About this file

Summary

This is a Special Provisions document for Bid #2026-40, FY27 Water Service-Premise Plumbing Maintenance, issued by the City of Bloomington, Illinois. The contract encompasses repair, replacement, and maintenance of water infrastructure to ensure safe, reliable, and continuous water service to customers throughout the city. The work will be performed on an as-needed basis with maintenance locations provided intermittently throughout the contract duration. The contractor must initiate work within 5 business days of receiving a maintenance location, or within 4 hours if the work is classified as an emergency. Sealed bids were due via the City's e-Procurement Portal by Thursday, April 16, 2026, at 10:00 am CST. The contractor must designate a Project Superintendent responsible for all work and shall coordinate activities to minimize overtime and avoid damage to adjacent pavements, curbs, gutters, parkways, driveways, buildings, and lawns.

All work shall be performed and paid on a time and materials basis with labor rates established through prevailing wage requirements per the Illinois Department of Labor. Labor rates include base pay, benefits, insurance, training, and markup, with a two-hour minimum per day for projects completing in less than two hours. Equipment will be paid hourly using FHWA rates from Equipment Watch Rental Rate Blue Book with no markup allowed, including one hour of mobilization per piece of equipment. Materials shall be paid at cost plus 5% markup, substantiated by supplier invoices, and must be pre-approved by the Water Department designee. Subcontractor services, off-site repairs, and professional engineering or testing services are compensated at cost plus 5% markup. The City of Bloomington has adopted a project labor agreement requirement for public works projects exceeding $50,000 in estimated value, though such agreements must comply with the Illinois Prevailing Wage Act and cannot mandate union membership. Certified payroll reports must be submitted with each invoice, with electronic copies directed to Michael Hurt at mhurt@cityblm.org and the assigned Water Department designee.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

FY27 Water Service-Premise Plumbing Maintenance Bid No. 2026-40

The work performed in this contract shall be performed in accordance with the following Standard

Specifications except as modified herein.

Coordination of contract documents shall be according to Article 105.05 of the Standard

Specifications for Road and Bridge Construction. The following table supplements Article 105.05 and states the version to be used:

Priority # SPECIFICATION / CODE TITLE VERSION PUBLISHED BY

1 Special Provisions Contract

2 Supplemental Specifications and Recurring

Special Provisions

Latest IDOT

3 Standard Specifications for Road and Bridge

Construction

Latest IDOT

4 City of Bloomington – Manual of Practice for the Design of Public Improvements

Latest City

5 Illinois Supplement to the National Manual on

Uniform Traffic Control Devices

Latest IDOT

6 Manual on Uniform Traffic Control Devices Latest FHWA

7 Manual of Test Procedures of Materials Latest IDOT

Final clarification of any conflict shall be as directed by the Water Department Director.

DESCRIPTION OF WORK

The work includes repair, replacement, and maintenance of water infrastructure to ensure safe, reliable, and continuous water service to customers.

PROSECUTION & PROGRESS

The Contractor's attention is called to Article 105.06 of the Standard Specifications for Road and

Bridge Construction. The contractor shall designate one individual as the Project Superintendent for this contract. This person shall be responsible for all work. The name and contact information for the Project Superintendent shall be supplied at the Pre-construction Meeting. The Project

Superintendent may be an individual from one of the labor trades if they meet the requirements of

Article 105.06.

LOCATIONS & SCHEDULE

Maintenance locations shall be provided to the Contractor intermittently throughout the duration of the contract. All work shall be scheduled such that minimal, if any, overtime will be necessary. The

Contractor shall initiate work within 5 business days of receipt of each maintenance location unless written justification is provided and approved by the City inspector. If the City determines the work to be an “Emergency”, then the Contractor shall initiate work within 4 hours of receipt of each maintenance location unless written justification is provided and approved by the City inspector.

Contractor shall then prosecute the work to its completion in a manner satisfactory to the City. The

Contractor’s failure to comply with this requirement may be considered breach of contract. The City reserves the right to perform the necessary work and seek reimbursement through the Contractor’s performance guarantee. The City may request the

Contractor work more than 8 hours to complete the work for the day. If the City requests more than

8 hours of work in one day, then the Contractor shall be paid with the “Emergency” bid items. No other compensation for overtime work shall apply.

