B525_Requirements_Analysis_SOW_1.pdf

PDF 456 KB Posted

Attached to
Requirements Analysis (A&E) for Army (ATEC)
Solicitation number
140D0426Q0842
Issued by

About this file

This is a Statement of Work (SOW) for a Requirements Analysis project to modernize Building 525 at Aberdeen Test Center under the U.S. Army Test and Evaluation Command (ATEC) G-4.

The project requires a comprehensive Requirements Analysis to address the 1941-era utility infrastructure in Building 525, which presents mission risks due to unreliable electrical power, inadequate HVAC systems, and absence of modern sewer and stormwater systems. The Consultant must conduct physical assessments and develop detailed cost estimates for electrical, mechanical, sewer, stormwater, and loading dock modernization efforts. Key deliverables include an RA out-brief/report, DD Form 1391 (fully completed and formatted for upload into the PAX Processor system), Sanitary Sewer and Stormwater system assessments, and Loading Dock assessments. All deliverables must include identified deficiencies, recommended Courses of Action (COAs), and rough order of magnitude (ROM) cost estimates for each COA. The Consultant must also participate in an in-person RA workshop at the site, coordinate with mission and Base representatives, review design and planning documents for UFC and regulatory compliance, and provide Subject Matter Expert support throughout the process.

The Period of Performance is 90 calendar days after Notice to Proceed, with completion defined as all contractual obligations except final As-Built drawings. The Contractor is authorized to work onsite 0700-1600 hours Monday through Friday (excluding every other Friday RDO) and must obtain security badges and provide escorts as required in the restricted area. Work must comply with Unified Facilities Criteria standards, Army Regulations, Executive Orders, Aberdeen Proving Ground design requirements, and applicable state regulations. The Contracting Officer retains sole authority to obligate the Government, with a Contracting Officer's Representative appointed to serve as the primary technical point of contact and inspection/acceptance authority.

View the file

Other files

File Type Posted
Bldg_525_Requirements_Analysis_Synopsis_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Army Test and Evaluation Command (ATEC) G-4 Project Name: Building 525 Requirements Analysis (RA) Date: 03/23/2026

STATEMENT OF WORK (SOW)

PN: 110417

Project Name: Requirements Analysis (RA) – Repair Weapons Assembly Building 525

MISSION OBJECTIVE

This project will execute a comprehensive Requirements Analysis (RA) to modernize the electrical, mechanical, sewer, and stormwater infrastructure within Building 525 and improve the loading dock directly enhancing the mission-critical capabilities of the Live

Fire Directorate at Aberdeen Test Center (ATC).

The Directorate's core mission involves the vital proofing of weapon systems and precise measurement of cannon tubes and mortar tubes, which relies on high-precision instrumentation.

The current 1941-era utility infrastructure in Building 525 presents a direct risk to this mission by offering unreliable electrical power, which can compromise the accuracy and validity of test data. Furthermore, the inadequate HVAC systems fail to provide the stable and properly ventilated conditions necessary for the optimal performance and longevity of the high-precision measurement instruments, which limits production capacity and can affect the reliability of test data. The absence of a modern sewer and stormwater system and an inadequate loading dock further hampers the facility’s operational efficiency and safety.

The scope of this project includes a physical assessment of the existing electrical, HVAC, sewer, and stormwater systems, as well as the loading dock, followed by a requirements analysis to define the necessary upgrades. This analysis will ensure that all modernization efforts directly support the restoration of full mission capability and adhere to current safety and fire regulations.

The project will conclude with a final report containing distinct cost estimates for the required electrical, mechanical, sewer, stormwater, and loading dock scopes, providing a clear path to enhancing the directorate's ability to test and certify superior materiel for the warfighter.

Date: 03/23/2026

PHOTOGRAPHS

RELEVANT REFERENCE DOCUMENTS

1. Army Regulation (AR) 420-1: Army Facilities Management

2. Unified Facilities Criteria (UFC) 1-200-01: DoD Building Code

3. Unified Facilities Criteria (UFC) 3-201-01: Civil Engineering

4. Unified Facilities Criteria (UFC) 3-301-01: Structural Engineering

5. Unified Facilities Criteria (UFC) 3-401-01: Mechanical Engineering

6. Unified Facilities Criteria (UFC) 3-410-01: HVAC Systems

7. Unified Facilities Criteria (UFC) 3-420-01: Plumbing Systems

PERIOD OF PERFORMANCE

Barring any contingencies that arise during construction, the Government requires completion of this project within 90 calendar days after the Notice to Proceed. The

Contract defines completion as the completion of all contractual obligations and requirements, except for the submission of the final As-Built drawings.

