Bid Document.pdf
PDF 1 MB Posted
- Attached to
- 1139 Bennett Loop, Loris - Single Family Rehab
- Solicitation number
- 2024-10-23
- Issued by
- Horry County, Lugoff CDP, South Carolina
About this file
The document is an Invitation for Bid (IFB) issued by Horry County, South Carolina for a Single Family Home Rehabilitation project located at 1139 Bennett Loop in Loris. The project is funded through the U.S. Department of Housing and Urban Development (CDBG) and United States Department of Agriculture (USDA) Section 533 Housing Preservation Grant. The bid (Bid #2024-10-023) requires electronic submission by October 23, 2024, at 2:00 p.m. local time, with a mandatory pre-bid meeting scheduled for October 9, 2024, at 10:00 a.m. at the project site. The contract term is sixty (60) calendar days, with contractors required to complete 100% of the Scope of Work within the specified timeframe and be responsible for a minimum of sixty percent (60%) of the project construction.
The project requires bidders to be properly licensed to do business in South Carolina and possess an active State of SC General Contractor's License. The bid includes specific requirements such as unit pricing, sales tax inclusion (8% county rate, 9% within Myrtle Beach city limits), and comprehensive insurance coverage, including workers' compensation and general liability. Liquidated damages of $200 per calendar day will be assessed for delays beyond the prescribed completion time. Bidders must submit a complete bid forms packet, including various signed forms such as non-collusion affidavit, anti-lobbying form, and proof of insurance. No bid bond is required for this solicitation, and the county reserves the right to accept or reject any bid deemed in the best interest of the county.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Required Bid Forms Packet-for IFB.pdf | ||
| 1139 Bennett Loop Pre Bid Sign In.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BID (IFB)
and
Contractual Requirements for
1139 Bennett Loop, Loris, SC 29569
Single Family Home Rehabilitation
Bid# 2024-10-023
Closing Date: 2:00 p.m. (Local Time) October 23, 2024
The Following Applies to this Solicitation:
• Mandatory Pre-Bid Meeting: October 9, 2024 @ 10:00 a.m. (Local Time), at 1139
Bennett Loop, Loris, SC 29569.
• Questions Acceptance Deadline: October 15, 2024 at 2:00 p.m. (Local Time).
• Required Bid Forms Packet must be submitted with responses to this IFB.
• A Bid Bond is not required.
ADVERTISEMENT
INVITATION FOR BID
Qualified and licensed contractors are invited to submit electronic sealed bids for "1139 Bennett
Loop, Loris, SC 29569 - Single Family Home Rehabilitation” -- IFB # 2024-10-023 Bids will be submitted via Horry County’s electronic bid software not later than October 23, 2024 2:00 p.m., (Local Time). No fax, email, telephone, hand delivered, or text bid submittals will be accepted.
The solicitation document (IFB) can be obtained from the County’s electronic bid software by visiting https://www.bidnetdirect.com/south-carolina/horrycounty.
Electronic bid submittals must include the bidder’s current (active) State of SC General
Contractor’s License.
Contact Information for this Project
Ms. Sharon Smith
Smith.sharon@horrycountysc.gov
843.915.7034
All questions shall be submitted in the Horry County’s e-bidding software.
END OF SECTION
http://www.bidnetdirect.com/south-carolina/horrycounty http://www.bidnetdirect.com/south-carolina/horrycounty
INSTRUCTIONS TO BIDDERS
General Terms and Conditions
General
This solicitation will be conducted in accordance with Horry County Procurement Code and
Regulation. This ordinance can be found in its entirety on the County’s website at:
https://www.horrycountysc.gov/media/ck1no5hq/county_of_horry_regulation.pdf
Horry County hereby notifies all those responding to this IFB that, in accordance with the provisions of the Civil Rights Act of 1964 (Chapter 21, Title 42, of the U.S. Code) and the
Regulations promulgated in connection therewith, that it will affirmatively ensure that any contract entered into pursuant to this IFB, disadvantaged business enterprises will be afforded full and fair opportunity to make submittals in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
Funding This project is U.S. Department of Housing and Urban Development CDBG and United States Department of Agriculture Section 533 Housing Preservation Grant funded and contingent upon funding availability;
therefore, all federal rules and regulations related to such funding will apply.