RESPONSIBILITIES OF THE CONTRACTOR

The Contractor shall so arrange the work site(s) such that no damage will result to the adjacent pavements, curbs, gutters, parkway, driveways, buildings, and lawns. The Contractor shall be solely responsible for and shall pay all costs associated with damages not directly associated with the work caused by the operations of the Contractor. The work by the contractor shall follow all applicable guidelines of the Public Rights of Way Accessibility Guidelines (PROWAG) and Americans with

Disabilities Act requirements.

LOCATION OF UTILITIES

The Contractor shall be responsible for contacting the Joint Utility Location Information for

Excavators (JULIE) and field locating all utility crossings/conflicts. This work will not be paid for separately. The contractor will be responsible for any damage to utilities caused by their work and will not be paid for by the City. Any conflict that can be avoided by altering the grade of the proposed improvement, slightly altering a proposed structure or slightly altering the horizontal location of the proposed improvement shall be the responsibility of the Contractor.

CONTRACTOR USE OF CITY FIRE HYDRANTS PROHIBITED

The Contractor will not be allowed to connect to City fire hydrants to obtain potable water or for any other use, even with a backflow prevention device. Any potable water required for this project shall be obtained without utilizing the City’s fire hydrants. As an option, a City of Bloomington potable water bulk dispensing station is located at 603 West Division Street, Bloomington, Illinois.

Purchase and transportation of water to the job site shall be incidental to the contract.

REMOVAL OF EXISTING SIGNS

All existing signs and signposts that interfere with the work shall be removed by the City of

Bloomington or the maintaining agency, except as directed by the City inspector. The City will remove and replace any sign installation that is owned and maintained by the City, at no charge to the Contractor providing the Contractor provides the city with not less than two (2) working days’ notice. Any Contractor or private party removing any sign will be billed for replacement costs associated with reinstallation of the sign and may be charged with a violation of Illinois Vehicle

Code 11-311.

MATERIAL ORIGINATION

All materials incorporated into this project shall be manufactured in countries signatory to the North

American Free Trade Agreement (NAFTA) or the Central American Free Trade Agreement

(CAFTA).

SHOP DRAWINGS

Unless requested by the City, shop drawing submittal will not be required for this project.

SALVAGE MATERIALS

This work shall consist of salvaging materials that are removed with the contract when directed by the City. All salvage materials shall become the property of the City of Bloomington and when so directed by the Water Department designee, the Contractor shall haul salvaged materials to a City property to be determined by the Water Department designee. All whole bricks extracted in the process of any excavation shall be separated from the waste debris, shall have loose material removed, and shall be transported to Rivian Motorway off Six Points Rd near Heartland Hills

Subdivision or other location as directed by the Water Department. Any bricks extracted shall be delivered to the storage site the same day of the excavation. The City representative will open the gate at the north end of Rivian Motorway for deliveries.

TRAFFIC CONTROL

Traffic Control shall be maintained throughout the project in accordance with the various City, State and Federal regulations. Local vehicular and pedestrian traffic shall be maintained throughout the project in accordance with applicable IDOT Highway Standards. The procedures and guidelines set forth in Part 6 of Manual of Uniform Traffic Control Devices for Streets and High- ways shall be fully followed. The Contractor shall notify the Water Department of an impending street closing prior to beginning work and after the street is clear. No streets shall be closed without prior notice to and the approval of the Water Department.

SAFETY

The contractor is responsible for all safety relative this contract and shall comply with all applicable federal, State, and local laws governing safety, health, and sanitation (23 CFR 635). The contractor shall provide all safeguards, safety devices and protective equipment and take any other needed actions as it determines to be reasonably necessary to protect the life and health of employees on the job and the safety of the public and to protect property in connection with the performance of the work covered by the contract.

GENERAL

All work performed under this contract shall be paid on a time and materials basis. The Contractor shall notify the Water Department designee by call, text, or email, before the end of the prior workday, of the Contractor’s intention to perform work on this Contract the following working day, unless other prior arrangements are made with the Water Department designee. Also, at the start of work for that day, the Contractor shall notify the Water Department designee by a text message, email, phone call, or other agreed upon notification method with the Water Department designee. If the Water Department designee does not receive proper notifications, the designee may elect to not sign off on work that he/she was not notified about, and the Contractor will not be paid for the work.

All known material and equipment shall be delivered to the project site prior to startup of any maintenance work. Labor, equipment and materials shall be tracked on a daily or project basis per the discretion of the Water Department designee. The attached City of Bloomington’s

“Maintenance and Repair Time & Materials Report” form shall be used for all records. The form shall be signed by the Contractor’s Superintendent and the City’s inspector and submitted no later than 48 hours from the completion of that day’s work, unless a written notice has been provided to the Water Department designee with an acceptable reason for variance. When the Time and

Materials sheet is not signed at the completion of the day’s work, the Contactor shall take a picture or scan the completed form and send it to the Water Department designee as an email before the end of that day.

The City reserves the right to NOT pay for work that has NOT been submitted according to these

Specifications. Invoices submitted which do not include a signed form will not be paid. Changes to a completed and signed form will not be allowed without prior approval from the Water Department designee. The referenced Standard Specifications for Road and Bridge Construction apply to the performance and quality of work. All provisions regarding measurement and payment in the

Standard

Specifications for Road and Bridge Construction are not applicable to this contract. This includes

Article 109.04, except as designated herein. City of Bloomington staff will determine the work to be performed by the Contractor under this contract. Similar work may be performed by City crews or other companies. All invoices shall be submitted within 60 days of completion of work at each location or as ap- proved by the City. Invoices shall be submitted as hard copies mailed or delivered to the City. Emailed invoices are acceptable only when approved by the City. Partial invoices at individual work locations may be approved or required at the direction of the Water Department designee.

LABOR

The labor required at each location shall be of the trades and quantity reasonably required to complete the work. All labor required for this contract shall be paid based upon time at each work location. The rates shall include base pay, benefits, insurance, training, markup and all other additions. Several of the trades included in the Illinois Department of Labor’s Prevailing Wage listing have multiple Regions, Types or Classes. The Contractor shall be paid the rate bid for each trade regardless of the Region, Type or Class. In addition, the Prevailing Wage listing includes a

Skilled Laborer trade designation and most of the trades also indicate a Foreman base pay rate. The

Contractor shall be paid the rate bid for each trade even if the worker is classified as a Foreman or as a Skilled Laborer instead of a Laborer. The Contractor shall be paid for the Project Superintendent at the rate bid for the labor trade represented by the designated individual. The Contractor shall be paid the same rate for “Cement Mason” or “Laborer” and the rates in the Contractor’s Proposal shall reflect the anticipated average rate for Utility Maintenance type projects.

Labor shall be paid from the start of work for that day until the end of work each day at each location. (Example – Contractor’s labor that shows up onsite and starts work at 7:15 AM, the Con-tractor’s labor stops work at 3:15 PM, and has ½ hour lunch will get 7.5 hours of work for that day).

The Contractor is responsible for daily mobilization of trades to and from the site locations and should be included in the rates bid per hour on the attached Contractor’s Proposal.

In the event labor trades, which are not included in the original contract, become necessary to perform requested work, payment shall be made in accordance with Article 109.04(b) (1) & (2) of the

Standard Specifications for Road and Bridge Construction except the allowed markup in

109.04 (b)(1) shall be 10% instead of 35%. Any apprentice labor classes used by the contractor shall be approved by the City and will be paid according to Article 109.04(b) (1) & (2) of the Standard

Specifications for Road and Bridge Construction except the allowed markup in 109.04 (b)(1) shall be 10% instead of 35%. A two-hour minimum will be allowed per day for projects that take less than two hours to complete. The two-hour minimum does apply to multiday projects if no other work is performed on City assigned work on that day. The two-hour minimum does not apply to multiple small projects in a one-mile area that can be completed in one day. The one-mile area shall be determined by straight line distance as seen from the air, not shortest driven route. An additional two hour minimum will apply to projects added by the City which are outside the initial one-mile area. Certified payroll reports shall be provided to the City for all work performed during this contract. Certified payroll shall be submitted with each corresponding invoice. In addition to submitting certified payroll with each invoice, the contractor shall send an electronic version of the payroll via email to Michael Hurt at mhurt@cityblm.org and copied to the Water Department designee that assigned the work.

mailto:mhurt@cityblm.org

EQUIPMENT

All equipment used during this contract shall be paid based upon time used on the project site.

Equipment rental rates will be paid for by the hour using the applicable FHWA hourly rate from the

“Equipment Watch Rental Rate Blue Book” (Equipment Watch).

The FHWA hourly rate is calculated as follows.

FHWA hourly rate = (monthly rate/176) x (model year adj.) x (Illinois adj.) + EOC Where: EOC =

Estimated Operating Costs per hour (from the Blue Book)

The Bloomington area regional adjustment shall not be used.

Rates for equipment not shown in Equipment Watch shall be obtained from the Illinois Department of

Transportation’s Schedule of Average Annual Equipment Ownership Expense, January 1, 2004 edition and the 2023 index factor of 1.838 or most current index factor. No markup shall be al-lowed on equipment. All overweight permits required by the City of Bloomington shall be obtained, but the fees will be waived for work performed under this contract. The Contractor shall be responsible for indicating on the permit application that the permit is relative to a City

Maintenance or Repair Contract. The equipment required at each location shall be of the type, size and quantity reasonably required to complete the work.

One hour of mobilization time will be allowed for each piece of equipment used at the project site.

The hour includes both mobilization and demobilization (half hour for each). Mobilization will also include any preparatory work, including but not limited to greasing machines, etc.…Mobilization for equipment brought under its own power will be paid at the equipment rate. Mobilization for equipment transported by trailer or special vehicle will be paid at the truck-trailer combination or special vehicle rates only (not the equipment). A special vehicle includes a truck or van with a lift gate or similar loading device. One mobilization will be paid for multiple pieces of equipment transported on the same trailer or special vehicle at the same time. Mobilization will not be paid for equipment that is brought to the project site but not used. Mobilization of small equipment, such as a cut-off saw, plate compactor or vibrator, which can be transported in a pickup truck or van will not be paid. The one-hour mobilization time also ap- plies to the Operating Engineer or Truck

Driver operating the equipment under its own power and a truck-trailer or special vehicle hauling equipment. Mobilization time will not be paid for any other labor trade as stated in the Labor section of these Special Provisions, mobilization time for all other trades shall be included in the rate bid per hour on the attached Contractor’s Proposal. Travel time for both labor and equipment between small projects that are completed during the same day will be compensated at the labor rate for each trade, at the equipment rate for equipment transported under its own power and at the truck-trailer or special vehicle rate for equipment that is hauled. Stand-by time for equipment, trucks, trailers or special vehicles will not be paid. Unless otherwise authorized, only vehicles with

Contractor decals or vehicles used for hauling equipment and/or significant materials for use in a project will be measured for payment.

TOOLS

For the purposes of this contract, TOOLS are defined as all hand tools or other miscellaneous items needed to complete the work which can be easily moved by an able-bodied person and are not operated by an electric or fuel drive motor as indicated in the manufacturer’s instructions. Smal pneumatic, electric or battery powered tools, such as drills, grinders, impact wrenches and carpentry saws, shovels, trowels, hand wrenches, hammers, ladders, wheelbarrows, gloves, safety items and similar items are considered TOOLS. Payment shall not be made for any tools used during this contract. Trench boxes, tapping equipment, vibratory compactors and other related items are not considered tools and shall be paid for as EQUIPMENT.

MATERIALS

All materials used in this contract shall meet the satisfaction of the Water Department designee.

Prior to obtaining materials for each location, the Contractor shall obtain the Water Department designee approval of the size, type and quality or grade of all anticipated materials. All materials shall be paid on a cost-plus markup basis. Material markup will be 5%. Actual cost shall be substantiated with a supplier invoice. Cost for small material quantities that the Contractor may have in stock can be substantiated by providing a supplier quote. In general, small Contractor provided material quantities shall consists of items the Contractor has in stock at the time work is being performed.

OFF-SITE REPAIRS

Repair of equipment or other components that are performed by an off-site repair facility may be performed under this Contract. The Contractor shall be compensated for required off-site repair services on a cost-plus markup basis. Off-site Repairs markup will be 5%. All repair services shall pre-approved by the Water Department designee. The invoice requirements described in the

Materials Special Provision shall apply. Please note that repair work that is not performed on-site is not required to comply with the Prevailing Wage requirements. Prevailing wage requirements are applicable for delivery and pick-up from the off-site repair facility.

SUBCONTRACTORS

Specialty work that cannot be readily performed by the Contractor can be completed by a subcontractor. The Contractor shall be compensated for subcontractor services on a cost-plus markup basis. Subcontractor markup will be 5%. All subcontractor services and costs shall be pre-approved by the Water Department designee per work location. The invoice requirements described in the Materials Special Provision shall apply. Prevailing wage requirements and certified payroll submittals are applicable for all subcontractor services.

In lieu of a paying for subcontractor work on a cost plus markup basis (subcontractor invoice), the

City, at its sole discretion, may require that subcontractor work be paid on a time and material basis with LABOR to be paid per Article 109.04(b) (1) & (2) of the Standard Specifications for Road and

Bridge Construction, except the allowed markup in 109.04 (b)(1) shall be 10% instead of 35%.

MATERIAL is to be paid per these Special Provisions, and EQUIPMENT is to be paid per these

Special Provisions. If any labor required to complete the work by a subcontractor is a “Labor/Item” included in the “Contractor’s Proposal”, the contractor, who utilizes the services of a subcontractor shall be paid for the “Labor” as bid in the schedule without further markup or other compensation unless the City elects to pay for LABOR per Article 109.04(b) (1) & (2) of the Standard

Specifications for Road and Bridge Construction, except the allowed markup in 109.04 (b)(1) shall be 10% instead of 35%.

PROFESSIONAL CERTIFICATIONS & OFFICE TIME

Professional Engineering and/or testing services may be required for Clean Construction or

Demolition Debris (CCDD) certifications and disposal, trench shoring and safety investigations and other observation or inspection needs. The City shall provide indication of potentially impacted properties for each excavation location. Sampling, testing, and certification, as necessary, will be the responsibility of the Contractor as the source site operator. As required, the Contractor shall retain the services of an environmental sampling and testing company for this work.

The Contractor shall be compensated for required engineering services and material testing and other external services, such as railroad crossing insurance and waste disposal fees, on a cost-plus markup basis. Engineering services, material testing and other external services markup will be 5%.

Subcontractors and equipment haulers are not considered external services. Labor, equipment and materials utilized by an equipment hauler or subcontractor shall be paid to the Contractor in accordance with the Special Provisions for these items. Clerical, ac- counting and all other office related activities performed relative to this contract will not be paid and shall be incidental to the

Contract. All Engineering, material testing and other external services, including company and personnel utilized, shall preapproved by the City and a report shall be provided to the City for all certifications performed during this contract. The invoice requirements described in the Materials

Special Provision shall apply.

REMOVAL AND DISPOSAL OF SURPLUS AND UNSUITABLE MATERIALS

The Contractor shall dispose of all surpluses, unstable or unsuitable materials in such a manner that public or private property will not be damaged or endangered. Suitable earth, stones or boulders naturally occurring within the right-of-way or on the project site may be placed in fills or embankments within the project in layers and compacted in accordance with the project specifications. Broken concrete without protruding metal bars, bricks, rock, stone, uncontaminated dirt and sand generated from construction or demolition activities may be used in embankment or in fill. If used in fills or embankments, these materials shall be placed and compacted to the satisfaction of the City of Bloomington or its assigned representative, shall be buried under a minimum of 600 mm (2 feet) of earth cover (except when the materials include only uncontaminated dirt); and shall not create an unsightly appearance or detract from the natural topographic features of an area. Broken concrete without protruding metal bars, bricks rock or stone may be used as rip rap as approved by the City of Bloomington or its assigned representative.

Aside from the materials listed above, all other debris or waste shall be disposed of in a licensed landfill, recycled, reused or otherwise disposed of as allowed by State or Federal solid waste disposal laws and regulations and solid waste determinations of the Illinois Environmental

Protection Agency. The contractor shall not conduct any generation, transportation, or recycling of construction or demolition debris, clean or general or uncontaminated soil generated during construction, remodeling, repair, and demolition of utilities, structures and roads that is not commingled with any waste, without the maintenance of documentation identifying the hauler, generator, place of origin of the debris or soil, the weight or volume of the debris or soil, and the location, owner, and operator of the facility where the debris or soil was transferred, disposed, recycled or treated. This documentation must be maintained by the Contractor for 3 years.

When surplus excavated material is disposed of off the right-of-way or project site, the Contractor shall obtain and file with the City of Bloomington permission in writing, from the property owner, for the use of the property for this purpose. Any such disposal shall not create an unsightly or objectionable appearance or detract from the natural topographic features, nor be placed at an elevation higher than that of the adjacent roadway without permission from the City of

Bloomington. The Contractor shall place no material as fill in any known flood way or flood plain without first obtaining the proper permits from the appropriate local, state, and federal agencies.

The Contractor shall comply with the Illinois Environmental Protection Agency’s Clean

Construction or Demolition Debris (CCDD) Requirements, including 35 Illinois Administrative

Code 100. The City shall provide indication of potentially impacted properties for each excavation location. Disposal, sampling, testing, and certification, as necessary, will be the responsibility of the

Contractor as the source site operator.

*** END OF SPECIAL PROVISIONS ***