This Project Manual is a bid set document for the Jefferson Transit Authority (JTA) Third Bay Fire Hydrant Project located at 63 Four Corners Road, Port Townsend, Washington. The scope of work includes installation of a fire main, pressure reducing valve, and fire hydrants; removal of an existing fire hydrant; removal and replacement of cement concrete pavement and curb; removal of existing trees; installation of storm drainage improvements and bollards; and restoration of disturbed areas. Sealed bids for Part 1 and Part 2 are due August 12, 2026, at 11:00 AM, with Part 3 bids due August 14, 2026, at 11:00 AM, both at 63 Four Corners Road, Port Townsend, WA 98368. A non-mandatory pre-bid site visit is scheduled for July 29, 2026, at 8:00 AM. The anticipated Notice to Proceed date is the week of August 17, 2026. The contract will be awarded to the lowest responsive and responsible bidder meeting all Award Requirements, including Washington State contractor registration, current unified business identifier number, industrial insurance coverage, employment security department number, state excise tax registration number, and compliance with prevailing wage requirements.

The estimated project cost range is $350,000 to $550,000, excluding alternates. All bids must be submitted on the prescribed bid forms with bid security equal to five percent of the Base Bid. Bidders are required to submit a Bid Price Form for the total lump sum amount, a unit price for concrete pavement replacement (up to 11,000 square feet), unit price modifiers for removal and export of excavated materials and unsuitable soils, and a separate line item for trench excavation safety provisions. The project is subject to Washington State prevailing wage requirements as determined by the Department of Labor and Industries. Bidders must list proposed subcontractors for HVAC, plumbing, electrical, structural steel installation, and rebar installation work at the time of bid submittal or within forty-eight hours as specified. The Contractor must furnish performance and payment bonds in the full amount of the Contract Sum plus applicable sales tax. The project is subject to Washington Industrial Safety and Health Act (WISHA) requirements, and the Contractor shall comply with all applicable safety regulations and COVID-19 procedures in effect at the time of bid.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jefferson Transit Authority (JTA)

Third Bay Fire Hydrant Project 63 Four Corners Road

Port Townsend, WA 98368

Project Manual Bid Set Documents

July 23, 2026

Jefferson Transit Authority Bid Set Third Bay Fire Hydrant Project July 23, 2026

PROJECT TEAM DIRECTORY 00 01 03 – Page 1 of 1

SECTION 00 01 03

PROJECT TEAM DIRECTORY

Owner: Jefferson Transit Authority

63 Four Corners Road

Owner’s Representatives:

Barker Creek Consulting, LLC P.O. Box 2011 Silverdale, WA 98383

Shannon Thompson, Principal-in-Charge shannont@barkercreek-ors.com Cell: 360-271-9207

Sydney Thompson, Project Manager sydneyt@barkercreek-ors.com Cell: 360-434-5889

Scott Thompson, Construction Manager scott.thompson@barkercreek-ors.com Cell: 801-636-6766

Civil Engineer: Ethos Civil 1901 65th AVE West, Suite 250 Tacoma, WA 98466 Office: 253-414-1989

William Thompson, PE william@ethoscivial.com Cell: 509-703-4050

END OF SECTION 00 01 03

mailto:shannont@barkercreek-ors.com mailto:sydneyt@barkercreek-ors.com mailto:scott.thompson@barkercreek-ors.com mailto:william@ethoscivial.com

TABLE OF CONTENTS 00 01 10 – Page 1 of 3

SECTION 00 01 10

TABLE OF CONTENTS

INTRODUCTORY INFORMATION

00 01 03 Project Directory 00 01 10 Table of Contents

DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 13 Bid Form 00 41 13 – A1 Part 1 – Bid Price Form 00 41 13 – A2 Part 1 – Contractor’s Bid Bond 00 41 13 – A3 Part 1 – Insurance Binder 00 41 13 – A4 Part 2 – Subcontractor Working List 00 41 13 – A5 Part 3 – Subcontractor Working List for Structural Steel and Rebar Installation 00 52 13 Agreement Form 00 52 13 – A A104-2017, Standard Abbreviated Form of Agreement Between Owner and

Contractor 00 61 13 Performance and Payment Bond 00 62 20 Statement of Intent to Pay Prevailing Wages 00 62 30 Affidavit of Wages Paid 00 73 00 Special Conditions of the Contract 00 73 00 – A Special Conditions of the Contract 00 73 19 Health and Safety Requirements 00 73 43 Wage Rate Requirements 00 73 43 – A1 Journey Level Prevailing Wage Rates for Jefferson County 00 73 43 – A2 Apprentice Level Prevailing Wage Rates for Jefferson County 00 73 43 – A3 Prevailing Wage Benefit Code Key

DIVISION 01 GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 25 00 Substitution Procedures 01 25 00 – A Substitution Request Form 01 26 00 Contract Modification Procedures 01 26 00 – A1 Engineer’s Supplemental Instructions Form