Submitting a Bid
Sealed bids shall be submitted via Horry County’s electronic bid software ONLY, on or before the due date and time noted on the cover page of this document. The only acceptable means of submitting a bid in reference to this project is through Horry County’s electronic bid software.
Therefore, no email, fax, hand-delivered, telephone, or text bid submittals will be accepted.
Pricing must be provided as indicated in the electronic bid software. For additional details see
Unit Prices.
The bidder must include the required items listed in this document or their bid may be deemed non-responsive.
The County, at its sole discretion, reserves the right to accept or reject any and all bids, in whole or in part, as deemed to be in the best interest of the County. It further reserves the right to waive technicalities and informalities, where it deems it advisable in protection of the best interest of
Horry County. The County will be the sole judge as to whether bids submitted meet all requirements contained in the IFB.
Examination of Bid Document
All official documents, as published by Horry County Government, should be downloaded from
Horry County’s electronic bid software (BidNet) and reviewed prior to submission of an offer, unless otherwise indicated.
Prior to submitting a bid, potential bidders must read all documents associated with this solicitation, thoroughly examining the bidding documents and specifications and/or requirements thereof, and notify Owner of all conflicts, errors, or discrepancies.
By submission of a bid, the bidder guarantees that all goods and services meet the requirements of the solicitation.
Bid proposals may be rejected for any omissions, alteration of form, additions not called for, conditional offers, or any irregularities of any kind are shown. Failure to comply with all requirements, as listed in the solicitation documents, may result in the offer being rejected as non-responsive.
Bids shall remain firm for no less than the specified number of calendar days indicated from the date of bid Closing Date as specified in the Comments to the Project.
The bidder’s name and solicitation number shall be included when specifications or descriptive papers are submitted with the invitation for bid (IFB).
The work under the resulting contract includes the furnishing of all labor, materials, equipment, and all items and services of every nature, whether particularly mentioned or not in this solicitation, as required to provide the services as specified, herein.
All work is to be done in accordance with drawings, specifications, and any permit conditions of federal, state, local or any other agencies having jurisdiction.
Required Bid Forms
Submit ALL required forms. The required forms packet is a separate downloadable file in BidNet, titled “Required Bid Forms Packet.” The bidder must include the required forms or their bid proposal may be deemed non-responsive.
Site Assessment
The bidder is expected to have become familiar with and take into consideration, site conditions which may affect the work and to check all conditions and dimensions at the site.
Each bidder shall acquaint themselves thoroughly as to the character and nature of the work to be done. Each bidder furthermore shall make a careful examination of the site of the work and inform themselves fully as to the difficulties to be encountered in performance of the work, the facilities for delivering, storing and placing materials and equipment and other conditions relating to construction and labor.
The bidder shall examine the premises and the site and compare them with any applicable drawings and specifications. (S)he shall familiarize themselves with the existing conditions.
No plea of ignorance of conditions that exist or may hereafter exist on the site of the work, or difficulties that may be encountered in the execution of the work, as a result of failure to make necessary investigations and examinations, will be accepted as an excuse for any failure or omission on the part of the Contractor to fulfill in every detail all the requirements of the contract documents and to complete the work for the consideration set forth therein, or as a basis for any claim whatsoever.
Insofar as possible, the Contractor, in carrying out his/her work, must employ such methods or means as will not cause interruption of or interference with the work of any other Contractor, or
County personnel at the site.
When geotechnical data is provided by the Owner, the Bidder shall assume responsibility for any conclusions he/she may draw from such data. (S)he may employ his/her own consultants to analyze available information and shall be responsible for any conclusions drawn from that information. The Bidder is encouraged to perform their own investigations if they would like to do so. The cost of such employment or investigations shall be borne solely by the Bidder.
Questions / Addendum
All questions must be submitted via Horry County’s e-bidding software prior to the Questions
Acceptance Deadline as specified in the e-bidding software. Each question must be submitted individually within the “Q&A” section of the electronic bid software. All questions and revisions will be provided in the electronic bid software in the form of addendum. If it becomes necessary to revise any part of this solicitation, an addendum will be published. It shall be the
Bidder’s responsibility to ensure he has all addenda which has been issued by visiting Horry
County’s e-bidding software https://www.bidnetdirect.com/south-carolina/horrycounty. Any information obtained outside of the procurement process is non-binding and shall not be used in the response to this solicitation.
