Bid Invitation
24 MB Posted
- Attached to
- PHASE 1 REKEYING
- Solicitation number
- 22-FAC-021
- Issued by
- Douglas County, Georgia
About this file
This is a Bid Invitation and Project Manual issued by the Dougherty County Board of Education for Phase 1 Rekeying services at five school facilities in Albany, Georgia. The scope of work encompasses all labor, materials, and equipment required to rekey all cylinders at Albany Middle School, Robert Cross Middle School, Alice Coachman Elementary School, Martin Luther King Jr. Elementary School, and the Central Administration Building. A mandatory pre-bid meeting is scheduled for 10:00 AM EST on Thursday, April 28, 2022, at the Facilities Services Department located at 1711 Schilling Avenue in Albany, Georgia; firms failing to attend will be ineligible to submit bids. Sealed bids must be received by 1:30 PM EST on Tuesday, May 17, 2022, at the Logistical Services Department located at 601 Flint Avenue, Albany, Georgia 31701, at which time bids will be publicly opened and read. The Owner intends to present a recommendation to the Board of Education to award the bid on June 13, 2022, with notice of intent to award issued by end of day June 14, 2022. The successful contractor must commence work within ten calendar days of receiving a written Notice to Proceed and achieve final completion within one hundred twenty calendar days of that date. The contract will be awarded to a single Georgia-licensed contracting firm acting as the prime contractor responsible for coordinating all work and ensuring timely project completion.
Bids exceeding $100,000.00 must be accompanied by a five percent surety bid bond; certified checks and other forms of bid security are not acceptable. The successful bidder will be required to furnish Performance and Payment Bonds in an amount equal to one hundred percent of the contract sum, issued by a corporate surety authorized to conduct business in Georgia. Contract award will be made to the lowest responsive and responsible bidder judged most advantageous to the Dougherty County School System based on lowest responsible bid, financial stability, and proof of ability to complete the project on schedule. The bid form includes twenty-two unit price line items for various lockset and exit device replacements, with bidders required to submit pricing for each item. All work must be performed during unoccupied times at schools to avoid disrupting students during school hours, with coordination required for work in non-student areas and administrative offices. Bidders must demonstrate a minimum of two years of experience under the present company name on similar projects and must provide references documenting recent work experience. The contract documents include general conditions, supplementary general conditions, performance and payment bond forms, insurance requirements, and compliance certifications including Georgia Security and Immigration Compliance Act E-Verify verification.
Text of this file
A Project Manual For
Dougherty County School System Phase 1 Rekeying
Bid No. 22-FAC-021
Bid Document
January 07, 2022 i
TABLE OF CONTENTS
Section A: Invitation to Bid Page A-1 to A-2
Section B: Bid Form Page B-1 to B-9
Section C: Instructions to Bidders Page C-1 to C-7 C-01 Bid Issuance/Owner Contacts Page C-1 C-02 Pre-Bid Meeting Page C-1 C-03 Schedules Page C-1 C-04 Special Conditions Page C-1 C-05 Interpretation/Addenda Page C-1 C-06 Examination of Site Page C-1 C-07 Bid Form/Submittal Page C-2 C-08 Bid Security Page C-2 C-09 Bid Acceptance/Award Page C-2 to C-3 C-10 Owner’s Right to Negotiate with Lowest Bidder Page C-3 C-11 Contractor Performance Page C-3 C-12 Contract Form Page C-3 C-13 Bonding and Insurance Page C-3 C-14 Georgia Immigration and Security Reform Act Page C-4 C-15 Application for Payment Page C-4 C-16 Changes in the Work Page C-4 C-17 Trade Names Page C-4 to C-5 C-18 Submittals Page C-5 to C-6 C-19 Release of Liability Page C-6 C-20 Non-Bias Statement Page C-6 C-21 DJEA - Equal Opportunity for Competitive Bids Page C-6 to C-7 C-22 Local/ Minority/DBE Participation Page C-7 C-23 Drug Free/Tobacco Free Statement Page C-7 C-24 Safe School Statement Page C-7 C-25 Asbestos Hazard Warning Page C-7
Section D: Construction Contract Page D-1 to D-3
Section E: Table of Contents for General Conditions Page E-i to E-ii General Conditions Page E-1 to E-24
Section F: Supplementary General Conditions Page F-1 to F-7
Section G: Exhibits Page G-1 to G-20 A. Performance Bond Page G-1 to G-2 B. Payment Bond Page G-3 to G-4 C. Casualty Endorsement Page G-5 D. Builder’s Risk Endorsement Page G-6 E Venue and Jurisdiction Form Page G-7 F. Georgia Security and Immigration Compliance Act Page G-8 to G-11 G. Application for Payment Page G-12 to G-15 H. Change Order Form Page G-16 I. Non-Influence Affidavit Page G-17 J. Statutory Affidavit Page G-18 K. Asbestos Containing Materials in Schools Page G-19 L. Certificate of Manufacturer Page G-20
Section H: Attachments A. Scope of Work/Specifications Page H-1-25
A-1
SECTION A
INVITATION TO BID
Dougherty County School System Phase 1 Rekeying
Sealed Bids will be received by the Dougherty County Board of Education in the Office of the Logistical Services Department located at 601 Flint Avenue, Albany, Georgia, 31701 until 1:30 PM EST on Tuesday, May 17, 2022. Those Bids will then be publicly opened and read. Bidders will be required to submit specific information/documentation with their Bids.
The scope of work includes all labor, material, and equipment required to rekey all cylinders at Albany Middle (1700 Cordell Road), Robert Cross Middle (324 Lockett Station Road), Alice Coachman Elementary (1425 Oakridge Drive), Martin Luther King Jr. Elementary (3125 Martin Luther King Jr. Drive), and the Central Administration Building (200 Pine Avenue).