TABLE OF CONTENTS 00 01 10 – Page 2 of 3

01 26 00 – A2 Request for Information Form 01 26 00 – A3 Change Order Proposal 01 26 00 – A4 Construction Change Directive Form 01 26 00 – A5 Construction Change Order Form 01 29 00 Payment Procedures 01 29 00 – A Progress Payment Form (Revised G702) 01 29 73 Schedule of Values 01 31 13 Project Coordination 01 31 19 Project Meetings 01 32 16 Schedules and Reports 01 32 33 Photographic Documentation 01 33 00 Submittals 01 33 13 Certificate of Compliance 01 33 15 No Hazardous Materials Certification 01 33 23 Shop Drawing, Product Data, and Samples 01 41 00 Regulatory Requirements 01 42 13 Abbreviations and Acronyms 01 42 16 Definitions 01 42 19 Reference Standards 01 45 29 Testing and Inspection Services 01 50 00 Construction Facilities and Temporary Controls 01 55 26 Traffic Maintenance Facilities 01 58 00 Project Identification 01 61 10 Materials and Equipment 01 65 10 Delivery, Storage, and Handling 01 71 25 Utility Location Requirements 01 73 29 Cutting and Patching 01 74 00 Construction Cleaning 01 74 19 Construction Waste Management 01 74 19 – A1 Waste Management Progress Report (Example) 01 74 19 – A2 Waste Management Plan (Example) 01 77 00 Closeout Procedures 01 77 00 – A Closeout Checklist 01 78 23 Operation and Maintenance Data 01 78 36 Warranties and Bonds 01 78 36 – A1 Warranty Contact List 01 78 36 – A2 Subcontractor’s Warranty 01 78 39 Project Record Documents

TABLE OF CONTENTS 00 01 10 – Page 3 of 3

01 91 00 Commissioning

END OF SECTION 00 01 10

ADVERTISEMENT FOR BIDS 00 11 13 – Page 1 of 1

SECTION 00 11 13

ADVERTISEMENT FOR BIDS

Jefferson Transit Authority (JTA) – Request for sealed bids for JTA Fire Hydrant Addition.

Bids Due: August 12, 2026, 11:00 AM (Part 1 and 2) Part 3 Bid Due: August 14, 2026, 11:00 AM Bid Opening Location: 63 Four Corners Road, Port Townsend, WA 98368 Start Date: Anticipated NTP Week of August 17, 2026

Non-Mandatory Pre-Bid Site Visit: July, 29, 2026 at 8:00 AM at Location: 63 Four Corners Road, Port Townsend, WA 98368

The estimated cost range for this project is: $350,000 to $550,000, excluding Alternate.

Owner Contact: Sydney Thompson, Barker Creek Consulting, sydneyt@barkercreek-ors.com

Note: Obtain the Bid Documents on ARC Planroom and Builders Exchange.

The Scope of Work to be completed under this Contract consists of the installation of a fire main, pressure reducing valve, and fire hydrants; removal of an existing fire hydrant; removal and replacement of cement concrete pavement and curb; removal of existing trees; installation of storm drainage improvements and bollards; restoration of disturbed areas; and other related improvements. All work shall be performed in accordance with the Contract Plans, these Contract Provisions, and the Standard Specifications.

This project is subject to meet Washington State prevailing wages rates. All work performed on the project will be subject to the approved wage determination rates in the bid documents.

Published: July 23, 2026 and July 28, 2026

END OF SECTION 00 11 13

Jefferson Transit Authority

INSTRUCTIONS TO BIDDERS 1

154263534.4

INSTRUCTIONS TO BIDDERS

1.01 DEFINITIONS

A. All definitions set forth in the General Conditions of the Contract for Construction or in other Contract Documents are applicable to the Bidding Documents.

B. “Addenda” are written or graphic instruments issued by the Architect or the Owner prior to the execution of the Contract which modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections. The contents of Addenda are issued in no particular order and therefore should be carefully and completely reviewed. Addenda relating to administrative matters, such as, for example, the date or time of meetings or Bid receipt, may be issued in writing by fax, mail or other delivery.

C. An “Alternate Bid” (or “Alternate”) is an amount stated in the Bid to be added to or deducted from the amount of the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, if accepted by the Owner.

D. “Award” means the formal decision by the Owner notifying a Bidder with the lowest Responsive Bid of the Owner’s acceptance of the Bid and intent to enter into a contract with the Bidder. A contract is only formed upon execution of the contract, and not simply by Award.

E. The “Award Requirements” include the following statutory requirements as a condition precedent to Award. The lowest Responsive Bidder shall:

(1) have a certificate of registration in compliance with RCW 18.27;

(2) have a current state unified business identifier number;

(3) if applicable, have industrial insurance coverage for the Bidder’s employees working in

Washington as required in Title 51 RCW;

(4) have an employment security department number as required in Title 50 RCW;

(5) have a state excise tax registration number as required in Title 82 RCW;

(6) not be disqualified from bidding on any public works contract under RCW 39.06.010

(unregistered or unlicensed contractors) or RCW 39.12.065(3) (prevailing wage violations);

(7) if bidding on a public works project subject to the apprenticeship utilization requirements in

RCW 39.04.320, not have been found out of compliance by the Washington state apprenticeship and training council for working apprentices out of ratio, without appropriate supervision, or outside their approved work processes as outlined in their standards of apprenticeship under RCW 49.04 for the one-year period immediately preceding the date of the Bid solicitation;

(8) have received training on the requirements related to public works and prevailing wages under chapters 39.04 and 39.12 RCW, or be exempt from such training requirements if the Bidder has completed three or more public works projects and has had a valid business license in Washington for three or more years; and

(9) within the three-year period immediately preceding the date of the bid solicitation, not have been determined by a final and binding citation and notice of assessment issued by the department of labor and industries or through a civil judgment entered by a court of limited or general jurisdiction to have willfully violated, as defined in RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW.

Further, under revised RCW 39.04.350, if the Bidder has a history of receiving monetary penalties for not achieving the apprentice utilization requirements pursuant to RCW 39.04.320, or is habitual

INSTRUCTIONS TO BIDDERS 2

154263534.4 in utilizing the good faith effort exception process, the bidder must submit an apprenticeship utilization plan within ten business days immediately following the Owner’s notice to proceed.

