This is a Bid Invitation document issued by the City of Beaumont, Texas Water Utilities Department for the rehabilitation and pump replacement of Loeb Well No. 3. The project encompasses a comprehensive scope including well video inspection, chlorination, performance testing at multiple flow rates and durations, supply and installation of a new well pump with three size options (2,500 GPM, 3,000 GPM, or 3,500 GPM capacity), column assembly installation, motor and oil pot reinstallation, site restoration, and related ancillary services. A mandatory in-person or virtual pre-bid conference will be held on October 21, 2026 at 10:00 A.M. Central Time at 1350 Langham Road, Beaumont, Texas, with attendance required for bid eligibility. The questions deadline is October 23, 2026 at 5:00 P.M. Central Time, and bids are due by October 29, 2026 at 2:00 P.M. Central Time. The bid invitation is a rebid of a previously issued opportunity. The contract encompasses 24 base bid items, all priced as lump sum, plus 4 optional extra work items. Following completion of well and pump performance testing, the Engineer will select one of the three pump size scenarios for installation, with the two unselected options deleted from the contract via deductive change order.
Mobilization and demobilization costs are capped at 5 percent of the subtotal of remaining bid items. All bids must include completed documentation including bid summary, corporate resolution, bid bond with visible seal, conflict of interest questionnaire and statement, insurance requirement affidavit, Schedule C for minority business enterprise participation, HB1295 acknowledgement, HB89 form verification, and local bidder consideration claim form if applicable. Contact for inquiries is Brent Schmitt at the Water Utilities Administration office, reachable at (409) 730-4409 or brent.schmitt@beaumonttexas.gov. No contract award date or contract term information is specified in the bid invitation document.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WU1027-02
Loeb Well No. 3 Rehabilitation and Pump Replacement - REBID
Issue Date: 10/8/2026
Questions Deadline: 10/23/2026 05:00 PM (CT)
Response Deadline: 10/29/2026 02:00 PM (CT)
Contact Information Contact: Brent Schmitt Address: Water Utilities/Administration
Water Administration 1350 Langham Road Beaumont, TX 77707
Phone: 1 (409) 730-4409 Email: brent.schmitt@beaumonttexas.gov
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 1 of 10 pages
Event Information Number: WU1027-02 Title: Loeb Well No. 3 Rehabilitation and Pump Replacement - REBID Type: Invitation to Bid Issue Date: 10/8/2026 Question Deadline: 10/23/2026 05:00 PM (CT) Response Deadline: 10/29/2026 02:00 PM (CT) Notes: A MANDATORY Pre-bid Conference will be held at 10:00 A.M. (CT), on
WEDNESDAY, OCTOBER 21, 2026, in-person at 1350 Langham Road, Beaumont, TX and virtually on Microsoft Teams. Attendees may join in-person, by internet, or phone call:
https://bit.ly/4dn8UTV +1 903-405-2009 Passcode:
852517007#
Attendance at the Pre-bid meeting is a prerequisite to bidding. Prior to the pre-bid conference, interested bidders should obtain forms of proposal, contract, bond, and specifications. No one will be allowed to enter the pre-bid virtually or in-person if arrival is later than 5 minutes after the designated time. Calls for any technical difficulties must be made prior to the meeting.
Ship To Information Contact: Brent Schmitt Address: Water Utilities/Administration
Water Administration 1350 Langham Road Beaumont, TX 77707
Phone: 1 (409) 730-4409 Email: brent.schmitt@beaumonttexas.gov
Billing Information Contact: Brent Schmitt Address: Water Utilities/Administration
Water Administration 1350 Langham Road Beaumont, TX 77707
Phone: 1 (409) 730-4409 Email: brent.schmitt@beaumonttexas.gov
Bid Attachments
WU1027-02 Loeb Well No. 3 Rehab & Pump Replacement REBID.pdf View Online
Please download and review CONTRACT DOCUMENTS, then acknowledge in the Attributes Tab.
Requested Attachments
*PLEASE READ BEFORE SUBMITTING YOUR BID*
Have ALL forms been double checked to assure what you are uploading has been completed and signed?
Forms not completed and signed may result in rejection of the bid.
Completed Bid (Attachment required)
Completed Bid Summary (Attachment required)
Completed Corporate Resolution (Attachment required)
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 2 of 10 pages https://beaumonttexas.ionwave.net//VendorLanding.aspx?e=cWs-hqpMe2ap-1aiZOk9FULCwcl6Hs-8xoSNBC-ccHSZdtHoEq01Z5YUu2UPDrXZRflhi9Nd5spVotAehq5xOQ
Completed Bid Bond (Attachment required)
Please upload a COPY with a VISABLE seal. After the Bid Opening and upon request by the Owner, the original Bid Bond or Security shall be submitted.
Completed Information Required of Bidder (Attachment required)
Please make sure when submitting that ALL requested documentation is provided.
Completed Conflict of Interest Questionnaire (Attachment required)
Completed Statement of City Charter Provision on Conflict of Interest (Attachment required)
Please submit ONLY the signature page.
Completed Insurance Requirement Affidavit (Attachment required)
Completed Schedule C (MBE Participation) (Attachment required)
Please note: The form must be signed and dated regardless of participation.
Completed HB1295 Acknowledgement (Attachment required)
Completed HB89 Form Verification (Attachment required)
IF APPLICABLE - Completed Local Bidder Consideration Claim Form & Certificate
* If Applicable
Bid Attributes
1 WU1027-02 Loeb Well No. 3 Rehabilitation and Pump Replacement REBID
By selecting "I Agree", you are confirming that you have downloaded, reviewed, and understand the proposed construction contract documents.