There will be a Mandatory Pre-Bid Meeting at 10:00 AM EST on Thursday, April 28, 2022 at Facilities Services Department; 1711 Schilling Avenue; Albany, Georgia 31705. The Pre-Bid Meeting will begin promptly at 10:00 AM and the Owner reserves the right to disqualify firms that arrive late.
A general discussion of the project will take place at the pre-bid meeting. A walk-thru of the site will be provided immediately after the meeting if requested.
Firms who do not attend the Mandatory Pre-Bid Meeting will not be eligible to submit a Bid.
All inquiries or questions concerning the Bid Documents shall be addressed to Tony Reese, Dougherty County School System, Facilities Services Department; 1711 Schilling Avenue; Albany, Georgia 31705; or by phone:
(229) 431-1301 or e-mail: treese@docoschools.org.
All expenses for preparing and submitting bids are the sole cost of the party submitting the bid. The DCSS is not obligated to any party to reimburse such expenses.
Bids must be submitted on the proper Bid Forms (include all required attachments). Bids received after the designated times and/or without the required attachments will not be considered. No oral, telephonic, telegraphic, facsimile, or written modification to the bid will be considered after bid time. No bid may be withdrawn for a period of 60 days after time and date of opening. The Owner reserves the right to reject any or all bids and to waive technicalities and informalities.
If the Bid exceeds $100,000.00, Bidders will be required to furnish a 5% Surety Bid Bond with their Bid. The successful Bidder will be required to furnish Performance and a Payment Bonds in an amount equal to 100% of the Contract Amount and issued by a Corporate Surety authorized to conduct business in the State of Georgia.
It is the Owners intent to award the project to a single Georgia Licensed Contracting Firm which will act as the Prime Contractor responsible for coordinating the work of all trades and ensuring the entire project is completed as scheduled. The Contract, if awarded, will be to the lowest responsive and responsible Bidder and in the manner deemed to offer the best value to the Owner.
The Dougherty County School System supports all equal opportunity policies: Federal, State, and Local. DCSS will not tolerate bias related activities, e.g. racial slurs, sexual harassment, from employees and/or contractors conducting work on behalf of DCSS.
A-2
The work to be performed under this Contract is subject to the Dougherty County Board of Education’s policy on Equal Opportunity for Competitive Bids, DJEA~E. The DCSS encourages all Local/Minority/DBE Contractors to compete for and receive contracts for goods, services and construction associated with this project. Prime Contractors are encouraged to voluntarily pursue the maximum use of Local/Small Business/Minority/DBE Sub-Contractors and Suppliers.
Dougherty County School System supports a drug free workplace and does not tolerate any use or possession of drugs and/or alcohol or use of such substances prior to performing any work on behalf of DCSS. Use of tobacco products is prohibited in all buildings and on all premises of DCSS.
The Dougherty County School System requires all individuals working within a school building, or on a school site, to submit to a background check pertaining to felony convictions and sex offender convictions. Violent felons and sex offenders shall not be allowed within a school building or on a school site while school staff or students are in the building or on the site. Convicted predatory sex offenders shall not be allowed on DCSS property at any time. All decisions made in this effort to promote a safe school environment shall be assessed at the sole discretion of the DCSS Staff and the Dougherty County Board of Education.
Sealed Bids should be addressed To: Note in Lower Left Corner of Envelope:
Sharonda Thompson, Director Bid Number: 22-FAC-021 Dougherty County School System Bid Name: Dougherty County School System Logistical Services Department Phase 1 Rekeying 601 Flint Avenue Bid Date: May 17, 2022 at 1:30 PM EST Albany, Georgia 31701
Company Name:
All inquiries concerning the receipt of Bid Packages shipped to the Logistical Services Department shall be addressed at (229) 431-1270.
B-1
SECTION B
BID FORM
Company Name: _______________________________________________________ Date: __________________
BASE BID:
Having carefully examined the Bid Documents entitled Dougherty County School System Phase 1 Rekeying, Bid No. 22-FAC-021 for the Dougherty County Board of Education, Albany, Georgia, dated January 07, 2022; its attachments; and addendum no. (s)___________; as well as the premises and conditions affecting the Work, the undersigned proposes to provide all services, labor, materials, and equipment required to perform the entire Work, in accordance with said Documents. The scope of work includes all labor, material, and equipment required to rekey all cylinders at Albany Middle (1700 Cordell Road), Robert Cross Middle (324 Lockett Station Road), Alice Coachman Elementary (1425 Oakridge Drive), Martin Luther King Jr. Elementary (3125 Martin Luther King Jr.
Drive), and the Central Administration Building (200 Pine Avenue) for the sum of:
______________________________________________________________________________________ Dollars
($__________________________) which sum is herein after called the “Base Bid”.
BID BOND:
Enclosed herewith is a Bid Bond in the amount of $__________________, being not less than 5% of the Base Bid payable to Dougherty County Board of Education. Certified checks or other forms of bid security are not acceptable.
Bids in excess of $100,000.00 must be accompanied by a five percent (5%) Surety Bid Bond. Bids less than $100,000 do not require a Bid Bond. The undersigned agrees that the above stated amount is the proper measure of liquidated damages which the Owner will sustain by the failure of the undersigned to execute the Contract and/or to furnish the Performance and Bond in case this Bid is accepted.
The undersigned further agrees that if this bid is accepted within sixty (60) days after the date set for the opening of bids and the undersigned fails to execute a Contract for the Work within ten (10) business days after written notice of such acceptance, or if he fails to furnish the Performance Bond, Payment Bond, and Insurance, the obligation of the Bid Bond, if applicable, will remain in full force and effect and the money payable thereon shall be paid into funds of the Owner as liquidated damages for such failure; otherwise the obligation of the bond will be null and void.
