proposal is materially unbalanced in accordance with Subsection 101.05.CT.2
• The Proposal is not properly signed.
• The Proposal is not typed or completed in ink.
• The bidder fails to provide a properly executed Proposal Guaranty, or irrevocable Letter of
Credit.
• The bidder fails to sign the unsworn statement made under penalty of perjury.
• The Proposal fails to comply with any material requirement of the Bid Notice.
• The bidder fails to properly comply with Disadvantaged Business Enterprise Requirements or to properly list eligible disadvantaged businesses if participation in accordance with the Proposal Forms.
PAGE 7 OF 51PROPOSAL ID : 260143
103-4(a-b) 19
6-8-20
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
SUBCONTRACTS FOR STATE FUNDED CONSTRUCTION CONTRACTS
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019
Standard Specifications for Highway Construction.
(Add the following:)
103.10 SUBCONTRACTS
A. General
All subcontracts and/or sub-agreements, including amendments to such, must be submitted for review and approval by the Department prior to the subcontractor performing contract work. Ensure all subcontracts conform to the requirements of Subsection 108.01, “Subletting of Contract,” and are executed in accordance with the Contract requirements and the provisions specified herein.
As a minimum, the following information must be included in all subcontracts:
• Full description of the contract work to be performed by the subcontractor
• Prompt Payment/Return of Retainage provisions (from the ODOT DBE Program Manual)
• Signature(s) of the prime contractor and subcontractor
The aforementioned subcontract documents can be downloaded from the ODOT website, and are available for the Contractors’ use: http://www.odot.org/subcontracts.
Subcontracts and sub-agreements may be submitted prior to the receipt of the signed Contract by the
Department.
B. Proof of Subcontract Assurances
Use either of the methods described below to provide the Department with assurance that each subcontract agreement complies with the requirements specified in Subsection 103.10.A above.
1. Subcontract Submission
Submit executed subcontracts and/or sub-agreements in pdf format to the Department using the following email address: constructionsubcontracts@odot.org. Submit all additional and/or modified subcontracts or sub-agreements to the Department via the same email address. To prevent delays in the approval of the subcontract, include the following information in all correspondence: contract
I.D., project number, prime contractor, and subcontractor.
PAGE 8 OF 51PROPOSAL ID : 260143
103-4(b-b) 19
6-8-20
2. Construction Subcontract Assurances Agreement (CSA)
In lieu of submitting the executed subcontract, electronically execute and submit the
Department’s Construction Subcontract Assurances Agreement (CSA) for State funded construction projects. The CSA constitutes an agreement between the Department and the Contractor. By executing the CSA the Contractor assures that the Contractor’s subcontract agreements include the required subcontract elements specified in Subsection 103.10.A above.
An executed CSA cannot be submitted in association with more than one subcontract agreement.
Independent assurances must be provided for each subcontract.
The CSA is located on the ODOT website at ok.gov/odot/Doing_Business/Construction.
PAGE 9 OF 51PROPOSAL ID : 260143
106-6(a) 19 5-22-23
OKLAHOMA DEPARTMENT OF
TRANSPORTATION SPECIAL PROVISIONS
FOR
BUY AMERICA
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the
2019 Standard Specifications for Highway Construction.
106.01 SOURCE OF SUPPLY AND QUALITY REQUIREMENTS (Replace with the following:)
B. Buy America
Buy America requirements shall not be enforced as a condition to complete state funded contract work.
PAGE 10 OF 51PROPOSAL ID : 260143
108-23(a) 19 1-10-20
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
FLEXIBLE NOTICE TO PROCEED
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction, English and Metric.
108.03 PROSECUTION AND PROGRESS (Add the following:)
The Notice to Proceed for this project will be issued in the normal time period (approximately 30 days after the award). The Contractor may begin work any time after the issuance of the Notice to Proceed, but no later than November 2, 2026. Time charges will begin on the date the Contractor begins work, or at the date specified in the Notice to Proceed, and will continue until the project is completed. Once the work begins, construction is expected to continue at an optimum rate until the work is done.
Notify the Resident Engineer, and when applicable the County Commissioner, at least 14 calendar days prior to beginning work.
There will be no additional compensation for any increased costs due to beginning work at or near the end of the flexible period.
PAGE 11 OF 51PROPOSAL ID : 260143
108-80(a) 19 1-19-23
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
LIQUIDATED DAMAGES
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction.