GOVERNMENT SERVICES

1. The Contracting Officer (KO) has sole authority to oblige the Government.

2. The Contracting Officer (KO) appoints the Contracting Officer’s Representative (COR) to serve as the Government's technical representative and primary point of contact in the field following contract award. The COR will perform all inspection and acceptance on behalf of the Government for this project.

3. The Government will provide limited Geodetic surveying services and project site maps.

Date: 03/23/2026

STATEMENT OF WORK (SOW)

Division 00 – Procurement and Contracting Requirements

1. The Consultant, also referred to as the Contractor, shall provide professional services, furnish all materials, transportation and equipment, and perform all labor required to analyze and prepare the Building 525 Requirements Analysis (RA) documentation. The work shall consist of program validation services, site investigations, coordination with mission and Garrison representatives, and written deliverables including the following:

• RA out brief / report

• Full Department of Defense (DD) Form 1391

• Sanitary Sewer and Stormwater system Assessment. Conduct comprehensive evaluation of existing sewer and drainage systems, including condition, capacity, compliance, and development of recommended Courses of Action and associated cost impacts.

• Loading Dock Assessment. Conduct comprehensive evaluation of existing loading dock and recommend Courses of Action and associated cost impacts.

2. The contents of this document shall prevail and supersede any exclusions or disclaimers listed on the Consultant’s proposal.

3. The Consultant shall develop and submit a fully detailed line-item proposal, to include a plan that shows how they will proceed with the work. This plan shall contain a timeline for completion of all contract requirements, including milestones for definable features of work.

4. The Consultant is to provide a baseline schedule and an approved Schedule of

Values (SOV) prior to the commencement of planning activities.

5. The Consultant shall prepare the DD Form 1391 in a format suitable for uploading into the Programming Administration & Execution System (PAX) Processor by the

Government.

6. The Consultant shall prepare the DD Form 1391 according to the latest United

States Army Installation Management Command (IMCOM) guidance.

7. The Consultant will perform the work in accordance with applicable Uniform Facility Criteria (UFC), Executive Orders, Army Regulations, Base Design, Guide, and other guidance provided by Aberdeen Test Center (ATC).

8. The RA event will be held in-person and on-site. Video conferencing may be an option at ATC’s discretion depending on the operating orders in effect at the time of the event.

9. The Consultant will review the proposed design and planning documents prepared related to the proposed improvements to ensure compliance with the current UFC, Aberdeen Proving Ground (APG) and state regulatory agency requirements and provide comments back to ATC.

10. The Consultant will discuss additional projects needed to support the mission requirements as part of the RA workshop effort.

Date: 03/23/2026

11. The Consultant will prepare rough order of magnitude (ROM) cost estimates for use in DD Form 1391, including distinct courses of actions (COA) with their corresponding cost impact.

12. The Consultant will prepare additional supporting documentation for the DD Form

1391 submittals, including updates to Tab A and preparation of data for Tabs B through E.

13. The Consultant shall be responsible for working with ATC to prepare the

Preliminary RA Workshop. During the workshop, the Consultant shall finalize and confirm additional projects needed to support the mission requirements. The Consultant’s team shall meet with mission and Base representatives during and after RA to execute the tasks listed below:

o Review Design and Planning Documents – Consultant will meet with

ATC mission personnel to support all design and planning related documentation to ensure all applicable state and local requirements are compliant. The Consultant will provide Subject Matter Expert’s (SME’s) to review and provide any comments to ATC that will be needed to update the facility and program documentation.

o Preliminary Cost Estimate – separate estimates for electrical and mechanical/plumbing, sewer / stormwater infrastructure, and loading dock scopes.

o Draft RA Out-Brief – Consultant shall prepare a draft RA Out-Brief that shall include meeting minutes and attendee lists from the RA, e-mail correspondence pertinent to the development of the program, and the preliminary cost estimates.

o RA Out-Brief – As part of the final day of the RA, the Out-Brief will be presented as a review meeting with ATC to elicit government comments.

