Bid Drawing Set - 11.2.2026.pdf
PDF 2 MB Posted
- Solicitation number
- 2140493
- Issued by
- Orange County, New York
About this file
This is a Bid Drawing Set for the Village of Tuxedo Park Water Treatment Plant Clearwell Upgrades project located at 80 Lorillard Road, Tuxedo Park, New York 10987. The project involves installation of geomembrane baffles in two clearwell basins, with six baffles to be added to each basin per the specifications detailed in the drawings. The scope of work includes crack repairs, modifications to existing piping systems, replacement of existing valves, installation of new instrumentation and controls, and an optional bid alternate for replacement of two existing vertical turbine backwash pumps with Goulds Model VIT-FUFM 12FRHO units rated at 40 HP. The project requires phased construction and demolition, with each phase requiring engineer examination and approval before subsequent phases commence. The contract documents specify detailed process mechanical requirements, including piping support analysis by a New York licensed professional engineer, pressure testing, and coordination of all equipment installations. The bid set was issued in October 2026 with drawings prepared by Weston & Sampson Engineers, Inc.
The project includes specific contracting goals, with a Service-Disabled Veteran-Owned Business (SDVOB) goal of 2.00% and a Disadvantaged Business Enterprise (DBE) goal of 0.00%. No business enterprises have been awarded an identical or substantially similar procurement contract within the past five years. The drawings contain comprehensive process and instrumentation diagrams, clearwell baffle details, pipe penetration specifications, and general notes addressing equipment coordination, field verification of dimensions, material requirements, and construction sequencing. All construction activities must maintain existing flows and flow metering through gravity, pumped bypasses, or other engineer-approved means. The contract requires contractors to coordinate with the owner and engineer regarding demolition, utility identification, temporary construction stoppages, and retention of equipment or materials by the owner.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Specifications Full Set - 10.30.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
\\w se
.lo ca l\W
SE
\P ro jec ts\
NY
\T ux ed o P ar k, NY
\24
-0
4-
VO
TP
-W
TP
C lea rw ell U pg ra de s\0
6-
BI
M-
CA
D\ G0
Co ve r.d wg
Issued For:
Issued Date:
LOCATION MAP
1" = 500'
VICINITY MAP
1" = 60,000'
Know what's before you dig.Call
R below.
READING, MA | BOSTON, MA | FOXBOROUGH, MA | WORCESTER, MA | PORTSMOUTH, NH | MANCHESTER, NH | WATERBURY, VT | ROCKY HILL, CT | ALBANY, NY | RHINEBECK, NY | NEWPORT NEWS, VA I VIRGINIA BEACH, VA I APEX, NC | NORTH CHARLESTON, SC | COLUMBIA, SC | GREENVILLE, SC | JACKSONVILLE, FL | FORT MYERS, FL
BID
OCTOBER 2026
VILLAGE OF TUXEDO PARK, TUXEDO PARK, NY
WATER TREATMENT PLANT CLEARWELL UPGRADES
80 LORILLARD RD, TUXEDO PARK, NY 10987
COPYRIGHT © 2026 WESTON & SAMPSON, INC.
© 2026 Microsoft Corporation © Maxar ©CNES (2026) Distribution Airbus DS © 2026 TMAP MOBILITY Earthstar Geographics SIO © Mapbox © 2026 TomTom © 2026 Zenrin © 2026 Microsoft Corporation © Maxar ©CNES (2026) Distribution Airbus DS © 2026 TMAP MOBILITY Earthstar Geographics SIO © Mapbox © 2026 TomTom © 2026 Zenrin © 2026 Microsoft Corporation © Maxar ©CNES (2026) Distribution Airbus DS © 2026 TMAP MOBILITY Earthstar Geographics SIO © Mapbox © 2026 TomTom © 2026 Zenrin
PROJECT AREA
PROJECT
LOCATION
www.westonandsampson.com
Weston & Sampson Engineers, Inc.
55 Walkers Brook Drive, Suite 100
Reading, MA 01867
978.532.1900 800.SAMPSON
DRAWING INDEX
SHEET TITLE
G000 COVER
M-000 PROCESS NOTES
M-001 CLEARWELL BAFFLES DETAIL
M-002 PROCESS AND INSTRUMENTATION DIAGRAM
AS INDICATED
SJB
GMM
JVR
PROCESS NOTES
M-000
PROCESS GENERAL NOTES
1. ALL EQUIPMENT AND PIPING LAYOUT DIMENSIONS SHALL BE FIELD VERIFIED AND COORDINATED WITH EQUIPMENT SUPPLIED, AND/OR EXISTING CONDITIONS.
