This document is a specification sheet for the Ohio Department of Natural Resources Division of Wildlife's project to remove and replace the metal roof, downspouts, fascia boards, gutters, and eave vents on an 80'x40' pole barn serving as the main office and workshop at the Fallsville Wildlife Area Headquarters. The project requires the installation of new 2x4 horizontal boards on the rafters as needed, 2x6 wood fascia on the eaves and gable ends with steel fascia caps, vented soffit, 28-gauge panel steel roof in white, snow guards, metal ridge cap, 5" seamless metal gutters and downspouts in white, and the disposal of all construction materials in the on-site dumpster. The Division will purchase any additional materials necessary for the structural integrity of the barn. Bids must be submitted through Ohio Buys by the close of business on Friday, October 11, 2024, with labor and materials costs separated for each specification. The selected contractor will be responsible for obtaining all required work permits and contacting Ohio Utility Protection Services.

The document does not provide any information about pricing terms, set asides, incumbents, funding requirements or sources, or contract amounts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Spec Sheet for Project Ohio Department of Natural Resources

Division of Wildlife

Project:

Metal Barn Roof Fallsville Wildlife Area Headquarters Address:

10221 Careytown Road New Vienna, Ohio 45159.

Phone:

937-987-2508

Email:

ron.adams@dnr.ohio.gov Title/Description:

Remove and Replace Metal Roof on Office/Shop Building Dear prospective bidders, ODNR Division of Wildlife is accepting bids to replace; metal roof, downspouts, fascia boards, gutters and eave vents on a building located at the address above, please submit bids to the specifications below. All bids must be submitted through Ohio Buys.

Sincerely

Kash Adams Specifications:

1. Remove and replace all existing metal roof material, fascia boards, soffit, downspouts and gutters on an 80’X40’ pole barn that serves as main office and workshop.

2. Install 2X4s horizontally on rafters as needed to replace any rotten ones.

3. Install 2X6 wood fascia on every eave and gable ends.

4. New fascia boards must be capped with new steel fascia (white in color) to protect from weather.

5. Install vented soffit around entire building.

6. Install 28 gage panel steel roof (white in color) and fasten with white screws appropriate for the attachment of stee roof.

7. Install corners on gable edge of roof

8. Install rail snow guard approximately 2’ above eave edge of roof

9. Install new metal ridge cap (white in Color)

10. Install 5” seamless metal gutters, (white) front and back, entire length of building.

11. Install 5" seamless metal downspouts (White) in all four corners Note: All construction materials may be placed in dumpster on site ODNR will purchase any extra materials that may be necessary for the structural integrity of the barn. Example, rotten rafters or horizontal 2X4’s as needed.

When submitting bids please separate labor and materials for each specification above, 1-11 Selected Contractor will be responsible for obtaining all work permits and contacting Ohio Utility Protection Services if applicable.

Please have all bids submitted by close of business on Friday October 11, 2024.

Please submit all question through Ohio buys.