108.09 FAILURE TO COMPLETE ON TIME (Revise Table 108:1 as follows:)
Table 108:1 Schedule of Liquidated Damages
Contract Amount, $ Daily Assessment Rate, $
# $200,000 $300 >$200,000 and #$1,000,000 $800
>$1,000,000 and #$5,000,000 $1,000 > $5,000,000 and #$10,000,000 $1,300
> $10,000,000 $1,800
PAGE 12 OF 51PROPOSAL ID : 260143
108-417(a-c) 19 5-7-26
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
LANE RENTAL
SSP-210F(128)PM, JP NO. 30079(10), CARTER COUNTY
These Special Provisions revise, amend, and where in conflict, supersede applicable Sections of the 2019 Standard Specifications for Highway Construction.
108.12 LANE RENTAL (Add the following:)
This provision establishes lane rental fees for lane restrictions. The completion of this contract requires lanes on I-35 to be reduced, in the southbound direction, as shown in the Traffic Control Details in the plans.
Short term daily lane closures will be allowed on the contract, but must follow the guidelines of this provision. Contact the Resident Engineer to request approval for the use of short term daily lane closures.
The Contractor's sequence may vary from the sequence shown in the plans in order to eliminate lane closures during the times specified in Subsection 108.12.A.(1).
Lane rental fees will apply if free flowing traffic is disrupted during the times specified in Subsection 108.12.A.(1) of this provision, and if the Contractor closes lanes without prior approval from the Resident Engineer.
Schedule work in a manner that minimizes the disruption of free-flowing traffic on I-35, to lessen concerns of safety and the inconvenience to the public.
A. Lane Restrictions
(1) General Lane Restrictions
Due to anticipated traffic well in excess of normal levels, no lane closures will be allowed on I-35 during the following times. If the contract extends beyond the special events and holidays listed, restrictions will still apply.
Weekdays • 7:00 A.M. through 7:00 P.M., Monday through Friday
Weekends • 8:00 A.M. Friday through 8:00 A.M. Monday
Labor Day Weekend
• 8:00 A.M. the Friday prior to Labor Day through 8:00 A.M. the
Tuesday after Labor Day.
OU/TX Weekend
• 8:00 A.M. Thursday, prior to the OU/TX football game through
8:00 A.M. Monday, after the OU/TX football game
Thanksgiving Weekend
• 8:00 A.M. Wednesday prior to Thanksgiving through 8:00 A.M.
Monday after Thanksgiving
PAGE 13 OF 51PROPOSAL ID : 260143
108-417(b-c) 19
Christmas/New Year’s
• 8:00 A.M. Friday, December 18, 2026 through 8:00 A.M.
Monday, January 4, 2027
Spring Break Week
• 8:00 A.M. Friday, prior to Oklahoma Spring Break through 8:00
A.M. Monday, after Oklahoma Spring Break (Verify the exact dates with the Engineer)
Memorial Day Weekend
• 8:00 A.M. the Friday prior to Memorial Weekend through 8:00
A.M. the Tuesday after Memorial Day.
July 4 Weekth • 8:00 A.M. Thursday, July 2, 2026 through 8:00 A.M. Monday, July 6, 2026
(2) Short Term Lane Restrictions
Contract work using short term, daily lane closures will be allowed without the assessment of lane rental fees. Short term lane closures typically do not include the use of median barrier. The Contractor must be present and performing contract work that requires a lane closure for the safety of the traveling public, and be able to safely open the highway to free-flowing traffic upon completion of the daily operation and any subsequent and reasonable time for curing. The Contractor will be expected to meet the drop-off standard (PDT-1-3) and to backfill any areas where a drop-off is present when lanes are opened. Short term lane closures will not be allowed during the times described in Subsection 108.12.A.(1) of this provision.
B. Lane Rental Fees
A lane rental fee of $5,000 per lane per hour will be assessed if I-35 is restricted to less than two (2) lanes, in either direction, during the periods described in Subsection 108.12.A.(1).
Lane rental fees will be charged in increments of fifteen (15) minutes. As applicable, lane rental fees will be charged against each progressive estimate until free-flowing traffic is achieved as specified in Subsection 108.12.C.
C. Free-Flowing Traffic
Free flowing, unrestricted, two lane traffic will generally include, but is not limited to, completed bridge deck and safety rails (including cure time in accordance with specifications), installation of guardrail and GET's in their final configuration, removal of temporary traffic signals, removal of barrier wall, smooth transition of grades and alignments between the surface of the approach roadway and bridge deck, installation of pavement markings (temporary stripe minimum), and other such items as determined by the Engineer.