UNIT PRICES:
Unit Prices shall be utilized to change quantities of work items from those indicated by the Bid Documents. Should conditions be encountered which require additional work to be performed beyond that defined in the Contract Documents or the Owner adjusts the size of the project, such cost of the work will be reduced or increased utilizing the unit prices listed below.
The Owner reserve the right to negotiate any and all unit prices where unit prices are not deemed fair and reasonable for the scope of the work to be performed or where the unit prices submitted are considered to be inflated when compared against other Bidders or normal costs for similar work.
The unit prices for the items listed below shall include the total cost(s) as defined by the Contract Documents to fully complete the work. Unit prices shall include all labor, materials, overhead, profit, insurance, bonding, etc. to cover work of the kinds identified and no additional surcharges shall be added to unit prices. The Unit Price Form shall be completed in its entirety.
B-2
Company Name: _______________________________________________________ Date: __________________
Unit Price Form:
ACCEPTANCE:
Prior to the bid opening date and hour, errors may be stricken or revisions made and corrections entered on the Bid Form(s) and/or on the outside of the Sealed Envelope, provided that any such strike-over or revision is signed in ink by the person signing the bid or their agent. No oral, telephonic, telegraphic, or facsimile modification to the Bids will be considered after the time set for opening proposals.
The undersigned agrees that this proposal may not be revoked or withdrawn after the time set for opening of bids, but shall remain open for acceptance for a period of sixty (60) days following such time.
Item Description Unit Price
Hardware Replacement
1 Remove and replace damaged CL3351 NZD 626 lockset (Corbin Russwin) EA $
2 Remove and replace damaged CL3352 NZD 626 lockset (Corbin Russwin) EA $
3 Remove and replace damaged CL3355 NZD 626 lockset (Corbin Russwin) EA $
4 Remove and replace damaged CL3357 NZD 626 lockset (Corbin Russwin) EA $
5 Remove and replace damaged CL3359 NZD 626 lockset (Corbin Russwin) EA $
6 Remove and replace damaged DL 2212 deadbolt (Corbin Russwin) EA $
7 Remove and replace damaged DL 2213 deadbolt (Corbin Russwin) EA $
Remove and replace damaged VD KR54 keyed removable mullion kit (Von Duprin)
EA $
9 Remove and replace damaged SVR 9927-996L exit device (Von Duprin) EA $
10 Remove and replace damaged 19R NL exit device (Falcon) EA $
11 Remove and replace damaged CL3381 NZD 626 lockset (Corbin Russwin) EA $
12 Remove and replace damaged 99 EO NL OP exit device (Von Duprin) EA $
13 Remove and replace damaged ML2051 ESF 626 lockset (Corbin Russwin) EA $
14 Remove and replace damaged ML2052 ESF 626 lockset (Corbin Russwin) EA $
15 Remove and replace damaged ML2053 ESF 626 lockset (Corbin Russwin) EA $
16 Remove and replace damaged ML2054 ESF 626 lockset (Corbin Russwin) EA $
17 Remove and replace damaged ML2057 ESF 626 lockset (Corbin Russwin) EA $
18 Remove and replace damaged rim cylinder with 3000-200 (Corbin Russwin) EA $
19 Remove and replace damaged lockset with UT5251 (Corbin Russwin) EA $
20 Remove and replace damaged lockset with UT5255 (Corbin Russwin) EA $
21 Remove and replace damaged lockset with UT5257 (Corbin Russwin) EA $
22 Remove and replace damaged lockset with UT5282 (Corbin Russwin) EA $
B-3
Company Name: ______________________________________________________ Date: __________________
BID AWARD:
It is the Owners intent to award the project to a single Georgia Licensed Contracting Firm which will act as the Prime Contractor responsible for coordinating the work of all trades and ensuring the entire project is completed as scheduled. The Contract, if awarded, will be to the lowest responsive and responsible Bidder and in the manner deemed to offer the best value to the Owner.
The undersigned understands and agrees, if this bid is awarded, it will be awarded to the lowest qualified Bidder judged most advantageous to the DCSS in the areas of lowest responsible bid, financial stability, and proof of ability to fully complete the project on schedule. Upon Owner’s request all information needed to document the above requirements will be provided immediately.
In the event the undersigned is notified in writing by facsimile, mail, or delivery of the acceptance of this bid within sixty (60) days after the time set for the opening of bids, the undersigned agrees to execute a Contract for the Work for the above stated compensation and/or to schedule a Pre-Contract Meeting with the Owner within ten (10) business days after the issuance of the Notice of Acceptance. All required Pre-Contract Submittals shall be reviewed during this meeting.
Once the Pre-Contract Submittals have been reviewed and approved, the Owner shall issue a Contract for the Work for the above stated compensation for the Contractor to execute.
The undersigned understands and agrees, if the Contract Sum exceeds $100,000.00, they shall be required to furnish a Performance and a Payment Bond, both in an amount equal 100% of the Contract Sum, issued by a Corporate Surety authorized to conduct business in the State of Georgia, and payable to Dougherty County Board of Education.
COMMENCEMENT OF WORK:
The undersigned agrees to commence actual physical work with an adequate force and equipment within ten (10) calendar days of a date to be specified in a written Notice to Proceed and shall achieve Final Completion of the work within one hundred and twenty (120) calendar days of said date.
If the undersigned fails to commence actual physical work with an adequate force and equipment within ten (10) calendar days of the date to be specified in a written Notice to Proceed, the Owner reserves the right to null and void the Contract.