At the review meeting, the Government and the Consultant shall develop a list of construction acquisition options to be included in the final report. The final report shall incorporate changes to the Out-Brief discussed during the meeting.

o DD Form 1391 – The Consultant shall assemble available data from the RA and APG into the DD 1391 for use for input by the Government into the PAX Processor. These products will be a final stand-alone deliverable and output of the RA process.

o Final RA Report – includes the Out-Brief, Government comments, meeting minutes and attendee lists, e-mail correspondence pertinent to development of the program, design documents, identify Base, State and

Federal permit requirements as available and shall include any revisions required for the preliminary cost estimates and DD 1391.

o Sewer System Assessment Report – (Sanitary and Stormwater), including existing conditions summary, identified deficiencies and risks, capacity and performance evaluation, recommend Course of Action COAs, and ROM cost estimates for each COA, impacts to mission operations and constructability considerations.

Date: 03/23/2026 o Loading Dock Assessment Report – (demolition and rebuild), including existing conditions summary, identified deficiencies and risks, capacity and performance evaluation, recommend Course of Action COAs, and ROM cost estimates for each COA, impacts to mission operations and constructability considerations.

Division 01 – General Requirements

1. The Government authorizes the Contractor to work onsite from 0700 to 1600 hours Monday through Friday. Government “Regular Day Off” (RDO) occurs every other Friday.

2. The Contractor is to perform work in the Restricted Area, and all personnel must adhere to the standing security requirements. The Contractor shall be responsible for obtaining all security badges for their employees and Subcontractors and for providing all required escorts for the Project.

Division 02 – Existing Conditions

The RA will plan and review the proposed work:

1. Demolish and dispose of existing concrete ramp at front entrance of Building 525.

2. Remove abandoned and existing boiler equipment. This scope includes any unserviceable plumbing and/or HVAC equipment. Demolition of existing electrical and mechanical systems, equipment, and materials.

3. Sewer system Assessment (Sanitary and Stormwater)

Division 03 – Concrete

The RA will plan and review the proposed work:

1. Design and install new concrete loading ramp at front entrance of Building 525.

2. In accordance with UFC 3-301-01, for slabs-on-ground subject to forklift traffic, the

UFC recommends that the minimum compressive strength for the concrete be

4,000 psi for pneumatic tire traffic and 5,000 for steel tire traffic.

Division 22 – Utilities

The RA will plan and review the proposed work:

1. Remove abandoned and existing boiler equipment. This includes any unserviceable plumbing and/or HVAC equipment.

2. Sewer and Drainage System Requirements.

The requirement Analysis (RA) shall include a comprehensive assessment of the existing Building 525 sanitary sewer and stormwater drainage systems. The assessment shall evaluate systems condition, capacity, functionality, and compliance with applicable codes and UFC criteria. The Consultant shall:

Date: 03/23/2026

• Identify and document all existing sanitary sewers, floor drains, trench drains, and stormwater conveyance infrastructure within and immediate adjacent Building 525.

• Evaluate pipe condition, age, material type, and structural integrity using available records and visual inspection (and CCTC where required).

• Assess system capacity relative to current and projected facility demand and mission requirements.

• Identify deficiencies including blockages, infiltration / inflow, backflow risks, improper slopes, or structural failures.

• Evaluate connections to installation utilities and confirm points of discharge and tie-in conditions.

• Identify code compliance issues in accordance with UFC 3-420-01 and applicable local/state regulations.

• Provide recommended Courses of Action (COAs) for repair, replacement, rerouting or system upgrades, including preliminary cost impact.

Division 23 – Heating, Ventilating, and Air Conditioning (HVAC)

The RA will plan and review the proposed work:

3. Requirement – shop area must have heating and adequate airflow for mission objective. Current building has radiant heating.

4. Recommendation – provide heating and air conditioning (A/C) in office areas.

Current office areas have multiple mini-split systems for A/C.

5. Design and construction for the new ductwork shall be in accordance with the most current edition of HVAC SYSTEMS DESIGN and HVAC DUCT CONSTRUCTION STANDARDS, both by the Sheet Metal and Air Conditioning Contractors National Association, Inc. (SMACNA).

