This document is a Statement of Work (SOW) for Barge Crane Service for the U.S. Coast Guard. The SOW requires a contractor to provide a barge crane to remove and reinstall an Appleton Marine Crane (KB20-10-50 Boom, 12,000 lbs) on the USCGC WYACONDA at the CG Schlimme Industrial Facility in St. Louis, MO. The project involves lifting the equipment approximately 80 feet high with a 70-foot outreach, with specific removal and installation dates of 2 April 2025 and 30 April 2025, respectively. The contractor must provide a crane capable of mooring outboard of the Coast Guard cutter and holding the load for an unspecified period while personnel position the boom.

Key requirements include providing a crane with sufficient lifting capacity for a minimum of five hours, using Coast Guard-provided lifting slings and straps, and submitting proof of a Certified Weight Test completed within the last twelve months. A Coast Guard Deck Supervisor will direct all lifting and movement, and the contractor must comply with all safety requirements set by the Coast Guard Industrial Facility and Army Corps of Engineers. The project location is Building 17 at 100 Arsenal Street, with work hours from 0700-1500, and any work outside these hours requires advanced approval from the project manager.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6-Feb-25

BARGE CRANE SERVICE

This work item describes the requirements for the Contractor to provide a barge crane to remove and install equipment on a Coast Guard Barge.

Project Manager: Mr. James Tepen

Industrial Detachment Supervisor* Office (314) 771-6044 x 2103 Cell (314) 565-8893 Fax (314) 771-6269 *Visits for possible estimates must be scheduled with the Industrial Detachment Supervisor

Project Location: CG Schlimme Industrial Facility

100 Arsenal Street Building 17

St. Louis, MO 63118

Location Work Hours: 0700 – 1500 (All work outside of these hours requires advanced approval from the Project Manager)

Vessel: USCGC WYACONDA (WLR 75403) Homeport: Dubuque, IA.

POC: MKC Philip Hanaburgh, or Cutter Representative* (563) 582-1965 *Schedule visits for possible estimates with POC and/or project manager

Remove Date: 2 Apr 2025 (8:00 am – 1:00 pm) Install Date: 30 Apr 2025 (8:00 am – 1:00 pm)

NOTE

Crane must be capable of mooring outboard of the USCG cutter, hoisting 12000 lbs and lowering it on the USCGC Wyaconda.

Approximately 80’ lift and 70’ outreach

1. SCOPE

1.1 This This work item describes the requirements for the Contractor to remove and reinstall the following equipment:

1ea Appleton Marine Crane, KB20-10-50 Boom 12000lbs

2. REQUIREMENTS

2.1 General. The Contractor shall provide a barge crane with sufficient lifting capacity for the above listed equipment for a minimum period of five (5) hours on the date specified above. Positioning of the Barge crane shall be outboard of the Coast Guard Barge and the Appleton Marine Crane boom shall be hoisted approximately

80’ height and 70’ outreach from the main pier to the cutter.

NOTE

Crane will be required to hold the load over the CGC Barge for an unspecified period while IPD St. Louis personnel position the boom onto the Appleton Marine Crane pedestal.

SAFETY CAUTION!

A Coast Guard Deck Supervisor (Yellow Hard Hat) will direct all lifting and/or movement of the crane.

2.2 Equipment Removal. The Contractor shall lift equipment from the Coast Guard

Barge to the main pier (approx. 80 feet above floating pier & 70 feet from centerline of the contracted floating crane) using lifting slings and straps provided by the Coast Guard. All equipment will be unfastened, unwired, and readied for removal by Coast Guard personnel.

2.3 Equipment Reinstall. The Contractor shall lift equipment from the main pier to the Coast Guard Barge for reinstallation by Coast Guard personnel using lifting slings and straps provided by the Coast Guard.

3. Quality Assurance

3.1 Certification. Contractor shall provided proof of Certified Weight Test of crane and weight handling equipment within the last twelve (12) months. Proof must be faxed to the project manager no later than one (1) week prior to start of project.

4. Notes

4.1 All persons conducting business with or at the U. S. Coast Guard Industrial

Facility and onboard Coast Guard Cutters while moored at this facility are required to meet all applicable safety requirements including weather conditions set forth by the Coast Guard Industrial Facility and the Army Corps of Engineers.