If weather conditions or other circumstances beyond the Contractor's control impede placement of permanent pavement markings, temporary pavement markings may be installed as approved by the Engineer at no additional cost to the Department. In such cases, submit a schedule for the Engineer's approval, indicating that permanent pavement markings will be installed as soon as practical. Use rolling lane closures in the vicinity of the personnel and equipment necessary for installing pavement markings operations. The Department will not consider compensation for costs associated with placement and removal of temporary pavement markings, nor any cost for preparation to install permanent pavement markings.
PAGE 14 OF 51PROPOSAL ID : 260143
108-417(c-c) 19
D. Critical Path Method (CPM)
Prepare and submit a Critical Path Method (CPM) analysis in accordance with Subsection 108.03 of the Standard Specifications within 30 days after the award of the contract. Include the cost of preparing and maintaining the CPM in other items of pay. Develop and maintain the CPM to meet all contract requirements. Submit schedule revisions to the Engineer for approval. Prepare and submit updates upon request by the Engineer, but no more than once every 30 days.
E. Additional Traffic Control, Attenuator, and Striping
The Contractor may submit an alternate schedule and traffic control plan to the Engineer for approval. Costs for quantities over and above plan quantity, items not shown in the plans but deemed necessary for traffic control, additional striping and stripe removal, additional relocation of barrier wall, and other safety appurtenances not shown in the plans but deemed necessary for compliance with applicable Standards and the MUTCD will be included in other items of work.
PAGE 15 OF 51PROPOSAL ID : 260143
109-14(a) 19 6-6-23
OKLAHOMA DEPARTMENT OF
TRANSPORTATION SPECIAL PROVISIONS
FOR
MATERIAL ON HAND
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction.
109.07 PAYMENT FOR MATERIAL ON HAND (Add the following:)
By way of these provisions, the Department hereby suspends the storage requirements associated with payments for material on hand, as required per section 109.07 of the Standard Specifications, and superseded on some contracts by Special Provision 109-11(a)09. All other requirements for the payment of material on hand will be enforced as specified in the aforementioned specifications and provisions.
Requests for payment that are deemed unreasonable by the Engineer will not be considered.
PAGE 16 OF 51PROPOSAL ID : 260143
711-3(a-h)19 6-6-24
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
TRAFFIC STRIPE
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction.
(Add the following:)
711.01 MATERIAL FOR HOT-APPLIED THERMOPLASTIC COMPOUNDS
Provide materials that have been approved by the Department and are currently listed on the Department's Approved Products List (APL) for preformed hot-applied thermoplastic materials. Prior to product installation, the Contractor must supply the Engineer a copy of all material certifications, product approvals, and any other documents requested by the Engineer. Ensure the Department, other state Department of Transportations, or AASHTO Product Evaluation & Audit Solutions (formerly NTPEP) have evaluated the material using a performance test of at least 12 months.
(Replace with the following:)
711.02 PERMANENT PAVEMENT MARKING TAPE
Provide plastic pavement marking tape free of cracks with straight and unbroken edges. Provide material in rolls with no greater than three splices per 150 ft.
Conform preformed words and symbols to the applicable shapes and sizes in accordance with the MUTCD. Package plastic pavement marking tape in standard commercial containers to prevent damage during shipment and storage. Ensure the plastic striping retains the properties required by the Contract when stored at temperatures no greater than 100°F and for no longer than one (1) year. Provide plastic pavement marking tape in accordance with Subsection 711.02.A, "Composition," through Subsection 711.02.L, "Effective Performance Life" of this provision.
Provide materials that have been approved by the Department and are currently listed on the Department's Approved Products List (APL). Prior to product installation, the Contractor must supply the Engineer a copy of all material certifications, product approvals, and any other documents requested by the Engineer. Ensure the Department, other state Department of Transportations, or AASHTO Product Evaluation & Audit Solutions (formerly NTPEP) have evaluated the material using a performance test of at least 12 months.
A. Composition
Distribute uniformly and firmly bond plastic materials, pigments, and glass beads on the top surface of retroreflective, preformed pavement marking film. Provide pre-coated preformed plastic film with a pressure-sensitive adhesive that is compatible with asphalt concrete (AC) and portland cement concrete (PCC) road surfaces.
B. Skid Resistance
Ensure the retroreflective preformed film surface provides skid resistance value of at least 35 British Pendulum Number when tested in accordance with ASTM E303.
C. Thickness
Provide a thickness from 60 mils to 90 mils for preformed plastic film, without adhesive, for lane and edge lines.