6. Terminate services and utilities in accordance with local laws, ordinances, rules and regulations.

7. Ensure adequate clearance exists for installation of work shown.

8. Ensure that mechanical equipment, ductwork, piping, valves and access locations have clearances in accordance with the contract documents and the manufacturer’s requirement for full accessibility and operation of mechanical systems.

9. Fire-stop mechanical penetrations through fire resistance rated walls, floors and assemblies in accordance with applicable codes and standards.

10. Provide access panels, in walls or ceiling, or access doors, in ductwork, required for access to concealed mechanical equipment or devices.

Date: 03/23/2026

11. The Contractor must establish the slopes and invert elevations before piping installation in order to maintain proper slopes.

12. Coordinate location of piping and equipment with plumbing, architecture, structural, civil, and electrical disciplines, as well as other mechanical work.

13. Do not run hydronic piping or locate mechanical equipment directly above electrical substations, cable trays, transformers, panel boards, or switchgear.

14. Provide manual drain connections at coil connections and low points of the system.

15. Piping and ductwork must run tight to the underside of the structure with space for insulation, unless otherwise noted.

16. Provide piping and ductwork so that valves and dampers are accessible.

17. Identify equipment with proper labeling scheme.

18. Recommendation – provide a redundant centralized air compressor system for mission objective.

Division 26 – Electrical

The RA will plan and review the proposed work:

1. Identify existing electrical code violations and provide courses of action (COAs) for potential replacement.

2. All power outages need to be coordinated with end users for logistics and construction planning.

3. Suggested – Furnish and install new 480V Wye electrical service with bus ducts along each bay (3 total) for branch connections.

4. Furnish and install new overhead lighting systems and controls.

5. Furnish and install all conduit and wiring and complete electrical terminations for a complete and functioning system. Make final connections to existing utilities for permanent power.

6. Installation of electrical work must conform to the AHJ’s latest accepted edition of the National Electrical Code (NFPA 70) and all applicable local codes and quality workmanship standards.

7. Coordinate work related to the electrical service directly with the utility company

(City Light and Power – CLP) and obtain approval before installation.

8. The specified equipment determines the electrical requirements for mechanical equipment. Coordinate exact requirements with mechanical shop drawings prior to ordering and installing equipment.

9. The Contractor is to furnish the Variable Frequency Drives (VFDs) under Division

23 unless otherwise noted.

10. Circuit numbers are for identification purposes only. The Contractor is responsible for balancing loads and correctly phasing the circuits in panel boards.

11. Cable tray installation must be coordinated in field with other trades.

12. The Contractor must provide openings and passages for conduits or wire ways through floor slabs, fire-rated walls, or partitions with UL listed fire-rated sleeve systems.

13. Electrical equipment located outdoors must have NEMA 4X enclosure unless otherwise noted.

Date: 03/23/2026

14. Outdoor underground concrete encased conduits shall be PVC schedule 40 unless otherwise noted.

15. Direct-buried underground conduits must be Schedule-80 unless otherwise noted.

16. Recommend Square D manufacturer for electrical equipment.

Division 33 – Utilities

The RA will plan and review the proposed work:

1. Coordinate work related to the electrical service directly with the utility company (City Light and Power – CLP) and obtain approval before installation.

2. Outdoor underground concrete encased conduits shall be PVC schedule 40 unless otherwise noted.

3. Direct-buried underground conduits must be Schedule-80 unless otherwise noted.

4. The available base utility plans determine the locations shown for existing utilities.

Locations of structures above the ground are approximate. Locate known underground utilities with a qualified underground utility location service prior to excavation. The Contractor must indicate all located utilities on the “As-Built” drawings.

5. Sanitary Sewer and Stormwater Utility Integration

The RA shall include evaluation of external sanitary sewer and stormwater utility system serving Building 525. The consultant shall:

• Confirm locations, depths, and condition s of existing underground sewer and stormwater utilities.

• Assess capacity of downstream infrastructure to support upgraded facility demands.

• Identify conflicts with proposed electrical, mechanical, and structural improvements.

• Evaluate the need for rerouting, upsizing or rehabilitation of utility lines

• Coordinate with DPW and installation utility records to validate system configuration and constraints