F. The “Ba se Bid” is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as the base to which work may be added or from which work may be deleted for sums stated in Alternate Bids.

G. “BidA ” is a complete and properly signed proposal to do the Work or designated portion thereof, submitted in accordance with the Bidding Documents, for the sums therein stipulated and supported by any data called for by the Bidding Documents.

H. “A Bidder” is a person or entity who submits a Bid for a prime contract with the Owner for the Work described in the Contract Documents.

I. “The Bidding Documents” include the Advertisement or Invitation to Bid, Instructions to Bidders, the Bid form, any other sample Bidding and contract forms, the Bid Bond, and the Contract Documents, including any Addenda issued prior to receipt of Bids.

J. “The Contract Documents” for the Work consist of the Agreement Between Owner and Contractor, the General Conditions of the Contract (as well as any Supplemental, Special or other Conditions included in the Project Manual), the Drawings, the Specifications, and all Addenda issued prior to, and all modifications issued after, execution of the Contract.

K. “The Owner” is Jefferson Transit Authority.

L. To be considered “Responsible” or meet “Responsibility” requirements, a Bidder must meet the following supplemental criteria applicable to this Project to the satisfaction of the Architect and the Owner:

(1) The ability, capacity, and skill to perform the Contract;

(2) The character, integrity, reputation, judgment, experience, and efficiency of the Bidder;

(3) Whether the Bidder can perform the Contract within the time specified;

(4) The previous and existing compliance by the Bidder with laws relating to the Contract;

(5) The quality of performance of previous contracts, including demonstration of successful completion of similar projects of equal or greater size, scope and value in the last three (3) years;

(6) The designated Project Manager shall have a minimum of three (3) years of successful experience in project management and scheduling of projects of similar scope and complexity;

(7) The designated Superintendent shall have a minimum of five (5) years of successful supervision of projects of similar scope and complexity;

(8) Any other qualifications required by the Contract Documents or Bidding Documents; and

(9) Such other information as may be secured having a bearing on the decision to award the contract.

M. “SubA -bidder” is a person or entity who submits a bid to a Bidder for materials, equipment or labor for a portion of the Work.

N. “A Unit Price” is an amount stated in the Bid as a price per unit of measurement for materials, equipment or services as described in the Bidding Documents or in the Contract Documents. The Owner reserves the right to reject at any time, without impairing the balance of the proposal, any or all such predetermined unit prices.

INSTRUCTIONS TO BIDDERS 3

154263534.4

1.02 BIDDER’S REPRESENTATIONS

By making its Bid, each Bidder represents that:

A. BIDDING DOCUMENTS. The Bidder has read and understands the Bidding Documents, and its Bid is made in accordance with them.

B. POSSIBLE SELF-PERFORMED WORK REQUIREMENT. The Bidder will perform with its own forces at least that percentage (if any) of the Work required by the Bidding Documents or the Contract Documents.

C. PRE-BID MEETING. The Bidder has attended any pre-bid meeting(s) required by the Bidding Documents.

D. BASIS. Its Bid is based upon the materials, systems, services, and equipment required by the Bidding Documents, without exception.

E. EXAMINATION. The Bidder has carefully examined and understands the Bidding Documents, the Contract Documents (including, without limitation, any liquidated damages and insurance provisions), and the Project site, including any existing buildings, it has familiarized itself with the local conditions under which the Work is to be performed and has correlated its observations with the requirements of the Contract Documents and it has satisfied itself as to the nature, location, character, quality and quantity of the Work, the labor, materials, equipment, goods, supplies, work, services and other items to be furnished, and all other requirements of the Contract Documents. The Bidder has also satisfied itself as to the conditions and other matters that may be encountered at the Project site or affect performance of the Work or the cost or difficulty thereof, including but not limited to those conditions and matters affecting: transportation, access, disposal, handling and storage of materials, equipment and other items; availability and quality of labor, water, electric power and utilities; availability and condition of roads; climatic conditions and seasons; physical conditions at the Project site and the surrounding locality; topography and ground surface conditions; and equipment and facilities needed preliminary to and at all times during the performance of the Work. The failure of the Bidder fully to acquaint itself with any applicable condition or matter shall not in any way relieve the Bidder from the responsibility for performing the Work in accordance with, and for the Contract Sum and within the Contract Time provided for in, the Contract Documents.

F. PROJECT MANUAL. The Bidder has checked its copies of the Project Manual with the Table of Contents bound therein to ensure the Project Manual is complete.

G. SEPARATE WORK. The Bidder has examined and coordinated all Drawings, Contract Documents, and Specifications for any other contracts to be awarded separately from, but in connection with, the Work being bid upon, so that the Bidder is fully informed as to conditions affecting the Work under the contract being bid upon.

H. LICENSE REQUIREMENTS. Bidders and their proposed Subcontractors shall be registered and shall hold such licenses as may be required by the laws of Washington, including RCW 18.27, for the performance of the Work specified in the Contract Documents.

I. NO EXCEPTIONS. Bids must be based upon the materials, systems and equipment described and required by the Bidding Documents, and terms and conditions in the Contract Documents, without exception.

INSTRUCTIONS TO BIDDERS 4

154263534.4

1.03 BIDDING DOCUMENTS

A. COPIES

1. Deposit. Bidders may obtain complete sets of the Bidding Documents from the issuing office and other locations designated in the Advertisement or Invitation to Bid in the number and for the deposit amount, if any, stated. The deposit (if any) will be refunded to Bidders who submit a bona fide Bid and return the Bidding Documents in good condition within ten (10) days after receipt of Bids. The cost of replacement of any missing or damaged documents will be deducted from the deposit. A Bidder awarded a Contract may retain the Bidding Documents, and its deposit will be refunded.

