Barge Crane Service WYACONDA SOW.doc
DOC document 60 KB Posted
- Solicitation number
- 70Z02925QNEWO072A
About this file
The document is a Statement of Work (SOW) for a barge crane service to remove and reinstall an Appleton Marine Crane (KB20-10-50, 12,000 lbs) on the USCGC WYACONDA for the U.S. Coast Guard. The project will take place at the CG Schlimme Industrial Facility in St. Louis, MO, with specific removal and installation dates of April 2, 2025 (8:00 am - 1:00 pm) and April 30, 2025 (8:00 am - 1:00 pm), respectively.
The contractor must provide a barge crane capable of lifting 12,000 lbs with approximately 80' lift height and 70' outreach, positioning outboard of the Coast Guard Barge. Key requirements include providing certified weight test documentation within the last 12 months, adhering to Coast Guard safety protocols, and using Coast Guard-provided lifting slings and straps. A Coast Guard Deck Supervisor will direct all lifting and movement operations. The solicitation (70Z02925QNEWO072A) indicates the contract will be awarded to the lowest-price qualified vendor registered in sam.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Commercial_Supplies_Services_Clauses_Provisions_FAC_2022_06_correct.doc | DOC document | |
| SF1449-21 Barge Crane WYACONDA.pdf | ||
| St. Louis Wages 15-5075.pdf | ||
| Barge Crane Service WYACONDA SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6-Feb-25
BARGE CRANE SERVICE
This work item describes the requirements for the Contractor to provide a barge crane to remove and install equipment on a Coast Guard Barge.
Project Manager:
Mr. James Tepen Industrial Detachment Supervisor* Office (314) 771-6044 x 2103
Cell (314) 565-8893 Fax (314) 771-6269 *Visits for possible estimates must be scheduled with the Industrial Detachment Supervisor Project Location: CG Schlimme Industrial Facility
100 Arsenal Street Building 17
St. Louis, MO 63118 Location Work Hours:
0700 – 1500 (All work outside of these hours requires advanced approval from the Project Manager)
Vessel: USCGC WYACONDA (WLR 75403) Homeport: Dubuque, IA.
POC: MKC Philip Hanaburgh, or Cutter Representative* (563) 582-1965
*Schedule visits for possible estimates with POC and/or project manager Remove Date: 2 Apr 2025 (8:00 am – 1:00 pm) Install Date:
30 Apr 2025 (8:00 am – 1:00 pm)
NOTE
Crane must be capable of mooring outboard of the USCG cutter, hoisting 12000 lbs and lowering it on the USCGC Wyaconda. Approximately 80’ lift and 70’ outreach
1. SCOPE
1.1 This This work item describes the requirements for the Contractor to remove and reinstall the following equipment:
· 1ea Appleton Marine Crane, KB20-10-50 Boom
12000lbs
2. REQUIREMENTS
2.1 General. The Contractor shall provide a barge crane with sufficient lifting capacity for the above listed equipment for a minimum period of five (5) hours on the date specified above. Positioning of the Barge crane shall be outboard of the Coast Guard Barge and the Appleton Marine Crane boom shall be hoisted approximately 80’ height and 70’ outreach from the main pier to the cutter.
NOTE
Crane will be required to hold the load over the CGC Barge for an unspecified period while IPD St. Louis personnel position the boom onto the Appleton Marine Crane pedestal.
SAFETY CAUTION!
A Coast Guard Deck Supervisor (Yellow Hard Hat) will direct all lifting and/or movement of the crane.
2.2 Equipment Removal. The Contractor shall lift equipment from the Coast Guard Barge to the main pier (approx. 80 feet above floating pier & 70 feet from centerline of the contracted floating crane) using lifting slings and straps provided by the Coast Guard. All equipment will be unfastened, unwired, and readied for removal by Coast Guard personnel.
2.3 Equipment Reinstall. The Contractor shall lift equipment from the main pier to the Coast Guard Barge for reinstallation by Coast Guard personnel using lifting slings and straps provided by the Coast Guard.
3. Quality Assurance
3.1 Certification. Contractor shall provided proof of Certified Weight Test of crane and weight handling equipment within the last twelve (12) months. Proof must be faxed to the project manager no later than one (1) week prior to start of project.
4. Notes
4.1 All persons conducting business with or at the U. S. Coast Guard Industrial Facility and onboard Coast Guard Cutters while moored at this facility are required to meet all applicable safety requirements including weather conditions set forth by the Coast Guard Industrial Facility and the Army Corps of Engineers.
File details come from the government source that posted it. Updated .