All Addenda forms a part of the documents for this project and modifies / amends / clarifies / adds to the original documents as described above. By submitting a response, responders acknowledge receipt and inclusion of the effects of this addendum.
Potential and actual bidders are not permitted to contact Horry County employees outside of the
Procurement Department during the procurement process. Potential and actual bidders are not permitted to contact any consultants contracted by the County to assist with efforts related, directly or indirectly, to the procurement process. Failure to comply with Horry County
Procurement Regulation, Chapter 4, Contractor Requirements and Standards of Conduct for
Horry County and Procurement Participants may result in the rejection of the submittal and other penalties as applicable.
Non-Collusion
By submitting a response, the party making the foregoing offer that such offer is genuine and not collusive or sham; that said Responder has not colluded, conspired, connived, or agreed, directly or indirectly with any responder or person, to put in a sham response, or that such other person shall refrain from offering and has not in any manner, directly or indirectly sought by agreement or collusion, or communication or conference, with any person to fix the submittal of affiant or any other responder or to fix any overhead, profit or cost element of said Response or of that of any other responder or to secure any advantage against owner any person interested in the proposed contract; and that all statements in said Response are true; and further, that such https://www.bidnetdirect.com/south-carolina/horrycounty responder has not, directly or indirectly submitted this Quotation Request, or the contents thereof, or divulged information or date relative thereto to any association or to any member or agent thereof.
Mistakes in Bid
Corrections and withdrawal of the submitted offer will be permitted within the e-bidding software prior to Bid due date and time.
Bid Opening
Unofficial Bid Results will be made publicly available in the County’s e-bidding software within an estimated time of 60 minutes after the established due date and time.
Mandatory Pre-Bid Walkthrough / Conference
A Mandatory Pre-Bid Walkthrough/Conference will be held on the date and time and at the location indicated on the cover page of this document. Non-attendees will not be allowed to submit a bid proposal. All sub-contractors are strongly encouraged to attend the Mandatory Pre-
Bid Conference.
Licenses
All BIDDERS must be properly licensed to do business in the State of South Carolina and must comply with the Code of Laws of South Carolina, including Section 40-11-200, when applicable.
Your company does not need to be based in South Carolina, but must be licensed to do business in the state of SC and specifically Horry County, if awarded a contract. Failure to comply with this requirement may result in the rejection of the bid as non-responsive.
Bid Bond (is not required)
Performance Bond (is not required)
Payment Bond (Labor and Materials Payment Bond) (is not required)
Liquidated Damages
Contractors shall complete 100% of the Scope of Work within the number of calendar days and at the cost indicated until final acceptance within the Comments to Project, based on the date on the Notice to Proceed. If liquidated damages are not paid, the contractor agrees the County may deduct the amount of liquidated damages from any money due or that becomes due to the contractor under this contract. All deductions from any money due to the contractor are considered to be liquidated damages and not a penalty.
Should the contractor fail to complete this contract and the work provided therein within the time fixed for such completion, the contractor shall become liable to the County for all loss and damage which the County may suffer on account thereof. It is agreed and understood that it will be difficult and impossible to ascertain and determine the actual damage which the County will sustain in the event of, and by reason of, such delay. It is therefore agreed that the contractor will pay to the County in liquidated damages of the dollar amount noted on the Comments to the Project of this document, per day for delays of completion by the contractor. If liquidated damages are not paid, the contractor agrees the County may deduct the amount of liquidated damages from any money due or that becomes due to the contractor under this contract. All deductions from any money due to the contractor are considered to be liquidated damages and not a penalty.
The contractor shall not be charged with resulting damage if:
A. The delay in completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to the act of God, acts of the public enemy, acts of the County, acts of another contractor in the performance of a contract with the County, fires, floods, epidemics, strikes, freight embargoes, delays of subcontractors or suppliers arising from unforeseeable causes beyond their control; and
B. The contractor, within ten (10) days from the beginning of such delay, unless the
County grants a further period of time before the date of final payment under the
Special Instructions and notifies the County in writing of the causes(s) of delay. The
County shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgement, the findings of facts justify such an extension, and his findings of fact shall be final and conclusive on the parties.