2. Sub-bidders. Bidding Documents will not be issued directly to Sub-bidders or others unless specifically offered in the Advertisement or Invitation to Bid.

3. Complete sets. Bidders shall use complete sets of Bidding Documents in preparing Bids and are solely responsible for utilizing established plan holder identification processes to obtain updated bid information; neither the Owner nor the Architect assumes any responsibility for errors or misinterpretations resulting from the use of incomplete and/or superseded sets of Bidding Documents. Printed copies of plans take precedence over any on-line images.

4. Conditions. The Owner and/or the Architect make copies of the Bidding Documents available on the above terms only for the purpose of obtaining Bids on the Work and do not confer a license or grant permission for any other use.

5. Legible Documents. To the extent any drawings, specifications, or other Bidding documents are not legible, it is the Bidder’s responsibility to notify the Owner and the Architect and to obtain legible documents from the plan center.

B. INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS

1. Format. The Contract Documents may be divided into parts, divisions, and sections for convenient organization and reference. Generally, there has been no attempt to divide the Specification sections into Work performed by the various building trades, any Work by separate contractors, or any Work required for separate facilities in or phases of the Project.

2. Notify Owner and Architect. Bidders and Sub-bidders shall promptly notify the Owner and the Architect in writing of any ambiguity, inconsistency, or error that they may discover upon examination of the Bidding Documents or of the site and local conditions. All Bidders and Sub-bidders shall thoroughly familiarize themselves with specified products and installation procedures and submit to the Owner and the Architect any objections (in writing) no later than seven (7) calendar days prior to the Bid Date. The submittal of the Bid constitutes acceptance of products and procedures specified as sufficient, adequate, and satisfactory for completion of the Contract.

3. Written request. Bidders and Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a written request which shall reach the Architect at least seven (7) calendar days prior to the date for receipt of Bids.

4. Addenda. Any interpretation, correction or change of the Bidding Documents will be made by written Addendum. Interpretations, corrections or changes of the Bidding Documents made in any other manner will not be binding, and Bidders shall not rely upon such interpretations, corrections and changes.

INSTRUCTIONS TO BIDDERS 5

154263534.4

5. Singular references. Reference in the singular to an article, device, or piece of equipment shall include as many of such articles, devices, or pieces as are indicated in the Contract Documents or as are required to complete the installation.

6. Utilities and runs. The Bidder should assume that the exact locations of any underground or hidden utilities, underground fuel tanks, and any plumbing and electrical runs may be somewhat different from any location indicated in the surveys or Contract Documents.

7. Division of Contract Documents. The Contract Documents may be divided into parts, divisions, and sections for convenient organization and reference. Generally, there has been no attempt to divide the Specification sections into Work performed by the various building trades, any Work by separate contractors, or any Work required for separate facilities in of phases of the Project.

C. SUBSTITUTIONS

1. Standard. The materials, products, procedures and equipment described in the Bidding Documents establish a standard of required function, dimension, appearance, and quality that must be met by any proposed substitution.

2. Substitution procedure. No substitution will be considered prior to receipt of Bids unless the Architect receives a written request for approval on the Architect’s Substitution Request form for the Project, with all data requested on the form completed, at least seven (7) days prior to the date for receipt of Bids. Each such request shall be submitted with a Request for Substitution form identical to or equivalent in content to the form found in the Project Manual, and shall include the name of the material or equipment proposed to be replaced and a complete description of the proposed substitute, including drawings, cuts, performance and test data, warranty information, and any other information necessary for an evaluation. A statement setting forth any changes in other materials, equipment or other Work that incorporation of the substitute would require shall be included. The proposer has the burden to prove the merit of the proposed substitute; by proposing the substitution, the Bidder represents that it has personally investigated the proposed material or product and determined that it is equal or better in all respects to that specified, that the same or better warranty will be provided for the substitution, that complete cost data, including all direct and indirect costs of any kind, has been presented, that the Contract Time will not be increased, and that it will coordinate the installation of the substitute if accepted and make all associated changes in the Work. The Architect’s decision to approve or disapprove a proposed substitution shall be final. Written requests for approval shall constitute a guarantee by the Bidder that the articles or materials are in all respects, including warranty and installation, equal or superior to those specified, unless otherwise noted. To the extent the proposed substitution will require additional services by the Architect or its consultants after Bid award, the Bidder, if successful, will be required to pay the Architect or its consultants for these services at their customary hourly rates.

3. Addendum. If the Architect approves a proposed substitution prior to receipt of Bids, the approval will be set forth in a written Addendum. Bidders shall not rely upon approvals made in any other manner. Substitution request forms returned by the Architect are a courtesy only, and Bidders/Sub-bidders shall rely solely on substitution approvals listed in an Addenda.

4. Post-Bid substitutions. After the Contract has been executed, the Owner and the Architect may consider a written request for the substitution of material or products in place of those specified in the Contract Documents only under the circumstances as specified therein.

INSTRUCTIONS TO BIDDERS 6

154263534.4

D. ADDENDA

1. Written. All Addenda will be written. They will be mailed, emailed, faxed delivered, and/or posted electronically with notice to those the Architect knows to have received a complete set of Bidding Documents.

2. Copies. Copies of Addenda will be made available for inspection wherever Bidding Documents are on file for that purpose.

3. Verification and acknowledgment of receipt. Prior to bidding, each Bidder shall ascertain that it has received all Addenda issued. Each Bidder shall acknowledge its receipt of all Addenda in its Bid.

