Past_Performance_Questionnaire_Fall_Arrest_System.pdf
PDF 45 KB Posted
- Attached to
- Indoor Firing Range Maintenace/Cleaning Federal contract opportunity
- Solicitation number
- BEP-RFQ-16-0943
About this file
Past Performance Questionnaire
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage_Determination_4-19-16.pdf | ||
| BEP-RFQ-16-0943_Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAST PERFORMANCE QUESTIONNAIRE
A. GENERAL INFORMATION:
Contractor’s Name: ____________________ Telephone Number: ____________________ Address: __________________________ Fax Number: _________________________ __________________________ Point of Contact: ______________________
Project Title and Brief Description of Work: _____________________________________*
Contract Number Provided by Offeror: ___________________ Dollar Amount: __________*
Contract Period or Dates of Performance Provided by Offeror: ________________________* Contractor performed as the Prime Contractor Sub-Contractor Key Personnel.
* Note: If offeror holds or has held other contracts with your agency/organization in the last 3 years, please complete separate evaluation forms for those contracts as well.
B. RESPONDENT INFORMATION:
Name of Respondent: _____________________ Title: ____________________________
Address: _____________________ Telephone Number: ___________________ _____________________________ Fax Number: _____________________ _____________________________ Email Address: _____________________
C. E-MAIL COMPLETED SURVEY FORM TO:
Julius Herbert Contract Specialist 14th and C Streets, SW Office of Acquisitions Bureau of Engraving and Printing Washington, DC 20228
E-mail: julius.herbert@bep.gov Please provide your timely response by COB on 5 August 2016.
mailto:julius.herbert@bep.gov
D. PERFORMANCE INFORMATION: Choose the appropriate letter on the scale (E, G, S, M, U, and N) that most accurately describes the contractor’s performance or situation. PLEASE
PROVIDE A NARRATIVE EXPLANATION FOR YOUR RATINGS.
E G S M U N Exceptional Good Satisfactory Marginal Unsatisfactory Neutral
Performance meets contractual requirements with many exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than a few minor problems for which corrective actions taken by the contractor were highly effective.
Performance meets contractual requirements with some exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than some minor problems for which corrective actions taken by the contractor were effective.
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Performance does not meet some contractual requirements.
The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
does not meet most contractual requirements and recovery is not likely in a timely manner.
The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
was not observed or not applicable to the current effort being reported against.
CONTRACTOR’S NAME: _______________ CONTRACT NUMBER: _______________
Place an “X” in the appropriate column using the definitions matrix above.
The contractor: E G S M U N
1. Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
2. Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.
3. Delegated authority to project managers and supervisors commensurate with contract requirements.
4. Home office participated in solving significant local problems.
The contractor: E G S M U N
5. Followed approved quality control plan.
6. Provided effective quality control and/or inspection procedures to meet contract requirements.
7. Corrected deficiencies in timely manner and pursuant to their quality control procedures.
8. Provided timely resolution of contract discrepancies.
9. Identified problems as they occurred.
10. Suggested alternative approaches to problems.
11. Displayed initiative to solve problems.
12. Developed realistic progress schedules.
13. Met established project schedules.
14. Provided timely resolution of warranty defects.
15. Was responsive to contract changes.
16. Provided adequate project supervision.
17. Obtained consent of surety for increases in bonding as work-in-progress increased.
18. Paid subcontractors/suppliers in a timely manner.
19. Provided accurate and complete line item cost proposals including all aspects of work required for each task.
20. Cooperated with Government personnel after award.
21. How would you rate the contractor's overall performance?
22. Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”
YES/NO
23. Would you award another contract to this contractor? If not, explain in “remarks.”
YES/NO
CONTRACTOR’S NAME: ___________________ CONTRACT NUMBER __________
Remarks:______________________________________________________________________
File details come from the government source that posted it. Updated .