B491 Fire Alarm Panel - Performance Work Statement.docx
DOCX document 30 KB Posted
- Attached to
- B491 Fire Alarm Repair
- Solicitation number
- FA460026Q0009
About this file
This Performance Work Statement (PWS) details the repair and rebuild of a Simplex 4100ES Fire Alarm Control Panel (FACP) at Facility 491 located at Offutt Air Force Base in Nebraska. The project requires the contractor to provide all necessary equipment and materials, maintain networked communication capability between B491 and B492 fire panels, program all devices and firmware, and conduct a comprehensive test of the fire alarm system in the presence of a Fire Inspector and Contracting Officer.
Key project parameters include a 30-day performance period, work hours between 0730-1630 daily (excluding weekends and federal holidays), and strict security and safety requirements for accessing Offutt AFB. The solicitation (FA460026Q0009) indicates a site visit on 16 December 2025 at the Offutt Visitor Center, with offer submissions due by 5 January 2026 at 11:00 AM CST. The project is being managed by the Department of the Air Force Air Combat Command, with contract point of contact being SrA Jason Arizmendi and Lt Ryan Brewster.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SCA WD 2015-5005 Rev 26.pdf | ||
| Solicitation - FA460026Q0009.pdf | ||
| 55 SFS NCIC Screening Pass Request-FILLED.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Repair failed Fire Alarm Panel at Facility 491
1. Scope: The work covered by this Performance Work Statement (PWS) consists of providing all equipment and materials, and performing all labor required to repair/rebuild Simplex 4100ES FACP at B491 using all existing functional devices. Maintain networked communication capability between B491 and B492 for fire pump activation.
2. Location of Work: The work location is 412 Looking Glass Ave, Facility 491, Offutt AFB, Nebraska.
3. Major Items of Work:
Provide & install equipment:
· Simplex 4100ES and all ancillary equipment required.
· NEMA 3 enclosure for fire alarm panel.
Program panel:
· Verify all Firmware, software, and patches are installed as required
· Program all devices and actions in the panel to ensure function.
Test/Inspect/Certify (after troubleshooting):
| • | After the troubleshooting is completed, and at such time as the Contracting Officer may direct, the contractor shall conduct an operating test for approval. |
| • | The contractor shall demonstrate the functionality of Fire Alarm system and connectivity to B492. |
| • | The test shall be performed in the presence of the Fire Inspector, Alarms Shop, and Contracting Officer or an authorized representative. The contractor shall furnish all the instruments and personnel required to perform the tests. |
4. Codes: All work and personnel shall conform to the latest applicable NFPA, OSHA, Air Force Instructions (AFI), United Facilities Criteria (UFC) 3-535-01, and other Industry Standards.
a. UFC: http://www.wbdg.org/ccb/browse_cat.php?c=4
5. Occupancy: During maintenance the Government will occupy the existing facilities. The contractor shall not restrict nearby pedestrian or vehicular traffic to this facility and shall coordinate construction with the Contracting Officer’s Representative to minimize conflicts and to facilitate usage. The contractor shall perform the work so as not to interfere with ongoing operations.
6. Coordination: The contractor shall coordinate and properly relate the work to be done to the site and to the work of all the trades. The contractor shall visit the premises and thoroughly familiarize him or herself with all the details of the work to be done and the working conditions. The contractor shall verify all of the dimensions in the field and advise the Contracting Office of any discrepancy before performing any work. If any conflicts arise during work necessitating departure from the Performance Work Statement (PWS), details of the departure and the reasons for the departure shall be submitted to the Contracting Office for written approval.
7. Submittals: The contractor shall submit two copies of inspection certifications and any applicable letters of findings to the Contracting Office.
8. Repair Work: The work shall be carefully laid out in advance. Where cutting, channeling, chasing, or drilling is necessary, it shall be done carefully. Any damage to buildings, piping, or equipment, shall be repaired by workers skilled in that particular trade, at no additional cost to the Government.
9. Clean Up: The contractor shall assure that the work area is cleaned up at the end of each day. Debris and trash shall be removed and properly disposed of by the contractor outside the confines of Offutt AFB.
10. Work Schedule: The working hours for this contract shall be between 0730 and 1630 hours daily, excluding Saturdays, Sundays, and Federal Holidays.
11. Performance Period: 30 Days
12. Use of Utilities: All reasonable quantities of utilities will be made available to the contractor without charge. Any temporary connections of lines that may be required will be installed, maintained and removed by the contractor at his own expense and in a manner satisfactory to the Contracting Officer. Removal of such connections or lines shall be accomplished prior to final acceptance of the contract.
13. Guarantee: The equipment furnished under this contract shall be guaranteed against defective materials, design, and workmanship for the full warranty period, which is standard with the manufacturer and/or supplier, but shall be no less than one year from the date of acceptance either for beneficial use or final acceptance (whichever is earlier). Upon receipt of notice, from the Government, of failure of any part of the guaranteed equipment, during the guarantee period, the affected part or parts shall be replaced promptly with new parts at the expense of, and by, the contractor.
14. Payment: All costs in connection with this contract shall be included in the lump sum price for all work to be performed under the contract.
15. Government Furnished Equipment: None
16. Security and Safety Requirements: The contractor shall comply with all requirements and procedures IAW FAR 5353.242-9000, Contractor Access to Air Force Installations.
Personal Security Requirements
• Contractor personnel shall be in possession of Government issued photo identification at all times while on Offutt AFB, and coordinate with Contracting Officer Representative (COR) through the Contracting Office for entry onto the Security Force’s Visitors List.
• Except where otherwise posted, the speed limit on Offutt AFB is 25 MPH. Seatbelts shall be worn at all times by driver and all passengers. Cellphone use is prohibited while driving anywhere on Offutt AFB, except while using hands-free device. All vehicles and personnel are subject to search at any time while on Offutt AFB.
Restricted Area Badges
• If necessary, the COR shall coordinate with Using Agency Facility Manager (UAFM) to obtain a United States Air Force (USAF) Restricted Area Badge for all personnel who require unescorted entry into a restricted area(s) for specific work, for the duration of the contract. It is the responsibility of the UAFM to assist the contractor and his/her employees in initiating a DD Form 254, DOD Contract Security Classification Specification, through the Unit Security Manager (USM). If for any reason the UAFM cannot assist the contractor in processing paperwork for restricted area badges, it is their responsibility to provide escorts. It is the contractor’s responsibility to fully document all cases where entry to restricted areas was not granted. All contractor personnel shall have proper identification prior to entry into restricted areas. It is the responsibility of each UAFM to brief all contractor personnel working in their area on procedures and policies of their particular restricted area.
17. Final Inspection: Contractor will remove material and construction equipment from the site. Contractor will provide submittals and turn in appropriate badges.