PAGE 17 OF 51PROPOSAL ID : 260143
711-3(b-h)19
D. Tensile Strength and Elongation
Provide film with a tensile strength of at least 40 psi of cross section when tested in accordance with ASTM D638, except test a 6 inch x 1 inch sample from 70°F to 80°F using a jaw speed from 10 inches to 12 inches per minute. Provide the sample with an elongation of at least 75 percent at break when tested by this method.
E. Conformability
Provide preformed film that conforms to pavement contours, breaks, and faults at normal pavement temperatures. Provide preformed plastic film that fuses with itself and previously applied marking film of the same composition.
F. Removability
Provide plastic pavement marking tape that cannot be easily removed after application.
G. Adhesive
Provide plastic pavement marking tape for longitudinal and transverse markings with pressure-sensitive backing without liner. Provide word and symbol tape with pressure-sensitive backing and protective liner.
H. Application Properties
Ensure the material adheres to asphalt concrete (AC) and portland cement concrete (PCC) surfaces when applied according to manufacturer's recommendations at surface temperature of at least 65°F. If applying the markings when the surface temperature is from 50°F to 65°F, apply in accordance with the manufacturer's recommendations, other special instructions, or both.
I. Glass Beads
Ensure the manufacturer incorporates glass beads for immediate and continuing retroreflection.
Ensure the size, quality, and refractive index of the glass beads are such that the beads perform in accordance with Subsection711.02.K, "Reflectance" of this provision. Provide bead adhesion so beads are not easily removed when scratching the material surface with a thumbnail.
J. Pigmentation
Thoroughly blend color pigments to provide a pavement marking film that maintains uniform color under both day and night lighting conditions throughout the expected life of the film. Provide white pavement marking film similar to Federal Standard Color No. 595-17886. Provide yellow pavement marking film similar to Federal Standard Color No. 595-13538.
K. Reflectance
Provide white and yellow films with an initial retroreflectance value using a 30m geometry, measured in accordance with the ASTM E1710. Ensure the specific luminance is measured in millicandelas per square foot-candle (mcd/ft2/fc) or millicandelas per square meter per lux [mcd/m /lux].2
Submit samples from the manufacturer of each color (white and yellow) of the product. Provide certification and/or independent lab test results for each sample which verifies that each product conforms to the requirements of these provisions, and is evaluated by AASHTO Product Evaluation & Audit Solutions (formerly NTPEP).
PAGE 18 OF 51PROPOSAL ID : 260143
711-3(c-h)19
Table 711:1 White and Yellow Film Reflective Properties
Property White Yellow
Entrance Angle 88.76E ± 0.02E 88.76E ± 0.02E
Observation angle 1.05E 1.05E
Specific Luminance mcd/ft /fc [mcd/m /lux]2 2 450 300
L. Effective Performance Life
Provide a film that leaves a neat, durable marking that will not flow or distort due to temperature if the pavement surface remains stable. Ensure the Department, another state Department of Transportation, or AASHTO Product Evaluation & Audit Solutions (formerly NTPEP) qualifies the tape using a performance test of at least 24 months. Provide a pliant polymer that supplies a cushioned, resilient substrate that reduces bead crushing and loss. Provide weather resistant film that does not fade, lift, tear, roll back, or shrink throughout the marking life.
(Add the following:)
711.03 NON-REMOVABLE TEMPORARY PAVEMENT MARKING TAPE
A. General
Provide material that has been approved by the Department and is currently listed on the Department's Approved Products List (APL). Supply the Engineer with a copy of all material certifications, product approval, and any other documents requested by the engineer prior to product installation. Additionally, all products may be tested by AASHTO Product Evaluation & Audit Solutions (formerly NTPEP).
(Add the following:)
711.04 REMOVABLE PAVEMENT MARKING TAPE
A. General
Provide material that has been approved by the Department and is currently listed on the Department's Approved Products List (APL). Supply the Engineer a copy of all material certifications, product approval, and any other documents requested by the Engineer prior to product installation.
Additionally, all products may be tested by AASHTO Product Evaluation & Audit Solutions (formerly
NTPEP).
(Replace with the following:)
711.05 GLASS BEADS FOR TRAFFIC STRIPE
A. Glass Beads for Traffic Stripe Paint
Provide glass beads for traffic stripe paint in accordance with AASHTO M247, Type II. Supply beads with a moisture-resistant coating.