The remedies provided for under this provision shall not be construed to limit, waive or otherwise abrogate any other remedy that the County shall be entitled to under other terms and conditions of this Contract. Failure of the County to enforce the liquidated damages provision of the contract shall not constitute a waiver of the breach of the contract for failure to perform in a timely manner. Any extension of time will be in the form of a Change Order duly authorized and signed by the appropriate County official, prior to contract completion date.
Penalties
Provider shall complete 100% of the Scope of Work within the number of calendar days and at the cost indicated, based on the date on the Notice to Proceed. Should the provider fail to complete this contract and the work provided therein within the time fixed for such completion, the provider shall be penalized $200 per calendar day, until the completion of the Work
Authorization / Task Order.
The provider shall not be charged with resulting penalty if the delay in completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the provider.
The provider agrees the County may deduct the amount of penalties from any money due or that becomes due the provider under this contract.
Payment Terms
Payment Terms are Net thirty (30) days upon receipt of correct invoice.
This solicitation does not commit the County of Horry to make an award, to pay any costs incurred in the preparation of the bid proposal, or to procure or contract for goods or services listed herein.
Unit Prices
Unit prices are requested for items in the bid. Each bidder shall include its pro-rata share of overhead, and other items necessary for completion of the project, per plans and specifications, not specifically listed in the schedule of values, so that the sum of the products obtained by multiplying the quantity shown for each item by the unit price bid represents the Total Bid. A
Bidder may choose to only bid on Division I or Division II, but must bid on all items in the respective division to be awarded. This includes base and alternate items. Any bid not conforming to this requirement may be rejected as non-responsive. Additional instruction for
Unit prices is found within the Comments to Project.
If there is no charge for a specific item listed, bidders must enter $0.00. Leaving item pricing blank indicates a “No Bid” for the item.
Sales tax should be included in unit prices. SHIPPING/DELIVERY charges should be included in the Unit Price, if it is not listed separately in the bid schedule. Any bid not conforming to this requirement may be rejected as non-responsive.
Sales Tax
Horry County Government is required to pay sales tax. Horry County’s tax rate is (8%) eight percent, except on purchases/work/deliveries within the city limits of Myrtle Beach, where the tax rate is (9%) nine percent. Sales Tax is expected to be included in the bidder’s electronic bid submittal.
Shipping / Delivery
All deliveries shall be bid as F.O.B. point Destination-freight prepaid, the seller pays and bears all freight charges; collect shipments will not be accepted. It is agreed by the parties hereto that delivery by the Contracted Supplier to the common carrier does not constitute delivery to the
County. Delivery must meet the guaranteed delivery date agreed upon after receipt of order
(ARO). Any claim for loss or damage shall be between the Contracted Supplier and the carrier.
Items must be shipped/delivered to the location(s) as indicated on the cover page of this document. Items ordered under the contract resulting from this IFB must be delivered within the time frame (ARO) as indicated on the cover page of this document.
Deviations
Any deviations from the scope of work, as indicated herein, must be submitted in writing and clearly noted and explained in detail on a separate form and attached to the submitted bid. If deviations are not noted within the bid submittal, all items/services offered must be in strict compliance with these specifications and successful bidder shall be held responsible thereto.
Written consent from the Director of Procurement must be submitted should any changes in specifications be made after the contract has been awarded; otherwise, the responsibility for such changes shall be with the bidder. Verbal information obtained otherwise will be non-binding.
Liability Coverage
The successful bidder shall provide proof of all required insurance(s), including workers’ compensation, automobile liability and general liability. Workers’ compensation shall include a minimum limit of $100,000 per accident and commercial general liability coverage shall provide minimum limits of liability of $1,000,000 per occurrence Combined Single Limit for Bodily
Injury and Property Damage. This shall include coverage for premises/operations, products/completed operations, contractual liability, independent contractors and vehicles used on/in premises/operations. The vendor/contractor must certify that coverage written on a “claims-made” form will be maintained without interruption from commencement of work until the expiration of all applicable statutes of limitation. Horry County shall be named as an Additional
Insured on all liability policies and expressed on the Certificate of Liability Insurance. Insurance shall indemnify County against any and all claims arising under or as a result of the performance of the contract resulting from this solicitation. The County must be provided written notice prior to cancellation, modification, or reduction in limits of any stipulated insurance. Certificate Holder for Certificate of Insurance must be: Horry County, Attention: Risk Management, P.O. Box 997
Conway, SC 29528. It is the responsibility of the contractor to ensure all subcontractors comply with all insurance requirements of this solicitation and the resulting contract.
Requirements for Construction Projects
Contact the Risk Manager at least thirty (30) days before project commencement to determine if the contractor or the County should acquire Builder’s Risk Insurance. Builder’s Risk insurance must be acquired for the construction of a new building or the major improvement, altercation or renovation of an existing structure.
Builder’s Risk coverage shall be with limits equal to 100% of the completed value of the structure(s), building(s), or addition(s). Machinery or Equipment Endorsement must provide coverage during transit when the contract calls for the installation of machinery or equipment as a permanent part of the structure. Construction materials beyond 100 feet of the structure are normally not covered by County insurer.
Disaster / Emergency Clause
In the event, services in the resultant contract may be necessary for emergency protective measures, disaster response, and disaster recovery. By submitting a response to this solicitation, the Proposer shall comply with all applicable federal laws, regulations, executive orders, FEMA policies, procedures, and directives, including but not limited to Appendix II to Part 200—
Contract Provisions for Non-Federal Entity Contracts Under Federal Awards with the exception of Part (D) Davis Bacon Act. Invoices for services related to emergency protective measures, disaster response, and disaster recovery shall be separate from non-emergency/disaster service invoices.
Contract Award
Award of contract will be made to the lowest responsible and responsive bidder whose bid meets the requirements and criteria set forth in the IFB. In determining the lowest responsive and responsible bidder, the County will consider/evaluate the bidders’ past and current performance of other County contracts, to include factors such as timely delivery and guaranteed delivery date. The awarded bidder will agree to the provisions contained in the attached “Contract.”
Contract Requirements Review Meeting
The apparent low bidder and major sub-contractors may be required to attend a Contract
Requirements Review Meeting(s) with the Procurement Director, and the Owners
Representative before a Notice of Award.
The General Contractor’s designated Project Manager, Superintendent and Estimator shall be required to attend this meeting(s).
Contractor Management by Horry County Designee
Horry County Community Development manages a U.S. Housing and Urban Development
CDBG grant and United States Department of Agriculture Section 533 Housing Preservation
Grant. Communication and construction coordination after the bid are awarded shall initiate between the contractor and Horry County. Roles and responsibilities will be discussed at the time of the preconstruction meeting.
Pre-construction Meeting
The awarded bidder will enter into a contract with the property owner. A pre-construction meeting will be scheduled no later than 10 days after the bid opening or contract requirements review meeting, whichever is later. A Sample Construction Agreement is attached to this bid package.
Compensation
The Contractor and Horry County shall determine an appropriate pay schedule as a part of the
Pre-Construction Meeting.
Term of Contract
The term of this contract shall be the amount of time specified within the Special Terms and
Conditions’ Scope of Work. The effective date of the contract shall be the date of the
Homeowner’s signature. The successful bidder will execute and abide by the attached Sample
Contract.
Time of Completion
The time of completion for all renovations to receive an “Acceptance of Work” will be the number of calendar days as specified within the Comments to the Project, which shall be no later than ten (10) business days after receipt of the Notice to Proceed.
Contract Assignment
No contract awarded under these terms, conditions, and specifications shall be sold, transferred, or assigned without the written approval of the County.
Contract Changes
Contract terms and conditions shall not be changed unless by a change order. Change must be deemed allowable, allocable, and reasonable for the completion of project scope. Changes shall be agreed upon by both parties and recorded using the approved change order document. The change to method, price, or schedule of the work must be clearly identified for each specific change which may occur. Additional process information is available within the Horry County
Procurement Regulation Subchapter 13-3: Post Award Issues.
Grievance / Bid Protest
Any actual or prospective responder who is aggrieved in connection with the procurement or award of a contract may protest to the County Administrator. The protest shall be submitted in writing within fourteen (14) days after such aggrieved person knows or should have known of the facts giving rise thereto provided that grievance has been made in accordance with solicitation requirements. Any grievance filed shall be made known prior to any bid opening in accordance with invitation to bids. Please reference Subchapter 15-3-Bid Protests of the Horry
County Code & Regulation by visiting:
https://www.horrycountysc.gov/media/ck1no5hq/county_of_horry_regulation.pdf
Freedom of Information Statement
Procurement information shall be a public record to the extent required by Chapter 4 of Title 30, Code of Laws of South Carolina (1976, as amended) (The Freedom of Information Act), with the exception that commercial or financial information obtained in response to a “Invitation for
Bids” which is privileged and confidential if so designated by the proposer shall be protected from disclosure. Such information must be clearly marked as “CONFIDENTIAL” by those submitting responses for each section of information so affected. Privileged and confidential information is information in specific detail not customarily released to the general public, the release of which might cause harm to the competitive position of the party supplying the information.
Title VI
The contractor, sub recipient or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR Part 26 in the award and administration of DOT-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate.
Legal Statement
Responders to this IFB must disclose involvement in any litigation within the last five (5) years in which a claim has been made against any team member (individual or company) asserting a cause of action other than Employment issues or Contracts not related to your professional work.
Explain the issues in these cases (or the fact there are none) as part of your submittal.
Special Terms and Conditions
COMMENTS TO THE PROJECT
1. A Bid Bond is not required for this solicitation.
2. Term of the contract: shall be sixty (60) calendar days with the effective date of the date of the Homeowner’s signature.
3. Time of Completion requiring an “Acceptance of Work”: sixty (60) calendar days from
Notice of Proceed date.
4. Liquidated damages will be in the sum of $200.00 per day for each and every calendar day of delay beyond the time herein prescribed for finishing the work.
5. The successful bidder will complete a minimum of sixty percent (60%) of the work involved in the project construction. The remainder may be accomplished by the subcontractors which must be approved by Horry County or its’ designee in writing.
6. The bid shall remain firm for not less than sixty (60) calendar days from the date of bid submission.
7. Your firm must provide a photo copy of your General Contractor’s License.
8. Project is funded by CDBG and USDA.
9. If your business is located outside of South Carolina, a Nonresident Taxpayer Registration form will be required. (Form located in Required Bids Form Packet.)
REQUIRED BID FORMS
The bidder must include the following items or their bid proposal may be deemed non-responsive. The County reserves the right to accept or reject any and all bids, in whole or in part, that are deemed to be in the best interest of the County at its sole discretion.
CHECKLIST
□ Completed and Signed Bid Submittal Form
□ Electronic Bid Proposal Item Pricing (to be completed within the e-bidding software)
□ Addendum Acknowledgment
□ Signed Non-Collusion Affidavit
□ Bid Bond (if applicable, will be stated on the cover sheet)
□ Signed Anti-Lobbying Form
□ Legal Litigation Form
□ Signed Debarment, Suspension, and Other Responsibility Matters
□ Signed S.C. Drug-Free Workplace Form
□ Copies of Active License(s)/business license(s)-Including State of SC General Contractor's
License
□ Sample Certificate of Insurance (COI)
□ Completed W-9
□ Nonresident Taxpayer Registration Form (applicable if business is located outside the State of
South Carolina)
REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK
CONTRACT
FORMS
Attachment A: Construction Agreement
Attachment B: Homeowner's Right of Rescission
Attachment C: Notice to Proceed
Attachment D: Scope of Work & Specifications
Sample Performance Bond – Not Required
Sample Labor and Material Payment Bond – Not Required
REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK
Attachment A
CONSTRUCTION AGREEMENT
This Agreement is made on the DATE, between Name (homeowner) and Name of Contractor (“Contractor”), for reconstruction work that the Contractor is to perform at Address of property (“the Property”).
WHEREAS, Homeowner applied to the Horry County Homeowner Rehabilitation Program and was approved to receive federal grant funding to rehabilitate the Property;
WHEREAS, Horry County has engaged Contractor, on behalf of and with Homeowner’s approval, in submitting a sealed bid for rehabilitation work at the Property under the Rehabilitation Program; and
NOW, THEREFORE, in consideration of the mutual promises and covenants herein contained, Homeowner and Contractor agree as set forth below.
1. Contractor shall furnish all supervision, labor, materials, machinery, tools, equipment, and services necessary to reconstruct the Property according to the drawings and specifications in the Bid Documents, Bid Attachments, and on the Work Write Up, Attachment “A,” DATE. Contractor shall perform all work and provide all materials in a manner consistent with generally accepted standards governing the construction industry.
2. Homeowner is entitled to rescind all obligations and commitments under this Agreement within three (3) business days from the date of execution of this Agreement in accordance with the Homeowner’s Right of Rescission, Attachment “B.” If Homeowner elects to rescind this Agreement, Homeowner shall notify Horry County Community
Development of the intention to rescind. Upon Homeowner’s exercising the
Homeowner’s Right of Rescission, all parties to this Agreement are released from obligation and commitments contained in this Agreement.
3. Contractor shall commence work within ten (10) business days of receiving a written
Notice to Proceed, Attachment “C,” but not before Homeowner’s three-day Right of
Rescission, Attachment “B,” has expired or has been waived. Contractor shall complete work on the Property no later than sixty (60) calendar days after issuance of the Notice to proceed unless the contract time has been extended by a Change Order, signed by
Homeowner and Horry County, as provided for in Paragraph 8 of this Agreement.
4. Notwithstanding the provisions in Paragraph 3, Contractor is excused from the sixty (60)
- day contract time requirement if delay is caused by any act or omission of Horry County, Homeowner, or any separate contractor employed by Homeowner; strikes; lockouts;
fires; unusual delay in transportation; unavoidable casualties; or causes completely beyond Contractor’s control.
5. Horry County has determined that,
a. Homeowner agrees to use due care to avoid interfering with Contractor’s completion of the work.
b. Homeowner agrees that to the best of Homeowner’s ability, the Homeowner will avoid interfering with Contractor’s progress on the job and to lessen the safety risks to Homeowner associated with Homeowner’s being on the jobsite.
c. Homeowner agrees to vacate the premises during the construction process.
6. Homeowner shall allow Contractor to use, at no cost to Contractor, existing utilities such as lights, heat, electricity, and water necessary to the performance of work under this
Agreement. Contractor shall not be responsible for the contents of the family’s belongings once they are put in the storage container and secured.
7. Except for purposes of affording protection against any emergency endangering health, life, limb, or property, Contractor shall make no changes in the materials used or the specified manner of construction or supply additional labor, services, or materials beyond that required to complete the work according to the Bid, Attachment “A.”
8. Contractor may request changes in the scope of work or project time under this
Agreement by submitting a written request for a Change Order. Contractor shall include a detailed description of the requested change in work or contract time, the proposed change in cost or contract time, and a statement that Contractor will perform all work included in the Change Order in accordance with requirements under this Agreement except as modified by the Change Order. No Change Order is effective unless signed by
Horry County and Homeowner.
9. Contractor shall obtain and pay for all licenses and permits necessary for the completion of work to be performed under this Agreement. If Contractor performs work contrary to governing laws, ordinances, or regulations, Contractor shall bear all costs arising from the nonconformity.
10. Contractor shall perform work in accordance with applicable local building codes and requirements.
11. Contractor is responsible for the quality of all work performed by Contractor, his employees, subcontractors, or subcontractors’ employees. Contractor shall warrant all work for a period of one year from the date of Final Payment. Contractor shall correct any defects in workmanship that appear within the one-year period at no cost to
Homeowner or Horry County.
12. Horry County shall pay Contractor on Homeowner’s behalf for satisfactory completion of the work on the Property. Homeowner shall make all necessary approvals to ensure that
Contractor receives timely payment for the percentage of project completion to date. If
Homeowner unduly delays Contractor’s receiving payment, Horry County may circumvent
Homeowner approval requirements that are delaying the payment process.
13. Before Horry County makes Final Payment to Contractor, Contractor shall furnish to
Homeowner a release of liens or claims for liens by subcontractors, laborers, and material suppliers for all completed work and installed materials.
14. Before Horry County makes Final Payment to Contractor, Contractor shall furnish to
Homeowner all manufacturers’ and suppliers’ written guarantees and warranties covering materials and equipment furnished under this Agreement, and release of the
Building Permit.
15. Contractor and Homeowner acknowledge that this project is funded with federal grant funds. Contractor and Homeowner shall allow Horry County and any local, regional, state, or federal government agent or their designees to access the work during all times
Contractor is on site for inspection of the work, materials, equipment, personnel, and employee working conditions.
16. If local ordinances require inspection of the work, Contractor shall arrange for and be present during all inspections. If Contractor covers any work without first obtaining required inspections and approvals, Contractor shall uncover the work to permit inspection at Contractor’s own expense.
17. Contractor shall maintain the premises in a clean and orderly manner during the course of work on the Property. Contractor shall remove all equipment, materials, and debris from the Property at the completion of work.