CONTRACTOR SHALL VERIFY ALL DIMENSIONS IN THE FIELD AS REQUIRED PRIOR TO BEGINNING CONSTRUCTION OF NEW FACILITIES, EQUIPMENT, OR PIPING THAT MAY BE AFFECTED. IF THE CONTRACTOR PROPOSES TO FURNISH EQUIPMENT THAT REQUIRES AN ARRANGEMENT OR SPACE WHICH DIFFERS FROM THAT WHICH HAS BEEN SPECIFIED OR INDICATED ON THE CONTRACT DRAWINGS, THE CONTRACTOR SHALL PREPARE AND SUBMIT DETAILED DRAWINGS FOR REVIEW BY THE ENGINEER AND OWNER. A SUBMITTAL SHALL SPECIFICALLY OUTLINE ALL NECESSARY CHANGES AND CONTAIN ALL FEATURES OF THE ALTERNATE EQUIPMENT AND/OR PROCESS SYSTEM WHICH IS BEING PROPOSED TO BE FURNISHED. THE INFORMATION SHALL INCLUDE BUT IS NOT LIMITED TO; PLAN/SECTION DRAWINGS, SCHEMATICS, AND ALL THE NECESSARY APPURTENANCES REQUIRED SUCH AS SUPPLIES, HYDRAULIC SYSTEMS, MAKE-UP WATER SUPPLIES, ELECTRICAL WIRING, CONTROLS, CHEMICAL FEED SYSTEMS, ETC. ANY SUCH CHANGES (IF APPROVED BY THE ENGINEER) SHALL BE AT NO ADDITIONAL COST TO THE OWNER. THE CONTRACTOR SHALL ASSUME ALL COST AND LIABILITY FOR SATISFACTORILY ACCOMPLISHING ALL NECESSARY CHANGES AS REQUIRED FOR EQUIPMENT AND/OR ARRANGEMENTS WHICH DIFFER FROM THE CONTRACT DOCUMENTS. NO CHANGE IN CONTRACT TIME SHALL BE GRANTED FOR EQUIPMENT AND/OR ARRANGEMENTS WHICH DIFFER FROM THE CONTRACT DOCUMENTS. REFER TO THE CONTRACT SPECIFICATIONS FOR ADDITIONAL DETAILS.
2. THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE ENGINEER OF ANY DIMENSIONS, LAYOUT OR ELEVATION CHANGES REQUIRED TO SUIT THE SPECIFIC EQUIPMENT BEING PROVIDED UNDER THIS CONTRACT. WHEN SUCH EQUIPMENT REQUIRES PADS, PIERS, CURBING, ETC., THAT DIFFERS FROM THAT SHOWN ON THE CONSTRUCTION DRAWINGS, THE CONTRACTOR SHALL COORDINATE THE STEEL REINFORCING SHOP DRAWINGS ACCORDINGLY.
3. THE MECHANICAL DRAWINGS MAY NOT SHOW ALL VALVES, GAUGES, SWITCHES, OPERATORS, DRAINS, VENTS, COUPLINGS, ETC. FOR COMPLETE AND OPERATIONAL SYSTEMS. ALL VALVE AND GATE OPERATORS SHALL BE LOCATED TO ALLOW CONVENIENT AND UNOBSTRUCTED ACCESS FOR OPENING/CLOSING AS REQUIRED. THE FINAL INSTALLED ORIENTATION OF ALL OPERATORS SHALL BE AS APPROVED BY THE ENGINEER. UNDER NO CIRCUMSTANCES SHALL VALVES BE
INSTALLED WITH OPERATORS OR STEMS ORIENTED IN THE VERTICAL DOWNWARD POSITION.
4. SMALL DIAMETER PIPING (2" AND SMALLER) RUNS MAY NOT BE SHOWN IN THEIR ENTIRETY FOR CLARITY ON DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD ROUTING ALL PIPING TO AVOID INTERFERENCES WITH OTHER DISCIPLINES OF CONSTRUCTION.
5. CONSTRUCTION AND DEMOLITION IS TO BE DONE IN PHASES. EACH PHASE MUST BE COMPLETED AND EXAMINED AND APPROVED BY THE ENGINEER BEFORE
SUBSEQUENT PHASES BEGIN.