PAGE 19 OF 51PROPOSAL ID : 260143
711-3(d-h)19
If blended glass beads for traffic stripe paint are used, provide a one-quart sample to the Department's Materials Division prior to installation, along with material certifications, product specifications, and a camsizer calibration for the testing/checking of the beads for conformity to the manufacture specifications. Additionally, ensure all blended beads meet, or exceed, all other requirements stated in this section.
B. Glass Beads for Traffic Stripe Thermoplastic or Plural Component
Provide drop-on glass beads in accordance with the following:
(1) Appearance
Provide colorless, clean and transparent glass traffic beads that are free of milkiness, excessive air bubbles, skins, and foreign material.
(2) Moisture
Provide glass traffic beads with no greater than 25 percent moisture by weight.
(3) Refractive Index
Provide glass traffic beads with a refractive index of at least 1.5 when tested by the liquid immersion method at 77°F.
(4) Shape
Provide spherically shaped glass traffic beads free of sharp, angular edges. Ensure the beads are free of scars and scratches.
(5) Static Charge
Provide glass traffic beads that do not create static electricity when flowing through a regular traffic bead dispenser.
(6) Gradation
Provide Standard Glass Beads for thermoplastic or plural-component with a gradation in accordance with AASHTO M 247, Type I or Type II.
Provide Large Glass Beads for thermoplastic or plural-component with a gradation in accordance with AASHTO M 247, Type III or Type IV.
If blended glass beads for thermoplastic or plural-component are to be utilized, provide a one-quart sample to the Department's Materials Division prior to installation, along with material certifications, product specifications, and a camsizer calibration for the testing/checking of the beads for conformity to supplied manufacture specification. Additionally, ensure all blended beads meet, or exceed, all other requirements stated in this section.
(7) Roundness
Provide glass beads that meet the roundness requirements of AASHTO M 247. The manufacturer will provide a Type A certification for roundness with each shipment of beads.
(8) Coatings
Provide standard and large glass beads with an adhesion coating to promote adhesion in thermoplastic pavement marking material in accordance with the thermoplastic material manufacture.
PAGE 20 OF 51PROPOSAL ID : 260143
711-3(e-h)19
Provide blended glass beads with an adhesion coating to promote adhesion in the thermoplastic pavement marking material in accordance with the thermoplastic material manufacture.
Provide standard and large glass beads with an adhesion coating to promote adhesion in the plural-component pavement marking material to be utilized on the project, and the coating shall be in accordance with plural-component manufacture.
Provide blended glass beads with an adhesion coating to promote adhesion in the plural-component pavement marking material in accordance with the plural-component material manufacture.
Supply standard glass beads in accordance with AASHTO M 247, Type I or Type II, with a moisture-resistant coating to prevent clumping.
(Replace with the following:)
711.06 TRAFFIC STRIPE PAINT-ACRYLIC WATERBORNE
Directly apply waterborne white and yellow traffic paint on AC or PCC surfaces or existing traffic stripe composed of solvent-based paint, waterborne paint, thermoplastic, or plural-component compounds. Apply with spray equipment, at application temperatures from 50°F to 150°F. Provide paint that receives and holds glass beads to produce retro-reflectorized traffic markings.
Provide material that has been approved by the Department and is currently listed on the Department's Approved Products List (APL). The contractor is to supply the engineer a copy of all material certifications, product approval, and any other documents requested by the engineer prior to product installation.
Ensure the Department, another state Department of Transportation, or AASHTO Product Evaluation & Audit Solutions (formerly NTPEP) have evaluated the material using a performance test of at least 12 months.
If the formula of the material is changed, the manufacture must resubmit for approval.
A. Materials
Provide paint free of lead and chromium with a limited quantity of volatile organic compounds (VOC). Provides materials in original containers with original labels.
B. General
The Resident Engineer must approve alternative materials before manufacture.
C. Pigment
(1) Titanium Dioxide
Provide titanium dioxide in accordance with ASTM D476, Type II, Rutile.
(2) Pigment Yellow 65
Provide Yellow 65 pigment from Hoechst Celanese, Engelhard, Sun Chemical, or an equivalent approved by the Resident Engineer.
(3) Calcium Carbonate
Provide calcium carbonate in accordance with the ASTM D1199, Type GC, Grade I, with at least 95 percent calcium carbonate and Type PC with at least 98 percent calcium carbonate.
PAGE 21 OF 51PROPOSAL ID : 260143
711-3(f-h)19
D. Vehicle
(1) Acrylic Emulsion Polymer
Provide Rohm and Haas HD-21, Dow DT400, or an equivalent approved by the Resident Engineer. Ensure the nonvolatile portion of the vehicle is composed of a 100 percent acrylic polymer and is at least 44 percent by weight.
