About this file

This is a Request for Proposal (RFP #27010) issued by Greenville County Parks, Recreation & Tourism in South Carolina for the renovation of two outdoor basketball courts located at Slater Hall Community Center and Welcome Park. The project encompasses crack repair, asphalt overlay, court resurfacing, goal system replacement, and court painting and striping at both locations. At Slater Hall Community Center (5 Whitney St, Slater, SC 29683), the scope includes renovating two half courts totaling 95'x100' and converting them into one full basketball court, one pickleball court, two four-square courts, and two hopscotch games. At Welcome Park (5 York Drive, Greenville, SC 29611), the scope includes complete demolition of existing paved surfaces (approximately 4,116 square feet of basketball court and 7,502 square feet of tennis court), constructing one new full-size basketball court with 95'x60' asphalt surface, and reseeding disturbed areas with grass. The RFP was issued on August 14, 2026, with a proposal submission deadline of September 15, 2026 at 3:00 pm. Non-mandatory pre-proposal meetings and site visits are scheduled for September 2, 2026 at 11:00 am (Slater Hall) and 1:30 pm (Welcome Park). The question submission deadline is September 8, 2026 at 2:00 pm. Award is anticipated for September 29, 2026, with contract negotiations occurring September 30 through October 7, 2026, and the Notice to Proceed issued October 8, 2026. The contractor must complete the project within 180 days of the Notice to Proceed or 180 days of consistent working weather, with a maximum timeline of 90 days requested in the proposal.

Pricing must be submitted as a lump sum for each location covering all labor, materials, equipment, mobilization, disposal, and transportation. Pricing is based on payment terms of thirty days, with no consideration given to discounts for earlier payment. The contractor must obtain a bid bond equal to 5% of the bid price and a performance and payment bond equal to the total bid price before contract execution. The contractor must provide evidence of a General Contractor's License and any specialty licenses required for asphalt paving and court paint application, along with authorization to use specific equipment and materials, particularly the SportMaster ColorPlus Pro System (7.2% pigment by volume) for court resurfacing. Insurance requirements include comprehensive general liability ($1,000,000 per occurrence/$2,000,000 aggregate), automobile liability ($1,000,000 per occurrence), and statutory worker's compensation with employers liability coverage. The county will be named as an additional insured on all policies except worker's compensation and automobile liability. Proposals will be evaluated in five phases based on responsiveness to the RFP, experience with similar projects, anticipated timeline, cost, and references, with each phase weighted equally at 5 points. The contractor must provide at least three project references, including any South Carolina governmental entities when applicable, and certifications regarding compliance with South Carolina immigration reform requirements, PREA (Prison Rape Elimination Act), asbestos management, and ADA accessibility standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP #27010

Greenville County Issue Date: August 14, 2026

Procurement Services Division Opening Date: September 15, 2026

BASKETBALL COURT RENOVATIONS

RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:

https:// procurement.opengov.com/portal/greenvillecounty/greenvillecounty

Robert Brewer, NIGP-CPP, CPPO, CPPB

Procurement Services Division Director https://secure.procurenow.com/portal/%7bproject.government.code%7d

Greenville County

Basketball Court Renovations

I. Public Notice II. Introduction

III. Scope of Work IV. Instructions to Offerors V. General Information

VI. Insurance VII. Evaluation Phases

VIII. Bonds IX. Terms and Conditions X. Sample Contract

XI. Vendor Questionnaire XII. Pricing Proposal

Attachments:

A - COG Sub W9

B - Sample Services Agreement

C - Slater_Hall_Community_Center_Court_Photos_and_Drawings

D - Existing_Welcome_Park_Courts

E - Porter_Goal_post_installation_instructions

F - Welcome_Park_Photos_and_Measurements

G - Existing_Conditions_of_Slater_Hall_Community_Center_Basketball_Courts

H - Porter_Goal_post_installation_instructions

Title: Basketball Court Renovations

1. Public Notice

Greenville County is soliciting sealed proposals in response to Basketball Court Renovations, subject to the conditions and all provisions set forth herein and attached. Sealed proposals will be received through the County’s online procurement portal located at https://procurement.opengov.com/portal/greenvillecounty until Tuesday, September 15, 2026, 3:00 pm, then publicly opened. The goods and/or services must be furnished as described and specified herein and submitted to Greenville County.

All inquiries regarding this proposal shall be submitted no later than Tuesday, September 8, 2026, 2:00 pm via the County’s online procurement Portal, located at https://procurement.opengov.com/portal/greenvillecounty. Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the County’s online procurement Portal. Offerors may also click “Follow” on this proposal to receive an email notification when answers are posted. It is the responsibility of the Offeror to check the website for answers to inquiries.

https://secure.procurenow.com/portal/greenvillecounty

2. Introduction

2.1. Summary

Greenville County Parks, Recreation &Tourism is seeking qualified vendors to renovate two outdoor basketball courts at two county parks - Slater Hall Community Center and Welcome Park.

Slater Hall Community Center, located at 5 Whitney St, Slater, SC 29683, currently has 2 half basketball courts - total court area is 95'x100'. Renovation includes tar repair of cracks, asphalt overlay, court resurfacer, goal system replacement and court paint and striping.

Welcome Park, located at 5 York Drive, Greenville, SC 29611, currently has one basketball court and one old tennis court. Renovation includes complete demolition of all paved surface, constructing one new full size basketball court with painting and striping, and establishing grass in affected areas.