6. PROVIDE CAST OR DUCTILE IRON WALL CASTINGS, OR GALVANIZED STEEL PIPE SLEEVES, FOR ALL PIPE PENETRATIONS MADE THROUGH CONCRETE FOUNDATIONS, WALLS, AND SLABS, UNLESS OTHERWISE NOTED ON THE DRAWINGS. ALL WALL SLEEVES AND WALL CASTINGS SHALL HAVE SEALING/ANCHORING COLLARS. SEE PROCESS, MECHANICAL, PLUMBING, AND STRUCTURAL DRAWINGS FOR LOCATIONS OF PENETRATIONS. NEW PENETRATIONS THROUGH EXISTING STRUCTURE WALLS SHALL BE BY CORING MACHINE AND UTILIZE LINK TYPE COMPRESSION SEALS, UNLESS OTHERWISE INDICATED. OPENINGS TO BE COMPATIBLE
WITH REQUIRED PIPING AND STANDARD LINK SEAL SIZES.
7. ALL MAGNETIC FLOW ELEMENTS SHALL BE LOCATED A MINIMUM OF THREE PIPE DIAMETERS DOWNSTREAM AND FIVE PIPE DIAMETERS UPSTREAM OF ANY HYDRAULIC DISTURBANCE, EXCEPT IN SITUATIONS WHERE DIMENSIONAL CONSTRAINTS PRECLUDE THESE SEPARATION DISTANCES. IN THESE CASES, THE ENGINEER WILL REVIEW THE LAYOUT AND PROVIDE REVISED MINIMUM SEPARATION DISTANCES.
8. FIELD LOCATE AND PROVIDE TAGS ON ALL PROCESS VALVES. THE PROCESS VALVE IDENTIFICATION NUMBERS AND TAGS SHALL BE AS INDICATED ON THE PROCESS AND INSTRUMENTATION DRAWINGS. SUBMIT SAMPLE TAG NUMBERING FOR REVIEW PRIOR TO ORDERING.
9. PORTIONS OF NON-PROCESS MECHANICAL PIPING (HVAC AND PLUMBING) MAY BE SHOWN ON THE MECHANICAL DRAWINGS FOR CLARITY AND COORDINATION BETWEEN DISCIPLINES DURING CONSTRUCTION. REFER TO THE APPROPRIATE DRAWINGS AND/OR SPECIFICATIONS FOR ADDITIONAL DETAILS AND REQUIREMENTS.
10. ALL PROCESS PIPING SYSTEMS SHALL BE PROVIDED WITH VENTS AT HIGH POINTS AND DRAINS AT LOW POINTS. PROVIDE ADDITIONAL VENT AND DRAIN CONNECTIONS AS INDICATED ON THE DRAWINGS. FIELD ROUTE DRAIN PIPING TO END TERMINATION AS DIRECTED BY ENGINEER OR AS INDICATED ON DRAWINGS.
11. PROVIDE DRIP PANS, WITH CENTRAL COLLECTION POINT AND DRAIN TO FLOOR, FOR ELECTRICAL AND INSTRUMENTATION EQUIPMENT LOCATED BENEATH LIQUID
CARRYING PIPES.
12. INSTALL CORPORATION COCKS ON ALL BUILDING AND STRUCTURE INTERIOR PIPING HIGH POINTS TO PREVENT AIR BINDING. CONTRACTOR IS RESPONSIBLE FOR DETERMINING EXACT NUMBER AND LOCATIONS OF THESE CORPORATION COCKS BASED UPON INFORMATION DEPICTED ON DRAWINGS AND ACTUAL FIELD ROUTING OF PIPING. REVIEW LOCATIONS WITH ENGINEER BEFORE INSTALLATION. THESE MANUAL AIR RELEASES SHALL INCLUDE A 1/2" BRASS CORPORATION COCK WITH 1/2" COPPER TUBING ADEQUATELY SUPPORTED, EXTENDING TO A LOCAL AREA DRAIN. ROUTING OF TUBING AND SELECTED DRAIN TO BE REVIEWED
WITH, AND ACCEPTED BY, ENGINEER.
13. ALL PIPES SHALL BE ADEQUATELY RESTRAINED AND SUPPORTED. ALL PIPING WHICH IS ADJACENT TO VALVES, COUPLINGS, INSTRUMENTS, EQUIPMENT, AND APPURTENANCES SHALL BE PROPERLY SUPPORTED AND/OR ANCHORED IN ACCORDANCE WITH THE RECOMMENDATIONS OF THE PIPING MANUFACTURER. ALL PIPING SHALL BE INDEPENDENTLY SUPPORTED. THE SUPPORT OF PIPING FROM OTHER ASSOCIATED PIPING SHALL NOT BE ACCEPTABLE.