(2) Methyl Alcohol
Provide methyl alcohol in accordance with ASTM D1152.
(3) Water
Provide potable water.
E. Mixed Paint
Strain the paint before filling with a screen no coarser than No. 40 mesh or a sieve meeting the Resident Engineer's approval.
Provide finished paint with no greater than 1.25 lb of VOC per gallon of total non- volatile paint, in accordance with ASTM D3960.
(1) Color
Provide white paint that dries to a flat white color, is free of tint, has opacity and visibility in both day and artificial light, and closely matches Color Chip 37925 of Federal Standard 559b.
Provide yellow paint that closely matches Color Chip 33538 of Federal Standard 595b and is within 6 percent of the PR 1 chart central color when read over the black portion of a 2A Leneta Chart.
(2) Flexibility
Provide paint that is flexible and will not crack or flake if tested in accordance with Federal Specification TT-P-1952B.
(3) Water Resistance
Provide water resistant paint in accordance with Federal Specification TT-P-1952B. Ensure the paint does not blister, lose adhesion, soften, or deteriorate after the examination.
(4) Freeze-Thaw Stability
Provide freeze-thaw stable paint that does not coagulate, discolor, or change in viscosity greater than 10 KU if tested in accordance with Federal Specification TT-P-1952B.
(5) Heat Stability
Provide heat stable paint that does not coagulate, discolor, or change in viscosity greater than 10 KU if tested in accordance with Federal Specification TT-P-1952B.
(6) Dilution Test
Provide paint that can be diluted with water without curdling or precipitation so that wet paint can be cleaned with water.
PAGE 22 OF 51PROPOSAL ID : 260143
711-3(g-h)19
(7) Storage Stability
Provide paint that will not cake, skin, liver, curdle, or hard settle after 30 days in a closed container filled three-quarter full. Ensure the paint can be remixed to a smooth, homogeneous state.
Ensure the viscosity does not differ from the original sample by greater than 5 KU.
Ensure the pigment will not settle or cake. Provide paint that will not skin, thicken, spoil, or change in consistency after nine months in storage from the packaging date.
Provide paint that can be re-dispersed with a paddle to a smooth, homogeneous condition.
(8) Contrast Ratio
Provide paint with a black/white contrast ratio of at least 0.96 when tested in accordance with ASTM D2805, and if applied at a wet film thickness of 15 mil on a 2A Leneta Chart, or equivalent, and air dried for 24 hr. The Department defines the contrast ratio as black over white.
(9) Reflectance
Ensure the daylight directional reflectance is at least 84 percent for white paint and at least 50 percent for yellow paint of a 15 mil wet film applied to a 2A Leneta Chart, or an equivalent. After drying for 24 hr, use a Colorimeter and ASTM E1349 to measure the reflectance of the paint over the black portion of the chart.
(10) Bleeding
Provide paint with a bleeding ratio of at least 0.97 if tested in accordance with Federal Specifications TT-P-1952B. Provide asphalt-saturated felt in accordance with ASTM D226, Type I.
(11) Abrasion Resistance
Provide at least 50 gal [190 L] of sand to remove paint film if tested in accordance with Federal Specification TT-P-1952B.
(12) No-Tracking Time Field Test
Dry the paint to a non-tracking condition in no greater than 3 min if applied at 17 mil ±1 mil wet film thickness plus 45 lb/ft³ of glass beads at the specified application temperature. The Department defines "no tracking" as the period when the line dries so a vehicle can run over the line at 40 mph without tracking the reflectorized line when viewed from 50 ft away.
(13) Dry Through Time
Apply the paint to a non-absorbent substrate at a wet film thickness from 17 mil ±1 mil. Place the paint in a humidity chamber controlled 90 ±5 percent relative humidity and from 72.5°F ±2.5°F.
Determine the dry-through time in accordance with ASTM D1640, except that the pressure exerted is the minimum amount to maintain contact with the thumb and film.
(Add the following:)
711.07 LONG LINE PAVEMENT MARKING
Provide the appropriate long line pavement marking material for various surfaces in accordance with Table 711:7, which defines the materials to be used for long line pavement markings in specific traffic volume
PAGE 23 OF 51PROPOSAL ID : 260143
711-3(h-h)19 thresholds, facility types, and pavement surface types.