2.2. Contact Information

Anthony Dawson

Buyer

301 University Ridge, Suite N-2400

Greenville, SC 29601

Email: adawson@greenvillecounty.org

Phone: (864) 467-4954

Department:

PARKS ADMINISTRATION

2.3. Timeline

Release Project Date August 14, 2026

Pre-Proposal Meeting (Non-Mandatory) September 2, 2026, 11:00am

Two Non-Mandatory Pre-Proposal Meetings will be held as follows: -

Slater Hall Community Center, located at 5

Whitney St, Slater, SC 29683, on September 2, 2026 at 11:00 AM EST

AND

Welcome Park, located at 5 York Drive, Greenville, SC 29611, on September 2, 2026 at 1:30 PM EST

Question Submission Deadline September 8, 2026, 2:00pm mailto:adawson@greenvillecounty.org tel:(864)467-4954

Proposal Submission Deadline September 15, 2026, 3:00pm

Review of Proposals September 16 - September 27

Tentative Date of Award September 29, 2026

Contract Negotiations September 30 - October 7

Issue Notice to Proceed October 8, 2026

3. Scope of Work

3.1. General Requirements

The Scope of Work for this project consists of renovating the existing basketball courts at Slater Hall

Community Center and Welcome Park. To meet these requirements, the Awarded Contractor shall:

A. Complete this project within 180 days of issuance of the Notice to Proceed or 180 days of consistent working weather.

B. Provide evidence of the General Contractor's License or any specialty licenses required to complete this project, such as Asphalt Paving and Court Paint application.

C. Furnish all materials, equipment, machinery, tools, apparatus, means of transportation, licenses and labor necessary to prepare the court for repairing cracks, resurfacing, goal post removal and installation, and painting of the courts. Goal systems including post, backboard, rim and net to be provided by County.

D. Repair all cracks using hot tar/rubber mix or approved equivalent and resurface the basketball ball courts in accordance with manufacturer's specifications.

1. Vendors must be authorized to use the proposed equipment and must provide evidence of the same with their proposal.

2. Requests for substitutions must be submitted for the County's consideration, in accordance with the Substitution section below.

E. Repaint and line all courts using SportMaster ColorPlus Pro System (7.2% pigment by volume), in accordance with manufacturer's specifications.

1. Vendor's must be authorized to utilize the SportMaster System and shall provide evidence of the same with their proposal.

2. Requests for substitutions for the SportMaster System must be submitted for the County's consideration, in accordance with the Substitution section below.

3.2. Substitutions

Any references to brand-specific products throughout this RFP are intended to serve only as a guide;

the County may consider substitutions where brand-names are specified, if the Contractor can demonstrate that proposed substitutions meet or exceed the specifications provided. The process is as follows to have the County consider substitutions for brand-specific products specified in this RFP:

A. Proposers must submit their request for substitutions to the County for consideration as a

"question", prior to the Questions and Answers Deadline noted on the Timeline.

B. The County will determine whether the substitution is acceptable, and respond to all requests for substitutions (received before the deadline) in the Questions and Answers Document.

3.3. Slater Hall Community Center Basketball Court Paving and Repair

To successfully achieve the desired outcome for repairing and resurfacing the courts, the Awarded

Contractor shall:

A. Remove current basketball goal systems (posts, backboard, rim and nets) and dispose of off-site.

B. Prepare disturbed area for repaving overlay by milling base and/or clean and fill cracks with a hot tar/rubber mixture. The County estimates that roughly 2000 linear feet of cracks or seams in need of repair; all measurements shall be independently verified by the Contractor.

C. Install asphalt overlay across the entire court surface at 1.5” thick, level without ponding after

24 hours to minimum slope of 0.833% and maximum slope of 1%.

3.4. Slater Hall Community Center Basketball Court Resurfacing

The Awarded Contractor shall construct the basketball courts in accordance with requirements specified in this RFP.

A. Resurface all courts using the SportMaster ColorPlus Pro System, or approved equivalent, in accordance with the following specifications:

1. Courts shall be cleaned using a stiff bristle broom and gas-powered blower or water-based pressure spray unit capable of generating 2500 PSI at the nozzle tip, to remove all dirt and debris.

2. All coatings shall be pure 100% acrylic, containing no asphaltic or tar emulsions, not any vinyl, alkyd or non-acrylic resins.

3. The color system shall be field-mixed as per manufacturer’s specifications, to meet the requirements of the ColorPlus Pro System (7.2% pigment). All materials shall be delivered to the jobsite in sealed containers with the manufacturer’s label affixed.

4. The surface to be coated shall be inspected and made sure to be free of grease, oil, dust, dirt and other foreign matter.

5. The surface shall be flooded. Any ponding water remaining that is deep enough to cover the thickness of a five-cent piece (nickel) shall be corrected.

6. Application shall proceed only if the surface is dry and clean and the air and surface temperature is at least fifty degrees (50°F) and rising during application and for at least 24 hours after. Do not apply if the surface temperature exceeds one hundred forty degrees

(140°). Do not apply coating when rain is imminent.

7. Each coat in the system must dry completely before the next application. Between each coat, inspect entire surface. Any defects should be repaired. Scrape surface to remove any lumps, and broom or blow off all loose matter.

8. Using a neoprene rubber squeegee, apply two (2) coats of SportMaster Acrylic Resurfacer, mixed and diluted per manufacturer’s specifications. Sand gradation shall be 50 to 60-mesh.

Allow each application to dry thoroughly.

9. Using a neoprene rubber squeegee, apply two (2) coats of SportMaster ColorPlus Pro

System, per manufacturer’s specifications. Allow each application to dry thoroughly.