18. Contractor shall not use or allow to be used any lead-based paint in the work on the
Property.
19. Termination.
a. If Contractor fails to fulfill any provision of this Agreement or fails to perform work as described in the Bid Documents, Bid Attachments and Work Write-Up, Attachment “ A,” H o m e o w n e r m a y d e l i v e r t o C o n t r a c t o r w r i t t e n n o t i c e o f
Termination of this Agreement. Homeowner shall allow Contractor ten (10) calendar days to cure the default before termination becomes effective.
b. If Horry County fails to pay Contractor under Horry County’s agreement with
Contractor, Contractor may terminate this Agreement by providing to Horry
County and Homeowner written notice of termination and allowing ten (10) calendar days to cure the default before termination becomes effective.
c. Notwithstanding subparagraphs (a) and (b) of this provision, the Parties may mutually agree to terminate this Agreement if irreconcilable differences or disputes develop.
20. Contractor solely is responsible for the safety of all individuals performing work under this Agreement and for any damages to the Property occurring as a result of his acts or omissions.
21. Homeowner acknowledges that Contractor is responsible for the quality and conduct of work on the Property. Homeowner agrees to hold harmless the Horry County, United
States Department of Housing and Urban Development, and these entities’ agents and assigns from liability and claims for damages for bodily injury, death, sickness, disease, or injury to property arising from Contractor’s operations under this Agreement.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed on the day and year first written above.
CONTRACTOR:
Signature Date
Witness
HOMEOWNER:
Signature Date
Witness
Attachment B
HOMEOWNER’S RIGHT OF RESCISSION
Today, the Date, 2023, you have entered into a transaction that may result in a mortgage or other security interest being placed on your home. Federal law provides you with the right to cancel this transaction, if you so desire, without any penalty or obligation at any time within three (3) business days from the above date. By cancelling this transaction, any lien, mortgage, or other security interest on your home resulting from this transaction is automatically void. If you desire to cancel this transaction, you may do so by notifying Horry County at the following address:
Community Development Director c/o Horry County Community Development
100 Elm Street Conway, SC 29526 by mail or any other form of written notice delivered to the above address no later than midnight on Date, 2023.
Please acknowledge your receipt of this notice by signing the form indicated below.
HOMEOWNER’S ACKNOWLEDGEMENT OF RIGHT OF RESCISSION
Each of the undersigned hereby acknowledges the receipt of two completed copies of the Homeowner’s Right of Rescission.
Homeowner Date
DECISION TO WAIVE HOMEOWNER’S RIGHT OF RESCISSION
I have read and understand the above and wish to waive my right of rescission.
Attachment C
NOTICE TO PROCEED
I, the undersigned, hereby authorize the Contractor to commence work on the property located at
Address, S.C. within ten (10) business days after the execution of the Construction Agreement.
However, Contractor shall not commence work before Homeowner’s three-day Right of
Recession, Attachment B, has expired or been waived. If the Contractor does not commence work within the specified time, the Homeowner, upon proper notification, may consider the Contractor to be in default.
The property will be available to the Contractor to perform the work stated in the Construction
Agreement between the hours of 7:00 a.m. and 5:00 p.m., Monday through Sunday, unless otherwise specified by the Homeowner.
I acknowledge that the work will be considered completed when all items listed on the Bid
Document, Bid Attachments and Work Write-Up, Attachment “A,” and any Change Orders have been finished and all work has been inspected and approved by Horry County or any other required entity.
Homeowner_____ Date _____________
Attachment D
SCOPE OF WORK AND SPECIFICATIONS
(See attached Bid Documents, Bid Attachments and Work Write-Up)
I understand and agree that:
• All work done on my house, located at Address, S.C. has been pre-determined by the contractor, authorized by Horry County Community Development & recorded on the Work Write-Up before construction begins.
• All funds authorized for the rehabilitation of my home will be used in their entirety;
therefore, the only work permitted through this Rehabilitation Program will be what is itemized on the Work Write-Up at the time of my signature.
• Any additional work arrangement between the Contractor and Homeowner may not commence until the scope of work in this contract has been completed and the contractor has been paid by Horry County.
• No additional work can be done at my request.
HOMEOWNER DATE
WITNESS DATE
CONTRACTOR DATE
WITNESS DATE
File details come from the government source that posted it. Updated .