Table 711:7 Long Line Pavement Marking Material Selection
Surface Type
Facility Type
AADT
< 8,000 8,000 - 40,000 > 40,000
Portland Cement Concrete (PCC)
Conventional Highway
Plural-Component* Paint
Plural-Component* Plural-Component
(Fast Set)**
Interstate & Controlled Access
Highways Plural-Component* Plural-Component*
Plural-Component (Fast Set)**
Asphalt (Superpave)
Conventional Highway
Thermoplastic Plural-Component*
Paint
Thermoplastic Plural-Component*
Paint
Thermoplastic Plural-Component
(Fast Set)**
Interstate & Controlled Access
Highways
Thermoplastic Plural-Component*
Thermoplastic Plural-Component*
Thermoplastic Plural-Component
(Fast Set)**
Chip Seal/Open- Graded Friction
Course/Permeable Friction
Course/Ultrathin/Stone Matrix Asphalt
Conventional Highway
Thermoplastic Paint
Thermoplastic Paint
Thermoplastic
Interstate & Controlled Access
Highways Thermoplastic Thermoplastic Thermoplastic
*All varieties of Plural-Component pavement markings include the following but not limited to various varieties of both fast setting and slow setting hybridized epoxies, modified urethanes/polyacrylates, methylmethacrylate (MMA), polyurea, or any other applicable plural-component material approved by the Department.
**Only fast set varieties of plural-component markings including materials that have a no-track time of under 20 minutes.
PAGE 24 OF 51PROPOSAL ID : 260143
856-3(a-j) 19 3-27-25
OKLAHOMA DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISIONS
FOR
TRAFFIC STRIPE (PLURAL-COMPONENT)
These Special Provisions revise, amend, and where in conflict, supersede applicable sections of the 2019 Standard Specifications for Highway Construction.
(Add the following:)
856.01 DESCRIPTION
This work consists of providing and placing reflectorized and non-reflectorized plural-component pavement markings on asphalt concrete (AC) and portland cement concrete (PCC) pavement surfaces.
Plural-component pavement markings includes multiple varieties of both fast setting and slow setting hybridized epoxies, modified urethanes/polyacrylates, methylmethacrylates (MMA), polyurea, or any other applicable plural-component materials approved by the Department.
856.02 MATERIALS
A. Physical Properties of the Mixed Compound
Provide a plural-component material that contains a homogeneous blend of liquid resins, pigments, and fillers and is also free of lead and other toxic heavy metals.
When heating to the application temperature, ensure the material does not emit toxic fumes.
Formulate and test the materials to ensure performance as a pavement marking material with glass beads applied to the surface.
Provide materials that are currently listed on the Department's Approved Products List (APL). Prior to product installation, supply the Engineer with a copy of all material certifications, product approval documentation, and any other documents requested by the Engineer.
Ensure the material has been evaluated by the Department, or another state Department of Transportation, using a performance test of at least 12 months. Alternatively, all products may be tested by AASHTO Product Evaluation & Audit Solution (formerly NTPEP). If the formula of the material is changed, the manufacturer must resubmit documentation for reapproval.
(1) Color
Provide material that complies with the requirements of ASTM D6628. Provide material that complies with the following minimum Daylight Reflectance Values at 45 degrees for white and 0 degrees for yellow:
• 75 % minimum for white
• 45 % minimum for yellow
(2) Hardness
Provide material with a minimum Shore D hardness of 75.
(3) Bond Strength of Concrete
Provide material that when catalyzed, has such a high degree of adhesion to the specified concrete surface that there is a 100% concrete failure. Apply the material at a film thickness of 0.01
PAGE 25 OF 51PROPOSAL ID : 260143
856-3(b-j) 19
± 0.001 inch to concrete, with a minimum compressive strength of 4000 psi. Allow the material to cure for 72 hours at 77EF before performing the test in accordance with AASHTO T237.
(4) Yellowness Index
Ensure the value after 72 hours in QUV is a maximum of 30 when tested at 0.01 ± 0.001 inch and after allowing 72 hours to cure. This is applicable to white markings only, and should be tested in accordance with ASTM E313.
(5) Drop on Glass Beads
Provide glass beads in accordance with Special Provision 711-3, Subsection 711.05.B, "Glass Beads for Traffic Stripe Thermoplastic or Plural Component." Provide a material certification from the glass bead manufacturer to the Engineer, for any glass beads prior to installation, including a document verifying that the provided glass have the appropriate coating for the plural-component material being installed. Additionally, provide a camsizer calibration for blended beads in addition to the material certification.
Provide a sample of all types of glass beads being utilized to the Engineer prior to installation.
Test the glass beads in accordance with AASHTO T346 in order to verify that the material meets the certification provided by the manufacture. Install beads in accordance with Subsection 856.04.C(2) of this provision.
(6) Non-Reflectorized Contrast or Shadow Markings
Install non-reflectorized contrast or shadow markings on all portland cement concrete (PCC) pavement surfaces, regardless of the length. Ensure the marking material used for the contrast or shadow marking conforms to the same formulation, material, and pre-approved sampling requirements, except for the following items: color pigments used, color requirements listed, and anti-skid material. Install anti-skid material in accordance with Subsection 856.04.C(2) of this provision.
(7) Sampling and Certification
Submit a Type D certification to the Engineer for each batch of stripe used on every project. The Engineer may require a one (1) quart sample of both the plural-component resin, as well as a one (1) quart sample of the material hardener to be submitted to the Department's Materials Division. This is for testing purposes of the material as well as to ensure the product is present on the Approved Products List (APL).
If the manufacturer makes any formulation changes to the plural-component striping material, ensure the manufacturer submits a written explanation of the changes to the formulation, the new physical and chemical properties for the resin, and a new safety data sheet (SDS) for the stripe to the Department's Traffic Engineering Division. The material will be re-evaluated, re-approval, and relisted on the APL at least thirty (30) days prior to its use.
(8) Other Available Colors
If a plural-component material is utilized on a project that is of a color other than white, yellow, or black, install this material per the project plans. It is preferred that Methylmethacrylate (MMA) plural-component material be used in these cases.
856.03 EQUIPMENT
Use equipment that sprays the plural-component materials in the manufacturer recommended proportions. Mount the equipment on a truck capable of applying uniformly dimensioned markings as required by the Contract.
PAGE 26 OF 51PROPOSAL ID : 260143
856-3(c-j) 19
Provide equipment with an automatic bead dispenser that also continuously mixes and agitates the pavement marking material.
Provide equipment capable of placing at least 40,000 ft of the following types of markings per day to the alignment, spacing, and thickness shown on the Plans:
• Solid or skipped stripes 6 in wide;
• Markings other than solid or skipped lines; and
• A centerline and no-passing barrier stripe configuration consisting of one skip stripe with two solid stripes, simultaneously.
Ensure the equipment places markings with clean edges of uniform cross section and thicknesses, with square ends, and with an approximate stripe-to-gap ratio of 1:3.
Ensure the equipment uniformly and instantly places the beads on the markings. When placing beads on two adjacent stripes, ensure each stripe has an equivalent bead coverage rate and embedment.
Provide equipment that heats and places each component within the component mix tolerances in accordance with the manufacturer recommendations.
Use equipment fitted with a functional data logging system. Ensure the data logging system is operational, calibrated, and in use before striping operations. Provide the Engineer with a certification that the data logging system equipment meets the manufacturer's recommended calibration, along with the manufacturer's recommendations for equipment calibration frequency.
Install materials that have the ability to be placed without the use of specific equipment discussed in this section (such as a roller) in accordance with the manufacturer’s recommendations and to the satisfaction of the Engineer.
856.04 CONSTRUCTION METHODS
A. Surface Preparation
Remove foreign material from the road surface before applying the plural-component material.
Ensure the pavement surface is dry.
Use abrasive blasting, grinding, or high-pressure water jet to remove existing, temporary, or permanent traffic markings until at least 95 percent of the underlying pavement is visible. Use these methods when removing existing material to apply a new material that is not of the same type, such as removing hot applied thermoplastic markings to install a plural-component marking material, or removing a type of plural-component material that will not bond to the existing material, unless otherwise specified by the manufacturer that the quantity of removal is not necessary for proper adhesion and longevity.
Remove the curing compound at least 1 inch beyond the width of the marking. After removing the curing compound, sweep and use a high-pressure air spray.
When removing a material to replace it with the same type of material and to minimize damage to the pavement surface while still providing a clean surface for new materials to bond to, use abrasive blasting, grinding, or a method approved by the Engineer to remove existing, temporary, or permanent traffic markings until 80 percent of the underlying pavement is visible, or to the inspector's preference.
Unless otherwise specified by the manufacturer, this reduced removal option is only allowed when the existing and new materials will bond to each other without cracking or loss of cohesion.
Minimize interference between temporary pavement markings and the permanent plural-component pavement marking materials.
PAGE 27 OF 51PROPOSAL ID : 260143
856-3(d-j) 19
Disposal of materials generated by the removal of existing pavement marking materials is…
This is the start of the file's text. The full file is on GovTribe.