B. Convert the existing two (2) half courts into one (1) full sized basketball court and the second half of the court into a pickleball court and other court games. See Attachments Slater Hall

Community Center Court Photos and Drawings

A. Key & Center Circle – color: SportMaster ColorPlus Pigment: Blue

B. Inside Basketball Playing Surface – color: SportMaster ColorPlus Pigment: Forest Green

C. Outside Basketball Playing Surface – color: SportMaster ColorPlus Pigment: Forest Green

D. Outside Pickleball Playing Surface - color: SportMaster ColorPlus Pigment: Forest Green

E. Inside Pickleball Playing Surface – color: SportMaster ColorPlus Pigment: Blue

F. Inside Four-square Court Playing Surface – color: SportMaster ColorPlus Pigment: Blue and

Forest Green in opposite opposing corners

G. Inside Hopscotch Playing Area – color: SportMaster ColorPlus Pigment: Forest Green

H. All Court Lines – color: SportMaster Textured White Line Paint

C. Prepare and paint the white lines for basketball on one (1) full Basketball Court, one (1)

Pickleball Court, two (2) Four-square Courts, and 2 Hopscotch games upon completion and

County acceptance of the court surface.

1. All lines must be applied by painting between masking tape with a paintbrush or roller.

D. Dimensions shall meet the specifications attached herein.

1. One Full Basketball Court: 84’x50’

2. One Pickleball Court: 20’x44’

3. Two Four-square games: 16’x16’

4. Two Hopscotch

3.5. Welcome Park Existing Court Removal and New Paving

A. Remove current basketball goal systems (posts, backboard, rim and nets) and dispose of off-site.

B. The County estimates 4,116 sq. feet of basketball court and 7,502 sq. feet of tennis court to be removed; all measurements shall be independently verified by the Contractor.

C. Existing surface area to be removed - dug up, and disposed of. This asphalt is compromised by age and existing tree roots. Area shall be leveled to new playing surface edge and stabilized with contractors blend grass, seed matting, or equivalent.

D. Remove broken asphalt from site and dispose of properly. Demolish existing water fountain and benches.

E. Install stone base for new asphalt section - minimum 4" thick compacted base course.

F. Pave overlay across entire court surface at 2" thick, level without ponding after 24 hours.

Minimum slope 0.833%, maximum slope 1%.

G. Finished surround surface must be level with new overlay. Excavated material must be disposed off-site unless used to level slope along new playing surface edge to ground level and stabilized.

H. 1 - Basketball court should measure 84'x50' of playing surface with a 95'x60' of physical asphalt surface

I. The rest of the disturbed area will be reseeded into an open grass field with contractors blend grass.

J. Resurface all courts using the SportMaster ColorPlus Pro System, or approved equivalent, in accordance with the following specifications:

o Courts shall be cleaned using a stiff bristle broom and gas powered blower or water based pressure spray unit capable of generating 2500 PSI at the nozzle tip, to remove all dirt and debris.

o All coatings shall be pure 100% acrylic, containing no asphaltic or tar emulsions, not any vinyl, alkyd or non-acrylic resins.

o The color system shall be field-mixed as per manufacturer’s specifications, to meet the requirements of the ColorPlus Pro System (7.2% pigment). All materials shall be delivered to the jobsite in sealed containers with the manufacturer’s label affixed.

o The surface to be coated shall be inspected and made sure to be free of grease, oil, dust, dirt and other foreign matter.

o The surface shall be flooded. Any ponding water remaining that is deep enough to cover the thickness of a five-cent piece (nickel) shall be corrected using a patch mix consisting of

Acrylic Patch Binder, 50-mesh sand and Portland cement, as per manufacturer’s directions.

Depressions must be primed with 50% dilution of Acrylic Patch Binder and water prior to patching. The Project Manager for the County, or his designee, shall be on site during this process.

o Application shall proceed only if the surface is dry and clean and the air and surface temperature is at least fifty degrees (50°F) and rising during application and for at least 24 hours after. Do not apply if the surface temperature exceeds one hundred forty degrees

(140°). Do not apply coating when rain is imminent.

o Each coat in the system must dry completely before the next application. Between each coat, inspect entire surface. Any defects should be repaired. Scrape surface to remove any lumps, and broom or blow off all loose matter.

o Using a neoprene rubber squeegee, apply two (2) coats of SportMaster Acrylic Resurfacer, mixed and diluted per manufacturer’s specifications. Sand gradation shall be 50 to 60-mesh.

Allow each application to dry thoroughly.

o Using a neoprene rubber squeegee, apply two (2) coats of SportMaster ColorPlus Pro

System, per manufacturer’s specifications. Allow each application to dry thoroughly.

o Prepare and paint white lines for basketball on one (1) Full Basketball Court 84'x50' o All lines are to be applied by painting between masking tape with a paintbrush or roller.

▪ Key & Center Circle – color: SportMaster ColorPlus Pigment: Blue

▪ Inside Basketball Playing Surface – color: SportMaster ColorPlus Pigment: Forest Green

▪ Outside Basketball Playing Surface – color: SportMaster ColorPlus Pigment: Forest Green

3.6. Goal System Installations

The County desires to provide the Awarded Contractor with two (2) goal systems at Slater Hall

Community Center and two (2) goal systems at Welcome Park; the specifications are as follows:

A. Install the provided equipment and footings in accordance with the attached specifications for the Porter Goal post installation instructions.

B. Obtain approval from the County designated project manager or their designee for Post Footing installations prior to concrete being poured.

4. Instructions to Offerors

4.1. Pre-Proposal Meeting

A Non-Mandatory Pre-Proposal meeting will be held at the date and time specified in the Timeline. A site visit will follow. Vendors are encouraged to RSVP for the meeting through the OpenGov portal. The

RSVP link is in the header of the solicitation.

4.2. Pricing

Pricing must be based upon payment in thirty (30) days. Discounts for payment in less than thirty (30) days will not be considered in making award.

Discounts shall be stated in proposals as a percentage. Time in connection with discount offered will be computed from date of delivery of commodities to carrier, when inspecting and acceptance is at point of origin; or date of delivery at destination; or if laboratory inspection is made part of bid, from date of laboratory report.

Unit pricing will govern over extended pricing, unless stated otherwise. Pricing shall include packing.

Unless indicated by County, pricing must be firm.

Vendors shall enter pricing in the Pricing Proposal section.

4.3. Bonding

Bonding will be required for this project. See Bonds section for the requirements.

4.4. Statement of Qualifications

Vendor shall include the following with their response:

A. Company Overview and Background

B. Corporate/Individual Qualifications and Experiences, including certifications

C. Project References - List of at least three (3) references including names, addresses, and telephone numbers of current or previous customers. Vendor should include any South Carolina governmental entity reference.

D. Scope of Work Understanding - Task list demonstrating comprehension of project requirements and proposed implementation steps

E. Project Schedule - Proposed timeline from Notice to Proceed through Final Acceptance (90-day maximum)

4.5. Submission Procedures and Requirements

A. All submissions must be received by Tuesday, September 15, 2026 at 3:00 pm. Submissions will not be accepted after the deadline. There will be no exceptions. Responders submitting https://procurement.opengov.com/governments/864/projects/290094/builder/create/document-editor?activeSection=9 https://procurement.opengov.com/portal/greenvillecounty/projects/290094/document?section=2794360 proposals shall be responsible for all cost of preparing such proposals. Information requested and not received at the time of submission may disqualify the submitted proposal.

B. Responders to this solicitation shall closely examine the specific requirements noted herein and the attached Terms and Conditions. Facsimile transmittals, hard copies, emails or offers communicated by telephone will not be accepted or considered.

C. Proposals shall be organized in the following manner with the subject headings and sequence indicated.Section 1: Statement of QualificationsCompany overview and background

Corporate qualifications, experience, and certifications

Minimum 3 project references (include SC governmental entities if applicable)

Evidence of understanding project scopeSection 2: Technical ApproachScope of Work demonstration showing understanding of:Court surface preparation, cleaning, and crack repair requirements

Asphalt overlay and paving requirements (Welcome Park removal/repaving)

Resurfacing and acrylic color coating application specifications

Court striping requirements (basketball, pickleball, four-square, hopscotch)

Basketball goal system installation

Project Timeline demonstrating completion within 90 calendar days from Notice to Proceed

Work sequence and phasing plan for each court type

Weather contingency plan and mitigation strategies

Quality assurance proceduresSection 3: Material Specifications & SubstitutionsMaterial substitution requests (if any) with comparison documentation

Manufacturer certifications (if applicable)

Compliance with 100% acrylic requirement for court coatings (no asphaltic, tar, vinyl, or alkyd resins)Section 4: Business DocumentationBusiness licenses and certifications

Insurance certificates

Acknowledgment that the selected contractor shall obtain all applicable licenses and permits, and promptly pay all applicable taxes required by the State of South Carolina and/or Greenville

CountySection 5: PricingCompleted Pricing Proposal Form (provided electronically)Proposals shall be organized in the following manner with the subject headings and sequence indicated.

4.6. Inquiries and Addenda

Offerors shall submit all inquiries regarding this RFP via the County’s online procurement Portal, located at https://procurement.opengov.com/portal/greenvillecounty. Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the County’s online procurement Portal. Offerors may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries. The County will not be responsible for or bound by any oral instructions made by any employee(s) of the County in regard to this RFP.

https://procurement.opengov.com/governments/864/projects/290094/builder/create/document-editor?activeSection=9

Addenda Notification: This RFP represents the most definite statement Greenville County will make concerning information upon which proposals are to be based. Offerors are required to register for an account via the County’s online procurement Portal hosted by OpenGov. Once you have completed the registration, you will receive addenda notifications to your email by clicking “Follow” on this project.

Ultimately, it is sole responsibility of each proposer to periodically check the site for any addenda at https://procurement.opengov.com/portal/greenvillecounty. No addenda will be issued later than five

(5) working days prior to the date for receipt for proposals except an addendum which, if necessary, postpones the date for receipt of proposals or cancels this RFP. Vendors shall acknowledge receipt of all addenda.

5. General Information

A. Proprietary Information – The County of Greenville is a public body and governed by the South

Carolina Freedom of Information Act. Documents submitted to the County relating to this

Solicitation are subject to requirements of the Freedom of Information Act and may be deemed public records.

B. Errors and Omissions – The Responder will not be allowed to take advantage of any errors or omissions in the Request for Proposals. Where errors or omissions appear in the RFP, the

Responder shall promptly notify the County of Greenville in writing of such error or omission it discovers. Any significant error, omission and/or inconsistency in the specifications are to be reported as soon as possible but no later than five (5) days before such time the response is to be submitted.

C. Withdrawal of Proposal – An official representative of a Responder may withdraw a

Responder’s response at any time prior to the proposal submission deadline. Acceptable proof establishing that he/she is the representative of the Responder must be provided.