1.04 BIDDING PROCEDURE

A. FORM AND STYLE OF BIDS

1. Form. Bids (including any required attachments) shall be submitted on forms identical to the form included with the Bidding Documents. Bids on different forms may be rejected. No oral, email, or telephonic responses or modifications will be considered to be Bids.

2. Entries on the Bid form. All blanks on the Bid form shall be filled in by typewriter or manually in ink.

3. Words and figures. Where so indicated by the makeup of the Bid form, sums shall be expressed in both words and figures; in case of discrepancy between the two, and regardless of any statement to the contrary on the Bid form, the amount written in figures shall govern and the words shall be used to determine any ambiguities in the figures. Portions of the Bid form may require the addition of component bids to a total or the identification of component amounts within a total. In case of discrepancy between component amounts listed and their sum(s), the component amounts listed shall govern.

4. Initial changes. Any interlineation, alteration or erasure must be initialed by an authorized representative of the Bidder.

5. Alternates and Unit Prices. All requested Alternates and unit prices should be bid. The Owner reserves the right, but is not obligated, to reject any Bid on which all requested Alternates or unit prices are not bid. If no change in the Base Bid is required for an Alternate, enter “No Change.” If there is no entry, it will be presumed that the Bidder has made no offer to accomplish this Alternate. If it is not otherwise clear from the Bid or nature of the Alternate, it will be presumed that the amount listed for an Alternate is an add rather than a deduct.

6. No conditions. The Bidder shall make no conditions or stipulations on the Bid form nor qualify its Bid in any other manner.

7. Identity of Bidder. The Bidder shall include in the specified location on the Bid form the legal name of the Bidder and, if requested, a description of the Bidder as a sole proprietor, a partnership, a joint venture, a corporation (including the state of incorporation), or another described form of legal entity. The Bid shall be signed by the person or persons legally authorized to bind the Bidder to a contract. A Bid submitted by an agent shall have a current power of attorney attached certifying the agent’s authority to bind the Bidder, and provide other information requested.

INSTRUCTIONS TO BIDDERS 7

154263534.4

8. Bid amounts do not include sales tax. The Bid shall include in the sum stated all taxes imposed by law, EXCEPT STATE AND LOCAL SALES TAX ON THE CONTRACT SUM.

9. Bid breakdown. The Bid form may contain, for the Owner’s accounting purposes only, a breakdown of some or all of the components included in the Base Bid.

B. POTENTIAL LISTING OF SUBCONTRACTORS

1. Procedure. On certain projects of the Owner, the Bid form includes a requirement that certain Subcontractors be listed, and the list must be submitted to the Owner as described in the bidding documents. In these circumstances, the Bidder must name the Subcontractor with whom the Bidder, if awarded the Contract, will subcontract directly (i.e., not lower-tier Subcontractors) for performance of the work of:

(a) HVAC (heating, ventilation and air conditioning),

(b) plumbing as described in RCW 18.106,

(c) electrical work as described in RCW 19.28,

(d) structural steel installation,

(e) rebar installation, and

(f) any other categories of Work listed on the Subcontractor listing form(s).

TIMING: The listing of HVAC, plumbing, and electrical subcontractors, with proof of license information, shall occur at the published bid submittal time. Errors in the proof of license information must be corrected by the Bidder within forty-eight hours of submission. The listing of structural steel installation and rebar installation subcontractors shall occur within forty-eight hours of the published bid submittal time. The listing of any other categories of Work listed on the Subcontractor listing form(s) shall occur as indicated on such forms or as otherwise described in the bidding documents.

SELF-PERFORMANCE: If the Bidder intends to self-perform any of these categories of Work, it must name itself for each such category of Work.

IF NO SUBCONTRACTORS: If there is no work to be performed by a HVAC, plumbing, electrical, structural steel installation, rebar installation, or other subcontractor category identified on the Bid form(s), the Bidder should insert “None” or “N/A” on the Bid form. If a category is left blank, that shall indicate that the Bidder believes that there is no Work to be performed by that trade.

MULTIPLE ENTRIES: The Bidder shall not list more than one (1) entity for a particular category of Work identified, unless a Subcontractor varies with an Alternate Bid, in which case the Bidder shall identify the Subcontractor to be used for the Alternate and the affected portion of the Work and otherwise make its Bid clear as to which subcontractor shall be utilized depending upon the selection of alternates.

MULTIPLE SUBMITTAL TIMES. In the event the Bidding Documents call for a second submittal time for receipt of alternate bids, and no additional Subcontractors are listed with such alternate bids, the Owner will consider that there is no change in the Subcontractors from those listed with regard to the base Bid.

2. Failure to Submit. In accordance with RCW 39.30.060, failure of a Bidder to submit the names of such proposed heating, ventilation and air conditioning, plumbing, electrical, structural steel installation, and rebar installation Subcontractors or to name itself to perform such Work or the naming of two or more Subcontractors to perform the same Work in the time periods described above shall render the Bidder’s Bid nonresponsive and, therefore, void.

INSTRUCTIONS TO BIDDERS 8

154263534.4

3. Requirement to Subcontract. The Bidder, if awarded the Contract, will subcontract with the listed Subcontractor for performance of the portion of the Work designated on the Form of Proposal, subject to the provisions of the Contract for Construction and RCW 39.30.060. The Bidder shall not substitute a listed Subcontractor in furtherance of bid shopping or bid peddling.

4. Replacement. If a listed Subcontractor is unable to comply with any bondability, qualification, or other requirements of the Contract or Bidding Documents (including without limitation a finding of Subcontractor non-Responsibility), the Owner may require the Bidder to replace the Subcontractor with a Subcontractor acceptable to the Owner at no change in the Contract Sum or Contract Time.