14. ALL PIPING OUTSIDE AND ABOVE 5'-0" DEPTH OF COVER SHALL BE INSULATED.
15. ALL PIPING SHALL BE CLEANED, TO THE SATISFACTION OF THE ENGINEER, BEFORE TESTING.
16. AFTER INSTALLATION, ALL PIPELINES SHALL BE PRESSURE TESTED FOR TIGHTNESS. ALL LEAKS SHALL BE CORRECTED AND RETESTED UNTIL PRESSURE TEST IS
SATISFACTORILY COMPLETED.
17. ISOLATION KITS, GASKETS, OR DIELECTRIC COUPLINGS, FLANGES, UNIONS, ETC. SHALL BE PROVIDED AND INSTALLED AT ALL CONNECTIONS OF DISSIMILAR
METALLIC PIPING.
18. PROVIDE 4" HIGH (MIN.) REINFORCED CONCRETE PAD UNDER ALL EQUIPMENT, CONTROL PANELS, PIPE AND EQUIPMENT SUPPORTS, TANKS, ETC. UNLESS
OTHERWISE INDICATED.
19. ALL REDUCERS SHALL BE CONCENTRIC TYPE UNLESS DESIGNATED AS ECCENTRIC (ECC) ON THE DRAWINGS. ECCENTRIC REDUCERS SHALL BE INSTALLED WITH
FLAT SIDE UP.
20. WHERE NEW PIPING IS TO BE CONNECTED TO EXISTING PIPING, THE CONTRACTOR SHALL FURNISH AND INSTALL ADAPTERS, FITTINGS, AND ADDITIONAL PIPE AS REQUIRED TO COMPLETE THE INSTALLATION. THE USE OF UNI-FLANGES WILL NOT BE ALLOWED UNLESS INDICATED ON THE DRAWINGS.
21. ALL STAINLESS STEEL FASTENERS FOR PIPING, EQUIPMENT, SUPPORTS, ETC. SHALL BE TIGHTENED WITH A TORQUE WRENCH IN ORDER TO LIMIT THE POTENTIAL
FOR GALLING.
22. CONTRACTOR SHALL COORDINATE INSTRUMENTATION MOUNTING DETAILS WITH THE INSTRUMENTATION SUPPLIER AND THE ELECTRICAL CONTRACTOR. REFER
TO EQUIPMENT MANUFACTURER MOUNT DETAILS AND REQUIREMENTS.
23. ALL CHECK VALVES SHALL BE SILENT TYPE CHECK VALVES UNLESS SPECIFICALLY CALLED OUT OTHERWISE ON THE DRAWINGS.
24. DO NOT SCALE DISTANCES OR DIMENSIONS FROM THE DRAWINGS. WRITTEN DIMENSIONS SHALL PREVAIL. REPORT ANY DISCREPANCIES IMMEDIATELY TO THE
ENGINEER.
25. THE CENTERLINE ELEVATION OF THE PIPELINES SHALL BE COORDINATED BY THE GENERAL CONTRACTOR TO SUIT THE SUPPLIED EQUIPMENT.
26. ALL EQUIPMENT PADS AND CONCRETE STRUCTURES SHALL BE CONSTRUCTED WITH A CHAMFERED EDGE UNLESS OTHERWISE SPECIFIED.
27. ALL PIPING (EXCLUDING BUILDING DRAINS/SEWER) INSTALLED BELOW SLABS SHALL BE ENCASED IN CONCRETE. PROCESS DRAWINGS DO NOT SHOW CONCRETE
ENCASEMENT FOR CLARITY. SEE STRUCTURAL DRAWINGS FOR DETAILS.
28. PIPES 3" IN DIAMETER AND SMALLER SHALL HAVE UNIONS INSTALLED ADJACENT TO EQUIPMENT AND TANKS, UNLESS OTHERWISE NOTED ON DRAWINGS. FLANGES
ARE ACCEPTABLE ON 3" DIAMETER PIPING.
30. ALL SAMPLE TAPS WITHIN THE TREATMENT FACILITY SHALL BE A SMOOTH-NOSED STYLE. NO THREADS SHALL BE ON ANY SAMPLE TAP.
31. THE PIPING SUPPORT DETAILS, LOCATIONS, AND PIPE STRESS AND FLEXIBILITY ANALYSIS SHALL BE DESIGNED AND ANALYZED BY THE CONTRACTOR AND STAMPED BY A NEW YORK LICENSED PROFESSIONAL ENGINEER. THE DESIGN AND ANALYSIS SHALL BE SUBMITTED TO THE ENGINEER PRIOR TO INSTALLATION.
PROCESS GENERAL DEMOLITION NOTES
1. REFER TO INDIVIDUAL DRAWINGS FOR SPECIFIC DEMOLITION NOTES.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL AND DISPOSAL OF ALL DEMOLISHED PIPING, EQUIPMENT, AND MATERIALS. THE OWNER RESERVES THE RIGHT TO RETAIN PIPING, EQUIPMENT, AND/OR MATERIALS ON SITE FOR THEIR USE. SUCH MATERIAL TO BE RETAINED SHALL BE PLACED IN AN ON-SITE STORAGE AREA, REVIEWED/COORDINATED WITH, AND ACCEPTABLE TO, THE OWNER AND ENGINEER. RETAINED EQUIPMENT SHALL BE REMOVED IN SUCH A WAY AS
NECESSARY TO MAINTAIN ITS FUNCTIONAL AND PHYSICAL INTEGRITY.
3. CONSTRUCTION AND DEMOLITION IS TO BE DONE IN PHASES. EACH PHASE MUST BE COMPLETED AND EXAMINED AND APPROVED BY THE ENGINEER BEFORE
SUBSEQUENT PHASES BEGIN.
4. THE CONTRACTOR SHALL KEEP A RECORD OF DEMOLITION AND LOCATION OF UTILITIES FOUND AS PART OF THE PROJECT RECORD DOCUMENTS.
5. REFER TO CIVIL DRAWINGS FOR ADDITIONAL INFORMATION REGARDING EXISTING UTILITIES. THE SIZES, LOCATIONS, AND MATERIALS OF CONSTRUCTION INDICATED ARE FROM THE BEST AVAILABLE INFORMATION AND MAY NOT BE COMPLETE OR ACCURATE. ALL SIZES, LOCATIONS, AND MATERIALS OF CONSTRUCTION SHALL BE VERIFIED BY THE CONTRACTOR IN THE FIELD AS REQUIRED. ALL EXISTING UTILITIES THAT ARE TO REMAIN, AND ARE DAMAGED BY THE CONTRACTORS ACTIVITIES, SHALL BE REPAIRED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER.
6. SEVERING THE EXISTING UTILITIES FOR ABANDONMENT, OR REMOVAL OF A SEGMENT FROM SERVICE, SHALL BE PERFORMED IN SUCH A MANNER AS TO ALLOW THE REMAINING ACTIVE SEGMENT TO CONTINUE IN ITS INTENDED SERVICE. CAP ACTIVE SEGMENTS WITH APPROPRIATE FITTING, JOINT RESTRAINT, ETC. TO ENSURE THEIR INTEGRITY. THE METHOD OF CAPPING SHALL BE REVIEWED WITH, AND ACCEPTABLE TO, THE ENGINEER.
7. ALL PIPING, EQUIPMENT, AND MATERIALS TO BE DEMOLISHED AND/OR REMOVED FROM SERVICE MUST BE COORDINATED WITH THE OWNER AND ENGINEER
BEFOREHAND.
8. THE CONTRACTOR SHALL TAKE ALL NECESSARY STEPS TO ENSURE THAT ALL FLOWS, FLOW METERING, AND LEVEL CONTROLS ARE MAINTAINED DURING CONSTRUCTION. GRAVITY, PUMPED BYPASSES, OR OTHER MEANS OF FLOW MAINTENANCE SHALL BE REVIEWED WITH, AND ACCEPTABLE TO, THE ENGINEER. THE CONTRACTOR SHALL COORDINATE ANY TEMPORARY STOPPAGES WITH THE OWNER AND ENGINEER. CONTRACTOR SHALL VERIFY WITH OWNER/ENGINEER ALL VALVES, GATES, EQUIPMENT, ETC. ARE FUNCTIONAL PRIOR TO ASSUMING UTILIZATION FOR FLOW ISOLATION.
9. WHERE PIPING OR CONDUIT THAT IS TO BE REMOVED PASSES THROUGH THE WALL OF THE STRUCTURE, IT SHALL BE CUT OFF AS NEAR TO THE WALL AS PRACTICAL AND PROPERLY SEALED ON EACH SIDE OF THE WALL, OR AS SHOWN ON THE DRAWINGS. SEAL METHOD SHALL BE SUBJECT TO REVIEW AND
ACCEPTANCE OF THE ENGINEER.
10. ALL WALL AND/OR FLOOR PENETRATIONS REMAINING AFTER THE REMOVAL OF PIPING OR CONDUIT ARE TO BE PATCHED AND FINISHED FLUSH TO MATCH EXISTING
SURFACES.
11. ALL WALL AND FLOOR SURFACES DAMAGED OR DISTURBED AS A RESULT OF DEMOLITION BY THE CONTRACTOR OR ITS SUB-CONTRACTORS, SHALL BE PATCHED
AND PAINTED.