I Agree (Required: Check if applicable)
Bid Lines
1 Package Header
BASE BID ITEMS
Quantity: 1 Total: $
Item Notes: Bid Items 1.16, 1.17, and 1.18 are incorporated into the Base Bid for bidding and contract award purposes and will be included in the Contract Award amount. Following completion of the well and pump performance testing, the Engineer will select one pump size scenario for installation. The two pump size scenarios not selected shall be deleted from the Contract by deductive Change Order at the lump-sum prices bid.
Supplier Notes:
Additional notes (Attach separate sheet)
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 3 of 10 pages
Package Items
1.1 Contractor mobilization and demobilization and delivery of service rig and all equipment, materials and personnel to and from Contractor office / yard, subcontractors and job site, including bonds, insurance, etc., in strict accordance with plans and specifications. The amount for this item shall not exceed 5% of the subtotal of the remaining Bid Items (including optional and extra work items).
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 01 71 13
No bid
(Attach separate sheet)
1.2 Well video inspection: Bail oil from the well and dispose of properly. Perform a well video survey of entire well depth interval and provide acceptable electronic copies, selected video images, and written report of each video survey, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.01
(Attach separate sheet)
1.3 Furnish, install, and remove appropriately sized steel tank(s) and temporary leak-proof discharge piping to convey water to discharge point at the well site during pumping, jetting, or testing operations, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODES:
001 74 16 33 01 10.57 33 01 10.91 33 11 33
(Attach separate sheet)
1.4 Chlorination of Well: Perform chlorine treatment of well screens by inserting and agitating chlorine, and jet out and neutralize chlorinated water from the well prior to discharge, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 01 10.57
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 4 of 10 pages
1.5 Retain G-M Services to conduct and submit written reports and data for well, pump, motor performance, and vibration testing. All testing and reporting to be in strict accordance with the plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODES:
33 01 10.91 33 11 33.01
(Attach separate sheet)
1.6 Perform a 6-hour pump test at a pumping rate of 750 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 01 10.91
(Attach separate sheet)
1.7 Perform a 6-hour pump test at a pumping rate of 1,500 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.8 Perform a 6-hour pump test at a pumping rate of 2,500 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.9 Perform a 12-hour pump test at a pumping rate of 2,500 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test.
All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 5 of 10 pages
1.10 Perform a 12-hour pump test at a pumping rate of 3,000 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.11 Perform a 12-hour pump test at a pumping rate of 3,500 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.12 Perform a 24-hour pump test at a pumping rate of 2,500 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.13 Perform a 24-hour pump test at a pumping rate of 3,000 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.14 Perform a 24-hour pump test at a pumping rate of 3,500 GPM in accordance with Section 33 01 10.91. Include all labor, equipment, monitoring, measurements, data collection, and incidentals necessary to complete the test. All testing and reporting to be in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 6 of 10 pages
1.15 Supply and install a steel fabricated / welded discharge head, with motor register, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.05
(Attach separate sheet)
1.16 Supply and install a new well pump including: 18DHC 6-stage oil bowl assembly designed for 2,500 gpm at 245 feet TDH, including all necessary electrical wiring and connections. Supply and installation in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 33
(Attach separate sheet)
1.17 Supply and install a new well pump including: 18DHC 6-stage oil bowl assembly designed for 3,000 gpm at 280 feet TDH, including all necessary electrical wiring and connections. Supply and installation in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.18 Supply and install a new well pump including: 18DHC 6-stage oil bowl assembly designed for 3,500 gpm at 320 feet TDH, including all necessary electrical wiring and connections. Supply and installation in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.19 Supply and install new 12” x 3-1/2” x 2-3/16” column assembly including: 260 feet of 20-foot sections of column pipe; 10-foot bottom section of column pipe; 10 feet of top special section of column pipe; oil tube; shaft; bearings; 280’ of continuous ¼” stainless steel airline with gauge assembly, and water level monitoring system, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.06
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 7 of 10 pages
1.20 Test pump and motor assembly, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODES:
33 11 33 33 11 33.01
(Attach separate sheet)
1.21 Transport and install existing well motor, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 33.01
(Attach separate sheet)
1.22 Re-install existing oil pot assembly, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.06
(Attach separate sheet)
1.23 Start-up and purging of well, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
(Attach separate sheet)
1.24 Well site restoration to restore land surface and grass to as good or better condition than existed prior to work, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODES:
01 74 16 33 01 10.91
(Attach separate sheet)
2 Package Header
EXTRA WORK (UNIT PRICE / CONTINGENT ITEMS)
Total: $
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 8 of 10 pages
Package Items
2.1 Perform acid treatment of well screens with hydrochloric acid or hydroxyacetic acid, including removal and neutralization of water and sediment, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 01 10.57
(Attach separate sheet)
2.2 Brush cleaning and agitation of well: Perform mechanical cleaning (wire brushing) of well screens, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.03
(Attach separate sheet)
2.3 Screen and casing repair, in strict accordance with plans and specifications.
(Response required)
Quantity: 5 UOM: EA Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.04
(Attach separate sheet)
2.4 Follow-up video inspection of the well after brush cleaning, in strict accordance with plans and specifications.
(Response required)
Quantity: 1 UOM: LS Price: $ Total: $
Item Notes: ITEM CODE: 33 11 13.01
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 9 of 10 pages
Supplier Information
Company Name:
Contact Name:
Address:
Phone:
Fax:
Email:
Supplier Notes
By submitting your response, you certify that you are authorized to represent and bind your company.
Print Name Signature
Deadline: 10/29/2026 02:00 PM (CT) WU1027-02Page 10 of 10 pages