5. Subcontractor Standards. Subcontractors shall meet contractual and technical qualifications standards, and provide specialized certification, licensing, and/or payment and performance bonding where specified.

C. BID SECURITY

1. Purpose and procedure. Each Bid shall be accompanied by a bid security payable to the Owner in the form required in the Bidding Documents and equal to five percent (5%) of the Base Bid. The bid security constitutes a pledge that the Bidder will enter into the Contract with the Owner in the form provided, in a timely manner, and on the terms stated in its Bid and will furnish in a timely manner the payment and performance bonds, certificates of insurance, Contractor’s Construction Schedule, and all other documents required in the Contract Documents. Should the Bidder fail or refuse to enter into the Contract or fail to furnish such documents, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as a penalty. By submitting its Bid and bid security, the Bidder agrees that any forfeiture is a reasonable prediction at the time of Bid submittal of future damages to the Owner.

2. Form. The bid security shall be in the form of a certified or bank cashier’s check payable to the Owner or a bid bond executed by a bonding company acceptable to the Owner and licensed in the State of Washington on the form included with the Bidding Documents (if any) or on an acceptable and equivalent form. The Attorney-in-Fact who executes the bond on behalf of the surety shall be licensed to do business in the State of Washington and shall affix to the bond a certified and current copy of that person’s Power of Attorney.

3. Retaining Bid Security. The Owner will have the right to retain the Bid Security of Bidders to whom an award is being considered until the earliest of either (a) the Contract has been executed, and payment and performance bonds have been furnished, or (b) the specified time has elapsed so that Bids may be withdrawn, or (c) all Bids have been rejected.

4. Return of Bid Security. Within sixty (60) days after the Bid Date, the Owner will release or return Bid securities to Bidders whose Bids are not to be further considered in awarding the Contract. Bid securities of the three apparent low Bidders will be held until the Contract has been finally executed, after which all unforfeited Bid securities will be returned.

D. SUBMISSION OF BIDS

1. Procedure. The Bid, the Bid security, and any other documents required to be submitted with the Bid shall be enclosed in a sealed opaque envelope. The envelope shall be addressed to the party specified in the Advertisement or Invitation to Bidders and shall be identified with the Bid number and submittal date. Bids must be hand delivered and may not be sent by mail.

2. Deposit. Bids shall be deposited at the designated location prior to the time and date for receipt of Bids indicated in the Advertisement or Invitation to Bid, or any extension thereof made by

INSTRUCTIONS TO BIDDERS 9

154263534.4

Addendum. Bids received after the time and date for receipt of Bids may be opened, retained unopened, or returned (open or unopened), all at the discretion of the Owner.

3. Responsibility. The Bidder assumes full responsibility for timely delivery at the location designated for receipt of Bids.

4. Form. Oral, fax, telephonic, email, electronic, or telegraphic Bids are invalid and will not be considered.

E. MODIFICATION OR WITHDRAWAL OF BID

1. After receipt time. A Bid may not be modified, withdrawn or canceled by the Bidder during a sixty (60) day period following the time and date designated for the receipt of Bids, and each Bidder so agrees by virtue of submitting its Bid.

2. Before receipt time. Prior to the time and date designated for receipt of Bids, any Bid submitted may be modified or withdrawn only by notice to the party receiving Bids at the place designated for receipt of Bids. Such notice shall be in writing over the signature of the Bidder or by email or fax; if by email or fax, written confirmation over the signature of the Bidder shall be hand delivered on or before the date and time set for receipt of Bids. The notice shall be worded so as not to reveal the amount of the original Bid. Email notice will not be considered.

It shall be the Bidder’s sole responsibility to verify that the notice has been received by the Owner in time to be withdrawn before the Bid opening.

3. Resubmittal. Withdrawn Bids may be resubmitted up to the time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders.

4. Bid security with resubmission. Bid security shall be in an amount sufficient for the Bid as modified or resubmitted.

F. NOTICE

1. Notice or a request from a Bidder under these Instructions to Bidders must be in writing over the signature of the Bidder and delivered in person or by express delivery, email or fax. If the notice is by email or fax, written confirmation over the signature of the Bidder must be hand delivered on or before the date and time set for the notice.

1.05 CONSIDERATION OF BIDS

A. OPENING OF BIDS: Unless stated otherwise in the Advertisement or Invitation to Bid or any Addendum, the properly identified Bids received on time will be opened publicly and will be read aloud. An abstract of the Base Bids and Alternate Bids, if any, will be made available to Bidders and other interested parties.

B. REJECTION OF BIDS: The Owner shall have the right but not the obligation to reject any or all Bids for any reason or for no reason, to reject a Bid not accompanied by required Bid security or by other material or data required by the Bidding Documents, or to reject a Bid which is in any way incomplete or irregular.

C. ACCEPTANCE OF BID (AWARD)

1. Owner. The Owner intends (but is not bound) to award a Contract to the lowest Responsible and Responsive Bidder, provided the Bid has been submitted in accordance with the requirements of the Bidding Documents and does not exceed the funds available. The Owner

INSTRUCTIONS TO BIDDERS 10

154263534.4 has the right to waive any informality or irregularity in any Bid(s) received and to accept the Bid which, in its judgment, is in its own best interests.

2. Alternates. The Owner shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided in the Contract Documents or Bidding Documents, and to determine the low Bidder on the basis of the sum of the Base Bid and the Alternates (if any) accepted. The Owner retains the right to accept Alternate Bid items at the price bid within sixty (60) days after the Agreement is executed.

3. Requirements for Award. Before the Award, the lowest Responsive Bidder shall meet the Award Requirements.

D. BID PROTEST PROCEDURES

1. Procedure. A Bidder protesting for any reason the Bidding Documents; a bidding procedure;

the Owner’s objection to the Bidder or a person or entity proposed by the Bidder, including but not limited to a finding of non-Responsibility; the rejection of a Bid; the award of the Contract;

or any other aspect arising from or relating in any way to the bidding or award or lack thereof, shall cause a written protest to be filed with the Owner within two (2) business days of the event giving rise to the protest and, in any event, no later than two (2) business days after the date upon which Bids are opened. (Intermediate Saturdays, Sundays, and legal holidays are not counted.) The written protest shall include the name of the protesting Bidder, a detailed description of the specific factual and legal grounds for the protest, copies of all supporting documents, and the specific relief requested. The written protest shall be delivered to:

Jefferson Transit Authority 63 Four Corners Road Port Townsend, WA 98368

2. Consideration. Upon receipt of the written protest, the Owner will consider the protest. The Owner may, within three (3) business days of the Owner’s receipt of the protest, provide any other affected Bidder(s) the opportunity to respond in writing to the protest. If the protest is not resolved by mutual agreement of the protesting Bidder and the Owner, the Superintendent of the Owner or his or her designee will review the issues and promptly furnish a final and binding written decision to the protesting Bidder and any other affected Bidder(s) within six (6) business days of the Owner’s receipt of the protest. (If more than one (1) protest is filed, the Owner’s decision will be provided within six (6) business days of the Owner’s receipt of the last protest.)

If no reply is received from the Owner during the six (6) business-day period, the protest shall be deemed rejected.

3. Waiver. Failure to comply with these protest procedures will render a protest waived.

4. Condition precedent. Timely and proper compliance with and exhaustion of these protest procedures shall be a condition precedent to any otherwise permissible judicial consideration of a protest.

1.06 POST BID INFORMATION

A. INFORMATION FROM APPARENT LOW BIDDER

1. Submittal. Within forty-eight (48) hours of the Architect’s request, the apparent low Bidder and any other Bidders so requested shall submit the following to the Architect and Owner:

INSTRUCTIONS TO BIDDERS 11

154263534.4

(a) additional information regarding the use of their own forces and the use of subcontractors and suppliers, if requested by Owner;

(b) a properly executed Contractor’s Qualification Statement on the form provided (unless otherwise required to be submitted at the time of the Bid);

(c) a letter or form from the Bidder’s insurance company stating that the insurance required by the Contract Documents will become effective upon execution of the Contract;

(d) a letter or form from the Bidder’s surety stating that the bond(s) required by the Contract Documents will become effective upon execution of the Contract;

(e) if requested by the Owner, a detailed breakdown of the Bid in a form acceptable to the Owner; and

(f) a signed statement in accordance with RCW 9A.72.085 verifying under penalty of perjury that the bidder is in compliance with the responsible bidder criteria of RCW 39.04.350(1)(g).

Failure to provide any of the above information in a timely manner may constitute an event of breach permitting forfeiture of the Bid security.

2. Responsibility. The Bidder will be required to establish to the satisfaction of the Architect and the Owner the reliability and Responsibility of the persons or entities proposed to furnish and perform the Work described in the Bidding Documents as well as qualifications set forth in the Sections of the Project Manual pertaining to such proposed Subcontractor’s respective trades.

The Responsibility of the Bidder may be judged in part by the Responsibility of these proposed entities. The following will be considered:

The ability, capacity, and skill to perform the contract;

The character, integrity, reputation, judgment, experience, and efficiency of the

Bidder;

Whether the Bidder can perform the contract within the time specified;

The quality of performance of previous contracts;

The previous and existing compliance by the Bidder with laws relating to the contract; and Such other information as may be secured having a bearing on the decision to award the contract.

CONSIDERATION. In considering a Bidder’s Responsibility, a Bidder shall be deemed to be unqualified to perform the Contract if, after review and verification of the representations included upon the Contractor’s Qualification Statement submitted by the Bidder, conditions such as, but not limited to, the following appear:

(a) The Bidder does not have sufficient prior experience (or an acceptable substitute thereof, as described below) with projects of a similar nature in technical, managerial, and financial requirements to that in the present Contract being bid. In addition to such established contractors, a newly established contractor may be considered qualified if it has shown on the Contractor’s Qualification Statement that it is staffed with sufficient technical, managerial, and financial personnel with prior experience in the nature of construction for which the Bids are invited.

(b) The Bidder does not have sufficient capability to undertake the obligations of the Contract. A determination will be made when the Owner’s review of the probable cash flow needs of the Bidder for this Project (including payroll, cost of material and supplies, equipment rental costs, and any other direct or incidental costs of the Contract), concludes that the Bidder does not have sufficient financial resources to enable it to satisfy its financial obligations under the Contract.

INSTRUCTIONS TO BIDDERS 12

154263534.4

(c) The Bidder has submitted unrealistic unit prices as determined by other Bidders’ unit prices for this Project.

(d) The Bidder does not have sufficient staff, equipment, or plant available to perform the Contract. The Owner’s determination in this matter will be based upon that represented by Bidder in the Contractor’s Qualification Statement.

(e) The Bidder has a history of unsatisfactory performance of contracts of this or similar nature, regardless of whether such contracts existed between the Owner and the Bidder, or other parties.

A determination of this nature will be made if the Owner, after review of the Bidder previous work experience, determines that the Bidder’s unsatisfactory performance has resulted predominantly from the Bidder’s failure rather than a failure to perform by another party. The Owner will give the Contractor an opportunity to explain such nonperformance’s before any final determination is reached.

A determination of failure to perform will be made if the Owner is satisfied after review of the Bidder’s prior experience, that the Bidder has failed to satisfy its obligations under past contracts and the Owner cannot safely assume satisfactory performance of the Contract by the Bidder.

In reaching its determination, the Owner may consider statements of other parties to the prior unperformed contracts, as well as the representations of the Bidder on its Contractor’s Qualification Statement.

3. Subcontractors. The Responsibility of the Bidder may be judged in part by the Responsibility of its Subcontractors. Bidders must verify Responsibility criteria for each first-tier Subcontractor. A Subcontractor of any tier that hires other Subcontractors must verify Responsibility criteria for each of its next lower-tier Subcontractors. Verification shall include that each Subcontractor, at the time of subcontract execution, is Responsible and possesses an electrical contractor license, if required by RCW 19.28, or an elevator contractor license, if required by RCW 70.87, and can obtain any payment and performance bonds required by the Bidding or Contract Documents.

4. Request to Modify Criteria. No later than ten (10) days prior to the Bid Date, a potential Bidder may request in writing that the Owner modify the Responsibility criteria listed in clause

(2) above or elsewhere in the Contract Documents or the Bidding Documents. The Owner will evaluate the information submitted by the potential Bidder and respond before the Bid Date. If the evaluation results in a change of the criteria, the Owner will issue an Addendum identifying the new criteria.

5. Objection. Prior to the Award of the Contract, the Architect will notify the Bidder in writing if either the Owner or the Architect, after due investigation, has reasonable objection to the Bidder or a person or entity proposed by the Bidder, and the Owner will provide the reasons for the determination. The Bidder may appeal the determination within two (2) business days of its receipt of the objection by presenting additional information to the Owner, and the Owner will consider the additional information before issuing its final determination. The Bidder may, after the Owner’s objection or determination, and at Bidder’s option, (1) withdraw the Bid, (2) submit an acceptable substitute person or entity with no change in the Contract Time and no adjustment in the Base Bid or any Alternate Bid, even if there is a cost to the Bidder occasioned by the substitution, or (3) appeal by filing a protest in accordance with paragraph 1.05(D). In the event of withdrawal, Bid security will not be forfeited.

INSTRUCTIONS TO BIDDERS 13

154263534.4

6. Change. Persons and entities proposed by the Bidder and to whom the Owner or the Architect have made no reasonable objection must be used on the Work for which they were proposed and shall not be changed except with the written consent of the Owner and the Architect.

7. Right to Terminate. The Bidder’s representations concerning its qualifications will be construed as a covenant under the Contract. Should it appear that the Bidder has made a material misrepresentation on its Contractor’s Qualification Statement, the Owner shall have the right to terminate the Contract for cause for the Contractor’s breach, and the Owner may then pursue such remedies as exist elsewhere under this Contract, or as otherwise are provided at law or equity.

B. INFORMATION FROM OTHER BIDDERS: All other Bidders designated by the Architect as under consideration for award of a Contract shall also provide a properly executed Contractor’s Qualification Statement, if so requested by the Owner.

C. BIDDING MISTAKES: The Owner will not be obligated to consider notice of claimed bidding mistakes received more than three (3) business days after the Bid opening. In accordance with Washington law, a low Bidder that claims error and fails to enter into the Contract is prohibited from bidding on the Project if a subsequent call for Bids is made for the Project.

1.07 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND

A. BOND REQUIREMENTS: Within forty-eight (48) hours after the issuance of the Owner’s notice of intent to award the Contract, and prior to the date of execution of the Contract, the Bidder shall furnish evidence satisfactory to the Owner of its ability to obtain statutory bonds pursuant to RCW

39.08 covering the faithful performance of the Contract and the payment of all obligations arising thereunder in the form prescribed in the Contract Documents and in the full amount of the Contract Sum plus sales tax. The cost of such bond shall be included in the Base Bid.

B. TIME OF DELIVERY AND FORM OF BONDS. The Bidder shall deliver the bonds and other documents required by the Contract Documents (including but not limited to certificates of insurance) to the Owner pursuant to the Contract Documents and in no event any later than seven

(7) days after the date of execution of the Contract and prior to commencing operations at the site.

The bonds shall be written in the form approved by the Owner for public work, as required by RCW

39.08. The bonds shall be written by a surety firm licensed to do business in the State of Washington, with an A.M. Best rating of at least A-/VII. The Bidder shall require the Attorney-in- Fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of that person’s Power of Attorney.

1.08 FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR

A. FORM TO BE USED: The Agreement for the Work will be written on the form(s) contained in the Bidding Documents, including any General, Supplemental or Special Conditions, and the other Contract Documents included with the Project Manual. In the event no form is enclosed, an AIA Document A101-2017, “Standard Form of Agreement Between Owner and Contractor, where the basis of payment is a Stipulated Sum,” along with the General Conditions (AIA Document A201- 2017), as both are revised, modified and supplemented by the Owner, will be used. All references in these Instructions to Bidder to the A101 or the A201 refer to the documents as revised by the Owner.

B. CONFLICTS: In case of conflict between the provisions of these Instructions and any other Bidding Document, these Instructions shall govern. In case of conflict between the provisions of the Bidding Documents and the Contract Documents, the Contract Documents shall govern.

INSTRUCTIONS TO BIDDERS 14

154263534.4

1.09 CONTRACT DOCUMENTS

This paragraph contains descriptions of some but not all of the provisions of the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .