The document is a Base Offer Price Breakdown template for a VA construction project at James A. Haley VA Hospital in Tampa, FL. The excel spreadsheet provides a detailed cost breakdown template organized by 34 construction divisions, allowing offerors to input labor and material costs for each division. The template includes sections for calculating overhead, profit, and bond percentages, with a final total base offer cost calculation.

This price breakdown corresponds to Solicitation Number 36C24825R0116 for a sanitary riser upgrade project (Project 673-21-154) valued between $1-2 million. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB), with proposals due by 07/21/2025. Key requirements include a site visit on 06/27/2025, submission of a payment and performance bond, compliance with Davis-Bacon wages, and demonstration of past performance in healthcare construction environments. Offerors must show at least 15% of contract costs will be performed by their own employees, and must have an Experience Modification Rate (EMR) not exceeding 1.0.

View the file

Other files

File Type Posted
RFI_BB Sanitary Riser-Responses.docx DOCX document
36C24825R0116 0002.docx DOCX document
36C24825R0116 0001.docx DOCX document
673-21-154-Bid-CD Drawings_Stamped-TMM2211.pdf PDF
36C24825R0116_1.docx DOCX document
Past Performance Questionnaire - 4 Pages.docx DOCX document
WD FL20250208 05232025.pdf PDF
7b Vol2 Specifications.pdf PDF
7a Vol1 Specifications.pdf PDF
EMR 1 page.pdf PDF
7 Drawings.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Offer Base Offer Cost Breakdown

Project Number: N/A Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0
Division 2Existing Conditions- 0- 0
Division 3Concrete- 0- 0
Division 4Masonry- 0- 0
Division 5Metals- 0- 0
Division 6Wood and Plastic- 0- 0
Division 7Thermal & Moisture Protect- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

Offerors shall provide additional price breakdown to avoiding lump sum, etc. This price offer breakdown is the overall base offer price for Government price analysis

File details come from the government source that posted it. Updated .