BID SUBMITTAL INFORMATION:
Bids shall be submitted on the Bid Form provided. The Bid Form shall not be changed or modified in any way. Fill in all blanks on the Bid Form. Bid submittal and signature of authorized representative shall indicate intention to comply with all of the requirements of the Bidding Documents.
Bid submittal certifies that Bidder has been granted and possesses all necessary, valid, current licenses to do business in the State of Georgia as issued by the respective State Boards and Government Agencies responsible for regulating and licensing the services to be provided and pursuant to this Agreement.
Provide one (1) original Proposal Form with the following information in the order specified:
1. Executed Bid Form.
2. Executed Bid Bond, if the Bid exceeds $100,000.00.
3. Statement of Bidders Qualifications
4. Executed Certification of Non-Collusion.
5. Executed Contractor’s Affidavit.
6. Executed DJEA-E Statement of Assurance for Competitively Bid Contracts.
7. Current Business License.
8. Provide a list of Sub-Contractors to be utilized on this project.
B-4
9. Provide list of two (2) projects of similar size completed in last two (2) years along with detailed Reference Contact Information.
BID CERTIFICATION:
The above Bid is in response to the Bid Documents titled Dougherty County School System Phase 1 Rekeying, Bid No. 22-FAC-021 for the Dougherty County Board of Education, Albany, Georgia; dated January 07, 2022; and its attachments and addenda.
By submitting this Bid, the undersigned acknowledges that they or their representative have visited the project site and have taken into consideration all observed conditions that might affect the work.
Under oath I certify that I am principal or other representative of the Bidder and that I am authorized by it to execute the forgoing offer on its behalf:
Company Name: ______________________________________________________________________________
Address: _____________________________________________________________________________________
City: __________________________________________________________ State: _____ Zip: _______________
Name: Title: __________________________________
Signature: Date: __________________
Notary Public: _____________________________
____________________________County, Georgia
(Apply Seal Here) My Commission Expires: ____________________
Subscribed and Sworn Before Me On This ___ Day of ____________________, 20___.
B-5
STATEMENT OF BIDDER’S QUALIFICATIONS
Bid No. 22-FAC-021
Name of Bidder________________________________________________________________________
Business Address______________________________________________________________________
When Organized________________________ Where Incorporated ______________________________
How many years have you been engaged in the business under the present firm name? _____________
Indicate if Bid is a Joint Venture: Yes ( ) or No ( ).
Bid price is $ _________________________________________________________________________
Credit Available for this Contract $________________________________________________________
Contracts now in hand, Gross Amount $____________________________________________________
Plan of Organization: Corporation: __________ Partnership: ________ Sole Proprietorship: _________
Have you ever refused to sign a contract based on your original bid? _____________________________
Have you ever defaulted on a contract? ____________________________________________________
Remarks_____________________________________________________________________________
By __________________________________________________________________________________
Date_______________
Printed Name and Title
Notary Public: _____________________________
____________________________County, Georgia
This_______ Day of _________________, 20___.
RETURN WITH BID FORM
B-6
CERTIFICATION OF NON-COLLUSION
I certify that this Bid/Proposal is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a Bid/Proposal for the same materials, supplies, or equipment, and is in all respects fair and without collusion or fraud per the requirements of OCGA 50-5-67 (e).
I certify that this Bid/Proposal is made without prior understanding, agreement, or connection with any member of the government agency letting this public works contract and is in all respects fair and without collusion or fraud per the requirements of OCGA 36-91-21 (f).
I further certify that the provisions of the Official Code of Georgia Annotated 45-10-20 et. seq. has not and will not be violated in any respect.
I understand that collusive bidding is a violation of State and Federal law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all conditions of this Bid/Proposal, and certify that I am authorized to sign this Bid/Proposal for the Bidder/Offeror.
The Bidder being sworn disposes and says, its agents, officers, or employees have not directly or indirectly entered into any agreements, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with this bid.
Name: Title: __________________________________
Signature: Date: __________________
(Apply Seal Here)
B-7
CONTRACTOR’S AFFIDAVIT
STATE OF GEORGIA, COUNTY OF ___________________________________________________,
______________________________________________________________________being duly sworn, (Insert Name of Affiant) hereby deposes and says that he/she has read, and is familiar with, the provisions of the Official Code of Georgia Annotated Section 36-91-21(d) which provides as follows:
Whenever a public works construction contract for any governmental entity subject to the requirements of this chapter is to be let out by competitive sealed bid or proposal, no person, by himself or herself or otherwise, shall prevent or attempt to prevent competition in such bidding or proposals by any means whatever. No persons who desires to procure such work for himself or herself or for another shall prevent or endeavor to prevent anyone from making a bid or proposal therefore by any means whatever, nor shall such person so desiring work cause or induce another to withdraw a bid or proposal for work.
And that he/she has not directly or indirectly violated said provisions of the law.
In accordance with the Official Code of Georgia Annotated Section 36-91-21(e):
If the Contractor is a Partnership, the Affidavit shall be executed by all partners and any officer, agent, or other person who may have represented or acted for them in bidding for or procuring the contract.
If the Contractor is a Corporation, the Affidavit shall be executed by all officers, agents, or other persons who may have acted for or represented the corporation in bidding for or procuring the contract shall execute the affidavit.
Further, Affiant saith not.
This ___ day of ____________________, 20____
(Signature of Affiant)
Notary Public:
____________________________County, Georgia
(Apply Seal Here)
B-8
DJEA~E
DJEA - COMPETITIVELY BID CONTRACTS
Equal Opportunity for Competitive Bids
It shall be the policy of the Dougherty County Board of Education to promote and insure equal opportunity for all persons, without regard to race, color, religion, sex, handicap, or national origin, employed by or seeking employment with vendors and/or contractors doing business with the Board. As a condition of doing business with the Board, each vendor and/or contractor shall furnish assurance that its business will be operated in accordance with the policy attached hereto and identified as "Competitively Bid Contracts," Policy DJEA.
The following equal opportunity clause shall be deemed incorporated into every contract and agreement between the Board and any of its vendors and/or contractors:
1. The vendor/contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, handicap, or national origin. The vendor/contractor shall take appropriate action to ensure that applicants are employed and that employees are treated during employment without regard to race, color, religion, sex, handicap, or national origin. Such action shall include, but shall not be limited to, the following: employment, upgrading, demotion, transfer, recruitment, layoff, termination, rates of pay or other forms of compensation, and training.
2. In the event of the vendor/contractor's noncompliance with the nondiscrimination policy of the
Board, any contract or purchase order may be canceled, terminated or suspended, in whole or in part, and the vendor/contractor may be declared ineligible to transact further business with the Board.
All vendors and persons desiring to transact business with the Board are to provide assurance that their business will be conducted in accordance with this nondiscrimination policy and that such vendors and/or contractors agree to and shall abide by the equal opportunity clause set forth in this policy.
It is the further policy of the Board to insure equal opportunity for minority/women owned businesses and minority/women professionals with regard to all work, services, and supplies purchased by the Board and all construction projects undertaken by the Board which are competitively bid by the Board.
B-9
DJEA~E
DJEA - COMPETITIVELY BID CONTRACTS
STATEMENT OF ASSURANCE
The undersigned Vendor/Contractor provides this Statement of Assurance to the Dougherty County School System wherein the Undersigned acknowledges receipt and awareness of the DJEA - Competitively Bid Contracts policy and agrees to observe and be bound by all applicable provisions contained therein.
The undersigned submits this Statement of Assurance, understanding that a failure to submit said Statement of Assurance may constitute a basis for rejecting the undersigned’s bid.
Name: Title: __________________________________
Signature: Date: __________________
(Apply Seal Here)
C-1
SECTION C
INSTRUCTIONS TO BIDDERS
Dougherty County School System Phase 1 Rekeying
Bid No. 22-FAC-021
C-01 Bid Issuance/Owner Contacts. This Bid is issued for Dougherty County School System (DCSS) by the Director of the Facilities Services Department, Bob Fowler. All expenses for preparing and submitting bids are the sole cost of the party submitting the bid and the DCSS is not obligated to any party to reimburse such expenses.
C-02 Pre-Bid Meeting. There will be a Mandatory Pre-Bid Meeting at 10:00 AM EST on Thursday, April 28, 2022 at Facilities Services Department; 1711 Schilling Avenue, Albany, Georgia 31705. The Pre-Bid Meeting will begin promptly at 10:00 AM EST and the Owner reserves the right to disqualify firms that arrive late.
A general discussion of the project will take place at the pre-bid meeting. Contractors interested in a walk-thru of the sites can be scheduled after the meeting.
Firms who do not attend the Mandatory Pre-Bid Meeting will not be eligible to submit a Bid.
C-03 Schedules. It is the intent of the Owner to present a Recommendation to the Board of Education to Award the Bid on June 13, 2022 and issue the Notice of Intent to Award the Contract to the Contractor by end of day June 14, 2022.
The undersigned agrees to commence actual physical work with an adequate force and equipment within ten
(10) calendar days of a date to be specified in a written Notice to Proceed and shall achieve Final Completion of all Work within one hundred and twenty (120) calendar days of said date.
If the undersigned fails to commence actual physical work with an adequate force and equipment within ten
(10) calendar days of the date to be specified in a written Notice to Proceed, the Owner reserves the right to null and void the Contract.
C-04 Special Conditions. The sites where the work is to take place will be occupied between 7am to 5pm, the contractor shall schedule work during unoccupied times at schools as not to disrupt students during school hours. Elementary Schools hours are from 8am to 2:30pm, Middle School hours are from 8:15am to 3:15pm, Dougherty High School hours are from 8:05am to 4:05pm and Monroe High School hours are from 8:20am to 4:35pm, and Westover High School hours are from 8:20am to 3:30pm.
Contractor shall coordinate with staff to work in non-student areas and administrative offices at schools and standalone administrative buildings.
C-05 Interpretations/Addenda. No oral interpretations will be made to bidders as to the requirements of the Bidding Documents (i.e., Project Manual/Specifications, drawings, and addenda thereto). Requests for interpretations of the Bidding Documents shall be made in writing to the Design Professional not later than five (5) work days prior to the date set for receipt of bids (i.e., May 10, 2022).
Any explanation desired by a bidder regarding ambiguity, meaning, or interpretation of any portion of this Bid Document must be presented in writing to Tony Reese; Dougherty County School System Facilities Services Department; 1711 Schilling Avenue; Albany, Georgia 31705. Phone: (229) 431-1301 or e-mail:
treese@docoschools.org.
All revisions/interpretations/clarifications will be issued in the form of an addendum to the Bid Documents.
No addenda will be issued within three (3) business days (i.e., 72 hours) of the date/time set for receipt of Bids. Such addenda are to be acknowledged in the appropriate location on the Bid Form. If the Bid is accepted, such addenda become part of the Bidding Documents.
It is the responsibility of each bidder presenting a Quotation to confirm with the Owner they have received all addenda prior to bidding. The contact person for confirmation of addenda is Tony Reese; Phone: (229) 431-1301 or e-mail: treese@docoschools.org.
C-2
C-06 Examination of Site. In undertaking the work under this Contract, the Contractor acknowledges that he has visited the Project Site and has taken into consideration all conditions that might affect the work.
C-07 Bid Form/Submittal. Sealed Bids will be received by the Dougherty County Board of Education in the Office of the Logistical Services Department located at 601 Flint Avenue, Albany, Georgia, 31701 until 1:30 PM EST on Tuesday, May 17, 2022. Those bids will then be publicly opened and read.
Bids must be submitted on the proper form and must be signed, notarized, and sealed by a notary public. Bids received after the designated time or without the required attachments will not be considered.
The inclusion of any condition, alternate, limitation, or provision not called for in the bid form will render the bid irregular, and shall be sufficient cause for rejection of a bid. Bid responses containing provisions for late or interest charges will not be considered for an award.
Fill in all blanks on the Bid Form, failure to complete entries in all blanks on the bid form shall be sufficient cause for rejection of a bid. Include all required attachments. The completed form shall be without interlineations, alterations, or erasures. Bid submittal and signature of authorized representative shall indicate intention to comply with all of the requirements of the Bid Documents.
A cost must be submitted for all specified alternates or unit costs, if any. If a price is not provided for all alternates or unit costs the Contractor’s bid may be determined non-responsive and not considered for award.
The Owner reserves the right to reject any or all Bids and to waive technicalities and informalities.
Prior to the bid opening date and hour, errors may be stricken or revisions made and corrections entered on the Bid Form(s) and/or on the outside of the Sealed Envelope, provided that any such strike-over or revision is signed in ink by the person signing the bid or their agent. No oral, telephonic, telegraphic, or facsimile modification to the Bids will be considered after the time set for opening proposals.
Bids may be withdrawn by bidders prior to the time set for official opening. After time has been called, no bid may be withdrawn for a period of sixty (60) calendar days after the time and date of opening, except as provided in O.C.G.A. Section 13-10-22 (appreciable error in calculation of bid). Negligence or error on the part of any bidder in preparing the bid confers no right of withdrawal or modification of the bid after time has been called, except as provided by Georgia law.
C-08 Bid Security. If the Bid exceeds $100,000.00, Bidders shall be required to furnish a 5% Surety Bid Bond with their Bid (certified checks or other forms of bid security are not acceptable). Bid Bonds shall be issued on forms accepted as standard by the insurance industry.
If the Bid is accepted within sixty (60) days after the date set for the opening of bids and the undersigned fails to execute a Contract for the Work within ten (10) business days after written notice of such acceptance, or if he fails to furnish the Performance Bond, Payment Bond, and Insurance, the obligation of the bid bond, if applicable, will remain in full force and effect and the money payable thereon shall be paid into funds of the Owner as liquidated damages for such failure; otherwise the obligation of the bond will be null and void.
C-09 Bid Acceptance/Award. It is the Owners intent to award the Work to a single Firm which will act as the Prime Contractor responsible for coordinating the work of all trades and ensuring the Work is completed as scheduled. The Owner reserves the right to reject any or all bids, to waive technicalities and informalities, and to reduce or expand the Project as they deem appropriate.
If the Owner chooses to accept Bid the Firm will act as the Prime Contractor responsible for coordinating the work of all trades and ensuring the Work is completed as scheduled.
If this bid is awarded, it will be awarded to the lowest qualified Bidder judged most advantageous to the Dougherty County Board of Education and Dougherty County School System (DCSS) Staff in the areas of lowest responsible and responsive bid, financial stability, and proof of ability to fully complete the project on schedule. All information needed to document the above requirements will be provided immediately upon request.
C-3
Contractors shall have a minimum of two (2) years of demonstrated experience under the present company name for projects of similar content and complexity. References about the firm and their work experiences may be a factor in determination of bid responsiveness and responsibility.
In the event the Bidder is notified in writing by facsimile, mail, or delivery of the acceptance of this bid within sixty (60) days after the time set for the opening of bids, the undersigned agrees to execute a Contract for the Work for the above stated compensation and/or to schedule a Pre-Contract Meeting with the Owner within ten (10) business days after the issuance of the Notice of Acceptance. All required Pre-Contract Submittals shall be reviewed during this meeting.
Once the Pre-Contract Submittals have been reviewed and approved, the Owner shall issue a Contract for the Work for the above stated compensation for the Contractor to execute. Once the Contract has been executed and the Pre-Contract Submittals have been reviewed and approved, the Owner shall issue a Notice to Proceed with the work.
C-10 Owner’s Right to Negotiate with Lowest Bidder. In accordance with 36-91-21©(2)(d), in the event all responsive bids are in excess of the budget, the Owner, in its sole and absolute discretion and in addition to the rights set forth above, reserves the right to negotiate with the lowest responsive and responsible bidder only for the purpose of making changes to the Project that will result in a cost to the Owner that is within the budget.
The Dougherty County School System (DCSS) reserves the right to identify and negotiate reductions or changes by the successful bidder which would be to their advantage. The cost or credit to the Owner from a change in the work and/or material consisting of additions, deletions, or modifications shall be determined by mutual agreement.
C-11 Contractor Performance. The successful Bidder shall be required to fulfill all the undertakings, covenants, terms, conditions, and agreements of the Contract. The successful bidder and his employees shall have been granted and possesses all necessary, valid, and current licenses to do business in the State of Georgia as issued by the respective State Boards and Government Agencies responsible for regulating and licensing the services to be provided and pursuant to this Agreement, including local licenses, permits, and certificates required to perform their work.
It is the responsibility of all Contractors and Sub-Contractors to register all work with the Albany/Dougherty County Planning and Development Services and obtain all required City/County permits, applications, and licenses. Contact (229) 431-2118 for information concerning licensing.
The successful bidder must submit a copy of their current City of Albany Business License, their current State Business License (if not from Albany), and their current Georgia Asbestos Licenses, Notifications, and Permits prior to performing any billable work.
C-12 Contract Form. The Contract Form is located in Section D and shall incorporate the provisions of the General Conditions and Supplemental General Conditions. The Contract must be executed by all parties prior to Contractor or Sub-Contractors providing any billable services.
C-13 Bonding and Insurance. Surety and insurance companies must be acceptable to the Owner. Only those sureties listed in the Department of Treasury’s Listing of Approved Sureties (Department Circular (570) are acceptable. All insurance certificates and bonds must be issued by a company licensed by the Georgia Insurance Commissioner to transact the business of insurance in the State of Georgia for the applicable line of insurance. Such company shall be an insurer with an A.M. Best Financial Strength Rating of “A- “or better and with an A.M. Best Financial Size Category of Class V or larger.
For Contracts in excess of $100,000, the successful Bidder shall be required to furnish Performance and Payment Bonds in an amount equal to 100% of the Contract Amount, by a Corporate Surety authorized to conduct business in the State of Georgia, and payable to Dougherty County Board of Education. The Performance and Payment Bond Forms are found in Exhibit A & B. Executed Bonds must be submitted to the Owner prior to Contractor providing any billable services.
C-4
Contractor shall provide, as a minimum, the insurance coverage’s as required by Article E-33 of the General Conditions.
All of the Insurance/Bonding costs shall be furnished and paid for by the Contractor for the duration of the Contract, and the cost of the premiums shall be included in the Bid.
C-14 Georgia Security and Immigration Compliance Act. Contractors, Sub-Contractors, and Sub-Sub- Contractors performing physical services/work on this project are subject to the requirements of O.C.G.A. § 13-10-91, the Georgia Security and Immigration Compliance Act, and shall verify that all trades on-site have registered with, are authorized to use, and use the federal work authorization program commonly known as E-verify and provide documentation of compliance to the Owner prior to commencement of work by any trade in accordance with Article E-05 of the General Conditions and the forms provided in Exhibit F.
C-15 Application for Payment. The Contractor shall submit an application for each payment to the Owner on a form supplied and/or approved by the Owner in accordance with Article E-58 of the General Conditions and Exhibit G. Invoices shall be processed by the Owner within thirty (30) calendar days of receipt by the Owner.
Mail all Payment Applications to the attention of Tony Reese; Dougherty County School System Facilities Services Department; 1711 Schilling Avenue; Albany, Georgia 31705. Applications for payment may be emailed to Mr. Reese at treese@docoschools.org.
C-16 Changes in the Work. The Owner reserves the right to reduce or expand the contract as they deem appropriate. The Owner may order changes in the schedule, work, and/or materials consisting of additions, deletions, or modifications. The contract sum and the contract time will be adjusted accordingly. All such changes shall be authorized by a written change order, signed by the Owner, prior to its performance in accordance with Article E-49 of the General Conditions and utilizing the Change Order Form in Exhibit H.
C-17 Trade Names. No Restriction of Competition. When reference is made in the Contract Documents to trade names, brand names, or to the names of manufacturers, such references are made solely to indicate that products of that description may be furnished and are not intended to restrict competitive bidding. If it is desired to use products of trade or brand names or of manufacturers’ names which are different from those mentioned in the bidding documents, application for the approval of the use of such products must reach the hands of the Design Professional at least ten (10) calendar days prior to the date set for the opening of bids.
The Owner may at any time add trade names, brand names or names of manufacturers by addendum.
Burden of Proof. The burden of proving acceptability of a proposed product must be accompanied by technical data that the party requesting approval submits in support of their application for approval. The application for approval of a proposed product must be accompanied by a detailed schedule/description how the materials or equipment submitted for consideration differ from the materials or equipment designated in the bidding documents. The degree of proof required for approval of a proposed product as acceptable for use in place of a named product is that amount of proof necessary to convince a reasonable person beyond all doubt. To be approved, a proposed product must also meet or exceed all express requirements of the Contract Documents. The Owner reserves the right to reject any products they deem not to meet the basis of design.
Issuance of Addenda. If the submittal is approved by the Design Professional, an addendum will be issued to all prospective bidders. Issuance of an addendum is a representation to all bidders that the product submitted for approval is acceptable and meets or exceeds all express requirements. In order for the Design Professional to prepare an addendum intelligently, an application for approval of a product must be accompanied by a copy of the published recommendations of the manufacturer for the installation of the product together with a complete schedule of changes in the drawings and specifications, if any, which must be made in other work in order to permit the use and installation of the proposed product in accordance with the recommendations of the manufacturer of the product. Unless requests for approvals of other products have been received and approvals have been published by addendum in accordance with the above procedure, the successful bidder may furnish no products of any trade names, brand names, or manufacturers’ names except those designated in the Contract Documents.
C-5
Conference with the Owner. Any party who alleges that rejection of a submittal is the result of bias, prejudice, caprice, or error on the part of the Design Professional may request a conference with a representative of the Owner, PROVIDED: That the request for said conference, submitted in writing, shall have reached the Owner at least five (5) calendar days prior to the date set for the opening of bids, time being of the essence.
C-18 Submittals.
Bid Submittals. One original copy of Bid Form and Bid Submittals.
1. Executed Bid Form.
2. Executed Bid Bond, if the Bid exceeds $100,000.00.
3. Statement of Bidders Qualifications.
4. Executed Certification of Non-Collusion.
5. Executed Contractor’s Affidavit.
6. Executed DJEA-E Statement of Assurance for Competitively Bid Contracts.
7. Current Business License.
8. Provide a list of all Sub-Contractors to be utilized on this project.
9. Provide list of four (4) projects of similar size completed in last two (2) years along with detailed
Reference Contact Information.
Pre-Contract Submittals.
1. Three signed Construction Contract Forms (as prepared by the Owner).
2. One original Performance Bond and Payment Bond (include Power of Attorney), if the Contract
Sum exceeds $100,000.00 (Section 00700, Exhibit A & B).
3. One original Insurance Certificate (faxes are not acceptable).
4. Casualty Endorsement (Exhibit C).
5. Venue and Jurisdiction Form (Exhibit E).
6. Non-Influence Affidavit (Exhibit I).
7. One copy of current City of Albany Business License or an application to obtain one.
8. One copy of the DCSS Vendor Form. Copies can be filled-out and/or printed from:
https://drive.google.com/file/d/1i4r0LGrspV_Uir1TUP0qAjZBTU-U45s9/view
Pre-Construction Conference Submittals.
1. A list of all Sub-Contractors that will be utilized on this project. Provide the company name, complete address, and the contract amount for their work.
2. General Contractor’s Certification that all Sub-Contractors are covered by their own Employers
Liability Insurance Coverage, or that of the General Contractor’s Coverage, per Article E-33 of the General Conditions.
3. Worker’s Background Check Form for each employee and sub-contract employee that will be on site. The Form HRS-F013 can be filled-out and printed from:
https://drive.google.com/file/d/1wqYu-v3uyQMMLvMct3daCZpT9DNYyBlA/view
4. Georgia Security and Immigration Compliance Act E-Verify Affidavits and Agreements for the
General Contractor, Sub-Contractors, and Sub-Sub-Contractors provided for Item No. 1 above (Exhibit F for proper forms).
5. All Pre-Construction Submittals required by the Technical Specification. Provide four (4) copies bound in a separate book.
Submittals Prior to Starting Work on Site.
1. Three copies of the schedule per Article E-08 of the General Conditions.
2. Shop Drawings, Product Data, and Samples required by the Technical Specifications.
3. Pay Application Form and Initial Breakdown/Schedule of Values (Exhibit G).
C-6
Submittals During Work.
1. Notification/Requests for Inspection(s). This includes, but is not limited to: Articles E-52, E-55, E-66, E-67, E-75, and E-76 of the General Conditions.
2. Written amendments to Performance and Payment Bonds per Article E-32.c of the General Conditions.
3. Submittals required by Technical Specifications. Provide two (2) copies of each.
Post-Construction Submittals (must be provided prior to Substantial Completion Notice).
1. Non-Influence Affidavit (Exhibit I).
2. Statutory Affidavit (Exhibit J).
3. Certificate of Manufacturer for all Equipment Installed (Exhibit K).
4. All Post-Construction Submittals required by the Technical Specification. Provide one (1) copy bound in a separate book and one (1) copy on a flash drive.
C-19 Release of Liability. It is expressly understood that the Dougherty County School System (DCSS) shall not be liable to any Contractor/Sub-Contractor and that said Contractor/Sub-Contractor will hold harmless DCSS, its officers, employees and agents from any loss, damage, expense or liability arising out of or in connection with the performance and installation work pursuant to this bid or any special contract resulting from this bid by Contractor/Sub-Contractor occasioned by the negligent acts or omissions of employees, officers or agents of Contractor/Sub-Contractor in accordance with Article E-33 of the General Conditions.
C-20 Non-Bias Statement. The Dougherty County School System (DCSS) supports all equal opportunity policies:
Federal, State, and Local. DCSS will not tolerate bias related activities, e.g. racial slurs, sexual harassment, from employees and/or contractors conducting work on their behalf.
C-21 DJEA - Equal Opportunity for Competitive Bids.
1. It shall be the policy of the Dougherty County Board of Education to promote and insure equal opportunity for all persons, without regard to race, color, religion, sex, handicap, or national origin, employed by or seeking employment with vendors and/or contractors doing business with the Board. As a condition of doing business with the Board, each vendor and/or contractor shall furnish assurance that its business will be operated in accordance with the policy attached hereto and identified as "Competitively Bid Contracts," Policy DJEA.
2. The following equal opportunity clause shall be deemed incorporated into every contract and agreement between the Board and any of its vendors and/or contractors:
The vendor/contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, handicap, or national origin. The vendor/contractor shall take appropriate action to ensure that applicants are employed and that employees are treated during employment without regard to race, color, religion, sex, handicap, or national origin. Such action shall include, but shall not be limited to, the following: employment, upgrading, demotion, transfer, recruitment, layoff, termination, rates of pay or other forms of compensation, and training.
In the event of the vendor/contractor's noncompliance with the nondiscrimination policy of the Board, any contract or purchase order may be canceled, terminated or suspended, in whole or in part, and the vendor/contractor may be declared ineligible to transact further business with the Board.
3. All vendors and persons desiring to transact business with the Board are to provide assurance that their business will be conducted in accordance with this nondiscrimination policy and that such vendors and/or contractors agree to and shall abide by the equal opportunity clause set forth in this policy.
4. It is the further policy of the Board to insure equal opportunity for minority/women owned businesses and minority/women professionals with regard to all work, services, and supplies purchased by the Board and all construction projects undertaken by the Board which are competitively bid by the Board.
C-7
C-22 Local/Minority/DBE Participation. The work to be performed under this Contract is subject to the Dougherty County Board of Education’s policy on Equal Opportunity for Competitive Bids, DJEA~E. The Dougherty County School System (DCSS) encourages all Local/Minority/DBE Contractors to compete for and receive contracts for goods, services and construction associated with this project. Prime Contractors are encouraged to voluntarily pursue the maximum use of Local/Small Business/Minority/DBE Sub-Contractors and Suppliers.
C-23 Drug Free/Tobacco Statement. The Dougherty County School System (DCSS) supports a drug free workplace and does not tolerate any use or possession of drugs and/or alcohol on its premises or use of…
This is the start of the file's text. The full file is on GovTribe.
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 | — | |
| Award Information | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .