Bid_Form_Event_4362.xlsx
XLSX spreadsheet 37 KB Posted
- Attached to
- BID-PW-LSLR Year 4, Event 2 of 2
- Solicitation number
- 0000004362
- Issued by
- Hennepin County, Minnesota
About this file
This is a Bid Form for Lead Service Line Replacements Year 4, Event 2 of 2, issued for five work packages: Blue, Orange, Brown, Red, and Teal. The project involves water service line replacements of varying diameters (1", 1-1/4", 1-1/2", and 2") with line items categorized by connection type (Main to Meter, Main to Curb Stop, Curb Stop to Meter, and Blind Run configurations). Each package includes estimated quantities for specific work types, with quantities ranging from zero to 185 items per line. For example, the Blue Package includes 31 Main to Meter (Short Water) connections at 1" diameter, while the Brown Package includes 185 Main to Curb Stop (Short Water) connections at 1" diameter. Additionally, all packages include 1 to 5 Discontinue Only and Exploratory Excavation line items. Bidders must enter unit prices for all line items in their selected work package(s), and the form will auto-calculate total bid amounts. The spreadsheet automatically computes extended prices and package totals that must be submitted in eSupplier at designated line numbers (Lines 1-10).
Each work package includes an optional add/alternate for Contractor to Perform Testing and Documentation, requiring a lump sum bid price for geotechnical testing services. Bidders must submit their bid response in the provided Excel format with all unit prices entered electronically; handwritten prices are not acceptable. The form specifies that estimated quantities are non-binding and mathematical errors result in unit prices prevailing. Award may be based on the base bid plus the add/alternate total for selected packages. Bidders must also indicate work package preferences ranked from 1 (most preferred) to 5 (least preferred) or mark as not applicable.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| BID FORM |
| Lead Service Line Replacements Year 4, Event 2 of 2 |
| Blue, Orange, Brown, Red, Teal Packages |
| Event # 4362 |
| Bid Form Information: |
| - Enter Company name in "Company" Field. |
| - If you are bidding on a work package, a Unit Price must be entered for all line items listed in that work package to be considered Responsive. |
| - Bid Form line items listed with an Estimated Quantity of zero (0) require a bid price. The price does not calculate into the bid total and is for owner review. |
| - The Bid Form includes an add/alternate for each work package. If you are bidding on a work package, a lump Sum bid price for the add/alternate is required. |
| - The Bid Form spreadsheet will auto-calculate the total bid amount for each package. No handwritten prices will be accepted. |
| - The auto-calculated total bid amount for each work package and add/alternate you are bidding on should be entered on the specified line number in eSupplier. |
| - Award of bid may be based on the total of the base bid plus the add/alternate for each work package. |
| - In the event of a mathematical error, the unit price shall prevail. |
| - The Bid Form quantities are estimates and are not a guarantee of future orders. |
| - The Bid Form must be filled out in the provided Excel format and a copy attached with your bid response. |
Company:
| BLUE PACKAGE | ||||||
| * NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review. | ||||||
| Item Number | Item Name | Diameter | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| 1 | Main to Meter (Short Water) | 1" | 31 | EA | $ - 0 | $ - 0 |
| 2 | Main to Meter (Long Water) | 1" | 37 | EA | $ - 0 | $ - 0 |
| 3 | Main To Curb Stop (Short Water) | 1" | 61 | EA | $ - 0 | $ - 0 |
| 4 | Main To Curb Stop (Long Water) | 1" | 64 | EA | $ - 0 | $ - 0 |
| 5 | Curb Stop to Meter (Short Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 6 | Curb Stop to Meter (Long Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 7 | Main to Curb Stop (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 8 | Main to Meter (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 9 | Main to Meter (Short Water) | 1-1/4" | 1 | EA | $ - 0 | $ - 0 |
| 10 | Main to Meter (Long Water) | 1-1/4" | 1 | EA | $ - 0 | $ - 0 |
| 11 | Main To Curb Stop (Short Water) | 1-1/4" | 2 | EA | $ - 0 | $ - 0 |
| 12 | Main To Curb Stop (Long Water) | 1-1/4" | 3 | EA | $ - 0 | $ - 0 |
| 13 | Curb Stop to Meter (Short Water) | 1-1/4" | 1 | EA | $ - 0 | $ - 0 |
| 14 | Curb Stop to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 15 | Main to Curb Stop (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 16 | Main to Meter (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 17 | Main to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 18 | Main to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 19 | Main to Box (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 20 | Main to Box (Long Water) | 1-1/2" | 1 | EA | $ - 0 | $ - 0 |
| 21 | Curb Stop to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 22 | Curb Stop to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 23 | Main to Curb Stop (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 24 | Main to Meter (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 25 | Main to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 26 | Main to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 27 | Main To Curb Stop (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 28 | Main To Curb Stop (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 29 | Curb Stop to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 30 | Curb Stop to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 31 | Main to Curb Stop (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 32 | Main to Meter (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 33 | Discontinue Only | N/A | 3 | EA | $ - 0 | $ - 0 |
| 34 | Exploratory Excavation | N/A | 5 | EA | $ - 0 | $ - 0 |
| BLUE PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 1 IN ESUPPLIER: | $ - 0 |
| Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications) | |||
| Add Alternate No. 1 | Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements. | $ - 0 | $ - 0 |
| BLUE PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 2 IN ESUPPLIER: | $ - 0 |
| ORANGE PACKAGE | ||||||
| * NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review. | ||||||
| Item No. | Item Name | Diameter | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| 1 | Main to Meter (Short Water) | 1" | 17 | EA | $ - 0 | $ - 0 |
| 2 | Main to Meter (Long Water) | 1" | 19 | EA | $ - 0 | $ - 0 |
| 3 | Main To Curb Stop (Short Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 4 | Main To Curb Stop (Long Water) | 1" | 67 | EA | $ - 0 | $ - 0 |
| 5 | Curb Stop to Meter (Short Water) | 1" | 102 | EA | $ - 0 | $ - 0 |
| 6 | Curb Stop to Meter (Long Water) | 1" | 1 | EA | $ - 0 | $ - 0 |
| 7 | Main to Curb Stop (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 8 | Main to Meter (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 9 | Main to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 10 | Main to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 11 | Main To Curb Stop (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 12 | Main To Curb Stop (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 13 | Curb Stop to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 14 | Curb Stop to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 15 | Main to Curb Stop (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 16 | Main to Meter (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 17 | Main to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 18 | Main to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 19 | Main to Box (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 20 | Main to Box (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 21 | Curb Stop to Meter (Short Water) | 1-1/2" | 1 | EA | $ - 0 | $ - 0 |
| 22 | Curb Stop to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 23 | Main to Curb Stop (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 24 | Main to Meter (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 25 | Main to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 26 | Main to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 27 | Main To Curb Stop (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 28 | Main To Curb Stop (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 29 | Curb Stop to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 30 | Curb Stop to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 31 | Main to Curb Stop (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 32 | Main to Meter (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 33 | Discontinue Only * | N/A | 0 | EA | $ - 0 | $ - 0 |
| 34 | Exploratory Excavation | N/A | 5 | EA | $ - 0 | $ - 0 |
| ORANGE PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 3 IN ESUPPLIER: | $ - 0 |
| Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications) | |||
| Add Alternate No. 1 | Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements. | $ - 0 | $ - 0 |
| ORANGE PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 4 IN ESUPPLIER: | $ - 0 |
| BROWN PACKAGE | ||||||
| * NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review. | ||||||
| Item No. | Item Name | Diameter | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| 1 | Main to Meter (Short Water) | 1" | 31 | EA | $ - 0 | $ - 0 |
| 2 | Main to Meter (Long Water) | 1" | 26 | EA | $ - 0 | $ - 0 |
| 3 | Main To Curb Stop (Short Water) | 1" | 185 | EA | $ - 0 | $ - 0 |
| 4 | Main To Curb Stop (Long Water) | 1" | 154 | EA | $ - 0 | $ - 0 |
| 5 | Curb Stop to Meter (Short Water) | 1" | 1 | EA | $ - 0 | $ - 0 |
| 6 | Curb Stop to Meter (Long Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 7 | Main to Curb Stop (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 8 | Main to Meter (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 9 | Main to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 10 | Main to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 11 | Main To Curb Stop (Short Water) | 1-1/4" | 1 | EA | $ - 0 | $ - 0 |
| 12 | Main To Curb Stop (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 13 | Curb Stop to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 14 | Curb Stop to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 15 | Main to Curb Stop (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 16 | Main to Meter (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 17 | Main to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 18 | Main to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 19 | Main to Box (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 20 | Main to Box (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 21 | Curb Stop to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 22 | Curb Stop to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 23 | Main to Curb Stop (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 24 | Main to Meter (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 25 | Main to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 26 | Main to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 27 | Main To Curb Stop (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 28 | Main To Curb Stop (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 29 | Curb Stop to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 30 | Curb Stop to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 31 | Main to Curb Stop (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 32 | Main to Meter (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 33 | Discontinue Only | N/A | 1 | EA | $ - 0 | $ - 0 |
| 34 | Exploratory Excavation | N/A | 5 | EA | $ - 0 | $ - 0 |
| BROWN PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 5 IN ESUPPLIER: | $ - 0 |
| Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications) | |||
| Add Alternate No. 1 | Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements. | $ - 0 | $ - 0 |
| BROWN PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 6 IN ESUPPLIER: | $ - 0 |
| RED PACKAGE | ||||||
| * NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review. | ||||||
| Item No. | Item Name | Diameter | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| 1 | Main to Meter (Short Water) | 1" | 8 | EA | $ - 0 | $ - 0 |
| 2 | Main to Meter (Long Water) | 1" | 9 | EA | $ - 0 | $ - 0 |
| 3 | Main To Curb Stop (Short Water) | 1" | 148 | EA | $ - 0 | $ - 0 |
| 4 | Main To Curb Stop (Long Water) | 1" | 134 | EA | $ - 0 | $ - 0 |
| 5 | Curb Stop to Meter (Short Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 6 | Curb Stop to Meter (Long Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 7 | Main to Curb Stop (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 8 | Main to Meter (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 9 | Main to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 10 | Main to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 11 | Main To Curb Stop (Short Water) | 1-1/4" | 1 | EA | $ - 0 | $ - 0 |
| 12 | Main To Curb Stop (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 13 | Curb Stop to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 14 | Curb Stop to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 15 | Main to Curb Stop (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 16 | Main to Meter (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 17 | Main to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 18 | Main to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 19 | Main to Box (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 20 | Main to Box (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 21 | Curb Stop to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 22 | Curb Stop to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 23 | Main to Curb Stop (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 24 | Main to Meter (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 25 | Main to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 26 | Main to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 27 | Main To Curb Stop (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 28 | Main To Curb Stop (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 29 | Curb Stop to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 30 | Curb Stop to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 31 | Main to Curb Stop (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 32 | Main to Meter (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 33 | Discontinue Only * | N/A | 0 | EA | $ - 0 | $ - 0 |
| 34 | Exploratory Excavation | N/A | 5 | EA | $ - 0 | $ - 0 |
| RED PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 7 IN ESUPPLIER: | $ - 0 |
| Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications) | ||||||
| Add Alternate No. 1 | Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements. | $ - 0 | $ - 0 | |||
| RED PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE #8 IN ESUPPLIER: | $ - 0 | |||||
| TEAL PACKAGE | ||||||
| * NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review. | ||||||
| Item No. | Item Name | Diameter | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| 1 | Main to Meter (Short Water) | 1" | 7 | EA | $ - 0 | $ - 0 |
| 2 | Main to Meter (Long Water) | 1" | 4 | EA | $ - 0 | $ - 0 |
| 3 | Main To Curb Stop (Short Water) | 1" | 2 | EA | $ - 0 | $ - 0 |
| 4 | Main To Curb Stop (Long Water) | 1" | 1 | EA | $ - 0 | $ - 0 |
| 5 | Curb Stop to Meter (Short Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 6 | Curb Stop to Meter (Long Water) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 7 | Main to Curb Stop (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 8 | Main to Meter (Blind Run) * | 1" | 0 | EA | $ - 0 | $ - 0 |
| 9 | Main to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 10 | Main to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 11 | Main To Curb Stop (Short Water) | 1-1/4" | 1 | EA | $ - 0 | $ - 0 |
| 12 | Main To Curb Stop (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 13 | Curb Stop to Meter (Short Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 14 | Curb Stop to Meter (Long Water) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 15 | Main to Curb Stop (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 16 | Main to Meter (Blind Run) * | 1-1/4" | 0 | EA | $ - 0 | $ - 0 |
| 17 | Main to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 18 | Main to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 19 | Main to Box (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 20 | Main to Box (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 21 | Curb Stop to Meter (Short Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 22 | Curb Stop to Meter (Long Water) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 23 | Main to Curb Stop (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 24 | Main to Meter (Blind Run) * | 1-1/2" | 0 | EA | $ - 0 | $ - 0 |
| 25 | Main to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 26 | Main to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 27 | Main To Curb Stop (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 28 | Main To Curb Stop (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 29 | Curb Stop to Meter (Short Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 30 | Curb Stop to Meter (Long Water) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 31 | Main to Curb Stop (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 32 | Main to Meter (Blind Run) * | 2" | 0 | EA | $ - 0 | $ - 0 |
| 33 | Discontinue Only | N/A | 2 | EA | $ - 0 | $ - 0 |
| 34 | Exploratory Excavation * | N/A | 0 | EA | $ - 0 | $ - 0 |
| TEAL PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 9 IN ESUPPLIER: | $ - 0 |
| Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications) | |||
| Add Alternate No. 1 | Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements. | $ - 0 | $ - 0 |
| TEAL PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE #10 IN ESUPPLIER: | $ - 0 |
| PACKAGE PREFERENCE INFORMATION | ||
| Enter your work package preference(s) for the LSLR Year 4, Event 2 of 2: | ||
| Item No. | Item Description | Preference: (1, 2, 3, 4, 5 or NA) |
| 1 | BLUE PACKAGE: Preference (1 is most preferred, 2 is second most, etc.) | |
| 2 | ORANGE PACKAGE: Preference (1 is most preferred, 2 is second most, etc.) | |
| 3 | BROWN PACKAGE: Preference (1 is most preferred, 2 is second most, etc.) | |
| 4 | RED PACKAGE: Preference (1 is most preferred, 2 is second most, etc.) | |
| 5 | TEAL PACKAGE: Preference (1 is most preferred, 2 is second most, etc.) |
File details come from the government source that posted it. Updated .