12. WHERE PIPING AND/OR EQUIPMENT THAT IS NOTED AS ABANDONED INTERFERES WITH THE CONTRACTOR'S CONSTRUCTION ACTIVITIES, CONTRACTOR SHALL
REMOVE AND DISPOSE OF AS NECESSARY AT NO ADDITIONAL COST TO THE OWNER.
\\w se
.lo ca l\W
SE
\P ro jec ts\
NY
\T ux ed o P ar k, NY
\24
-0
4-
VO
TP
-W
TP
C lea rw ell U pg ra de s\0
6-
BI
M-
CA
D\
-P ro ce ss
Me ch an ica l\P ro ce ss
N ote s.d wg
COPYRIGHT © 2026 WESTON & SAMPSON, INC.
Project:
www.westonandsampson.com
Consultants:
Seal:
Revisions:
No. Date Description
Issued For:
Drawing Title:
Sheet Number:
Scale:
W&S File No.:
W&S Project No.:
Approved By:
Date:
Reviewed By:
Drawn By:
COA:
VILLAGE OF TUXEDO PARK
80 LORILLARD RD
TUXEDO PARK, NY 10987
WATER TREATMENT PLANT
CLEAR WELL UPGRADES
TUXEDO PARK, NY
BID
OCTOBER 2026
ENG24-0884
Weston & Sampson Engineers, Inc.
55 Walkers Brook Drive, Suite 100
Reading, MA 01867
978.532.1900 800.SAMPSON
EXISTING 8" DIP TO LIFTING PUMPS
TO DISTRIBUTION
EXISTING 8" DIP FROM FILTERS
EXISTING 8" VALVES TO BE REPLACED
EXISTING 8" VALVES TO BE REPLACED
EXISTING 10" DIP TO
FILTERS (BACKWASH)
8" DIP PENETRATION
(SEE PIPE PENETRATION DETAIL)
GEOMEMBRANE BAFFLE PANEL
13'-3" X 12'-3"
SEE SPECIFICATIONS SECTION
11209 - CLEARWELL BAFFLES
(SEE DETAILS 2&3)
EXISTING 10" DIP TO FILTERS (BACKWASH)
EXISTING 8" VALVES
TO BE REPLACED
EXISTING 8" DIP
TO LIFTING PUMPS
TO DISTRIBUTION
CONCRETE ROOF
CONCRETE TANK WALL
1/4" X 2" SST WALL BATTEN
W/ Ø 1/2" HOLES 12" O.C.
13'-3" 2'-0" 2'-0" 13'-3"
'-3
TO EXISTING
DRAINAGE SYSTEM
6'-0" 4'-01 2" 4'-01
2" 4'-01 2" 4'-01
2" 4'-01 2" 4'-01
2"
3'-11" 3'-11" 3'-11" 3'-11" 3'-11"7'-10" 2'-11"
2'-01 2"
2'-01 2"
2'- 0"
2'- 0"
8" DIP
PENETRATION
(SEE PIPE
PENETRATION
DETAIL)
GEOMEMBRANE
BAFFLES
GEOMEMBRANE BAFFLES
'-3
'-3
30'-4"
30'-4"
15'-3" 15'-3"
3'-4" 3'-4" 3'-4" 3'-4" 3'-4"3'-4"3'-4"3'-4"
DEMOLISH THE
EXISTING PIPE
SECTION
ROTATE THE
EXISTING 90°
BEND TO FACE
UPWARD
REMOVE THE EXISTING
BLIND FLANGE
ADD A 90° BEND
FACING UPWARD
BLIND FLANGE
BLIND FLANGE
BLIND FLANGE
4'- 0"
4'- 0"
EXISTING BACKWASH PUMPS
(NOTE 2)
BOTTOM AT WALL
TOP AT WALL
BOTTOM AT FLOW AROUND END
TOP AT FLOW AROUND END
BOTTOM AT FLOOR
TOP AT CEILING
CUT BAFFLE MATERIAL TO
NEAREST WALL OR FLOOR
1/4" X 2" STAINLESS
STEEL BATTEN
4" CAP STRIP (FIELD
WELDED TO BAFFLE)
STAINLESS STEEL
BAND CLAMPS (2)
BAFFLE MATERIAL
FACTORY FABRICATED PIPE BOOT FLANGE
(FIELD WELDED TO BAFFLE)
EXISTING PIPE
PIPE
FACTORY FABRICATED
PIPE BOOT SLEEVE
4" CAP STRIP (FIELD
WELDED TO BAFFLE)
CUT BAFFLE MATERIAL
AROUND PIPE TO
NEAREST PIPE SUPPORT
PIPE
1/4" X 2" STAINLESS
STEEL BATTEN
BAFFLE MATERIAL
FACTORY FABRICATED
PIPE BOOT FLANGE
(FIELD WELDED TO
BAFFLE)
FACTORY FABRICATED
PIPE BOOT SLEEVE
OVERLAPPING SEAM
(FIELD WELDED)
STAINLESS STEEL
BAND CLAMPS (2)
SCALE:
PLAN - CLEAR WELL WITH BAFFLES1 3/8" = 1'
SCALE:
SECTION A-A2 3/8" = 1'
A
A
SCALE:
PIPE PENETRATION DETAIL4 NTS
SCALE:
CLEARWELL BAFFLE DETAILS3 NTS
NOTES:
1. ORANGE COUNTY DEPARTMENT OF HEALTH PLAN APPROVAL IS LIMITED
TO FIVE (5) YEARS. TIME EXTENSIONS FOR PLAN APPROVAL MAY BE
GRANTED BY THE ORANGE COUNTY DEPARTMENT OF HEALTH BASED
UPON DEVELOPMENT FACTS AND ANY NEW REGULATIONS, OR
GUIDANCE, IN EFFECT AT THAT TIME. A NEW PLAN SUBMISSION MAY BE
REQUIRED TO OBTAIN A TIME EXTENSION.
2. BID ALTERNATE 1 SCOPE: CONTRACTOR SHALL REPLACE THE TWO (2)
EXISTING VERTICAL TURBINE BACKWASH PUMPS AND MOTORS IN KIND.
PUMP SHALL BE GOULDS MODEL VIT-FUFM 12FRHO WITH 40 HP VERTICAL
HOLLOW SHAFT MOTOR, 1800 RPM.
\\w se
.lo ca l\W
SE
\P ro jec ts\
NY
\T ux ed o P ar k, NY
\24
-0
4-
VO
TP
-W
TP
C lea rw ell U pg ra de s\0
6-
BI
M-
CA
D\
-P ro ce ss
Me ch an ica l\G 5_
Cl ea rw ell
_P lan
_1 0-
-2
5.d wg
COPYRIGHT © 2026 WESTON & SAMPSON, INC.
Project:
www.westonandsampson.com
Consultants:
Seal:
Revisions:
No. Date Description
Issued For:
Drawing Title:
Sheet Number:
Scale:
W&S File No.:
W&S Project No.:
Approved By:
Date:
Reviewed By:
Drawn By:
COA:
VILLAGE OF TUXEDO PARK
80 LORILLARD RD
TUXEDO PARK, NY 10987
WATER TREATMENT PLANT
CLEAR WELL UPGRADES
TUXEDO PARK, NY
BID
OCTOBER 2026
ENG24-0884
Weston & Sampson Engineers, Inc.
55 Walkers Brook Drive, Suite 100
Reading, MA 01867
978.532.1900 800.SAMPSON
AS INDICATED
CRU
SCC
JVR
CLEARWELL
BAFFLES DETAIL
M-001
STATIC MIXER
RAW WATER
PUMPS
POTASSIUM
PERMANGANATE
FEED PUMP
FLOW METER
RECORDER
REMOTELY
LOCATED ALUM FEED
PUMPS
TU
R
BI
D
IM
ET
ER
TO
DRAIN
DIFFERENTIAL
PRESSURE
TRANSMITTER
TO
DRAIN
TU
R
BI
D
IM
ET
ER
pH M
ET
ER
PRESSURE
TRANSMITTER
CLEARWELL LEVEL
SODIUM
HYDROXIDE
FEED
PUMPS
CHLORINE
FEED
PUMP
CLEARWELL
(6) BAFFLES SHALL BE
ADDED TO EACH BASIN
PER DRAWING M-001
HIGH LIFT
PUMP
C H
LO
R
IN
E
R
ES
ID
U
AL
AN
AL
YZ
ER
RECORDERZINC PHOSPHATE
FEED PUMP
EFFLUENT
PUMPS
TO CP
TO CP
TO CP
TO CP
TO PEN
RECORDER
TO MCPLEGEND
GATE VALVE
SOLENOID VALVE
PUMP
STATIC MIXER
FLOW METER
CHLORINE RESIDUAL ANALYZERCHLORINE RESIDUAL ANALYZER LOCATION
PROP ULTRASONIC FLOW METER LOCATION
PROP
ULTRASONIC
FLOW METER
CHLORINE FEED PUMP LOCATION
MAIN CONTROL
PANEL (MCP)
AE ANALYZER ELEMENT
AI ANALOG INPUT
AIT ANALYZER INDICATING TRANSMITTER
AO ANALOG OUTPUT
MCP CONTROL PANEL
DI DIGITAL INPUT
DO DIGITAL OUTPUT
FE FLOW ELEMENT
FIT FLOW INDICATING TRANSMITTER
NOTE: EXIST CHLORINE FEED PUMP
SHALL BE UPGRADED TO PROVIDE
FLOW PACED SPEED CONTROL.
FILTERCLARIFIER
FILTERCLARIFIER ST
IL
L
TU
BE
W
/ C
LE
AR
W
EL
L
LE
VE
L
IN
D
IC
AT
O
R
TO MCP
SHEET GENERAL NOTE:
1. THE CONTROL PANEL, CHEMICAL METERING PUMP, ULTRASONIC FLOW METER, AND PROCESS CONTROLS
SHALL BE UPGRADED PER SPECIFICATION SECTIONS 11241,13410, AND 13420.
FIGURE 1 NOTES:
1. FURNISH AND INSTALL ULTRASONIC FLOW METER AS PER
SPECIFICATION SECTION 13420.
2. REMOTE TRANSMITTER SHALL BE INSTALLED IN AN OPERATOR
ACCESSIBLE LOCATION.
3. TRANSMITTER SHALL BE POWERED BY THE MAIN CONTROL
PANEL (MCP).
4. COORDINATE ROUTING OF POWER AND SIGNAL WIRING IN THE
FIELD. MCP IS APPROXIMATELY 75 LINEAR FEET FROM
PROPOSED FLOW METER LOCATION. UPGRADE CONTROL
LOGIC PER SPECIFICATION SECTION 13410.
FIGURE 2 NOTES:
1. DEMO EXISTING CHLORINE FEED PUMP AND DISCONNECT
EXISTING SIGNAL WIRING FROM THE MCP. DISCONNECT
POWER FROM LOCAL OUTLET.
2. FURNISH AND INSTALL CHLORINE FEED PUMP AND CONTROL
STATION PER SPECIFICATION SECTION 11241.
3. COORDINATE ROUTING OF SIGNAL WIRING IN THE FIELD. MCP IS
APPROXIMATELY 100 LINEAR FEET FROM THE CHLORINE FEED
PUMP.
4. POWER CONTROL STATION TO CLOSEST ELECTRICAL PANEL
(FIELD COORDINATE).
5. UPGRADE CONTROL LOGIC TO INCORPORATE FLOW PACING AS
PER SPECIFICATION SECTIONS 11241 AND 13410.
FIGURE 3 NOTES:
1. EXISTING CHLORINE RESIDUALS ANALYZER TO REMAIN. UPDATE CONTROLS LOGIC PER SPECIFICATION SECTION 13410.
BACKWASH
PUMPS
BID ALTERNATE 1 SCOPE: BACKWASH
PUMPS SHALL BE REPLACED IN KIND
PER DRAWING M-001.
FIGURE 4 NOTES:
1. EXISTING CLEARWELL LEVEL TRANSDUCER TO REMAIN.
UPDATE CONTROLS LOGIC PER SPECIFICATION SECTION
13410.
AS INDICATED
SJB
GMM
JVR
PROCESS AND
INSTRUMENTATION
DIAGRAM
M-002
\\w se
.lo ca l\W
SE
\P ro jec ts\
NY
\T ux ed o P ar k, NY
\24
-0
4-
VO
TP
-W
TP
C lea rw ell U pg ra de s\0
6-
BI
M-
CA
D\
-P ro ce ss
Me ch an ica l\P &I
D.
dw g
COPYRIGHT © 2026 WESTON & SAMPSON, INC.
Project:
www.westonandsampson.com
Consultants:
Seal:
Revisions:
No. Date Description
Issued For:
Drawing Title:
Sheet Number:
Scale:
W&S File No.:
W&S Project No.:
Approved By:
Date:
Reviewed By:
Drawn By:
COA:
VILLAGE OF TUXEDO PARK
80 LORILLARD RD
TUXEDO PARK, NY 10987
WATER TREATMENT PLANT
CLEAR WELL UPGRADES
TUXEDO PARK, NY
BID
OCTOBER 2026
ENG24-0884
Weston & Sampson Engineers, Inc.
55 Walkers Brook Drive, Suite 100
Reading, MA 01867
978.532.1900 800.SAMPSON
120 VAC
POWER TO MCP
2#14 / 1#14G
VENDOR CABLE
WALL
MOUNT AT
5'-6" AFF
2#18TSH (TYP) 2#16 (TYP)
2#18TSH
| G-000 COVER |
| WSE_LAYOUT_36x24 |
| Bid Drawing Set - 11.2.2026 |
| M-000 |
| Layout1 |