D. Non-Endorsement – If the County awards a contract, the successful Responder shall not issue any news release or other statement relating to the award or servicing of the agreement which state or imply the County of Greenville’s endorsement of the successful Responder’s services.

6. Insurance

6.1. Insurance Requirements

The contractor is responsible for and must have all required insurance listed below and shall not commence work under the associated contract until it has obtained all insurance required, and the

County has approved such insurance in writing, nor shall the Contractor allow any subcontractor to commence work on its subcontract until all similar insurance required of the subcontractor has been obtained. All insurance policies shall be maintained for the life of the contract.

A. THE COUNTY SHALL BE NAMED AS “ADDITIONAL INSURED” FOR ITS INTERESTon all policies of insurance except Worker’s Compensation, Automobile Liability, and Professional Errors and

Omissions, as regards ongoing operations, products and completed operations, and this shall be noted on the face of the Certificate of Insurance. As a part of the certificate of insurance requirement the contractor shall also include acknowledgement and acceptance of the wavier of subrogation provision granted to Greenville County. This acknowledgement and acceptance should be included in the same section of the Certificate of Insurance that evidences the

“Additional Insured” provision.

B. Certificates for all such policies of insurance shall be provided by the Contractor's insurance agent or broker to the County within 10 working days from the date of Notice of Award.

C. All Certificates of Insurance submitted shall provide on the face of the certificate reference to

County's RFP #RFP #27010.

D. Contractor will provide County a minimum of 30 days advance notice in the event the insurance policies (or an insurance policy) are canceled. Subcontractors approved to perform work on this project are subject to all of the requirements in this Section.

E. Contractor agrees to maintain and keep in force during the life of this Agreement, with a company or companies authorized to do business in South Carolina, the following insurance policies:

1. Comprehensive General Liability:

a. $1,000,000 per occurrence - combined single limit /

b. $2,000,000 general aggregate, to include products and completed operations.

2. Automobile Liability:

a. $1,000,000 per occurrence - combined single limit (Coverage shall include bodily injury and property damage and cover all vehicles including owned, non-owned and hired)

3. Statutory Worker's Compensation:

a. Coverage A - State of SC

b. Coverage B - Employers liability

i. $1,000,000 Each Accident

ii. $1,000,000 Disease, Per Employee

iii. $1,000,000 Disease, Policy Limit

c. Policies shall contain a waiver of subrogation in favor of and/or that applies to

Greenville County, its departments, agencies, boards, employees, and commissions for losses from work performed by or on behalf of the contractor.

No deviation from this coverage’s will be accepted unless, in the County’s sole discretion, it is more advantageous to the County, i.e., $1,000,000 - a $2,000,000 or $5,000,000 limit would be acceptable.

7. Evaluation Phases

The proposals will be evaluated on the following criteria. Greenville County reserves the right to interview responders or have demonstrations to this RFP at its discretion. Greenville County will not be responsible for any costs associated with interviews of responders or demonstrations. If interviews or demonstrations are needed, a second phase of the evaluation process may be implemented at the

County's discretion. Point values are described below.

5 = High

4 = Medium High

3 = Average

2 = Medium Low

1 = Low

0 = Non-Responsive

7.1. Phase 1

No. Evaluation Criteria Scoring Method Weight (Points)

1. Responsiveness to RFP 0-5 Points 5 (100% of Total)

7.2. Phase 2

No. Evaluation Criteria Scoring Method Weight (Points)

1. Experience with Projects of Similar Size and

Scope 0-5 Points 5

7.3. Phase 3

1. Anticipated Timeline 0-5 Points 5

7.4. Phase 4

1. Cost 0-5 Points 5

7.5. Phase 5

1. References 0-5 Points 5

8. Bonds

8.1. Bid Bond:

This project requires a Bid Bond and a Performance/Payment Bond. Proposers shall submit with their proposal, a Bid Bond in the amount of 5% of the bid price. This bond may be in the form of Bid Bond from the American Institute of Architects (AIA), electronically through Surety 2000, Certified Check, Cashier’s or Bank Money Order of any national or state bank and shall be made payable to Greenville

County. Proposals submitted without being accompanied by any of the foregoing as required, may be considered informal and may be rejected. Any proposal accompanied by a bid bond not properly executed in the opinion of the County Attorney, may be rejected. The bond will be forfeited to the

County by the successful bidder as liquidated damages in case a proposal award is made to that bidder and the contract and bond are not promptly and properly executed.

1. Instructions for Bond through AIA or similar bond document: The Original (hard- copy) Signed-Bid

Bond must be delivered to the Procurement Services Office by the Bid Due Date/Time specified. The

Bid Bond must be submitted in a sealed-envelope to: Greenville County Procurement Services Division;

301 University Ridge, Suite N-2400; Greenville, SC, 29601. The following information must be included, on the outside of the envelope:

A. “Bid Bond” (labeled)

B. Bid Number

C. Company Name

2. Instructions for Surety2000:

The County has an account with an online Bid Security program called Surety2000. This is a fee-based program that bidders can use to obtain an electronically issued, verified and legal bid bond which can be used for bidding purposes. No bid bond can be created by the bonding agent on the site without the

Surety being fully aware of that bond. Only agents appointed directly by the Surety can issue bid bonds on the site.

If your company chooses to use Surety2000 to obtain the bid bond, please access Surety2000 at www.surety2000.com. Complete the necessary steps to log in to the site and obtain the bid bond.

Bond Identifier: RFP #27010

USE THIS CODE WHEN ACCESSING SURETY2000

Once an official bid bond is issued, use the space below to input your company's E-Bond Serial Number.

The number will look something like this: SNJ5185268

This number will then be used at the bid opening to verify your company's bid bond.

If you are not using this method for Bid Security submission please write "N/A" in the field provided.

Please note that the County is not responsible for late submissions and no consideration will be made for bid security received after the date and time stipulated in the Notice to Bidders even if you have electronically submitted your bid on time.

If the original bid security is not able to be verified by the date and time stipulated in the Notice to

Bidders, your submission will be rejected.

If required per solicitation and after proposals are awarded, the Procurement Services Division will return immediately all checks, except that of the successful bidder. The check of the successful bidder will be returned upon compliance with the performance and payment bond requirements.

If required per solicitation, the successful bidder, within fifteen (15) working days after acceptance of the bidder’s offer by the County, shall furnish a satisfactory performance and payment bonds in the amount of the total bid price. The performance and payment bonds must be received by the county prior to issuance of an executed contract and Notice to Proceed. The fifteen (15) working days may be extended upon written approval by the Procurement Director. A copy of the written approval shall be transmitted to the successful bidder stating the terms of any extension. In the event that the bidder fails to deliver to the County Procurement Services Division the performance and payment bonds in said period of fifteen (15) working days after acceptance of the bidder’s offer by the County, then the bid bond of the bidder shall be retained by the County in its entirety and the award will be withdrawn from the bidder. The successful bidder shall have as surety a corporate surety authorized to act as surety in

South Carolina. The Performance and Payment Bonds will insure that the successful bidder will promptly make payments to all persons supplying labor or materials to the bidder; and shall guarantee to indemnify and save the County, its officers, divisions, and employees harmless from all costs, damages, and expenses growing out of or by reason of the successful bidder’s failure to comply and perform the work and complete the contract in accordance with the specifications in the matter of making, furnishing and/or delivering said work or supplies. The Performance and Payment Bonds will be in effect for one year after completion of the contract.

If bonding is required per the solicitation, the bonding company must have an agent available to meet with County officials to clarify and explain the County’s responsibility in maintaining the integrity of the bond.

8.2. Return of Bid Bond:

After a contract is awarded, the Procurement Services Division will return immediately all checks, except that of the successful bidder. The check of the successful bidder will be returned upon compliance with the performance and payment bond requirements.

8.3. Performance and Payment Bond:

The successful bidder, within fifteen (15) working days after acceptance of the bidder’s offer by the

County, shall furnish a satisfactory performance and payment bonds in the amount of the total bid price.

The performance and payment bonds must be received by the county prior to issuance of an executed contract and Notice to Proceed. The fifteen (15) working days may be extended upon written approval by the Procurement Director. A copy of the written approval shall be transmitted to the successful bidder stating the terms of any extension. In the event that the bidder fails to deliver to the County

Procurement Services Division the performance and payment bonds in said period of fifteen (15) working days after acceptance of the bidder’s offer by the County, then the bid bond of the bidder shall be retained by the County in its entirety and the award will be withdrawn from the bidder. The successful bidder shall have as surety a corporate surety authorized to act as surety in South Carolina.

The Performance and Payment Bonds will insure that the successful bidder will promptly make payments to all persons supplying labor or materials to the bidder; and shall guarantee to indemnify and save the County, its officers, divisions, and employees harmless from all costs, damages, and expenses growing out of or by reason of the successful bidder’s failure to comply and perform the work and complete the contract in accordance with the specifications in the matter of making, furnishing and/or delivering said work or supplies. The Performance and Payment Bonds will be in effect for one year after completion of the contract.

8.4. Availability of Bonding Agency:

The bonding company must have an agent available to meet with County officials to clarify and explain the County’s responsibility in maintaining the integrity of the bond.

9. Terms and Conditions

9.1. Safety, Health, and Security

Contractor shall be solely responsible for its activities, that of its employees on the site and activities of its consultants, contractors and/or subcontractors for maintaining a safe job site. Contractor’s activities and activities of its consultants, contractors and/or subcontractors shall comply with all local, state, and federal safety regulations and their enforcement agencies. Contractor shall at all times conduct its operations under this Contract in a manner to avoid risk of endangerment to the health and safety of persons and property. The Contractor shall have sole responsibility for implementing its safety and health programs, taking all safety and health precautions necessary and continuously inspecting all equipment, materials and work to prevent, discover, determine and correct any conditions which might result in personal injury, equipment damage or damage to property or the public. Contractor’s safety, health and security programs shall be in compliance with all regulatory requirements and shall furnish accident, incident, injury, and other records and reports required by the Occupational Safety and Health

Administration, State and Local laws, or by the County.

9.2. Response Opening and Award:

Responses shall be publicly opened and only the names of the offerors disclosed at the opening. For

IFBs, the name of the responder as well as the price will be disclosed. However, no decision will be made until Procurement Services and the user Division have had ample time to review each response. Award will be made at the earliest possible date. The County reserves the right to award in whole or in part, by item, group of items, geographic area or by section where such action serves the County’s best interest.

The contract will be awarded to the response that meets the requirements and criteria set forth in the

Solicitation. No response may be withdrawn for a period of sixty (60) days after the opening date.

Submissions will not be accepted after the deadline. There will be no exceptions. By submission of a response, you are guaranteeing that all goods and services meet the requirement of the solicitation during the contract period.

9.3. Rights Reserved by Greenville County:

Greenville County reserves the right to reject any and all responses, any portion thereof, and waive any technicalities. Accordingly, the right is reserved to make awards in the best interest of the County.

Integrity, reputation, experience and past performance will be heavily weighed in response evaluation.

This solicitation does not commit the County of Greenville to award a contract, to pay any costs incurred in the preparation of the response, or to procure or contract for goods or services listed herein.

9.4. Responders Qualification:

Responders must, upon request of the County, furnish satisfactory evidence of their ability to furnish products or services in accordance with the terms and conditions of these specifications. The County reserves the right to make the final determination as to the responder’s ability to provide the products or services requested herein.

9.5. Responders Responsibility:

Each responder shall be fully acquainted with the conditions relating to the scope and restrictions attending the execution of the work under the conditions of this response. It is expected that this will sometimes require on-site observation. The failure or omission of a responder to be acquainted with existing conditions shall in no way relieve the responder of any obligations with respect to this response or to any contract as a result of this response.

9.6. References:

The County requires responders to list at least three (3) references including their company name, name of contact, address, telephone number, and email address of contact person with whom the responder has performed or provided similar work, service or product. The reference may be contacted to fill out a short questionnaire on the work with that company. If the reference does not complete the questionnaire by the time requested, the County may ask the responder to give an alternate reference.

The County asks that responders do not list County representatives or departments as a reference.

9.7. Waiver:

The County reserves the right to waive any Instructions to Responders, General or Special Terms and

Conditions, specifications, or technicalities when it is deemed to be in the best interest of the County to do so.

9.8. Rejection:

Greenville County reserves the right to reject any response that contains prices for individual items or services that are inconsistent or unrealistic when compared to pricing of like responses; or ambiguous responses which are uncertain as to terms, delivery, quantity, or compliance with specifications may be rejected or otherwise disregarded if such action is in the best interest of the County.

9.9. Response Signature and Solicitation Alterations:

The responder shall sign the response correctly or the response may be rejected. If the response shows any omissions, alteration of form, unauthorized additions, a conditional response or any irregularities of any kind, the response may be rejected.

9.10. Specification Changes, Additions and Deletions:

Responders are required to register for an account via the County’s online procurement Portal hosted by OpenGov. Once responder has completed registration, you will receive addenda notifications to your email by clicking “Follow” on this project. Ultimately, it is sole responsibility of each responder to periodically check the site for any addenda at https://procurement.opengov.com/portal/greenvillecounty.

The County of Greenville shall not be responsible for any verbal information given by any employees of the County of Greenville in regard to this proposal.

9.11. Response Changes:

Responses, amendments thereto or withdrawal requests received after the advertised time for response opening, shall be void regardless of when they were submitted.

9.12. Response Price:

The price presented as a result of these specifications shall be for the contract period. The response shall be acceptable for sixty (60) days from the date of opening. All prices and notations shall be printed in ink or typewritten. Errors should be crossed out, corrections entered and initialed by the person signing the response. Erasures or use of typewriter correction fluids may be cause for rejection. No response shall be altered or amended after specified time for opening.

9.13. Federal, State and Local Laws:

The contractor assumes full responsibility and liability for compliance with any and all local, state and federal laws and regulations applicable to the contractor and its employees including, but not limited to, compliance with the EEO guidelines, the Occupational Safety and Health Act of 1970, and minimum wage guidelines.

9.14. Tie Bids:

In the case of tie bids, the County reserves the right to make the award based on the factors outlined in

Section 7-305(9) of the Greenville County Code of Ordinance (Chapter 7, Article VIII), or in what it considers to be in the best interest of the County.

9.15. Deduction and Holdbacks:

In addition to the County’s right of termination, the County shall be entitled to full reimbursement for any costs incurred by the County by reason of the contractor’s failure to perform or to satisfactorily perform its responsibilities and duties. Such costs may include, but are not limited to, the cost of using the County’s employees or employees of any other entity to perform the obligations of the contract. The

County may obtain any such reimbursement by deduction from payments otherwise due to the contractor or by any other proper and lawful means. All deductions from any money due the contractor are to be as liquidated damages and not as a penalty. It is the County’s intent to give the contractor a reasonable opportunity whenever practicable, to correct any such failure to perform or satisfactorily perform its responsibilities and duties. In no circumstances shall any uncorrected situation extend for more than five days. The County will make the following deductions from the contract sum in the event that the contractor fails to perform any of the required work within the required time limits in the event the County carries out the work using its forces or another contractor.

A. For use of County’s forces – actual cost involved.

B. For use of another contractor – the amount charged by said contractor.

The County reserves the right to hold back and/or withhold part of complete payments for unsatisfactory work, deficiencies, etc. until said defects are satisfactorily corrected or cleared.

9.16. Evaluation Criteria:

The proposals will be evaluated using the criteria listed in the Evaluation Phases included in this RFP.

Greenville County reserves the right to interview responders or ask for demonstrations to this RFP at its discretion. Greenville County will not be responsible for any costs associated with interviews of responders or demonstrations.

9.17. Quality:

Unless otherwise indicated in this solicitation it is understood and agreed that any items offered or shipped on this solicitation shall be new and in first class condition unless otherwise indicated herein.

9.18. Affirmative Action - Small, Disadvantaged and Minority Businesses (SDMB):

A. Vendors submitting responses are encouraged to solicit small, disadvantaged and minority businesses participation in fulfilling their contract. Indicate in your response any SDMB areas of involvement for monitoring purposes.

B. The successful vendor will take affirmative action in complying with all Federal and State requirements concerning fair employment and treatment of all employees, without regard or discrimination by reason of race, color, religion, age, sex, national origin or physical handicap.

9.19. Default:

In case of default by vendor the County may procure the item or services from other sources and may recover the loss occasioned thereby from any unpaid balance due the vendor or by proceeding against the vendor’s performance bond, if any, and/or by suit against vendor.

9.20. Termination for Cause:

Any awarded contract is subject to termination for failure to comply with the specifications, terms and conditions by the County or the contractor upon written notice by registered mail. Such termination will be effective not less than ten (10) days nor more than sixty (60) days after receipt of such notice from the County nor less than thirty (30) days nor more than sixty (60) days after receipt by the County from the contractor. Receipt of notice by one party to terminate the contract will nullify any subsequent reciprocal notice by the receiving party prior to the announced termination date. In the event of termination, the County shall be responsible to pay the contractor only for work satisfactorily completed upon the effective date of termination and shall not be responsible for any other charges.

9.21. Termination for Convenience:

Greenville County may terminate for convenience any contract resulting from this solicitation by providing sixty (60) calendar days advance written notice to the vendor.

9.22. Non-Appropriation:

Any contract entered into by the County resulting from this solicitation shall be subject to cancellation without damages or further obligation when funds are not appropriated or otherwise made available to support continuation of performance in a subsequent fiscal period or appropriated year.

https://secure.procurenow.com/portal/greenvillecounty/projects/290094/document?section=2794359

9.23. Incorporation of Proposal into Contract:

The terms, conditions, and specifications of this proposal and the selected firm’s response are to be incorporated, in total, into the contract.

9.24. S.C. Law Clause:

Upon award of contract under this response, the person, partnership, association or corporation to whom the award is made must comply with the laws of South Carolina which require such person or entity to be authorized and/or licensed to do business with this State. Notwithstanding the fact that applicable statutes may exempt or exclude the successful bidder from requirements that it be authorized and/or licensed to do business in this State, by submission of this signed response, the responder understands and agrees to be bound to the jurisdiction and process of the courts of the State of South Carolina, as to all matters and conflicts or future conflicts under the contract and the performance thereof, including any questions as to the liability for taxes, licenses, or fees levied by the

State.

9.25. Illegal Immigration Reform Act Compliance:

By submitting an offer, Contractor certifies that it will comply with the applicable requirements of Title

8, Chapter 14 of the South Carolina Code of Laws (originally enacted as Section 3 of The South Carolina

Illegal Immigration Reform Act , 2008 S.C. Act No. 280) and agrees to provide upon request any documentation required to establish either: (a) the applicability of Title 8, Chapter 14 to Contractor and any subcontractors or sub-subcontractors; or (b) the compliance with Title 8, Chapter 14 by Contractor and any subcontractor or sub-subcontractor. Pursuant to Section 8-14-60, “A person who knowingly makes or files any false, fictitious, or fraudulent document, statement, or report pursuant to this chapter is guilty of a felony, and upon conviction, must be fined within the discretion of the court or imprisoned for not more than five years, or both.” Contractor agrees to include in any contracts with its subcontractors language requiring the subcontractors to (a) comply with the applicable requirements of

Title 8, Chapter 14, and (b) include in any contracts with the sub-subcontractors language requiring the sub- subcontractor to comply with the applicable requirements of Title 8, Chapter 14. In the event any contractor, subcontractor and/or sub-subcontractor is found not to be in compliance with the SC

Immigration Reform Act [hereinafter "The Act"], the contractor agrees to fully indemnify the County for any loss suffered by the County as a result of such contractor, subcontractor or sub-subcontractor's failure to comply with the Act.

9.26. Assignment Clause:

Successful responder will be required to give the County ninety (90) days’ notice in the event of a change in the ownership of this contract. The County is under no obligation to continue this contract with an assignee. No contract or its provisions may be assigned, sublet, or transferred without the written consent of the County.

9.27. Indemnification:

Contractor agrees to defend, indemnify and save harmless the County and all County officers, agents and employees from and against any loss, damage, claim or action, including all expenses incidental to such claim and action, to the extent arising from any negligent acts or omissions by Contractor, its agents, staff, consultants and contractors employed by it, in the performance of the services under this

Agreement. Contractor shall not be responsible for any loss, damage, or liability to the extent arising from acts of the County, its agents, staff, and other consultants employed by it.

9.28. Deviations from Specifications:

Any deviation from specifications indicated herein must be clearly pointed out; otherwise, it will be considered that items offered are in strict compliance with these specifications, and successful responder will be held responsible therefore. Deviations must be explained in detail on separate attached sheets(s). The listing of deviations, if any, is required but will not be construed as waiving any requirements of the specifications. Deviations found in the evaluation of the response and not listed may be cause for rejection. Responders offering substitute or equal items must provide information sufficient enough to determine acceptability of item offered.

9.29. Minor Deviations:

The County reserves the right to negotiate minor deviations from the prescribed terms, conditions and requirements with the selected vendor.

9.30. Contractor License Requirement:

The contractor shall procure all permits and licenses, and pay all charges and fees necessary and incidental to the lawful conduct of his business. Contractor shall keep fully informed of existing and future Federal, State, and Local Laws, ordinances and regulations which in any manner affect the fulfillment of his contract and shall comply with the same.

9.31. Conflict of Interest Statement:

The contractor may become involved in situations where a conflict of interest could occur due to individual or organizational activities within the County.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .